Undisclosed QCBS as a Curable Procedural Illegality in Advanced Public Works Tenders: No Cancellation Absent Mala Fides; Prospective Transparency Mandate
1. Introduction
This writ appeal before the Gauhati High Court (Kohima Bench jurisdiction) arose from a tender under the Pradhan Mantri Gram Sadak Yojna (PMGSY-III Batch-I, 2024-25),
where M/s Vertex Construction (appellant) challenged the award of contract to M/s S.N. Enterprise (respondent No.4).
The State of Nagaland and its PWD authorities (respondent Nos.1–3) were the procuring entities.
The core controversy was that the tender was evaluated using Quality and Cost Based Selection (QCBS) with a 60:40 technical-to-financial weighting,
even though this methodology was allegedly not disclosed in the NIT/Standard Bidding Document (SBD) and the minutes of the pre-bid meeting said to have adopted QCBS were not uploaded
or otherwise notified to bidders. The appellant asserted it was the L-1 (lowest-price) bidder and would have won under a price-only regime, but lost because QCBS was applied.
The appeal thus raised a classic tender-law tension: strict adherence to disclosed tender conditions versus restraint in judicial review where public projects are underway
and larger public interest would be harmed by disruption.
2. Summary of the Judgment
- The Division Bench acknowledged the principle that tender conditions are “the law of the tender” and that any methodology materially affecting inter se ranking should be disclosed upfront.
- It also recognized that non-disclosure of QCBS in the NIT/SBD was unfair and should not be approved as a practice.
- Nevertheless, the Court held that in the facts of the case, the lapse was a procedural illegality that did not automatically warrant setting aside the award, particularly since:
- the QCBS decision was taken in pre-bid meetings months before the NIT, when bidders were allegedly unknown;
- work had already commenced and was substantially progressed;
- the project was under a centrally funded scheme, and cancellation risked loss/lapsing of central funds and project derailment.
- The appeal was dismissed, but the Court issued a strong prospective caution: future tenders must clearly disclose the evaluation methodology, including any QCBS proposal.
3. Analysis
A. Precedents Cited
(i) On non-deviation from tender terms and the transparency mandate
The appellant relied on Dutta Associates Private Limited -Vs- Indo Merchantiles Private Limited & Ors. :: (1997) 1 SCC 53,
where the Supreme Court emphasized that a tendering authority cannot deviate from tender conditions to the prejudice of bidders.
The appellant also cited Naga Construction -Vs- East West Construction & Ors. :: (2019) 4 GLR 370,
a Division Bench decision reiterating that introduction of undisclosed criteria in evaluation offends Article 14 and the principle of transparency.
The Division Bench in the present case did not dispute these propositions in the abstract; instead, it distinguished the relief stage and context:
even where an undisclosed criterion is found, the court’s remedial response must be calibrated to public interest and project progress.
(ii) On limited judicial review in tenders and deference to administrative choices
The Court anchored its restraint in a line of Supreme Court authorities warning against converting judicial review into an appellate re-evaluation of tenders:
- Jagdish Mandal -Vs- State of Orissa & Ors. :: (2007) 14 SCC 517 (courts interfere only when decision is mala fide/arbitrary/irrational; public interest is central).
- Michigan Rubber (India) Limited -Vs- State of Karnataka & Ors. :: (2012) 8 SCC 216 (high deference in policy/contractual matters; limited grounds of interference).
- Banshidhar Construction Private Limited -Vs- Bharat Coking Coal Limited & Ors. :: (2024) 10 SCC 273 (reaffirming restraint; weigh equities and public impact).
The Court further relied on cases emphasizing non-interference where the contract is underway, absent fraud/mala fides:
- Tata Cellular -Vs- Union of India :: (1994) 6 SCC 651
- Raunaq International Limited -Vs- IVR Construction Limited :: (1999) 1 SCC 492
- Silppi Constructions Contractors -Vs- Union of India & Anr. :: (2020) 16 SCC 489
- M/s N.G. Projects Limited -Vs- M/s Vinod Kumar Jain & Ors. :: (2022) 6 SCC 127
- Kirloskar Ferrous Industries Limited & Anr. -Vs- Union of India & Ors. :: (2025) 1 SCC 695
These authorities shaped the Court’s remedial conclusion: even if a procedural lapse exists, the court should avoid relief that triggers administrative chaos,
derails public projects, or causes disproportionate harm to public interest.
