CGIA Notice Strictly Runs from Discovery of Injury—Not Discovery of the Proper Public Entity
Introduction
In Mostellar v. City of Colo. Springs, 2026 CO 22, the Colorado Supreme Court addressed whether
the Colorado Governmental Immunity Act (“CGIA”) notice deadline can be delayed when a claimant timely
notifies one public entity, but learns only later—through that entity—that a different public entity may be liable
under an intergovernmental agreement.
Petitioner Jaimi J. Mostellar alleged she was injured on August 26, 2021, after tripping on a public sidewalk in Manitou Springs.
She timely provided CGIA notice to Manitou Springs, but Manitou Springs did not disclose until April 2023 that an intergovernmental
agreement allegedly made Colorado Springs responsible for the condition at issue. Mostellar then provided CGIA notice to Colorado Springs
on May 30, 2023—well beyond 182 days from the date of injury. The key issues were (1) when the CGIA notice clock starts under
section 24-10-109(1), and (2) whether strict compliance should yield where a different public entity’s delay makes timely notice effectively impossible.
Summary of the Opinion
The Court affirmed dismissal for lack of subject matter jurisdiction. It held that:
-
Section 24-10-109(1) unambiguously requires notice within 182 days after “discovery of the injury,”
not after discovery of the responsible public entity or legal theory.
-
Strict compliance was required because Colorado Springs (the entity entitled to notice) did not mislead Mostellar or impede notice,
and the case did not present true “impossibility” of compliance.
-
The notice period began on August 26, 2021 (date of injury), making the May 30, 2023 notice untimely and the claim “forever bar[red].”
Analysis
Precedents Cited
1) Trinity Broad. of Denver, Inc. v. City of Westminster
The Court relied on Trinity Broad. of Denver, Inc. v. City of Westminster, 848 P.2d 916, 923 (Colo. 1993)
for the governing post-1986 rule: the CGIA notice period is triggered when a claimant discovers they have been wrongfully injured;
the claimant “need not yet know the cause of the injury or the extent of the damage.”
Mostellar treats Trinity as controlling authority that forecloses tying the notice clock to identifying the correct public entity.
2) State v. Young (and its legislative override)
The district court relied on State v. Young, 665 P.2d 108, 109-11 (Colo. 1983) for the idea that a claimant must have a reasonable
opportunity to discover “basic and material facts” before notice is due. The Supreme Court rejected that reliance, emphasizing that the
General Assembly amended section 24-10-109(1) in 1986 to override Young.
The Court cited Reg'l Transp. Dist. v. Lopez, 916 P.2d 1187, 1193 (Colo. 1996) to confirm the amendment’s purpose and effect.
This is the opinion’s doctrinal pivot: Young is not the operative framework for section 24-10-109(1) as now written.
3) Mesa Cnty. Valley Sch. Dist. No. 51 v. Kelsey and City & Cnty. of Denver v. Crandall
The Court reinforced that section 24-10-109(1) is a “non-claim” statute and a jurisdictional prerequisite:
failure to strictly comply requires dismissal for lack of subject matter jurisdiction.
It quoted Mesa Cnty. Valley Sch. Dist. No. 51 v. Kelsey, 8 P.3d 1200, 1206 (Colo. 2000) for mandatory dismissal and for the
proposition that the deadline is “not subject to equitable defenses such as waiver, tolling, or estoppel,” and cited
City & Cnty. of Denver v. Crandall, 161 P.3d 627, 633 (Colo. 2007) as accord.
These cases supplied the opinion’s baseline: courts cannot use equity to soften section 24-10-109(1)’s deadline.
4) Finnie v. Jefferson County School District R-1 (narrowed to subsection (3))
Mostellar invoked Finnie v. Jefferson County School District R-1, 79 P.3d 1253 (Colo. 2003) to argue for a purpose-driven,
equity-sensitive approach where governmental conduct thwarts the CGIA’s objectives.
The Court distinguished Finnie as addressing section 24-10-109(3) (where to file notice), not section 24-10-109(1) (when notice is due).
It reiterated Finnie’s internal division:
(1) requires strict compliance as jurisdictional, whereas (3) permits “substantial compliance” on a case-by-case basis,
considering agency/equity and protection against misrepresentations.
Crucially, the Court explained that even if Finnie-style considerations could be imported, they would not help Mostellar because
Colorado Springs “did nothing to impede” timely notice. Any alleged delay or omission by Manitou Springs was deemed irrelevant to the
statutory duty owed to Colorado Springs as the entity “entitled to notice.”
5) Other cited authorities supporting method and statutory purpose
-
City of Boulder v. Pub. Serv. Co. of Colo., 2018 CO 59, ¶ 14, 420 P.3d 289, 293:
de novo review of a C.R.C.P. 12(b)(1) ruling when the dispute is legal characterization rather than contested jurisdictional facts.
-
Pub. Serv. Co. of Colo. v. Outdoor Design Landscaping LLC, 2026 CO 6, ¶¶ 23-24, 583 P.3d 778, 783:
plain-language statutory interpretation principles (apply unambiguous text as written).
