Contains public sector information licensed under the Open Justice Licence v1.0.
Skyros Maritime Corporation & Anor v Hapag-Lloyd AG (Re 'SKYROS' & 'AGIOS MINAS')
Factual and Procedural Background
This appeal arises from an arbitration under the LMAA Rules between the Owners of two container vessels (the "Owners") and the Charterer (Company A). Two materially identical New York Produce Exchange time charterparties were entered: one for Vessel A (charter commenced 20 February 2017) and one for Vessel B (charter concluded 23 March 2020). Each charter established a latest contractual redelivery date in late May 2021. During the charter periods the Charterer employed the vessels and paid hire at the contract rates.
Before the latest redelivery dates the Owners entered into memoranda of agreement (MOAs) to sell the vessels to buyers (Company B and Company C), under which the Owners agreed not to conclude further fixtures prior to delivery to those buyers. Both vessels were nevertheless redelivered late (Vessel A by about two days; Vessel B by about seven days). The Charterer paid hire at the contract rates during the overruns, but the market hire rates at the relevant time were substantially higher.
The parties consented to refer a preliminary issue to the arbitrators: whether, on the assumed facts that the Owners would not and could not have re‑chartered the vessels after timely redelivery because of the sale contracts, the Owners were entitled either to substantial damages assessed by reference to the market rate for the overrun period or only to nominal damages. The arbitrators held the Owners were entitled to substantial damages. On an appeal under section 69 of the Arbitration Act 1996, a Commercial Court judge (Judge Bright) allowed the Charterer's appeal and restricted the Owners to nominal damages. The Owners obtained permission to appeal to the court that produced the opinion summarised here.
Legal Issues Presented
- Whether, where a vessel under a time charter is redelivered late but the Owners had committed to sell the vessel and would not (or could not) have re‑chartered it after timely redelivery, the Owners are nevertheless entitled, in principle, to recover substantial damages assessed by reference to the market rate for the period of the overrun.
- Whether Owners are, in principle, entitled to recover user damages for late redelivery (this was one of the two issues on which permission to appeal was given by the judge).
- Whether the Owners' contracts for the sale of the vessels (the MOAs) must be disregarded in assessing any damages (this was the other issue on which permission to appeal was given by the judge).
Arguments of the Parties
Owners' Arguments (Appellants)
- Owners submitted they are entitled to the normal measure of damages for late redelivery: the difference between the market rate and the contract rate for the period of the overrun, regardless of whether they could or would have entered the market to fix the vessel in that period.
- That measure compensates for the value of the use of the vessel during the overrun which the Owner was deprived of by the Charterer's breach.
- Alternatively, the MOAs should be treated as too remote or as res inter alios acta (collateral) and therefore disregarded when assessing loss.
Charterer's Arguments (Respondent, Company A)
- Charterer submitted that the compensatory principle (Robinson v Harman) restricts recovery to the loss actually suffered: damages for late redelivery compensate the owner for loss of the opportunity to fix in the market, an opportunity which these Owners did not have because of the sale contracts; accordingly only nominal damages should be recoverable.
