Colorado Public Works Act: Disputed/Unliquidated Delay Claims Permitted in Verified Statements; Excessive-Claim Forfeiture Limited to Statutory Remedies

Introduction

Ralph L. Wadsworth Construction Company, LLC (a subcontractor) and Regional Rail Partners and related entities (the design-build contractor team and surety, collectively “Defendants”) disputed payment stemming from delays and disruptions on the RTD North Metro Rail Line project. The case arose after Wadsworth filed a verified statement of claim under the Colorado Public Works Act, §§ 38-26-101 to -110, C.R.S. (2025), seeking payment from public funds retained on the project (later substituted with a surety bond).

Two issues drove the Supreme Court’s review: (1) whether a verified statement of claim may include disputed or unliquidated amounts—particularly delay and disruption damages—and (2) whether the penalty for filing an “excessive” claim under § 38-26-110 is forfeiture of all legal remedies or only forfeiture of statutory remedies created by the Public Works Act.

The trial court found Wadsworth’s claim not excessive and awarded damages after a bench trial. The court of appeals reversed, holding the claim excessive as a matter of law and concluding Wadsworth forfeited recovery of the amounts included in the claim. The Colorado Supreme Court reversed the division.

Summary of the Opinion

The Court held:

  1. Disputed or unliquidated amounts may be included in a verified statement of claim under § 38-26-107(1), including delay and disruption damages, so long as those amounts fall within the statute’s covered categories (e.g., labor, materials, equipment) used in the prosecution/performance of the work and the filing is not “excessive” under § 38-26-110.
  2. If a claim is “excessive” under § 38-26-110, the claimant forfeits only the statutory rights and remedies provided by the Public Works Act—not all common-law or other legal remedies.

Applying these principles, the Court deferred to the trial court’s fact findings and concluded the trial court did not clearly err in determining Wadsworth’s claim was not excessive on this record. The case was remanded to the court of appeals to address cross-appeal issues it had not reached.

Analysis

Precedents Cited

1) Statutory interpretation framework

  • People in Int. of B.C.B. (de novo statutory construction; plain meaning; harmonize the statutory scheme; avoid surplusage and absurdity). The Court invoked this to anchor a text-and-structure reading of §§ 38-26-107 and -110 rather than importing extra limitations (e.g., a “no disputes allowed” rule) not found in the statute.
  • People v. Hudson (ambiguity permits use of interpretive tools beyond plain text). The Court used Hudson to justify consulting legislative history and related statutory analogues when construing the ambiguous forfeiture phrase “all rights to the amount claimed.”

2) Appellate deference to trial-court fact finding

  • French v. Centura Health Corp. and Lo Viento Blanco, LLC v. Woodbridge Condo. Ass'n (trial court fact findings stand unless clearly erroneous/unsupported by the record). These cases supplied the doctrinal reason the Supreme Court would not replace the trial court’s view of whether there was a “reasonable possibility” amounts were due—an inquiry keyed to the time of filing and to record evidence.

3) Purpose and structure of Public Works Act remedies

  • W. Metal Lath, a Div. of Triton Grp., Ltd. v. Acoustical &Constr. Supply, Inc. (Public Works Act provides lien-like protection on public projects because mechanics’ liens do not attach to public property; § 38-26-107 creates the retained-funds remedy). The Court relied on this to frame the Act as remedial and protective, making an interpretation that excludes disputed sums (a common construction-project reality) inconsistent with the Act’s function.
  • City of Westminster v. Brannan Sand &Gravel Co. (the Act protects suppliers on public works; mechanics’ liens don’t apply to public projects). This reinforced the Court’s explanation for why the statute’s language must be read to provide workable protection on public work, not a fragile remedy that evaporates whenever payment is disputed.
  • South-Way Constr. Co. v. Adams City Serv. (Public Works Act stands in lieu of mechanics’ lien protections on public projects). The Court used this “statutory substitute” concept to justify reading the Public Works Act in parallel with the Mechanics’ Lien Act when deciding the scope of forfeiture.

