Letters of Intent Create Contractual (Not Writ-Enforceable) Rights; Contractors Cannot Mount “Proxy” Challenges to Inter-Agency Project Transfers
Case: M/S Anu Enterprises Thru.Proprietor Anu Singh v. State Of U.P. Thru. Addl. Chief Prin. Secy. Secondary Edu. Lko. And 6 Others
Court: Allahabad High Court, Lucknow Bench (Court No. 3)
Date: 28-07-2026
Coram: Hon'ble Shekhar B. Saraf, J. and Hon'ble Abdhesh Kumar Chaudhary, J.
Proceeding: Writ - C No. 7398 of 2026 (Article 226)
1. Introduction
The petitioner, M/S Anu Enterprises, was declared successful in tenders invited by respondent no. 3,
the Uttar Pradesh State Construction and Infrastructure Development Corporation, for construction of two
Mini Indoor Stadiums at (i) Pandit Deen Dayal Upadhyay Rajkiya Model Inter College, Khajuri, Ambedkar Nagar and
(ii) Rajkiya Inter College, Akbarpur, Ambedkar Nagar. Letters of Intent (LOIs) were issued on 21.04.2026 and 22.04.2026.
Shortly thereafter, by a Government communication dated 29.04.2026, the Special Secretary directed that
U.P. Projects Corporation Limited (respondent no. 7) would act as the nodal agency instead of respondent no. 3.
Consequentially, the petitioner was restrained from executing the allotted works and respondent no. 7 floated
short-term e-tenders dated 30.06.2026 for the same projects.
The key issue before the High Court was whether the petitioner could enforce, under Article 226, rights said to
have accrued from the tender award/LOIs and challenge the Government’s inter-agency transfer and the fresh tenders,
or whether the petitioner must pursue ordinary contractual remedies (arbitration/civil suit).
2. Summary of the Judgment
Holding: The writ petition was dismissed. The Court held that the petitioner’s grievance was essentially
contractual and not enforceable under Article 226; the petitioner’s remedy lies in arbitration or civil proceedings
(e.g., damages/loss of profit) against respondent no. 3. Further, the petitioner could not indirectly challenge the
Government’s decision (directed at respondent no. 3) through a writ—this would amount to impermissible “proxy litigation.”
2.1 Reliefs sought and outcome
- Certiorari to quash Government communication dated 29.04.2026: Denied.
- Certiorari to quash e-tenders dated 30.06.2026 issued by respondent no. 7: Denied.
- Mandamus to allow completion of work under LOIs: Denied.
- Liberty to pursue contractual remedies (arbitration/civil suit) against respondent no. 3: Granted.
3. Analysis
3.1 Precedents Cited (and their role in the decision)
(a) Bareilly Development Authority v. Ajai Pal Singh, AIR 1989 SC 1076
This case was used as a foundational authority for the proposition that purely contractual, non-statutory rights
are ordinarily not enforceable by a writ under Article 226. The High Court relied on it to categorize the petitioner’s claims
as arising from a private law contract (tender/LOI arrangement), thereby pushing the dispute out of writ territory.
(b) Kerala State Electricity Board and another Vs. Kurian E. Kalathil and others, 2000(6) SCC 293
The Court invoked this precedent to reinforce that breach of contractual terms is ordinarily not remedied by writ,
and must be decided under ordinary contract law principles. This supported the Court’s refusal to adjudicate allegations that
the petitioner was wrongfully prevented from executing the work post-LOI.
(c) State of U.P. and others v. Bridge & Roof Co.; AIR 1996 SC 3515
Quoted for the clear rule that where the contract is in the realm of private law (non-statutory),
disputes regarding interpretation/enforcement of contractual terms should go to arbitration or civil court.
The High Court used this to emphasize that resolving the petitioner’s grievances would require interpreting contractual conditions,
which is unsuitable for a writ court.
This decision was cited to reiterate that disputes involving interpretation of terms and conditions cannot be examined under Article 226,
and must be adjudicated before the appropriate forum (civil court/arbitration/tribunal as applicable).
The High Court relied on it to explain that the present petition would inevitably require contractual interpretation.
(e) Rajasthan State Industrial Development and Investment Corporation and Anr. v. Diamond and Gem Development Corporation Ltd. and Anr.; 2013(5) SCC 470
The Court cited this as a consolidating authority reaffirming that contractual disputes and enforcement of contract terms do not lie in writ jurisdiction.
It functioned as a doctrinal “capstone” to the earlier authorities.
Though that case discusses the discretionary nature of entertaining writ petitions and the significance of alternative forums,
the High Court used it (together with older authority) to underscore a principle of self-imposed restraint:
when an efficacious alternative remedy exists, writ jurisdiction should not become a substitute route.
(g) Thansingh Nathmal v. A. Mazid, Superintendent of Taxes, AIR 1964 SC 1419
The Constitution Bench passage was quoted to emphasize that Article 226 is discretionary, and is not meant to bypass
statutory/ordinary remedial machinery; writ courts generally avoid fact-heavy inquiries requiring elaborate evidence.
