Defining “Construction and Design of Improvements” Under the Springfield Water Special Act: Fact-Specific PWA Coverage and No Metcalf Incompatibility
Case: Nicholls v. Veolia Water Contract Operations USA, Inc. (1st Cir. Aug. 19, 2026)
Court: United States Court of Appeals for the First Circuit
Key Statutes: Massachusetts Prevailing Wage Act (“PWA”), Mass. Gen. Laws ch. 149, §§ 26-27H (2024); 1997 Mass. Acts ch. 155 (“Special Act”), § 6
I. Introduction
This appeal arises from a prevailing-wage dispute involving four Veolia employees (Jeremiah Nicholls, Walter Goodrow, Wesley Dinsmore, and Richard Ruppert)
who performed repair and replacement work at wastewater facilities operated under Veolia’s service contract with the Springfield Water and Sewer Commission
(“Commission”). The Commission entered the contract pursuant to a 1997 “Special Act,” which preserves PWA coverage for work falling within “the construction and
design of improvements.”
The district court (sitting in diversity) granted summary judgment to Veolia on two legal premises: (1) that the employees’ second-stage work (ongoing operations,
maintenance, repair, and replacement) categorically could not qualify as “construction and design of improvements” under § 6 of the Special Act; and (2) that
applying the PWA would be “unworkable” under reasoning drawn from the Massachusetts Supreme Judicial Court’s decision in Metcalf v. BSC Group, Inc.
On an earlier appeal, the First Circuit certified two questions of Massachusetts law to the SJC. After the SJC answered both questions in ways that rejected the
district court’s legal premises, the First Circuit addressed the consequences: whether summary judgment could still be affirmed on the existing record or whether
the case must return to the district court for a fact-intensive classification of the employees’ tasks under the SJC’s clarified standard.
II. Summary of the Opinion
The First Circuit reversed the summary-judgment order for Veolia, vacated the judgment, and remanded. The court held that, in light of the SJC’s answers:
-
The district court’s categorical exclusion of the plaintiffs’ second-stage work from “construction and design of improvements” could not stand, because the SJC
adopted a technical, property-law meaning of “improvements” that requires a task-specific inquiry and is not defined by contract labels (such as “ICI”).
-
The district court’s reliance on Metcalf v. BSC Group, Inc. to find an incompatibility between the Special Act procurement scheme and the PWA was
foreclosed; the SJC held the Special Act is not incompatible with the PWA and that Metcalf does not control.
-
Veolia’s attempts to salvage affirmance by claiming factual “concessions” and by recharacterizing the SJC’s opinion were contradicted by the record and by the
SJC’s explicit reservation of disputed factual questions regarding the employees’ day-to-day tasks.
The First Circuit emphasized that it is for the district court “in the first instance” to decide whether and to what extent the disputed repair and replacement work
constitutes “construction and design of improvements” under § 6 as construed by the SJC, and to resolve any remaining factual and legal issues.
III. Analysis
A. Precedents Cited
1. Nicholls v. Veolia Water Cont. Operations USA, Inc., 144 F.4th 354 (1st Cir. 2025)
This is the First Circuit’s earlier decision in the same litigation, primarily important here for two reasons. First, it set out the factual and statutory background
and framed the dispositive uncertainties in Massachusetts law that warranted certification. Second, it contained a waiver/abandonment statement: the First Circuit
noted it understood Veolia to have “abandoned” an argument that Veolia could not be liable under the PWA because the service contract did not require prevailing
wages. In the 2026 opinion, the court relies on that earlier characterization to refuse Veolia’s attempt to “revive” the defense on remand of the certified-question
answers.
2. Nicholls v. Veolia Water Cont. Operations USA, Inc., 281 N.E.3d 966 (Mass. 2026)
The SJC’s certified-question decision is the controlling legal development. The First Circuit treats the SJC’s holdings as eliminating the two legal foundations of
the district court’s summary judgment:
-
Meaning of “construction and design of improvements” (§ 6): The SJC held the phrase is not synonymous with “construction” as defined by
the PWA and instead uses the “technical meaning of ‘improvements’ as it pertains to property.”