4) “Excessive” claim doctrine and time-of-filing perspective

  • E.B. Roberts Constr. Co. v. Concrete Contractors, Inc. (excessiveness evaluated in light of information available at filing; later-awarded lesser amount does not automatically make the claim excessive). This was central: the Supreme Court rejected the court of appeals’ tendency to infer excessiveness from disparity between the filed amount and the trial award, emphasizing the statute’s mens rea and reasonableness components.
  • Galiant Homes, LLC v. Herlik (parallel mechanics’ lien language; similarly recognizes that ultimate recovery may be less without making the lien “excessive” at filing). The Court used it to show consistency across lien-like regimes.
  • Byerly v. Bank of Colorado (excessive lien where claimant knew conditions precedent had not occurred, so no reasonable possibility the amount was due). The Court distinguished Byerly: conditions precedent address when payment becomes due, whereas disputed/unliquidated amounts address what is due. That distinction undercut the division’s view that “due” necessarily excludes disputed sums.

5) Limits on lienable/claimable components (value-added vs. consequential damages)

  • In re Regan (lien rights attach to labor/materials that add value to property, under similar mechanics’ lien phrasing). The Court used this as an analogue to reinforce that § 38-26-107 is about reimbursing project inputs (labor/materials/equipment), not every downstream economic harm.
  • Tabor v. Armstrong (mechanics’ lien covers labor actually performed and materials actually furnished). This supported the Court’s line-drawing: delay/disruption damages are includable only to the extent they represent increased costs of labor/materials/equipment actually used in prosecuting the work, not purely consequential losses.

6) Forfeiture scope and legislative mirroring of mechanics’ lien penalties

  • Frazier v. People (statutory title can aid interpretation). The Court used this to support reliance on the 2003 act’s title emphasizing consistency with mechanics’ lien requirements, strengthening the conclusion that forfeiture should be similarly limited.
  • Honnen Equip. Co. v. Never Summer Backhoe Serv., Inc. and Barnes v. Colo. Springs &C. C. D. Ry. Co. (mechanics’ lien excessive-claim provisions aim to deter/punish bad-faith overstatement; willful falsity matters). These cases reinforced that the forfeiture mechanism is a bad-faith deterrent within the statutory lien-like remedy, not a universal annihilation of substantive contract rights.

Legal Reasoning

1) The Court’s reading of §§ 38-26-107 and 38-26-110 permits disputed/unliquidated amounts

The Court treated § 38-26-107(1) as a broad authorization to file a verified statement for unpaid amounts in enumerated categories (“labor, materials, sustenance, or other supplies” and “rental machinery, tools, or equipment”) used in prosecuting the work. It then read § 38-26-110 as a guardrail: the Act does not ban claims that are later reduced; it penalizes claims that are (i) greater than due, (ii) filed with no reasonable possibility of being due, and (iii) filed with the claimant’s knowledge of the overstatement.

On that structure, “disputed” is not synonymous with “not due.” A disputed amount may still have a “reasonable possibility” of being owed, and the statute’s three-part excessiveness test already addresses the policy concern about inflated filings by requiring both objective unreasonableness (“no reasonable possibility”) and subjective culpability (“with the knowledge”).

2) Delay and disruption damages are not categorically barred, but must be “input-cost” based

The Court rejected an interpretive rule that delay/disruption damages are inherently outside § 38-26-107. Instead, it adopted a functional approach:

  • Permitted: delay/disruption components that reflect increased costs of labor, materials, equipment, tools, etc., used in performance/prosecution of the work.
  • Not permitted: “purely consequential damages” such as lost profits or idle-time damages that do not fit the statutory categories.

This distinction matters because it aligns the Public Works Act remedy with the statute’s “used or consumed” language and with lien-law concepts limiting security remedies to value-adding inputs rather than all economic fallout.

3) Deference to the trial court on “not excessive” findings

The Supreme Court emphasized the standard of review: the trial court found a “reasonable possibility” that the claimed amount was due and thus found the claim not excessive. Because that is fact-intensive and the Supreme Court could not say the finding lacked record support, it deferred under French v. Centura Health Corp. and Lo Viento Blanco, LLC v. Woodbridge Condo. Ass'n.

