Contains public sector information licensed under the Open Justice Licence v1.0.
North East Pylon Pressure Campaign Ltd. & anor v. An Bord Pleanala & ors
Factual and Procedural Background
These proceedings concern a judicial review challenge to a decision made by An Bord Pleanála on 19th December 2016, granting planning approval under section 182B of the Planning and Development Act 2000 for the North-South 400kV Interconnector development. This project involves a 400kV overhead line circuit approximately 138km in length, including about 34km in Northern Ireland, linking substations in County Meath and County Tyrone. The interconnector aims to provide a second high-capacity all-Ireland electricity interconnector. The applicants sought various reliefs, including orders of certiorari quashing the approval decision and declarations of breaches of EU Directives and constitutional rights. The procedural history involves extensive environmental impact statements, public submissions, a 35-day oral hearing, and a lengthy inspector's report.
Legal Issues Presented
- Whether EirGrid requires the consent of landowners to make an application for approval under section 182A of the Planning and Development Act 2000.
- Whether EirGrid is entitled to make the application for approval for the North-South Interconnector under section 182A.
- Whether the designation of An Bord Pleanála as competent authority under the PCI Regulation was valid and whether this designation gives rise to bias or affects the validity of the decision.
- Whether the decision of An Bord Pleanála complies with the Environmental Impact Assessment Directive and Habitats Directive.
- Whether the decision was affected by delay or considerations arising from Brexit.
- Whether the planning decision contains an error on the face of the record concerning jurisdiction over development located partly in Northern Ireland.
- Whether the assessment of access, alternatives, health impacts, and other environmental matters was adequate.
- Whether the conditions attached to the approval, including those relating to access and liaison with landowners, were lawful and appropriate.
- Whether the applicants have sufficient standing to bring claims on behalf of affected landowners (jus tertii).
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Frescati Estates v. Walker [1975] I.R. 177 | Establishes that an applicant for planning permission must have a sufficient legal estate or interest to carry out the proposed development; restricts indiscriminate applications by third parties. | The court distinguished Frescati as inapplicable to EirGrid's statutory role under section 182A, noting that EirGrid is a statutory undertaker intending to carry out development and not a mere interloper. |
Electricity Supply Board v. Gormley [1985] I.R. 129 | Confirms statutory powers of ESB to place electric lines without landowner consent subject to compensation; clarifies interest necessary to support planning permission applications. | The court applied Gormley to affirm that ESB has statutory powers and that EirGrid, through its relationship with ESB, has the requisite interest to make the application. |
Electricity Supply Board v. Killross Properties Limited [2016] IECA 210 | Clarifies the regulatory structure and delegation of powers concerning wayleave notices and the distinct roles of ESB, EirGrid, and ESB Networks entities. | The court relied on Killross to reject arguments that ESB delegated its statutory powers unlawfully and to clarify that EirGrid does not have power to issue wayleave notices but procures ESB to carry out construction with statutory powers. |
Callaghan v. An Bord Pleanála [2015] IEHC 357 | Addresses allegations of bias arising from dual roles of An Bord Pleanála; establishes test for reasonable apprehension of bias in planning decisions. | The court applied Callaghan to reject allegations of bias against An Bord Pleanála, noting its limited and administrative role as competent authority under the PCI Regulation. |
Maher v. Minister for Agriculture and Food [2001] 2 IR 139 | Considers constitutional issues arising from implementing EU regulations domestically and the independence of national legislation from EU law. | The court used Maher to support the principle that the PCI Regulation is directly applicable and that designation of competent authority need not be effected by domestic legislation. |
W.T. v. Minister for Justice and Equality [2015] IESC 73 | Confirms the Carltona principle that departmental officials act as the minister’s alter ego and that no express delegation is necessary for administrative decisions. | The court relied on W.T. to reject contention that designation of An Bord Pleanála by a senior official was invalid or lacked authority. |
Fawdry & Co. v. Murfitt [2002] 3 WLR 1354 | Doctrine of de facto officers validates acts of persons acting under colorable authority despite defects in appointment. | The court analogised this doctrine to uphold the validity of An Bord Pleanála’s designation and acts as competent authority even if formal legislative designation were defective (which was not accepted). |
Coppard v. Customs and Excise Commissioners [2003] QB 1428 | Clarifies limits of de facto officer doctrine where knowledge of lack of authority is relevant. | The court applied principles from Coppard analogously to An Bord Pleanála’s designation and found no evidence of knowledge or neglect of invalidity. |
Klohn v. An Bord Pleanála [2009] 1 IR 59 | Interprets the requirements of the EIA Directive regarding the extent of environmental impact assessment and information required. | The court referenced Klohn to conclude that EirGrid was not obliged to assess the environmental effects of alternatives that were discounted on objective grounds. |
Boland v. An Bord Pleanála [1996] 3 I.R. 435 | Establishes criteria for validity of planning conditions leaving matters of detail to be agreed post-permission. | The court applied Boland criteria to uphold conditions imposed by An Bord Pleanála relating to access and construction management plans as matters of detail consistent with proper planning and sustainable development. |
Court's Reasoning and Analysis
The court undertook a detailed analysis of the statutory framework governing the planning consent process for strategic infrastructure developments under the Planning and Development Act 2000, particularly sections 182A and 182B. It examined whether EirGrid required landowner consent to make the application and concluded that the legislation does not mandate such consent. The court distinguished the decision in Frescati Estates v. Walker as inapplicable to EirGrid's statutory role as a transmission system operator empowered to carry out development without landowner consent, especially given the statutory powers of the Electricity Supply Board (ESB) to acquire wayleaves and construct infrastructure.
