Contains public sector information licensed under the Open Justice Licence v1.0.
Malone v GCHL & Ors (Approved)
Factual and Procedural Background
This opinion concerns a costs application arising from a prior judgment in an enforcement action initiated by the Plaintiff against Company A (the first named Respondent) and the Agency (the second named Respondent) regarding unauthorized developments and waste disposal at a quarry site in County Kildare. The Plaintiff sought multiple reliefs, including an order prohibiting the Agency from processing a waste licence application submitted by Company A. The court in the principal judgment determined that there was no jurisdictional basis for the relief sought against the Agency in relation to that prohibition, resulting in the striking out of that part of the Plaintiff's claim. The enforcement action against Company A continues with other reliefs intact. The current judgment addresses the Agency's application for costs following the principal judgment.
Legal Issues Presented
- Whether the Agency is entitled to an award of costs in respect of the preliminary application that led to the striking out of the relief sought against it.
- Whether the default no costs rule under the Environment (Miscellaneous Provisions) Act 2011 ("the 2011 Act") applies or is displaced by exceptions concerning frivolous or vexatious claims or the manner in which proceedings were conducted.
- The applicability of the Aarhus Convention, particularly Article 9(4), and its interpretative obligation on national procedural law in relation to costs and ensuring costs are "not prohibitively expensive".
- Whether the relief sought against the Agency constituted an abuse of process and was properly struck out for lack of jurisdiction.
Arguments of the Parties
Agency's Arguments
- The relief sought against the Agency had no jurisdictional basis and was bound to fail, constituting an abuse of process.
- The Agency is entitled to costs under exceptions in section 3(3)(a) and (b) of the 2011 Act, either because the claim was frivolous or vexatious or due to the manner in which the Plaintiff conducted the proceedings.
- The enforcement action falls within the scope of the 2011 Act, which governs costs in civil proceedings relating to certain licences.
- A process of measuring costs is required to ensure compliance with the Aarhus Convention's principle that costs should not be prohibitively expensive (NPE), with reference to relevant case law and UK Civil Procedure Rules guidance.
- The Agency incurred legal costs amounting to €20,250.21 and sought an opportunity for the Plaintiff to provide financial details to assess the reasonableness of a costs order.
Plaintiff's Arguments
- The Plaintiff requested that the court defer ruling on costs until substantive EU law issues raised in the case are adjudicated by an EU court, invoking Article 19(1) TEU.
- The Plaintiff relied on written submissions and an affidavit emphasizing the primacy of EU law over domestic law and alleged failures by the Agency to implement EU legislation and CJEU judgments.
- The Plaintiff referenced procedural rules and case law relating to appeals and costs but did not seek to resist the jurisdictional ruling on the relief against the Agency.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Malone v Company A & The Agency & Ors [2024] IEHC 336 | Jurisdictional basis for relief against Agency in enforcement action | Principal judgment struck out relief against Agency for lack of jurisdiction |
Hoey v Waterways Ireland [2024] IECA 272 | Default position on costs under Legal Services Regulation Act 2015 | Supported the principle that a wholly successful party is entitled to costs unless the court orders otherwise |
Little v The Chief Appeals Officer & Ors [2024] IESC 53 | Costs in public interest litigation and limits on court discretion | Emphasized legislative limits on costs discretion in environmental litigation |
Kelly Dunne v Guessford Ltd [2022] IEHC 427 | Interpretative obligation under Aarhus Convention and costs protection | Applied to interpret national law consistently with Aarhus Convention provisions |
Heather Hill Management Company CLG v An Bord Pleanála & Ors [2022] IESC 43 | Costs protection in environmental enforcement proceedings | Confirmed application of Aarhus Convention principles in costs rulings |
McCoy v Shillelagh Quarries Ltd [2015] IECA 28 | Costs provisions in enforcement actions under planning and waste management laws | Confirmed applicability of 2011 Act costs protections in enforcement proceedings |
McCann v Furlong [2024] IEHC 559 | Costs awards relative to success and conduct under 2011 Act | Outlined exceptions to default no costs rule in environmental cases |
North Westmeath Turbine Action Group & Ors v An Bord Pleanála & Ors [2022] IECA 126 | Procedural questions relating to environmental enforcement and appeals | Referenced in context of procedural issues left open for future cases |
Mount Salus Residents' Owners Management Company Ltd v An Bord Pleanála & Others [2023] IEHC 691 | Discussion of procedural and jurisdictional issues in environmental cases | Considered relevant to procedural questions left unresolved in principal judgment |
Case C-260/11 Edwards & Pallikaropoulos v Environment Agency | Interpretation of Aarhus Convention provisions on costs | Supported argument on costs not being prohibitively expensive |
Case C-470/16 North East Pylon Pressure Campaign v An Bord Pleanála | Interpretative obligation of national courts under Aarhus Convention | Applied to ensure national law aligns with environmental procedural protections |
Court's Reasoning and Analysis
The court began by affirming the principal judgment's determination that the relief sought against the Agency was not appropriate within the statutory enforcement framework and lacked jurisdictional basis, thus was struck out. The Agency argued it should recover costs based on exceptions to the default no costs rule under the 2011 Act, due to either frivolous or vexatious claims or the manner in which the Plaintiff conducted proceedings. The court carefully considered the legislative scheme, including the default costs provisions and their exceptions, and the interpretative obligation arising from the Aarhus Convention to ensure costs are not prohibitively expensive.
In applying these principles, the court distinguished between relief that was incorrect and relief that was unreasonable or indicative of improper conduct. It found that although the relief against the Agency was misconceived and bound to fail, it did not amount to unreasonable behaviour or abuse warranting a costs award against the Plaintiff. The court emphasized that the statutory framework explicitly provides for a default no costs order in such environmental enforcement proceedings, reflecting legislative intent to protect certain categories of litigants.
Consequently, the court declined to disapply the default no costs rule and considered that the process of measuring costs suggested by the Agency was unnecessary. The court also addressed the Plaintiff’s request to defer costs pending EU law adjudication and found it appropriate to determine costs at this stage.
Holding and Implications
The court made no order as to costs in relation to the Agency's application concerning the struck-out relief in the enforcement action. This means that each party bears its own legal costs for this application.
The direct effect is that the Plaintiff is not liable to pay the Agency’s costs arising from the preliminary application. The court’s decision reinforces the statutory default position under the 2011 Act that costs are generally not awarded against unsuccessful parties in certain environmental enforcement proceedings, absent exceptional circumstances. No new precedent altering the established legal framework was created by this decision.
Please subscribe to download the judgment.
Comments