B. Legal Reasoning
(i) “Tender conditions are the law of the tender” — and why the Court still declined to set aside
The Bench expressly accepted that “tender conditions constitute the law of tender” and that “any change in evaluation methodology, particularly the one that materially affects the inter-se ranking must be disclosed upfront.”
It also accepted that it would have been “more fairer” to disclose QCBS in the NIT/SBD or before evaluation and notify all bidders.
However, the Court characterized the omission as procedural illegality rather than a defect warranting the “nuclear remedy” of cancellation.
The reasoning proceeds on three interlinked findings:
-
Absence of mala fides/favouritism foundations:
since the QCBS decision was taken months before issuance of NIT/SBD “when it was not known as to who all will be the bidders,” the appellant could not plausibly ground a case of targeted manipulation.
-
Remedial proportionality:
courts may “disapprove” a lapse yet refuse a remedy that is disproportionate to the demonstrated wrong, especially where the challenge is “only on principle” without establishing fraud or corruption.
-
Public interest override in advanced-stage projects:
with substantial work progress and a PMGSY timeline (completion by March 2026), setting aside the contract risked loss of central funding and burdening the State with completion—an outcome the Court treated as outweighing the bidder’s procedural grievance.
(ii) Prospective correction as the chosen judicial tool
Instead of quashing the award, the Court adopted a compliance-forward remedy:
non-interference coupled with prospective directions that future tenders must clearly disclose evaluation methodology (including QCBS),
and authorities must upload/notify relevant pre-bid minutes or equivalent addenda/corrigenda.
This is significant: the Court effectively separated illegality identification from contract-disrupting relief,
making transparency a forward-looking obligation while preserving ongoing public works.
C. Impact
-
Remedial threshold in tender disputes is reinforced:
even where evaluation methodology was not properly disclosed, cancellation is not automatic—especially once the project has materially progressed and public funds/timelines are at stake.
-
Prospective transparency becomes judicially emphasized:
the judgment sends a clear compliance message to procuring authorities: evaluation methodology (including QCBS weightages) must be stated in the tender documents or formally notified.
-
Strategic litigation consequences:
bidders challenging tenders late (after work commencement) face a higher hurdle; they must demonstrate mala fides/fraud or such grave arbitrariness that public interest nonetheless demands disruption.
-
Operational lesson for procurement under schemes:
for centrally funded schemes with strict timelines, courts may be more reluctant to derail contracts, pushing disputes toward prospective correction and administrative accountability rather than retrospective cancellation.
4. Complex Concepts Simplified
- L-1 bidder
- The bidder quoting the lowest price. Many tenders award to L-1, but not all; some allow quality-based selection.
- QCBS (Quality and Cost Based Selection)
- An evaluation method combining technical quality and price. Here, technical and financial scores were combined in a 60:40 ratio, meaning the lowest price alone would not decide the winner.
- NIT / SBD
-
NIT is the Notice Inviting Tender; SBD is the Standard Bidding Document.
These set out the rules of participation and evaluation; bidders are entitled to rely on them.
- Addendum / Corrigendum
- A formal amendment/clarification to the tender documents. If evaluation methodology is changed or clarified after a pre-bid meeting, good procurement practice (and often the tender’s own clauses) requires issuing an addendum/corrigendum and notifying bidders.
- Article 14 (transparency and non-arbitrariness)
- The constitutional guarantee of equality, used in tender law to require fairness, non-discrimination, and transparency in state contracting.
- Procedural illegality vs. setting aside the contract
-
A procedural illegality is a defect in process (e.g., non-uploading minutes or non-notification).
Courts may still refuse to cancel a contract if cancellation would cause disproportionate harm to public interest—particularly once work has commenced—unless mala fides/fraud is shown.
- Judicial review in tender matters
- Courts review the decision-making process (fairness, legality, absence of mala fides), not the merits as if they were a tender appellate authority.
5. Conclusion
The judgment in M/S VERTEX CONSTRUCTION, v. THE STATE OF NAGALAND AND 3 ORS crystallizes a pragmatic rule in public procurement disputes:
undisclosed application of QCBS is condemnable and contrary to transparency, but where the project has substantially progressed and no mala fides/fraud is established, the defect may be treated as a curable procedural illegality not warranting cancellation.
The Court preserved the ongoing PMGSY work to protect public interest and central funding timelines, while issuing a clear prospective mandate for procurement authorities to
explicitly disclose evaluation methodology in future tenders.