Wind Farm EIAs: Grid Connections Require a Fact-Specific “Single Project” Evaluation (and Reasons)
1. Introduction
Raeshaw Farms Limited appealed under section 239 of the Town and Country Planning (Scotland) Act 1997
against a decision of a Scottish Ministers’ reporter granting planning permission for Wull Muir Wind Farm,
promoted by Energiekontor UK Ltd (interested party). The wind farm application covered eight turbines and associated
on-site infrastructure, but did not include the off-site grid connection.
The central legal issue was whether, for the purposes of environmental impact assessment (EIA), the wind farm and its grid connection
could lawfully be treated as separate, or whether they were in reality a single “project” whose
cumulative environmental effects required assessment before permission was granted. A related issue was whether the
reporter’s reasoning on “salami slicing” (project splitting) and on the need for a cumulative assessment was legally adequate.
2. Summary of the Judgment
The Inner House (Lady Wise delivering the Opinion) held that the reporter committed material legal errors in dealing
with the grid connection issue and in providing reasons. In particular:
-
The reporter failed to conduct the necessary fact-specific evaluative exercise to decide whether the wind farm and
grid connection formed a single project for EIA purposes.
-
The reporter misdirected himself by treating “salami slicing” as turning on an attempt to circumvent
the EIA regime, whereas the authorities show the focus is on the objective effect of splitting on environmental assessment.
-
The reasons given (a single paragraph) were inadequate, amounting largely to assertion and failing to demonstrate that
the live issue had been understood and resolved on a legally correct basis.
-
There was force in an associated irrationality challenge: it is potentially irrational to attribute weight to the benefits dependent on
the grid connection (renewable generation, climate benefits, socio-economic benefits) without addressing the corresponding adverse impacts
of the completed scheme to the extent possible.
The court therefore quashed the reporter’s decision dated 14 January 2025 and remitted the appeal to a
different reporter for a fresh decision.
3. Analysis
3.1 Precedents Cited
(a) CJEU authorities on “project” and cumulative assessment
-
Bund Naturschutz v Freistaat Bayern (Case C-396/92) [1994] ECR I-3717
The court drew support from Advocate General Gulmann’s influential analysis: EIA must, as far as practicable, take account of planned
extensions and the broader context so that environmental effects are considered “at the earliest possible stage”. Although the ECJ’s
decision ultimately turned on transitional provisions, the Opinion was treated as persuasive in framing the purpose-led approach to
defining the relevant “project”.
-
Commission v Spain (Case C-227/01) [2005] Env LR 20; [2004] ECR I-8253
A core authority for the proposition that the Directive’s objectives cannot be undermined by splitting a scheme into smaller parts.
Critically, the Inner House relied on the principle that the benchmark is not subjective intention but whether a project is
likely to have significant environmental effects—supporting the court’s conclusion that the reporter erred by treating salami
slicing as requiring an “attempt” to circumvent the EIA regime.
-
Umweltanwalt von Kärnten v Kärntner (Case C-205/08) [2010] Env LR 15; [2009] ECR I-11525
Reinforces that ignoring cumulative effects must not lead to projects escaping assessment in practice where, taken together, they are
likely to have significant effects. This underpinned the court’s insistence that the reporter had to grapple with the cumulative effects
question rather than defer it by reference to a possible later application.
(b) Scottish authorities
-
Skye Windfarm Action Group v Highland Council [2008] CSOH 19
Used to illustrate a fact-sensitive approach to whether elements can be assessed separately. The Lord Ordinary accepted that integral
parts “should not normally be considered in isolation”, but upheld separation in that case because earlier assessment had not identified
significant effects from borrow pits and a cumulative assessment had in any event been sought and considered. The Inner House treated
this as supporting the need to examine the “particular circumstances”.
-
Wildland v Highland Council [2021] CSOH 87; 2022 SLT 1082
Distinguished. There, postponement of assessment of visitor facilities was rationally justified by uncertainty (e.g., exclusion zone not
clarified) and it was clear that a further planning application would follow, at which stage cumulative impact would be assessed.
Here, by contrast, the reporter proceeded on the basis that it was unknown whether planning permission and/or EIA would be
required for the grid connection, which made a careful “single project” evaluation more—not less—important.
-
West Lothian Council v Scottish Ministers [2023] CSIH 3; 2023 SLT 175
Provided the benchmark for adequacy of reasons: decisions must identify the live issues and make clear what considerations were taken
into account. The court held paragraph 129 of the reporter’s decision did not meet that standard.