-
Compatibility with the PWA / Metcalf: The SJC held the Special Act is not incompatible with the PWA and that “Metcalf does not
control” the Special Act’s application or its compatibility.
Critically, the SJC also expressly declined to decide which specific tasks performed by Veolia employees qualify under the clarified definition, noting the parties’
dispute about the scope of day-to-day work and stating those disputes did not affect the answers to the certified questions.
3. Metcalf v. BSC Group, Inc., 214 N.E.3d 1043 (Mass. 2023)
Metcalf supplied the district court’s “unworkability” rationale: concern that a “retrospective, fact-intensive inquiry into the work performed by each employee”
would be impractical and unsupported by the PWA. The First Circuit, however, treats Metcalf as sidelined in this statutory context because the SJC
distinguished it. Unlike the statute in Metcalf, the Special Act expressly contemplates that some work under the Commission’s arrangements remains governed by
the PWA—namely, “construction and design of improvements”—which necessarily implies some classification at the work/task level.
The upshot is not that Metcalf is irrelevant to prevailing-wage doctrine generally, but that it cannot be used as a broad veto against applying the PWA
whenever a service contract includes mixed duties.
4. Summary-judgment and remand authorities: Friedman v. Cent. Me. Power Co., 174 F.4th 233 (1st Cir. 2026); Appleton v. Nat'l Union Fire Ins., 145 F.4th 177 (1st Cir. 2025); LimoLiner, Inc. v. Dattco, Inc., 839 F.3d 61 (1st Cir. 2016); Bos. Gas Co. v. Century Indem. Co., 588 F.3d 20 (1st Cir. 2009)
These cases supply the appellate framework:
-
Friedman and Appleton anchor the de novo standard of review and the principle that summary judgment is proper only when there is no genuine dispute
of material fact and the movant is entitled to judgment as a matter of law.
-
LimoLiner and Bos. Gas Co. support the proposition that, where an appellate court’s legal clarification exposes unresolved factual and legal issues,
the district court should decide them “in the first instance” on remand.
B. Legal Reasoning
1. The district court’s “categorical exclusion” approach is incompatible with the SJC’s definition
The First Circuit’s central move is to align the litigation posture with the SJC’s interpretive choice. The district court had effectively treated “construction and
design of improvements” as coextensive with contract-defined ICI (Initial Capital Improvements) and, conversely, treated “repair and replacement” as categorically
outside § 6. The SJC rejected a contract-label approach by adopting a property-law definition of “improvement” and by drawing a line that is functional rather than
formal: improvements are “valuable addition[s]” or “amelioration[s]” beyond “mere repairs or replacement,” intended to enhance value/utility or adapt property for new
or further purposes.
The First Circuit therefore concludes that the district court’s legal framing cannot survive. Under the SJC’s reading, the relevant inquiry is not whether the work is
performed during the “second stage” of the contract, but whether specific tasks—potentially even within a maintenance/replacement article—rise to the level of
“improvements” as that term is technically understood.
2. Record-based rebuttal: no binding “concession” that all plaintiffs’ work is excluded
Veolia attempted to preserve affirmance by recasting the plaintiffs’ summary-judgment admission (that they did not perform contract-defined ICI or ICI Design-Build
work) as a broader concession that they performed only the types of tasks the SJC said are excluded (ordinary repairs, routine inspections, day-to-day operations and
maintenance, or ordinary replacements). The First Circuit rejects this as contrary to the record: the admission was limited to ICI categories, and plaintiffs had
consistently maintained that some of their second-stage work qualifies as “construction and design of improvements.”
The opinion also underscores that the contract’s own structure cuts against a simplistic classification: Article 8 is titled “Maintenance, Repair and Replacement,” but
it distinguishes “Ordinary Maintenance” from “Major Maintenance, Repair and Replacements,” some of which may be “structural” or “capital” in nature. The court cites
a concrete example from the record (a work order for a “PROJECT” to fabricate and install a PVC/stainless piping system) to illustrate why task-level analysis remains
necessary—without prejudging how any task should ultimately be classified.