The court analysed the relationship between EirGrid and ESB, supported by the Infrastructure Agreement, concluding that EirGrid, as the transmission system operator, is the entity intending to carry out the development, while ESB, as transmission system owner, undertakes construction under EirGrid’s direction. The court rejected arguments that the requirement for landowner consent arises from application forms or letters accompanying the application, finding these to be descriptive rather than prescriptive of legal requirements.
Regarding the designation of An Bord Pleanála as competent authority under the PCI Regulation (EU Regulation No. 347/2013), the court held that European regulations are directly applicable and binding without the need for implementing domestic legislation. It found that the designation by administrative letter complied with the regulation and that no legal infirmity arises from this process. Allegations of bias were rejected on the basis that An Bord Pleanála’s role as competent authority is largely administrative and coordinating, without substantive decision-making power that would affect impartiality.
The court addressed concerns about delay and Brexit, finding the delay issue irrelevant to the relief sought and Brexit considerations speculative at the time of the decision. It held that the decision was correctly made considering the UK’s EU membership status at that time and that no legal basis existed to invalidate the decision on Brexit grounds.
On environmental and planning matters, the court reviewed the inspector’s report and supporting evidence. It found that access routes, although not themselves subject to planning consent, were properly considered as part of the environmental impact assessment (EIA). The court upheld the imposition of conditions relating to access, construction management, and liaison with landowners as lawful and appropriate under the Boland criteria. It rejected arguments that the conditions unlawfully delegated decision-making or exceeded the scope of the application.
The court considered the adequacy of the assessment of alternatives, including undergrounding and route options. It found that EirGrid conducted a comprehensive evaluation consistent with the requirements of the EIA Directive and that the inspector’s acceptance of the overhead line as the optimal solution was well-founded. The court rejected the contention that a full EIA of rejected alternatives was required.
Health impact concerns, including electromagnetic fields and childhood leukaemia, were addressed through extensive scientific evidence and expert reports. The court accepted the inspector’s findings that the development complies with international guidelines and that no causal link between exposure and health effects was established.
The court found no merit in arguments that the planning decision unlawfully included development in Northern Ireland or that the applicants had standing to advance claims on behalf of third parties.
Holding and Implications
The court refused all relief sought by the applicants.
The court held that there is no legal requirement for landowner consent for applications made by EirGrid under section 182A of the Planning and Development Act 2000. It affirmed that EirGrid is entitled to make the application as the statutory transmission system operator, with ESB undertaking construction under statutory powers. The designation of An Bord Pleanála as competent authority under the PCI Regulation was lawful and did not give rise to bias or invalidate the decision. The environmental assessments, including access, alternatives, and health impacts, were adequate and supported by extensive evidence. The planning conditions imposed were lawful and appropriate. Finally, the applicants lacked standing to assert certain claims on behalf of affected landowners.
No new precedent was set; the decision confirms the application of existing legal principles to planning consent processes for strategic infrastructure developments involving public utilities and the direct applicability of EU regulations in such contexts. The direct effect of the ruling is to uphold the planning approval granted to EirGrid for the North-South Interconnector project.
Please subscribe to download the judgment.
Comments