(c) England & Wales authorities on defining the “project” and staged assessment
-
R (Wingfield) v Canterbury City Council [2020] JPL 154
Central to the Inner House’s critique: Lang J’s non-exhaustive factors (common ownership; simultaneous determinations; functional
interdependence; stand-alone justification) were approved elsewhere and were the kind of structured evaluative approach the reporter
failed to undertake. The Inner House emphasised that “functional interdependence” was plainly relevant because the wind farm cannot
function without a grid connection.
-
R (Ashchurch Rural Parish Council) v Tewkesbury BC) [2023] EWCA Civ 101; [2023] Env LR 25
Key authority used twice: (i) “project” must be understood “broadly, and realistically”; (ii) intention to circumvent is not required;
(iii) irrationality may arise if benefits of a wider scheme are weighed without assessing corresponding adverse effects where possible.
The Inner House used this to support both the legal error on salami slicing and the force of the appellant’s irrationality argument.
-
R (Finch) v Surrey County Council [2022] EWCA Civ 187; [2022] Env LR 27 and [2024] UKSC 20; [2024] 4 All ER 717
Although not directly on grid connections, the Supreme Court’s discussion of Directive interpretation reinforced that validity requires a
systematic and comprehensive assessment of likely significant effects before decision, and that public participation is integral—values
undermined if a decision-maker too readily treats an essential component as outside scope without proper evaluation.
-
R (Together against Sizewell C Ltd) v Secretary of State for Energy Security and Net Zero [2023] EWCA Civ 1517; [2024] Env LR 22
Cited for the legitimacy, in principle, of staged/cumulative assessment “as soon as” cumulative effects can be meaningfully assessed.
The Inner House did not reject staged approaches generally; rather, it held the reporter failed to decide (on the facts) whether staging
was lawful and compliant given the uncertainty about whether grid works would later be subject to EIA.
(d) Republic of Ireland authorities on wind farms and grid connections
-
Ó Grianna v An Bord Pleanála [2014] IEHC 632
Treated as strong persuasive reasoning: wind farm and grid connection were “one project” because neither serves a purpose without the
other; therefore their cumulative effects should be assessed for compliance. The Inner House agreed that Irish courts’ Directive-focused
approach is valuable, while stopping short of adopting an absolute rule that applications must always include the grid connection.
-
Daly v Kilronan Windfarm Limited [2017] IEHC 308
Emphasised that while consent routes may differ, EIA is required for the whole project; parts cannot be separated and treated as exempt
so as to defeat Directive objectives.
-
Sweetman v An Bord Pleanála [2023] IEHC 89 and North Westmeath Turbine Action Group v An Bord Pleanála 2025 IEHC 608
Reinforced the Irish line that EIA must address the entire project, and that screening of a part does not substitute for a compliant EIA
where a full-project EIA is required.
-
An Taisce - The National Trust for Ireland v An Bord Pleanála (Kilkenny Cheese Ltd, Notice Party) [2022] IESC 8; [2022] 2 IR 173
Not directly in point on its ratio, but referenced as recognising that some off-site activities can have a “clear and unbreakable
inter-relationship” with the project for assessment purposes—Ó Grianna being an example.
(e) Comparative EU material
-
Asociación Ambiental e Cultural Petón do Lobo v Dirección Xeral de Planificación Enerxética e Recursos Naturais (Do Lobo Environmental and Cultural Association v Directorate General of Energy Planning and Natural Resources), Judgment 00368/2025
A Galician decision supporting the view that turbines and associated power line/grid feed are components of a single wind farm project
requiring a single environmental impact statement in that application.
3.2 Legal Reasoning
(a) The correct legal question: what is the “project” for EIA?
The statutory appeal was rooted in EU Directive 2011/92/EU (as amended) and the Town and Country Planning (Environmental Impact
Assessment) (Scotland) Regulations 2017. The Directive requires assessment of direct and indirect significant effects, with emphasis on
considering effects at the earliest possible stage.
The Inner House held the reporter’s analysis never properly addressed the legally prior question: whether, on the facts, the wind farm and
its grid connection were so closely connected that they formed a single project for EIA purposes, such that cumulative
effects required consideration before granting permission for the turbines.
(b) “Salami slicing” is about objective effect, not intention
The reporter treated “salami slicing” as properly referring to an attempt to circumvent the EIA regime. The court held this was
a misdirection: the authorities emphasise the practical consequence of splitting (whether it undermines the Directive’s
purpose), not the developer’s motive. This error mattered because it diverted the reporter from the required inquiry into
interrelationship, functional dependence, and cumulative effects.