This supported the Court’s conclusion that the petitioner should be left to ordinary contractual remedies.
(h) Subodh Kumar Singh Rathour v. Chief Executive Officer and others reported in 2024(7) SCR 532 : 2024 AIR (SC) 3784
The petitioner relied on this Supreme Court authority to argue that accrued rights post-tender/LOI could not be taken away as done here.
The High Court, however, held that the cited judgment lays down “general principles” and is distinguishable on facts,
and therefore did not assist the petitioner in the “peculiar facts and circumstances” of this case.
3.2 Legal Reasoning
(i) Characterization of the dispute: private law contract, not public law wrong
The Court treated the petitioner’s complaint—being prevented from executing work after LOIs—as one essentially of
breach/non-performance of contractual obligations arising out of the LOIs and connected tender conditions.
Such claims typically require examination of contractual terms (scope, obligations, consequences of administrative changes, termination/novation clauses, risk allocation, etc.).
The Court held that Article 226 is not the forum for this exercise.
(ii) Locus and the “proxy litigation” bar
A significant strand of reasoning is the Court’s view that the Government’s letter dated 29.04.2026 was an action
“upon” respondent no. 3 (changing the nodal agency). If anyone was to challenge that administrative transfer decision
as an institutional grievance, it would be respondent no. 3. The Court held that respondent no. 3 “cannot be permitted
to indulge in proxy litigation through the petitioner.” In other words, the petitioner could not use its contractual position
as a vehicle to litigate respondent no. 3’s public law grievance about being replaced as executing agency.
(iii) Alternative remedies: arbitration/civil suit for damages and consequential reliefs
The Court expressly preserved the petitioner’s liberty to seek compensation (loss of profit) and other consequential reliefs
by invoking the arbitration clause or by instituting appropriate civil proceedings against respondent no. 3.
This frames the petitioner’s dispute as one of remedial substitution: not “restore me the contract by writ,” but
“claim contractual damages/remedies before the proper forum.”
(iv) Refusal to compel performance by mandamus
The Court reaffirmed the principle that it will not issue directions under Article 226 to compel authorities to “remedy a breach of contract, pure and simple.”
Consequently, mandamus to allow completion of the work under the LOIs was refused.
3.3 Impact
-
Reinforcement of the “contractual disputes” bar in writ jurisdiction:
The decision adds to the consistent line that tender/LOI-based disputes—where the remedy turns on contract interpretation or alleged breach—belong to arbitration/civil courts.
-
Proxy litigation doctrine in tender execution disputes:
By expressly disallowing indirect challenge to an inter-agency transfer (where the primary affected entity is the erstwhile nodal agency),
the judgment may be cited to resist writ petitions where contractors attempt to challenge governmental administrative restructuring that primarily concerns the State and its agency.
-
Practical consequence for contractors:
Even if fresh tenders are floated after an LOI, contractors may have to pivot from “restoration” strategies in writ to
“damages and contractual remedies” strategies before the agreed forum.
-
Administrative flexibility preserved:
The State’s ability to change implementing/nodal agencies for project execution is less likely to be injuncted at the instance of a contractor in writ proceedings,
absent a clear public law element or statutory violation (not found here).
4. Complex Concepts Simplified
-
Article 226 (Writ Jurisdiction): A constitutional power of High Courts to remedy public law wrongs (illegality, arbitrariness, breach of statutory duty).
It is discretionary and not meant to replace ordinary civil/adjudicatory mechanisms for private law disputes.
-
Certiorari: A writ used to quash an order/decision. Here, the petitioner sought to quash the Government communication and subsequent tenders.
-
Mandamus: A writ commanding a public authority to perform a public duty. Courts generally do not use mandamus to enforce
performance of a non-statutory contract as if it were a public duty.
-
Letter of Intent (LOI): Commonly indicates intent to award/work; whether it constitutes a concluded contract depends on terms and subsequent steps.
In this case, regardless of LOI status, the Court treated the dispute as contractual and remediable through arbitration/civil court, not writ.
-
Non-statutory contract: A contract not created/regulated as a statutory instrument; it is governed mainly by the Contract Act (private law),
making writ enforcement generally inappropriate.
-
Alternative remedy: Where the law/contract provides another effective route (e.g., arbitration), High Courts usually decline writ intervention.
-
Proxy litigation: Litigation brought by one party to indirectly vindicate the rights/grievance of another party who should sue in its own name.
The Court held respondent no. 3 cannot litigate through the petitioner.
5. Conclusion
The Allahabad High Court’s decision firmly locates tender/LOI execution disputes within the domain of contract law remedies,
not writ enforcement. Two takeaways stand out: (1) a contractor cannot ordinarily use Article 226 to enforce LOI-derived contractual expectations
or to compel continuation of contractual work; and (2) a contractor cannot indirectly challenge an administrative decision that primarily affects
the nodal agency—doing so risks being treated as impermissible proxy litigation. The judgment thereby preserves the doctrinal boundary
between public law review and private law contract enforcement, while keeping open the contractor’s path to damages/compensation before the appropriate forum.