3. Metcalf cannot supply an “incompatibility” escape hatch
The district court’s second premise—administrative “unworkability” under Metcalf—is directly foreclosed by the SJC’s answer to the second certified question.
The First Circuit treats the SJC’s statement (“Metcalf does not control”) as dispositive: whatever Metcalf’s concerns in other procurement settings,
the Special Act explicitly preserves prevailing-wage governance for a defined subset of work, meaning that some classification is contemplated by the statute itself.
4. Waiver/abandonment: Veolia cannot reintroduce a contract-only defense
Veolia suggested that, even if the Special Act does not exempt the contract from the PWA, it cannot be liable because the service contract does not require payment of
prevailing wages. The First Circuit refuses to entertain this as a renewed basis for affirmance, citing its earlier statement that Veolia had “abandoned” that defense.
The doctrinal significance is procedural but meaningful: parties generally cannot resurrect waived or abandoned theories after certification clarifies the law and the case
returns to the appellate court, particularly when the prior appeal put the parties on notice about the abandonment characterization.
C. Impact
1. A clarified, property-law-based threshold for prevailing-wage coverage under the Special Act
In practical terms, the decision operationalizes the SJC’s definition by requiring lower courts to evaluate whether particular repair/replacement tasks amount to
“improvements” rather than relying on contract phases or headings. This invites litigation and compliance attention around boundary questions—especially where service
contracts include “major” replacements that may be structural/capital in nature.
2. Limits on using Metcalf to avoid PWA application in mixed-work arrangements
The First Circuit’s remand, coupled with the SJC’s incompatibility holding, signals that “unworkability” arguments cannot categorically defeat prevailing-wage claims
when the governing statute affirmatively preserves PWA coverage for a subset of work. Future defendants in Massachusetts prevailing-wage disputes may still invoke
administrability concerns, but they will need to do so within the statutory scheme as construed—not as a general objection to task-by-task analysis.
3. Incentives for careful task documentation and contract administration
Because the remand anticipates a task-specific inquiry, public entities and contractors operating under special acts (and analogous enabling statutes) may face stronger
incentives to:
- Define and document “major” versus “ordinary” work with operational clarity;
- Maintain work orders and project scopes that can support classification under the “improvement” standard;
- Evaluate whether certain replacements (e.g., system upgrades, structural retrofits) could be treated as improvements even within an operations contract.
IV. Complex Concepts Simplified
-
Prevailing Wage Act (PWA): A Massachusetts law requiring certain public works to pay workers at wage rates set to reflect prevailing local wages for
comparable work.
-
Special Act (§ 6) and “construction and design of improvements”: A statute specific to the Springfield Water and Sewer Commission that preserves PWA
coverage for a defined category of work. After the SJC’s interpretation, the key question is whether a task is an “improvement” in the property-law sense—more than
ordinary repair or ordinary replacement and aimed at enhancing value/utility or adapting for new/further purposes.
-
Certification to the SJC: A process where a federal court asks a state’s highest court to answer unsettled questions of state law that are important
to resolving the federal case.
-
Summary judgment: A pretrial ruling granted only when no material facts are genuinely disputed and the moving party is entitled to win as a matter of
law. Here, the SJC’s answers showed the district court used incorrect legal standards, and factual disputes about what work was actually performed remained.
-
De novo review: The appellate court reviews the summary-judgment decision fresh, without deferring to the district court’s legal conclusions.
V. Conclusion
The First Circuit’s 2026 decision implements the SJC’s clarified construction of § 6 of the 1997 Special Act and resets the case for a fact-specific determination.
The core takeaways are:
-
“Construction and design of improvements” under the Special Act turns on a technical, property-law concept of “improvements,” not on contract-defined phases or
labels.
-
The Special Act is not incompatible with the PWA, and Metcalf v. BSC Group, Inc. cannot be used to categorically defeat PWA coverage in this statutory
setting.
-
Where the record plausibly supports that some “repair and replacement” work may be structural/capital in nature, summary judgment is inappropriate; the district
court must classify the tasks under the SJC’s standard and resolve remaining issues on remand.