Limitation for Section 18 Reference Cannot Be Defeated by State’s Failure to Notify Award and Tender Compensation

Case: GHULAM MOHAMMAD RAH AND ORS. v. UNION TERRITORY OF J AND K AND ORS. (REVENUE DEPARTMENT)

Court: Jammu and Kashmir High Court (Srinagar Bench)

Date: 04-03-2026

Coram: Hon’ble Mr. Justice Javed Iqbal Wani

1. Introduction

The petitioners, landowners at Nunwan, Pahalgam, challenged an order of the Collector Land Acquisition/ACR, Anantnag (respondent no. 8) rejecting their request for a court reference for enhanced compensation. Their land (10 kanals 03 marlas) had been acquired for the Pahalgam Development Authority, and an award was passed on 15.05.1982. The petitioners’ consistent grievance was that the award had been made “at their back”, without notice, and that compensation was neither tendered nor paid despite repeated litigation and contempt proceedings.

The central issues before the High Court were:

  • Whether the Collector could reject the petitioners’ request for a reference under Section 18 of the J&K Land Acquisition Act, 1990 (1934 AD) as time-barred, when notice/payment events were not established.
  • How to characterize the petitioners’ application dated 27.10.2017 (seeking payment “under protest” to enable a reference) versus the later application dated 15.11.2023 (expressly seeking a Section 18 reference).
  • The effect of the State’s failure to tender compensation, issue notice, and/or properly deposit compensation in court under Section 32.

2. Summary of the Judgment

The High Court allowed the writ petition, quashed the Collector’s order dated 01.07.2023, and directed respondent no. 8 to treat the petitioners’ application dated 15.11.2023 as an application under Section 18 and to forward it to the Principal District Judge, Anantnag within six weeks.

The Court found the impugned rejection “grossly misconceived and misplaced” because:

  • The record did not show that the petitioners were informed of the award dated 15.05.1982 or were called to receive compensation.
  • The respondents’ own record (including notices dated 27.12.2023) suggested compensation had not been paid earlier.
  • The 27.10.2017 application was not, in substance, a Section 18 reference application; it sought payment to enable receipt “under protest” and then to seek reference.
  • The delay was not attributable to the petitioners in the factual matrix where the statutory scheme required tender/deposit and notice.

3. Analysis

3.1 Precedents Cited (and Prior Proceedings Relied Upon)

The judgment is notable for deciding the controversy primarily from the statutory text (Sections 18 and 32) and the procedural history, rather than by applying named reported precedents. The “precedential” influence appears in two forms: (i) the Court’s reliance on its own prior order between the parties, and (ii) an unnamed Supreme Court holding mentioned in the narrative.

  • OWP No.632/2015 (judgment and order dated 04.10.2017):
    • This earlier decision formed the backbone of the present reasoning. It had refused the petitioners’ prayer for alternate land (Section 32(3)) based on the respondents’ plea of non-availability, but it simultaneously emphasized the Collector’s statutory obligation to deposit the awarded amount “immediately and forthwith” and to notify interested persons to collect compensation.
    • Crucially, OWP No.632/2015 also reserved the petitioners’ liberty to pursue remedies under the Act of 1990—setting the stage for the Section 18 controversy.
  • The “judgment by the Apex Court” (case title not specified in the text):
    • The petitioners withdrew WP(C) No.1450/2022 in light of this Supreme Court holding that acquisitions initiated in the erstwhile State of J&K before the J&K Reorganization Act, 2019 continue to be governed by the Act of 1990, not the 2013 Act.
    • Although not a cited authority by name, its practical effect was decisive: it restored the Act of 1990 as the governing statute for the petitioners’ remedy framework (including Sections 18 and 32).
  • CCP(S) No.510/2022 in OWP No.632/2015 and related contempt history:
    • The contempt proceedings were used evidentially to test the respondents’ claim of payment/deposit. The respondents’ stand there—that compensation was forwarded/deposited only around May–August 2022—supported the Court’s inference that compensation had not been duly tendered earlier.
    • The subsequent return of the deposit from the Principal District Judge, Anantnag (due to “non-pendency of any reference proceedings”) illustrated a procedural deadlock created by the administration’s sequencing: deposit without an active reference, and denial of reference as time-barred.

3.2 Legal Reasoning

(A) The Court’s core factual finding: absence of proof of notice/tender.

Section 18(2) ties limitation to either (i) presence/representation at the time of award (six weeks from award), or (ii) receipt of notice under Section 12(2) (six weeks), subject to an outer limit of six months from award (whichever expires first). Against this, the High Court recorded that it was “not forthcoming from the record” that the petitioners were informed of the award or asked to receive compensation. This was not treated as a minor omission: it went to the legitimacy of the Collector’s time-bar objection.

(B) Section 18 as a “valuable right” and the role of natural justice.