Argument on User Damages (Attorney Board)
- It was submitted that user damages compensate for invasion of a proprietary or possessory right and are not available here because the Owners retained possession and the Charterer's use conformed to the charterparty; and that timely redelivery was of no economic value to the Owners given the sale commitments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Robinson v Harman (1848) 1 Exch 850 | Fundamental compensatory principle: place injured party in the position he would have been in had the contract been performed. | Used to frame the compensatory inquiry and contrasted with the res inter alios acta principle when assessing loss. |
| Federal Republic of Nigeria v Process & Industrial Developments Ltd [2025] UKSC 36 | Recent application of the Robinson compensatory principle. | Cited as a recent confirmation of the compensatory principle; no novel departure from that principle was accepted. |
| Hyundai Merchant Marine Co Ltd v Gesuri Chartering Co Ltd (The Peonia) [1991] 1 Lloyd's Rep 100 | Distinction between legitimate and illegitimate last voyage; statement that damages for late redelivery are the difference between market and charter rate. | Quoted for the legitimate/illegitimate distinction and authority for the normal measure of damages for overruns. |
| Watson Steamship Co v Merryweather & Co (1913) 18 Com Cas 294 | Early authority affirming that damages for late redelivery equal the difference between market and contract hire. | Identified as the earliest cited case supporting the normal measure of damages. |
| Meyer v R.F. Sanderson & Co (1916) 32 TLR 428 | Part of line of authority stating the normal measure for late redelivery. | Included among authorities establishing the standard measure. |
| The Dione [1975] 1 Lloyd's Rep 115 | Authority stating the same measure of damages for overruns. | Included in the court's list of supporting authorities. |
| The Johnny [1977] 2 Lloyd's Rep 1 | Authority on measure of damages for late redelivery; noted division on a related question and that it bears on what market rate is relevant. | Identified as the only case bearing on the question of which market rate (short‑term v longer fixture) is the relevant comparator; to be considered by arbitrators on remittal. |
| The Black Falcon [1991] 1 Lloyd's Rep 77 | Authority stating the normal measure for late redelivery. | Included in the line of authority supporting the normal measure. |
| The Gregos [1995] 1 Lloyd's Rep 1 | Authority stating the normal measure for late redelivery. | Included in the line of authority supporting the normal measure. |
| The Paragon [2009] 2 Lloyd's Rep 688 | Discusses when quantum meruit may apply and scope of services performed under a contract. | Cited by the judge for the proposition that quantum meruit cannot apply where services were provided pursuant to the charterparty and hire was paid at the charter rate. |
| The Achilleas [2008] UKHL 48; [2009] 1 AC 61 | Held that losses beyond the ordinary consequences (loss of a particular follow‑on fixture) were too remote; but affirmed entitlement to normal measure (difference between market and charter rate for overrun period). | Used to show limits on recovery for loss consequential on overruns and to support that the normal measure is the appropriate compensatory measure for overruns. |
| The Doric Valour [2024] EWCA Civ 1312; [2025] 1 Lloyd's Rep 401 | Example where collateral arrangements were disregarded and damages awarded despite the claimant having received full price from its buyer. | Applied as an example of the res inter alios acta principle: collateral contractual arrangements may be disregarded when assessing loss. |
| One Step (Support) Ltd v Morris-Garner [2018] UKSC 20; [2019] AC 649 | Modern authority on user damages: available where there is an invasion of the claimant's property rights even if no pecuniary loss is shown. | Analysed to consider whether user damages should be available for late redelivery; the court declined to extend user damages into a novel basis here. |
| Watson, Laidlaw & Co Ltd v Pott, Cassels & Williamson (1914) SC (HL) 18 | Lord Shaw's formulation that wrongful use of property may attract payment of price or hire even if no pecuniary loss is shown. | Cited as historical authority supporting the concept of user damages and wrongful use compensation. |
| Stoke-on-Trent City Council v W & J Wass Ltd [1988] 1 WLR 1406 | Illustration of user damages principles and the wider meaning of 'loss' for wrongful use of property. | Quoted to show analogy with wrongful use examples (e.g., Lord Halsbury's chair) when considering user damages for late redelivery. |
| The Mediana [1900] AC 113 | Lord Halsbury's example used to demonstrate that wrongful use can attract damages even if no conventional financial loss is shown. | Used as an illustrative historical example in the analysis of user damages. |
| Rodocanachi, Sons & Co v Milburn Brothers (1886) 18 QBD 67; Wertheim v Chicoutimi Pulp Co [1911] AC 301; Williams Brothers v Ed. T. Agius Ltd [1914] AC 510; Slater v Hoyle & Smith Ltd [1920] 2 KB 11; R & H Hall Ltd v W.H. Pim Jnr & Co Ltd (1928) 30 Ll L Rep 159 | Authorities in the sale and carriage of goods context concerning when sub‑contracts should be taken into account for damage assessment. | Alluded to; the court declined to explore them in depth and decided the appeal on the straightforward res inter alios acta / compensatory basis. |
| Manchikalapati v Zurich Insurance PLC [2019] EWCA Civ 2163 | Example where subsequent events (no repairs carried out) did not defeat recovery of repair cost as ordinary measure of loss. | Relied on analogously to illustrate that subsequent contractual or factual arrangements should not necessarily reduce the recoverable loss. |
| The London Corporation [1935] P 70 | Illustration that sale of a damaged vessel to be broken up did not prevent recovery of repair costs; sale treated as an accidental circumstance. | Used by a concurring judge to support disregarding the Owners' sale contracts when assessing damages. |
Court's Reasoning and Analysis
The court began from the established line of authority that, in actions for late redelivery under a time charter when the market rate exceeds the contract rate, the normal measure of damages is the difference between the market rate and the contract rate for the overrun period. The opinion emphasised the long and consistent maritime authority to that effect and the reflection of that position in leading textbooks.
