Staged Consents Under the Dual-Consent Regime: No “Prematurity” Veto and No Automatic Importation of “AG” Zoning via Deemed Existing-Use Zoning

Court: High Court of Ireland (Planning & Environment)
Judge: Humphreys J.
Citation: [2026] IEHC 224
Date: 17 April 2026
Decision under review: An Coimisiún Pleanála approval (17 July 2025) under s. 182A/s. 182B of the Planning and Development Act 2000 for an electricity substation and 10.2km grid connection to serve a separately-consented solar farm.

1) Introduction

This judicial review concerned the “dual consent” architecture in Irish planning law: the solar farm itself required planning permission (ultimately granted on appeal by An Coimisiún Pleanála), while the associated electricity transmission development (a 220kV substation and underground cable connection) fell to be approved directly by the Commission under s. 182A of the Planning and Development Act 2000.

The applicants (local residents and environmental participants) sought certiorari quashing the Commission’s July 2025 approval for the substation and grid connection. Their case turned on three core themes: (i) whether the site was (deemed) zoned “Agriculture (AG)” under the Cork County Development Plan 2022–2028 and whether the Commission misapplied that zoning; (ii) whether it was unlawful or inadequately reasoned to approve enabling grid infrastructure while the solar farm permission was still pending (“prematurity”); and (iii) whether the Commission misapplied renewable-energy policy objectives (ET 13-14 and ET 13-21) by treating them as unqualified support for the infrastructure without grappling with conditions and contingencies.

Key holdings in brief

  • Deemed existing-use zoning does not automatically trigger the mapped “Agriculture (AG)” zoning regime. “Agricultural use” is not interchangeable with “Agriculture (AG) zoning”.
  • No justiciable “prematurity” rule requires a developer (or the Commission) to sequence staged consents in a particular order, or to show “reasonable certainty” that later consents will be granted.
  • Workability is a decisive constraint on proposed legal rules in judicial review; the court rejected bright-line rules that would make complex, multi-consent projects effectively impossible.
  • Ashchurch is confined to its facts: it was an “extreme” case where harms were directed to be ignored; it does not mandate contingency/Grampian-type conditioning in ordinary staged-consent scenarios.

2) Summary of the Judgment

Humphreys J. dismissed the proceedings. The court held that the applicants had not established any legal error in the Commission’s interpretation of the Cork County Development Plan or in its approach to staged consents. The “AG zoning” argument failed because the Development Plan’s “deemed zoning” for lands not explicitly zoned did not transform agricultural land into land subject to the specific “Agriculture (AG)” zoning objective (which was mapped and purpose-specific). The “prematurity” argument failed because Irish law (reinforced by the Supreme Court in Concerned Residents of Treascon and Clondoolusk v. An Bord Pleanála [2024] IESC 28) permits overall developments to be consented in parts, and the applicants’ proposed requirement of “reasonable certainty” about later consents was unworkable and unsupported by statute or EU law. The Development Plan policy argument failed because the Commission was entitled to treat renewable-energy and associated grid infrastructure policy as applicable and, on the evidence, had considered the relevant environmental and planning factors; the applicants did not discharge the onus of proof.

The court also indicated that, even had an error been established, it would (counterfactually) have been disposed to refuse certiorari on proportionality/discretion grounds in light of the statutory and EU-policy importance attached to renewable infrastructure—though discretion was not reached given the findings on validity.

3) Analysis

3.1 Precedents Cited (and how they shaped the decision)

(A) Staged consents, “prematurity”, and project-splitting

The judgment is anchored in the Supreme Court’s endorsement of staged consenting in Concerned Residents of Treascon and Clondoolusk v. An Bord Pleanála [2024] IESC 28. Humphreys J. treated Treascon as dispositive of attempts to convert sequencing concerns into a legal veto: once the legal system accepts consent “in parts”, uncertainty about later parts is not an aberration—it is inherent.

The court also drew support from High Court authority rejecting “prematurity” as a free-standing legal objection: McGowan v. An Coimisiún Pleanála [2025] IEHC 405 and Hoctor & Ors v. An Coimisiún Pleanála [2026] IEHC 65. Relatedly, it cautioned against reliance on an “obviously poorly-considered and misconceived” obiter remark in Ó Gríanna v. An Bord Pleanála & Ors [2014] IEHC 632, noting that it “failed at the first test” and was not even followed in Ó Gríanna v. An Bord Pleanála (No. 2) [2015] IEHC 248.

A key analytical move was to reframe “project-splitting” as not inherently unlawful: it becomes problematic only where it undermines EU environmental assessment obligations. The court’s position is that the legality question is not “splitting” as such, but whether (where relevant) the overall project is assessed for EIA/AA purposes and thresholds are handled in that overall context.