(c) Staged approaches can be lawful, but only after evaluative justification
The court accepted that staged assessment may be legitimate in principle (as reflected in the authorities discussing avoiding “sclerosis”),
and endorsed the view that it cannot be stated in absolute terms that every wind farm application must include grid connection detail.
However, staging must be justified through a proper evaluation of whether cumulative effects can be meaningfully assessed later, and—crucially
in this case—whether a later EIA is even likely to occur, given the reporter’s acceptance that it was unknown whether the grid solution would
require planning permission.
(d) Adequacy of reasons: why the single paragraph failed
Paragraph 129 of the decision:
- did not show that the reporter had identified the real issue (single project/cumulative assessment);
- rested on assertion (“not part of the current proposal”) rather than legal evaluation;
- invoked an incorrect intention-based definition of salami slicing;
- offered an opaque assurance that the grid connection would be “subject to its own evaluation” without addressing whether that satisfied
the Directive’s “earliest possible stage” requirement on the facts.
Applying West Lothian Council v Scottish Ministers [2023] CSIH 3; 2023 SLT 175, the reasons did not adequately disclose
what considerations were taken into account and why the objection was rejected.
(e) The associated irrationality point
The reporter gave “positive weight” to operational benefits (renewable generation and climate change mitigation), which are dependent on a
grid connection. Drawing on R (Ashchurch Rural Parish Council) v Tewkesbury BC) [2023] EWCA Civ 101; [2023] Env LR 25,
the court considered there was force in the submission that it is irrational to take benefits that presuppose the wider/completed scheme
without considering adverse impacts of that completed scheme to the extent possible. The point reinforced the practical difficulty of
treating the wind farm and grid connection as analytically separate when the planning merits case is advanced on the basis of their combined
operational outcome.
3.3 Impact
-
Decision-makers must explicitly evaluate “single project” arguments: A bare statement that the grid connection is not in
the application is not enough. Reporters must demonstrate a structured, fact-specific evaluative judgment on interrelationship and
cumulative effects.
-
Intent is not the test for salami slicing: Scottish EIA practice should align with the objective-effects approach reflected
in the cited CJEU and UK authorities.
-
Greater pressure to address grid connection uncertainty: Where it is unknown whether later grid works will require planning
permission and/or EIA, the risk of non-compliance increases if the turbines are consented first without cumulative assessment.
-
Reasons scrutiny in EIA cases remains demanding: While not “conveyancing” scrutiny, EIA decisions must show the live issue
has been properly understood and answered.
-
Practical development implications: Developers may need to provide more information on likely grid connection options (even
if not finalised) to enable meaningful cumulative assessment, or clearly justify a staged approach by reference to what can realistically
be assessed at each stage and when.
4. Complex Concepts Simplified
- EIA / “Environmental impact assessment”
-
A pre-permission process requiring the developer to supply an EIA report and the decision-maker to reach a reasoned conclusion on likely
significant environmental effects, so the public can participate on an informed basis.
- “Project” (Directive) / “Development” (Regulations)
-
The real-world scheme to be assessed. It may be broader than the boundaries of a single planning application if parts are functionally and
environmentally connected.
- “Salami slicing” / project splitting
-
Dividing what is in substance one scheme into separate parts so that the overall environmental effects are never properly assessed. The key
question is the effect on the EIA process, not whether the developer meant to avoid scrutiny.
- “Cumulative effects”
-
The combined environmental impacts of connected components or phases taken together, which may be greater or different than each part
considered alone.
- Wednesbury rationality
-
A public law standard of review: the court does not remake the planning judgment, but can intervene if the decision-maker’s evaluative
judgment is irrational or legally flawed (including failure to ask the right question).
- Staged / multi-stage assessment
-
Sometimes environmental assessment can properly proceed in phases (e.g., where detail is not yet knowable), but only if cumulative effects
will be assessed as soon as they can be meaningfully identified, and without undermining the Directive’s purpose.
5. Conclusion
The Inner House’s decision establishes that, in Scottish EIA practice, a reporter must not treat exclusion of an off-site grid connection
from a wind farm application as determinative. The reporter must instead undertake (and explain) a fact-specific evaluation
of whether the wind farm and grid connection are a single project requiring assessment of cumulative effects at the
permission stage, particularly where it is uncertain whether later grid works will be subject to any EIA process. The judgment also clarifies
that “salami slicing” is not intent-based and reinforces that reasons must demonstrate real engagement with the live EIA issue. The remedy—
quashing and remit to a different reporter—signals the centrality of lawful scoping and reasoning to the integrity of environmental decision-making.