Two important doctrinal distinctions informed the analysis. First, the court distinguished between the compensatory principle (Robinson v Harman) and the remoteness inquiry (Hadley v Baxendale) as stages in assessing damages. Second, it explained and applied the principle that certain matters are treated as collateral and disregarded when assessing what the claimant has lost (res inter alios acta).
Applying these principles, the court held that the Owners' contractual arrangements for sale of the vessels (the MOAs) were collateral to the contractual relationship with the Charterer and arose independently of the breach. Accordingly those arrangements must be disregarded when calculating the Owners' loss for the purpose of awarding compensatory damages for late redelivery. The late redelivery deprived the Owners of the opportunity to take advantage of the market rate during the overrun period; whether the Owners in fact could or would have taken that opportunity is collateral and not relevant to the assessment.
The court considered alternative bases on which the arbitrators had awarded damages (quantum meruit, user damages and negotiating damages). The court accepted that quantum meruit did not apply where the services were provided pursuant to the charterparty and hire had been paid at the charter rate (following The Paragon). On user damages, the court analysed the principles in One Step (user damages for wrongful use of property) and the analogous historic examples, but declined to extend user damages as a novel basis of recovery where the ordinary compensatory principle (with collateral matters disregarded) already afforded a remedy. The court therefore did not accept introducing user damages to award recovery where no conventional loss had been shown.
The court also considered The Achilleas and related authorities to underline that the normal measure of damages for the overrun period is the accepted compensatory rule and that broader consequential losses (such as loss of a particular follow‑on fixture or the Owners' sale arrangements) may be too remote unless they fall within the ordinary course of events contemplated by the parties.
Holding and Implications
HOLDING: The appeal is ALLOWED. The court restored the arbitrators' preliminary award that the Owners are entitled, in principle, to substantial damages for the period of the overrun assessed by reference to the market rate versus the contract rate.
Implications and direct effects:
- The case is remitted to the arbitrators to assess the quantum of damages for the overrun periods on the basis that the Owners may recover the difference between the market rate and the contract rate for those periods.
- The assessment must determine the relevant market rate for the overrun periods (the court noted that The Johnny bears on that question and that the arbitrators will need to decide which market comparator is appropriate).
- The court held that the Owners' sale contracts are to be disregarded as collateral (res inter alios acta) for the purpose of assessing compensatory loss; the Charterer's liability is not to be reduced on that account.
- The court did not accept that a novel expansion of user damages should be used to award recovery where the ordinary compensatory principle (with collateral matters disregarded) provides the award; quantum meruit and negotiating damages were not before the court on the issues on which permission was given and so were not decided here.
- The court stated that the decision promotes commercial certainty by preserving the well‑established normal measure for late redelivery and by avoiding a requirement to investigate owners' collateral arrangements to determine liability.
Please subscribe to download the judgment.
Comments