(B) Judicial review discipline: legality, not merits; onus of proof; reasons

The judgment contains an extensive consolidation of judicial review principles. It emphasises that judicial review targets legality, not correctness, citing: Sweeney v. Fahy [2014] IESC 50, the State (Keegan) v. Stardust Compensation Tribunal [1986] I.R. 642, Meadows v. Minister for Justice, Equality and Law Reform [2010] IESC 3, and R (Cart) v. Upper Tribunal [2011] UKSC 28. It also relies on Sherwin v. An Bord Pleanála [2024] IESC 13 for the proposition that evaluative planning judgments are generally reviewed on irrationality where not tainted by legal/procedural error.

On the practical reading of administrative decisions (avoiding semantic over-parsing), the court invoked a line of authority including M.R. (Bangladesh) v. International Protection Appeals Tribunal [2020] IEHC 41, St. Margaret's Recycling v. An Bord Pleanála [2024] IEHC 94, and O'Sullivan v. HSE [2023] IESC 11. This posture mattered to all three grounds: the applicants’ case repeatedly depended on treating the absence of particular phrasing as evidence that matters were not considered.

On onus, the court reiterated that applicants bear the burden of proof in judicial review, with shifts only in defined situations, supported by Ballyboden Tidy Towns Group v. An Bord Pleanála & Ors. [2024] IESC 4 and related authority. This was central to the claim that the project was “fundamentally inconsistent” with agricultural use, and to the asserted inadequacy in considering environmental safeguards: assertion was not enough.

(C) Workability as a constraint on proposed legal rules

A distinctive feature of the judgment is its insistence on workability as a threshold criterion for relief and for interpreting obligations. The court relied on Waltham Abbey v. An Bord Pleanála; Pembroke Road Association v. An Bord Pleanála [2022] IESC 30 and An Taisce v. An Bord Pleanála (Kilkenny Cheese) [2022] IESC 8 to reject constructions that yield “strange incongruities” or impose “impossibly onerous and unworkable obligations”.

This workability analysis was the primary engine for rejecting the applicants’ proposed “reasonable certainty” and contingency-conditioning requirements for staged consents.

(D) The English “enabling development” case and its limits

The applicants relied heavily on R. (Ashchurch) v. Tewksbury Borough Council [2023] EWCA Civ 101. Humphreys J. treated Ashchurch as fact-specific: an “extreme” case where the decision-maker invited substantial weight to future benefits while directing that harms be “left out of account entirely”. That was characterised as a paradigmatic irrationality error of excluding relevant considerations—not a general rule requiring decision-makers to address every contingency in every staged project.

(E) Development plans and “have regard to” duties

On the statutory “have regard to” obligation, the judgment drew an analogy with Ryanair DAC v. An Bord Pleanála [2025] IEHC 74 and the Supreme Court determination Ryanair DAC v. An Bord Pleanála [2025] IESCDET 84, emphasising that where the statute requires “have regard to” (rather than compliance), departure does not automatically produce invalidity. This provided a further backstop answer to the applicants’ Development Plan-based arguments in the s. 182A/s. 182B setting.

(F) Draft judgment confidentiality (procedural but practically important)

The judgment contains an express direction restricting dissemination of draft judgments, supported by comparative authority including Attorney General v. Crosland (No. 2) [2021] UKSC 58. While not part of the planning law ratio, it is a notable procedural statement for Planning & Environment judicial review practice (especially in expedited matters).

3.2 Legal Reasoning

(1) Core Ground 1 — “Deemed zoning” does not convert “agricultural use” into “Agriculture (AG) zoning”

The applicants’ strongest textual hook was Objective ZU 18-4 (“Land Use Zoning of Other Lands”), which deems the “specific zoning” of unzoned lands to be the existing authorised use. The court accepted there was a typo in ZU 18-4 (the word “not”), but held that the objective still operated coherently as a residual zoning mechanism.

The key interpretive step was distinguishing:

  • Residual deemed zoning: a mechanism to avoid “uncharted” land by treating it as governed by its existing authorised use; versus
  • Mapped “Agriculture (AG)” zoning: a labelled, purpose-driven zoning category with a particular planning intent (described as preventing premature development adjacent to development areas).

The court rejected what it called the applicants’ “sleight of hand”: the assertion that because the authorised existing use was agricultural, the full “panoply” of AG zoning objectives necessarily applied. The Commission’s stance that “agricultural use is not the same as the express ‘Agriculture (AG)’ zoning objective” was endorsed.

The judge also pointed to the factual character of the redlined development (including extensive works along roads) and treated it as unrealistic to collapse the entire corridor into a single “field” analysis. In any event, the court held the Commission did consider the existing authorised use, and further observed that solar farms and associated infrastructure can, in principle, co-exist with agricultural activity (referencing Navan Co-Ownership v. An Bord Pleanála [2016] IEHC 181).

(2) Core Ground 2 — No legal requirement to defer or condition approval pending the solar farm decision

The applicants argued that the inspector recommended the Commission “consider the status” of the solar farm application and that the planning authority suggested “prematurity”. The court treated the “failure to have regard” complaint as unsustainable: the Commission’s order expressly referenced the solar farm application and the dual-consent obligation, and it had the inspector’s report.

