Vesting of Project Land in the State Does Not Suspend Execution of RERA Refund Orders: Recovery Must Proceed Under the Land Revenue Act
1. Introduction
The Himachal Pradesh High Court in PAWAN WASANT BORLE v. THE UOI AND OTHERS (CWP No. 1153 of 2026, decided on 25.02.2026)
addressed a practical enforcement impasse frequently encountered in real-estate disputes: whether execution of a final refund/compensation order
under the Real Estate (Regulation and Development) Act, 2016 (“RERA”) can be stalled merely because the project land—connected to the underlying
transaction—has later vested in the State under Section 118 of the H.P. Tenancy and Land Reforms Act, 1972.
The petitioner (a homebuyer/allottee) had paid substantial consideration for a unit in a housing project (“Aamoksh @ Kasauli”) promoted by respondents
No. 5 & 6. Upon non-delivery of possession and breach of the agreement to sell, the petitioner succeeded before the Himachal Pradesh Real Estate
Regulatory Authority (respondent No. 4), which ordered refund with interest. When the promoters failed to comply, RERA issued a recovery certificate
under Section 40(1) RERA, which the District Collector translated into a demand order as arrears of land revenue, but the Tehsildar (Recovery)
effectively halted recovery proceedings citing vesting of the land in the State.
Procedurally, the petitioner initially sought broader reliefs including an asserted override of Section 118 by RERA; however, during hearing the
petition was confined to relief (d): a mandamus to the District Collector and revenue machinery to execute and comply with RERA’s orders in terms of
Section 103 of the H.P. Land Revenue Act, 1954.
2. Summary of the Judgment
The High Court held that recovery proceedings to enforce a final RERA monetary order cannot be put on hold merely because the project land has
vested in the State. Section 40 RERA expressly provides for recovery of amounts as arrears of land revenue, and the H.P. Land Revenue Act contains
multiple statutory modes for recovery (writ of demand, arrest/detention, distress and sale of movables/crops, attachment/sale of holdings, proceedings
against other immovable property, etc.).
The Court found the stoppage of recovery since 15.09.2023 unjustified and contrary to law, emphasizing that where the statute prescribes an explicit
procedure for recovery, it must be adhered to fully; deviation is impermissible. It directed respondent No. 3 (District Collector, Solan) to ensure
that recovery proceedings pursuant to the RERA order (26.02.2021), the recovery certificate (17.10.2022), and the demand order (14.11.2022) are taken
to their logical conclusion expeditiously, in accordance with law.
3. Analysis
3.1 Precedents Cited
The recovery authority’s “zimini” order dated 15.09.2023 referred to State of H.P Vs Data Ram and Ors. as the basis for stating that the land stood vested
in the State Government. Although the High Court did not undertake a substantive exposition of that case, it treated the reference as explaining the
administrative reason for pausing attachment of the particular land.
Crucially, the High Court’s reasoning shows how such a precedent—at most—may bear upon the availability of a particular asset (the project land) for a
specific execution step (e.g., attachment/sale of that land), but cannot be elevated into a doctrine that neutralizes a final monetary recovery certificate.
The Court effectively distinguished the relevance of State of H.P Vs Data Ram and Ors. to only one aspect of recovery (the status of the subject land),
while reaffirming that the statutory recovery framework provides alternative routes that remain enforceable against the defaulters’ other assets and
person, as permitted by law.
3.2 Legal Reasoning
A. Finality and enforceability of RERA orders
The Court anchored its decision on the undisputed finality of the RERA order dated 26.02.2021. The promoters did not challenge it; thus, it attained
finality and created a binding obligation to refund the ordered amounts with interest (9.3% p.a., being SBI highest MCLR + 2% as recorded).
Once non-compliance occurred, RERA’s issuance of a recovery certificate dated 17.10.2022 under Section 40(1) RERA (read with the relevant State Rules and
Regulations mentioned in the judgment) activated the specialized enforcement route: recovery “as arrears of land revenue.”
B. Section 40 RERA and the “arrears of land revenue” enforcement model
Section 40(1) RERA statutorily deems unpaid interest/penalty/compensation recoverable in the prescribed manner as arrears of land revenue. The Court
treated this not as a discretionary facilitation but as a firm legislative command that the State’s revenue recovery machinery must operationalize.
C. Section 103 read with Chapter VI of the H.P. Land Revenue Act: multiple modes, not a single-asset execution
The Court reproduced and relied on Section 103 of the H.P. Land Revenue Act, 1954 (recovery of other sums as arrears of land revenue) and the detailed
recovery processes in Chapter VI (Sections 74 to 83, as extracted).
