Contains public sector information licensed under the Open Justice Licence v1.0.
Village Residents Association Ltd. v. An Bord Pleanala
Factual and Procedural Background
On 30th April 1999, the first named Respondent (the Board), on appeal by the second named Respondent (Company B), granted permission for the change of use of part of the ground floor of existing premises adjoining the Village Inn, Upper Patrick Street, The City, from a hotel facility to a restaurant with a drive-through facility for the sale of hot food for consumption off the premises, subject to conditions. The Applicant, incorporated on 24th June 1999 as a company limited by guarantee representing members of the local community concerned with the preservation and protection of local amenities, initiated judicial review proceedings challenging the Board's decision. The Applicant sought leave to apply for relief including an order of Certiorari to quash the Board's decision on the basis that the Board did not give adequate reasons for granting permission, particularly regarding an alleged material contravention of the development plan.
The application for leave was heard over three days in October 1999 before Judge Geoghegan, who granted leave on one ground related to the adequacy of reasons given by the Board. Company B challenged the Applicant's locus standi during the hearing. The freehold owner of the premises, a private individual, is not a party to the proceedings and has commenced development in accordance with the Board’s decision. Two applications are before the Court: Company B’s application seeking security for costs from the Applicant, and the Applicant’s application seeking a pre-emptive costs order, exemption from furnishing security for costs, and an order for costs incurred to date.
Legal Issues Presented
- Whether the Court has jurisdiction to grant a pre-emptive costs order protecting the Applicant from liability for costs to other parties in these proceedings.
- Whether the Applicant should be required to provide security for costs to Company B under Section 390 of the Companies Act, 1963.
- Whether an order should be made in relation to the reserved costs from the previous interlocutory stage of the proceedings.
Arguments of the Parties
Applicant's Arguments
- The Court has jurisdiction to grant a pre-emptive costs order analogous to the English High Court’s jurisdiction recognized in R. -v- Lord Chancellor, ex p, CPAG.
- The case involves a public interest challenge warranting protection from adverse costs orders.
- The Applicant should not be required to provide security for costs, as this would stifle a legitimate claim and the Applicant possesses special circumstances.
- The Applicant seeks costs incurred to date against the Board and Company B jointly and severally.
Company B's Arguments
- The Applicant should provide security for costs pursuant to Section 390 of the Companies Act, 1963, as the Applicant is unlikely to be able to discharge a costs order at the conclusion of proceedings.
- The provision of security for costs may be a quid pro quo for the Applicant’s locus standi.
- The Applicant’s challenge does not raise issues of general public importance and does not meet the criteria established for pre-emptive costs orders.
The Board's Position
- The Board did not contest the existence of jurisdiction for pre-emptive costs orders but did not support the Applicant’s entitlement to such an order in this case.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Lancefort Limited -v- An Bord Pleanala [1998] 2 ILRM 401 | Principles on locus standi for companies incorporated to represent community interests and the possibility of security for costs as a factor in locus standi challenges. | The Court relied on this precedent to uphold the Applicant’s locus standi and to acknowledge that security for costs applications may follow. |
R. -v- Lord Chancellor, ex p, CPAG [1998] 2 All ER 755 | Jurisdiction to grant pre-emptive costs orders in public interest challenges and the criteria for such orders. | The Court considered the principles set out by Dyson J. regarding pre-emptive costs orders but found the present case did not meet the necessary criteria. |
McDonald -v- Horn [1995] 1 All E.R. 961 | General rule that costs follow the event and the difficulty of granting pre-emptive costs orders in ordinary litigation. | Quoted to emphasize the rarity and exceptional nature of pre-emptive costs orders. |
State (Fitzgerald) -v- An Bord Pleanala [1985] I.L.R.M 117 | Planning authority’s consideration of injury caused by unlawful structures is restricted in retention permission applications. | Applied to reject the Applicant’s argument that ongoing development undermined the Court’s jurisdiction. |
Lismore Homes Ltd (in Receivership) -v- Bank of Ireland Finance Ltd [1997] 1 I.R. 501 | Strength of a party’s case is generally irrelevant to security for costs applications except in unanswerable cases. | Referenced to confirm that the Applicant’s established substantial grounds do not constitute special circumstances to refuse security. |
Comhlucht Paipear Riomhaireachta Teo -v- Udaras na Gaeltachta [1990] 1 I.R. 320 | Similar principle on the strength of a case in security for costs applications. | Supported the principle that the merits do not usually influence security for costs decisions. |
Fallon -v- An Bord Pleanala [1992] 2 I.R. 380 | Supreme Court’s reluctance to entertain security for costs applications on questions of law of public importance on appeal. | Considered in assessing whether the matter raised a question of law of public importance. |
Blakeston Limited, Beauross Limited -v- Kennedy | Delay in seeking security for costs may preclude the making of such an order if the other party is prejudiced. | Applied to find no delay or prejudice in the timing of Company B’s application. |
Lancefort Limited -v- An Bord Pleanala [1998] 2 IR 511 | Security for costs as a mechanism to ensure commitment by company members in planning challenges. | Used to support the Court’s view that the Applicant’s bona fides require cautious consideration and that security for costs may be appropriate. |
Court's Reasoning and Analysis
The Court began by considering the Applicant’s entitlement to a pre-emptive costs order, noting that such orders are exceptional and typically confined to public interest challenges involving issues of general public importance where the Applicant has no private interest. The Court found that the Applicant’s members have a private interest in the outcome and that the issue granted leave did not raise a sufficiently immediate question of general public importance. Furthermore, the Court did not have sufficient appreciation of the merits to justify such an order and rejected the notion that Company B, a private company, should be penalised by such an order.
Regarding security for costs, the Court acknowledged the accepted criteria under Section 390 of the Companies Act, 1963, including the presumption that a plaintiff unlikely to pay costs should provide security unless special circumstances exist. The Court considered the argument that security might be a quid pro quo for locus standi in this context, referring to relevant case law. It rejected all asserted special circumstances, including the claim of public importance, alleged collusion between Company B and the property owner, the Applicant’s substantial grounds, delay, and alleged intent to stifle the claim. The Court found no evidence justifying refusal of security for costs and ordered the Applicant to provide security, with the amount to be quantified by the Master, and stayed further proceedings until security is furnished.
Finally, the Court addressed the reserved costs from the interlocutory application for leave, holding that absent statutory authority or agreement, it had no jurisdiction to determine costs on an interlocutory application at this stage and declined to make any order regarding costs.
Holding and Implications
The Court granted Company B's application for security for costs and dismissed the Applicant's application for a pre-emptive costs order and related relief.
ORDER: The Applicant is ordered to provide security for Company B’s costs of opposing the proceedings. All further proceedings are stayed pending the provision of such security. No order is made regarding the reserved costs from the prior interlocutory application.
The direct effect of this decision is to require the Applicant to secure costs before continuing the judicial review challenge, potentially limiting the Applicant's ability to proceed if members do not finance the security. No new legal precedent was established beyond the Court's application of existing principles to the facts of this case.
Please subscribe to download the judgment.
Comments