The decisive move, however, was to treat the applicants’ case as (in substance) seeking a new rule that a staged consent is unlawful unless there is “reasonable certainty” the remainder of the project will proceed, or unless explicit contingency conditions are imposed. Humphreys J. rejected this as:

  • Unsupported by statute or EU law (no sequencing mandate was identified),
  • Inconsistent with Treascon (staged consents inherently involve uncertainty), and
  • Unworkable for complex infrastructure (the court used the practical reality of large projects to show that such a rule would paralyse multi-consent development).

The court characterised the sequencing issue as falling within evaluative judgment: decision-makers may consider stranded-asset risk and potential conditions, but are not bound to treat such contingencies as “main issues” requiring express reasons in every case. The later grant of permission for the solar farm rendered the prematurity concern academic, though the court’s analysis was not confined to mootness.

(3) Core Ground 3 — Renewable-energy objectives can apply to enabling grid infrastructure even before the generator is consented

The applicants contended that objectives ET 13-14 and ET 13-21 were “conditional” (appropriate location, safeguards, proper planning considerations) and could not rationally support approval where the solar farm was still undetermined. The court treated this as largely a repackaging of the prematurity argument: the Commission did consider environmental and planning issues for the electricity transmission development, and was entitled to invoke pro-renewables policy (including climate-law obligations) that recognises the importance of associated electricity infrastructure.

The attempt to leverage Ashchurch into a general obligation to address all downstream contingencies and to impose Grampian-style conditions was rejected for the reasons already given: unworkability and mismatch with Ashchurch’s “leave out harms entirely” fact pattern.

3.3 Impact

(A) Planning practice: staged consenting and dual-consent projects

The judgment reinforces (at High Court level) that objections framed as “prematurity” will not readily translate into illegality where the statutory scheme contemplates separate consents. It is particularly significant for renewable and grid projects where generation and connection infrastructure may proceed on different statutory tracks and timelines.

(B) Development plan interpretation: “deemed zoning” is not a shortcut to stricter mapped zoning

The court’s insistence that residual “existing authorised use” zoning is conceptually distinct from a labelled zoning objective is likely to matter beyond Cork. Many plans contain residual provisions for non-mapped lands; this decision cautions against treating such provisions as importing the full suite of the “closest” mapped zoning category.

(C) Litigation discipline: workability and burden of proof

The judgment is also a signal case on workability and the inadmissibility of transforming merits concerns into bright-line legal rules that cannot operate at scale. Coupled with the reiterated onus principles, it raises the bar for speculative or structurally unworkable grounds in planning/environmental judicial review.

(D) Discretion and the climate context (obiter but pointed)

Although not determinative, the court’s willingness (counterfactually) to consider proportionality/discretion against quashing in the climate-emergency context—especially for “technical or procedural” errors—may influence how parties argue relief in future renewable-energy challenges, including how “real-world consequences” are placed before the court.

4) Complex Concepts Simplified

Dual consent

A project may require separate consents under different statutory routes (here, solar farm permission under the ordinary planning code, and grid/substation approval under s. 182A). Separate consents can be processed on different timelines; the law does not necessarily require them to be synchronised.

“Deemed zoning” versus a mapped zoning category

“Deemed zoning” provisions often operate as a residual rule: if land isn’t coloured/labeled on zoning maps, it is treated as governed by its existing authorised use. That is not the same thing as saying it falls into a specific mapped zoning category with its own distinct policy purpose and constraints.

Prematurity

In planning discourse, “prematurity” is an argument that a decision should wait until some other plan/permission is decided. The court held that, in staged-consent settings, “prematurity” does not become a legal veto unless a statute (or EU assessment law) actually demands such sequencing.

Grampian condition

A condition that prevents development from commencing until off-site works/other consents are secured. The judgment treats the use of such conditions in staged projects as a matter of evaluative planning judgment, not a routine legal requirement.

“Have regard to”

A statutory duty to consider a plan/policy is not always a duty to comply with it. Even where a plan points one way, a decision may remain lawful if the plan was considered and the statutory scheme permits departure.

Workability

Courts avoid adopting interpretations or supposed “rules” that cannot sensibly operate in the real world. Here, a requirement of “reasonable certainty” about future consents (or of addressing every possible contingency) was rejected as incapable of functioning for complex, multi-consent infrastructure.

5) Conclusion

Connolly and Anor v An Coimisiun Pleanala and Ors (Approved) [2026] IEHC 224 strengthens the legal architecture around staged consents in Ireland, especially within the dual-consent regime for renewable generation and grid infrastructure. It clarifies that residual “existing authorised use” zoning is not a doctrinal bridge to import stricter mapped zoning objectives, and it decisively rejects “prematurity” as a proxy legal rule requiring sequencing, “reasonable certainty”, or routine contingency conditioning. The judgment is also a notable restatement of judicial review discipline—onus, reasons, legality-not-merits—and a clear warning that unworkable bright-line rules will not be entertained, particularly where they would obstruct complex infrastructure consenting.