Contains public sector information licensed under the Open Justice Licence v1.0.
TECJET LTD AGAINST KIER CONSTRUCTION LTD
Factual and Procedural Background
This case arises from a fire at the Mackintosh Building of the Glasgow Art School on 15 June 2018. The Plaintiff was the tenant of adjacent premises known as the O2 Building, operating it as a nightclub and music venue. The Defendant was the principal contractor undertaking remedial work at the Art School site following an earlier fire in 2014. The fire in June 2018 caused extensive damage, spreading to adjoining buildings including the Plaintiff's premises. The Plaintiff brought an action against the Defendant for loss and damage caused by the fire, suing both in its own right and as assignee of claims from two other companies within its corporate group. The Plaintiff's case relied on the maxim res ipsa loquitur, contending that the fire's occurrence and spread under the Defendant's control evidenced negligence. The Defendant challenged the relevancy of the Plaintiff's case on several grounds, including the Plaintiff's title to sue and the sufficiency of pleadings.
Legal Issues Presented
- Whether the Plaintiff had title to sue for its own alleged losses at the time the action was raised, particularly regarding the sufficiency of averments on leasehold interest and interruption of the prescriptive period.
- Whether the Plaintiff had title to sue on behalf of the assignor companies for their alleged losses, considering the validity, execution, and intimation of assignations transferring rights.
- Whether the pleadings of the Plaintiff were relevant and sufficiently detailed to establish a duty of care owed by the Defendant and to specify the quantum of losses claimed.
- The applicability of the Construction (Design and Management) Regulations 2015, specifically regulation 29, to the Plaintiff's claims.
Arguments of the Parties
Defendant's Arguments
- The Plaintiff failed to establish the nature or basis of its right to claim damages for its own losses at the time the summons was served, as the pleadings only averred tenancy without reference to a lease until much later, after the prescriptive period expired.
- The summons as served did not constitute a "relevant claim" to interrupt prescription under the Prescription and Limitation (Scotland) Act 1973 because it lacked sufficient averments of title to sue.
- The first assignation purportedly transferring claims from the assignor companies to the Plaintiff did not convey property rights but only a mandate to litigate on their behalf, and was invalidly executed and not properly intimated as required by statute.
- The second assignation was executed and intimated after proceedings had started and could not cure any defect in title at the commencement of the action.
- The Plaintiff had no title to sue for the assignors' claims at the date proceedings were raised, rendering those claims prescribed and the action a nullity as to those claims.
- The Plaintiff's pleadings contained contradictions and lacked sufficient detail to establish a duty of care, particularly in respect of the assignors who were not tenants.
- The quantum of losses claimed was inadequately specified and amounted to a "global" claim without fair notice.
- The Construction (Design and Management) Regulations 2015, specifically regulation 29, were irrelevant to claims for property damage as they relate to preventing personal injury.
Plaintiff's Arguments
- The Plaintiff made claims both for the building and its contents, so the Defendant's argument on title only affected the claim related to the premises.
- A lack of specification of title in the pleadings at the outset did not prevent the summons from constituting a relevant claim interrupting prescription, as the substance of the obligation was brought into issue.
- The first assignation, properly construed, conveyed all rights to bring and conduct proceedings on behalf of the assignors, including compromise and settlement, thus conferring title to sue.
- The typographical error in the first assignation's reference to "Academy Group Limited" was an obvious mistake and did not affect its validity.
- The forms of intimation prescribed by statute were not exhaustive; intimation is a matter of fact and the Plaintiff had complied.
- The Defender did not challenge the formal validity of the first assignation's execution, and proof of authority was a matter for evidence.
- In the event the first assignation was ineffective, the second assignation, although subsequent, could cure defects in title during proceedings, consistent with established authority allowing title to be perfected after commencement in certain cases.
- The Plaintiff's case on duty of care was based on the neighbour principle and was neither novel nor controversial; the Defendant owed a duty to avoid causing damage by fire to neighbouring property.
- The losses claimed related primarily to contents (primary loss) and loss of profit arising from property damage, and the pleadings, including schedule of loss and vouching, gave fair notice of the claim.