The Court characterized the Section 18 reference mechanism as a “valuable right” of a person whose land is acquired. It further held that while deciding an application for reference, the “basic principles of natural justice” must be observed. In this case, a rigid limitation objection was held unsustainable where the State failed to demonstrate foundational fairness: notice of award and a meaningful opportunity to pursue the statutory remedy.

(C) Interlocking operation of Sections 18 and 32: protest, payment, and State default.

The Court read Section 18 together with Section 32 to emphasize the acquisition authority’s duties after the award: tender payment (Section 32(1)) and deposit in court in specified contingencies (Section 32(2)). The Court stressed that for an owner to effectively invoke Section 18 in the statutory ecosystem, the owner must have knowledge of the award and, where compensation is received, it must be “under protest” to preserve reference rights (as reflected in the provisos to Section 32(2)).

On the Court’s analysis, the petitioners’ inability to proceed earlier was causally linked to the respondents’ default: compensation was not actually paid, and the administrative record did not establish legally meaningful notice.

(D) Correct characterization of the 27.10.2017 application.

A key move in the reasoning was the Court’s classification of the petitioners’ 27.10.2017 application. The Collector treated it as a belated Section 18 request and rejected it on 01.07.2023 as time-barred. The High Court disagreed: the 27.10.2017 application was “in essence” not an application seeking reference, but a request for payment so the petitioners could receive it “under protest” and then seek a reference.

This distinction mattered because it exposed a category error in the impugned order: the Collector rejected a request for payment-enabling steps as if it were the reference itself, and then used limitation to foreclose the statutory pathway.

(E) The operative legal direction: treat 15.11.2023 as the Section 18 application.

The Court held that the Collector had not rejected the “actual application” seeking reference (15.11.2023) and therefore directed that it be treated as a Section 18 application and forwarded to the Principal District Judge, Anantnag. This is the practical doctrinal outcome: where the record shows the administration’s failure to tender/notify and a misconstruction of the landowner’s earlier request, the reference right should not be defeated by an erroneous limitation rejection.

3.3 Impact

  • Constraint on limitation objections in legacy acquisitions: In long-past awards (here, 1982), the State’s limitation defence will be scrutinized against its own compliance with statutory duties of tender/deposit and notice. A mere assertion of “time-bar” is vulnerable if the record does not evidence notice and tender/payment conduct.
  • Substance-over-form handling of landowner applications: Collectors must read applications contextually. Requests that seek compensation “under protest” as a precursor to reference cannot be mechanically treated as the reference itself, and then rejected on limitation.
  • Administrative sequencing discipline: The case highlights a recurrent institutional problem: depositing compensation without an active reference, followed by return of deposit for “non-pendency,” can trap landowners in a procedural loop. The judgment pushes the administration toward a legally coherent sequence—tender/payment and processing of reference requests consistent with Sections 18 and 32.
  • Continuity of the Act of 1990 post-reorganization (as narrated): For acquisitions initiated pre-2019, litigants and authorities in J&K must continue to use the Act of 1990 remedial architecture, including Section 18 references, rather than shifting to the 2013 Act solely due to the reorganization.

4. Complex Concepts Simplified

  • Writ of certiorari: A High Court order quashing an illegal or procedurally defective decision of a public authority (here, quashing the Collector’s rejection order dated 01.07.2023).
  • Writ of mandamus: A High Court command directing a public authority to perform its legal duty (here, directing forwarding of the reference application to the civil court).
  • “Reference” under Section 18: A statutory route by which an aggrieved landowner asks the Collector to send the dispute (measurement, compensation amount, entitlement, apportionment) to the civil court for adjudication.
  • “Under protest” (Section 32 proviso): If a landowner takes compensation without recording protest, they may lose the right to seek a Section 18 reference. Taking it “under protest” preserves the ability to challenge adequacy of compensation.
  • Deposit in court (Section 32(2)): If compensation cannot be paid due to refusal, incapacity, or dispute, the Collector must deposit it in the court where a Section 18 reference would lie—so funds remain secured and available for lawful disbursement.
  • Natural justice (in this context): At minimum, fairness through notice and a genuine opportunity to assert statutory rights; the Court treated the absence of record proof of notice/tender as undermining a strict limitation-based denial.

5. Conclusion

The judgment’s significance lies in its practical rule of fairness in acquisition administration: a landowner’s Section 18 reference right—described as a valuable right—cannot be nullified through a limitation objection when the State cannot demonstrate that it gave notice of the award and meaningfully tendered/handled compensation in the manner contemplated by Sections 18 and 32. By quashing the Collector’s misconceived rejection and directing that the later, explicit application (15.11.2023) be forwarded as a Section 18 reference, the Court reinforces a substance-based, rights-protective approach to legacy land acquisition disputes in J&K under the Act of 1990.