The key doctrinal move is the Court’s insistence that the statutory scheme is not limited to proceeding against a single parcel of land. Even if the
project land is unavailable due to vesting, the Act authorizes:
- service of a writ of demand (Section 74(a) read with Section 75);
- arrest and detention (Section 74(b) read with Section 75-A, subject to statutory limits);
- distress and sale of movable property and crops (Section 74(c) read with Section 76);
- attachment/sale processes and management mechanisms (Sections 78–82);
- proceedings against other immovable property of the defaulter (Section 74(h) read with Section 83).
Therefore, vesting of the “subject land” does not collapse enforceability; it merely changes the recovery strategy within the same statutory toolkit.
D. Vesting under Section 118 of the H.P. Tenancy and Land Reforms Act does not defeat the recovery certificate
The Court accepted as fact that proceedings under Section 118 were initiated and culminated in orders vesting the land in the State (District Collector’s
order dated 05.01.2023, affirmed by the Divisional Commissioner on 29.11.2024). However, it held that this subsequent vesting cannot operate as a legal
justification to halt recovery of a personal monetary liability already crystallized under a final RERA order and recovery certificate.
In other words, the judgment draws a distinction between:
- rights in rem over a specific land parcel (affected by vesting), and
- personal liability in personam of the promoters to pay the decretal/recoverable amount (enforceable through multiple recovery modes).
E. Administrative inaction as illegality: “explicit procedure must be scrupulously adhered to”
The Court’s strongest normative statement is that when a statute provides explicit recovery procedures, authorities must follow them “in its entirety” and
“no deviation is permissible.” This converts what may be perceived as an administrative pause into a jurisdictional error: the Tehsildar (Recovery) cannot
indefinitely withhold recovery when lawful alternative modes exist.
3.3 Impact
A. For RERA enforcement in Himachal Pradesh
The decision reinforces that RERA’s Section 40 mechanism is not symbolic: once a recovery certificate is issued and transmitted, the Collectorate and
subordinate revenue officers have a duty to carry execution forward using the Land Revenue Act’s processes, even if one asset becomes unavailable.
B. For cases involving Section 118 vesting
Projects in Himachal Pradesh often face complications from Section 118 restrictions and consequent vesting orders. This judgment clarifies that such
vesting cannot become a universal shield against monetary enforcement. Authorities must pivot to other permissible recovery modes rather than stop.
C. For administrative accountability
By directing the District Collector to “ensure” expeditious completion, the Court places responsibility at the supervisory level—signaling that inertia at
the Tehsil/Recovery level can invite judicial correction and that the Collectorate must actively manage execution of recovery certificates.
D. For future litigation strategy
Homebuyers and decree-holders can rely on this judgment to argue that execution cannot be stalled due to post-order changes in asset status (including
vesting/attachment disputes), and to seek mandamus compelling the revenue machinery to employ alternative statutory modes (notably, Section 83 proceedings
against other immovable property).
4. Complex Concepts Simplified
-
Recovery “as arrears of land revenue” (Section 40 RERA):
RERA allows its monetary directions to be collected like unpaid land revenue—using the State’s revenue recovery machinery, which is generally faster and
more coercive than ordinary civil execution.
-
Recovery certificate:
A formal instrument issued by RERA specifying the recoverable amount; it enables the Collector to start revenue recovery proceedings.
-
Vesting in the State (Section 118 context):
A legal consequence where ownership/interest in land is transferred to the State by operation of a statutory order. It may remove that land from the
defaulter’s attachable pool, but it does not erase the defaulter’s personal monetary liability.
-
“Zimini orders”:
Day-to-day brief orders recorded during revenue proceedings noting steps taken or reasons for adjournments/pauses.
-
Mandamus:
A constitutional writ directing a public authority to perform its statutory duty—used here to compel execution of a final recovery process.
5. Conclusion
PAWAN WASANT BORLE v. THE UOI AND OTHERS establishes a clear operational rule: vesting of the project land in the State does not justify suspending
execution of a final RERA refund/compensation order. Where Section 40 RERA triggers recovery as arrears of land revenue, the revenue authorities must
proceed to enforce the recovery certificate using the comprehensive mechanisms under the H.P. Land Revenue Act, including alternative modes when the
originally contemplated property is unavailable.
The judgment strengthens the credibility of RERA remedies by ensuring that enforcement does not fail due to asset-status complications, and it underscores
that statutory recovery procedures are not optional—they must be carried through to their logical conclusion.