-
Jefferson Cnty. Health Servs. Ass'n v. Feeney, 974 P.2d 1001, 1003 (Colo. 1998):
CGIA notice purposes (prompt investigation/remedy, settlement, fiscal planning, defense preparation),
used to show that strict adherence is consistent with legislative objectives.
-
The court of appeals decision, Mostellar v. City of Colo. Springs, No. 23CA1908 (Oct. 24, 2024),
is affirmed; the Supreme Court largely adopted its view that the 182-day deadline is jurisdictional and not subject to tolling/estoppel.
Legal Reasoning
-
Text controls. The Court treated section 24-10-109(1) as unambiguous: notice is due within 182 days of “discovery of the injury,”
“regardless of whether the person then knew all of the elements of a claim.”
-
Discovery means injury discovery, not defendant-identity discovery.
By invoking Trinity and the 1986 amendment (via Reg'l Transp. Dist. v. Lopez),
the Court rejected the district court’s Young-based approach that would delay the clock until discovering who caused the injury.
-
Equity is categorically limited for subsection (1).
The Court reaffirmed the “non-claim” and “jurisdictional” character of subsection (1) under Kelsey and Crandall,
and thus the unavailability of waiver/tolling/estoppel.
-
No “impossibility” on this record.
The Court noted Mostellar offered no evidence establishing she could not have discovered Colorado Springs’ involvement,
suggesting alternatives such as an open records request or research into local transit organization.
Without a factual showing, the “impossibility” framing could not overcome the statute’s strict terms.
-
Misleading conduct must be by the entity entitled to notice.
The Court treated Finnie as, at most, a misrepresentation case (and a subsection (3) case).
Here, Colorado Springs did not mislead or direct Mostellar; therefore, any alleged delay by Manitou Springs did not excuse
Mostellar’s failure to notify Colorado Springs within the statutory period.
-
Harshness is for the legislature to fix.
Echoing concerns raised in the special concurrence below, the Court acknowledged the outcome may feel inequitable,
but held that courts must apply subsection (1)’s plain language; policy adjustments belong to the General Assembly.
Impact
-
Protective-notice practice is incentivized. Claimants injured on public property may feel compelled to provide CGIA notices to multiple
potentially connected public entities early—especially where responsibility may be allocated by contract or intergovernmental agreement.
-
Responsibility-disclosure gaps remain largely unremedied in subsection (1). Even extended engagement by one public entity,
without identifying other potentially responsible entities, will not delay the notice clock for those other entities—absent legislative change.
-
Litigation will likely shift to factual “could have discovered” disputes. The Court’s discussion of open records requests and other
investigative steps signals that future claimants may attempt to build records showing diligence and practical inability,
even if equitable doctrines remain formally unavailable under subsection (1).
-
Municipal risk allocation can be litigation-critical. Intergovernmental agreements may determine operational responsibility,
but they do not, under this decision, alter the statutory trigger for notice; they instead heighten the need for early investigation.
Complex Concepts Simplified
- CGIA notice (section 24-10-109(1))
-
A written warning to the public entity that you intend to assert an injury claim. Under subsection (1), it must be filed within 182 days after you
discover the injury, and it is a prerequisite to suing.
- Non-claim statute
-
A deadline that extinguishes the right itself if missed (not merely the remedy). Courts treat it as strict and generally not subject to equitable exceptions.
- Jurisdictional prerequisite / subject matter jurisdiction
-
A condition that must be satisfied for the court to have power to hear the case. If CGIA notice is late under subsection (1), the court must dismiss.
- Discovery rule (as used here)
-
Under subsection (1) as interpreted post-1986, “discovery” refers to learning you are injured (and wrongfully injured), not learning the correct defendant,
the legal theory, or all claim elements.
- Equitable tolling / estoppel / waiver
-
Doctrines that sometimes soften deadlines when fairness demands it (e.g., misleading conduct). The Court reaffirmed these do not apply to subsection (1).
- Substantial vs. strict compliance
-
“Strict compliance” demands exact adherence (used for subsection (1)). “Substantial compliance” allows some deviations if statutory purposes are met
(recognized in Finnie for subsection (3)’s filing-location rules).
- Intergovernmental agreement
-
A contract between public entities to allocate responsibilities. The agreement may determine who is responsible operationally,
but it does not change the CGIA notice trigger under this decision.
Conclusion
Mostellar cements a hard-edged rule for section 24-10-109(1): the 182-day CGIA notice period begins upon discovery of the injury,
not upon discovery of which public entity is legally responsible. The Court further clarified that any equitable concerns arising from delayed disclosure
by a different public entity do not excuse late notice to the entity entitled to receive it—particularly where that entity did not mislead the claimant.
The decision reinforces strict jurisdictional dismissal for late notice and places the burden of early, sometimes multi-entity investigation and notice
squarely on claimants, while leaving any policy-based safety valve to legislative reform.