- The averments regarding the CDM Regulations were relevant to demonstrate the Defendant's control over the site and standards expected of principal contractors, supporting the negligence claim.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Bentley v Macfarlane 1964 SC 76 | At the date of raising an action, if the pursuer has no title to sue, the defect cannot be cured by a subsequent assignation; a claim without title is a nullity. | The court applied this principle to dismiss the assignors' claims as prescribed since the Plaintiff lacked title at commencement and subsequent assignation could not cure this. |
Royal Insurance (UK) Limited v Amec Construction (Scotland) Ltd (No 2) 2008 SLT 825 | A claim which is irrelevant as a matter of law can still interrupt prescription if the obligation is adequately brought into issue; precise form is less important than substance. | The court agreed that the summons as served was a relevant claim for the Plaintiff's own losses despite some inadequacies in pleadings. |
Slattadale Limited v Tilbury Homes (Scotland) Limited 1997 SLT 153 | A pursuer's title to sue, although incomplete or qualified, can be perfected during the course of proceedings in certain circumstances. | The court distinguished this case from the present, finding the Plaintiff's position regarding assignors' claims did not fall within this category as no title existed initially. |
British Railways Board v Strathclyde Regional Council 1981 SC 90 | A writ that is "fundamentally null" will not interrupt prescription. | The court found the summons as served was not fundamentally null in respect of the Plaintiff's own claims. |
Gordon's Trustees v Campbell Riddell Breeze Paterson LLP 2017 SLT 1287 | The prescriptive period begins when the obligation to make reparation becomes enforceable. | The court confirmed the prescriptive period began on the date of the fire for the claims in this case. |
Donoghue v Stevenson 1932 SC (HL) 31 | The neighbour principle establishing duty of care to avoid causing foreseeable harm to neighbours. | The court accepted the Plaintiff's duty of care claim based on this principle in relation to fire damage to neighbouring premises. |
Goldman v Hargrave 1967 1 AC 645 | Occupiers' duty to remove or reduce hazards on their land to neighbours. | The court cited this authority in support of the duty of care owed by the Defendant as principal contractor. |
Dynamco Ltd v Holland & Hannen & Cubitts (Scotland) Ltd 1971 SC 257 | No duty of care exists for secondary economic losses caused by damage to another's property. | The court noted the Defendant's argument but found the Plaintiff's claim related primarily to primary losses as tenant. |
Heather Capital Limited v Levy & McRae [2017] CSIH 19 | The pursuer must set out the "bare bones" of the case to give fair notice. | The court found the Plaintiff's schedule of loss sufficient at this stage but allowed opportunity to clarify quantum. |
Cabot Financial UK Limited v MacLennan and another [2021] SC ABE 6 | No formal method of intimation is required under the Transmission of Moveable Property (Scotland) Act; intimation is a matter of fact. | The court found the Plaintiff's intimation of assignation sufficient on the evidence presented. |
Christie, Owen and Davies PLC v Campbell 2009 SC 436 | Section 2 of the Transmission of Moveable Property Act is permissive, not prescriptive. | The court would not uphold the Defendant's intimation argument against the Plaintiff. |
Mannai Investment Co Limited v Eagle Star Life Assurance Co Limited [1997] AC 749 | Typographical errors should not alter the parties' clear intention in contract construction. | The court treated the omission of "Music" in the assignation as a typographical error. |
FES Ltd v HFD Construction Group Limited [2024] CSOH 20 | Contractual interpretation requires ascertaining parties' objective intention from the language used. | The court applied this principle to construe the first assignation narrowly. |
Court's Reasoning and Analysis
The court first examined the Plaintiff's title to sue for its own losses. It found that the summons as served met the statutory definition of a "relevant claim" under the Prescription and Limitation (Scotland) Act 1973 despite initial inadequacies in pleading the leasehold interest. The court emphasized that the substance of the claim and the Plaintiff's status as tenant were sufficient to interrupt prescription for the Plaintiff's own losses.
Regarding the assignors' claims, the court undertook a detailed construction of the first assignation. It held that the assignation conveyed only a mandate to litigate on behalf of the assignors and did not transfer property rights or title to sue. Consequently, the Plaintiff lacked title to sue for these claims at the time proceedings were raised. The second assignation, executed after commencement, could not cure this fundamental defect, rendering the action a nullity as to the assignors' claims. Accordingly, those claims were prescribed and dismissed.
The court rejected the Defendant's arguments concerning intimation and execution defects of the first assignation, finding those arguments unpersuasive and not determinative given the primary issue of lack of title.
On the relevancy of the Plaintiff's pleadings, the court found that the Plaintiff had pled a relevant duty of care based on established neighbour principles and that the claim was neither novel nor controversial. The Plaintiff's averments, while not highly detailed, were sufficient at this stage to give fair notice of the claim and its basis.
The court also found that the Plaintiff's averments relating to the Construction (Design and Management) Regulations 2015 were relevant to the issue of control exercised by the Defendant over the site and thus to the negligence claim.
Finally, the court recognized the need for the Plaintiff to revisit its quantum averments to exclude losses attributable to the assignors, given the dismissal of those claims.
Holding and Implications
The court sustained the Defendant's third plea-in-law and dismissed the action insofar as it related to the losses of the assignors, Academy Music Group Limited and Live Nation (Music) UK Limited. The Plaintiff's claim in its own right was not dismissed and was found to be a relevant claim capable of interrupting prescription.
The court ordered the case to be put out by order to allow the parties to address further procedure in light of the decision, particularly concerning the Plaintiff's quantum averments. All questions of expenses were reserved.
No new legal precedent was established; the decision applied existing principles on title to sue, prescription, and the construction of assignations. The direct effect is that the Plaintiff may proceed with its own claims but not on behalf of the assignors.
Please subscribe to download the judgment.
Comments