This portion of the opinion implicitly cautions appellate courts against converting § 38-26-110 into a hindsight arithmetic test (filed claim minus trial award) and instead preserves the statute’s time-of-filing, knowledge-based design.

4) The forfeiture for an excessive claim is limited to statutory remedies

The Court found “all rights to the amount claimed” ambiguous and used legislative history and statutory purpose to resolve it. It leaned heavily on the Act’s origins as a public-project substitute for mechanics’ lien protections and the 2003 legislative record indicating the excessive-claim provision was intended to track the Mechanics’ Lien Act’s penalty.

The Court also invoked purposivism/avoidance of absurd results: stripping all non-statutory remedies would chill legitimate use of a remedial statute designed to protect payment rights on public projects. A claimant should not risk forfeiting its contract claim entirely merely by invoking the statutory security mechanism and later losing some disputed components.

Impact

  • Broader access to statutory security on public projects: Subcontractors can file verified statements even when the amount is disputed or not yet fully liquidated, which is common for delay/disruption claims. This restores the Act’s practical utility in real-world construction disputes.
  • Sharper component-by-component scrutiny: Claimants and challengers will focus on whether claimed delay/disruption amounts are tethered to § 38-26-107 categories (labor/materials/equipment used) versus excluded consequential items (e.g., lost profits). Expect expert reports and claim exhibits to be drafted to map damages into statutory buckets.
  • Excessiveness litigation will pivot to knowledge and reasonableness at filing: Challengers must prove all three § 38-26-110 elements, including the claimant’s knowledge and lack of reasonable possibility at the time of filing—not merely that the claim was later reduced.
  • Forfeiture is no longer existential for non-statutory claims: Even if a claim is deemed excessive, the contractor/subcontractor may still pursue contract or other non-Act remedies. This reshapes settlement leverage and reduces the “nuclear option” character the court of appeals’ approach would have created.
  • Appellate review constraints: Trial courts’ excessiveness findings—often dependent on credibility, project documentation, and expert methodology—will receive meaningful deference, making the trial record and findings particularly important.

Complex Concepts Simplified

Verified statement of claim (Public Works Act)
A statutory filing by a contractor/subcontractor on a public project that triggers withholding of contract funds (or substitution with a bond) to secure payment—functionally similar to a mechanics’ lien, but adapted to public projects where liens against the property are not available.
Disputed vs. unliquidated amounts
“Disputed” means the other side contests entitlement or amount. “Unliquidated” means the amount is not fixed or readily calculable at the time—often requiring proof, allocation, or expert analysis. The Court held these can still be claimed if there is a reasonable possibility they are due and they fit the statute’s covered cost categories.
Delay and disruption damages
Costs a contractor/subcontractor claims arose because the work took longer (delay) or became less efficient (disruption). Under this opinion, they are includable only to the extent they represent increased labor/material/equipment-type costs used to perform the work—not purely consequential items like lost profits.
“Excessive” claim under § 38-26-110
Not simply a claim that turns out too high. The challenger must show: (1) the claim was greater than due, (2) there was no reasonable possibility the amount was due, and (3) the claimant knew the claim exceeded what was due at filing.
Forfeiture of rights (statutory vs. common-law)
“Statutory rights” are the special remedies created by the Public Works Act (e.g., security against retained funds/bond). “Common-law rights” include breach of contract and related claims. The Court held forfeiture for an excessive claim removes only the statutory benefits—not the underlying contract claim.

Conclusion

This opinion establishes two practical rules for Colorado public construction payment disputes: first, a verified statement of claim may include disputed and unliquidated amounts—including delay and disruption damages—so long as they are grounded in the statute’s covered “inputs” (labor/materials/equipment, etc.) used to prosecute the work and are not filed in a knowingly and unreasonably inflated manner under § 38-26-110. Second, the Act’s excessive-claim penalty is not a total forfeiture of all legal remedies; it is limited to forfeiture of the Public Works Act’s statutory remedies.

In the broader legal context, the Court re-centers the Public Works Act as a workable, lien-substitute security device—balancing protection for unpaid project participants with targeted deterrence of bad-faith overstatement, rather than imposing an all-or-nothing trap for legitimate but contested claims.