Contains public sector information licensed under the Open Justice Licence v1.0.
Connolly v. Casey
Factual and Procedural Background
The Plaintiff commenced proceedings against the Defendants, solicitors, alleging professional negligence in relation to their handling of a personal injury claim against her former employer, the Board of St. James's Hospital. The Plaintiff contended that the Defendants negligently issued proceedings against the wrong defendant, the Eastern Health Board, and failed to serve the Plenary Summons properly or to issue proceedings within the statutory time against the correct employer. As a result, the Plaintiff’s claim against the true employer was statute barred.
The Defendants joined a Third Party, a barrister, contending that if the Plaintiff succeeded, they were entitled to indemnity or contribution from the Third Party for any damages and costs awarded. The Third Party applied to have the Third Party Notice struck out (treated as an application to set aside the Third Party proceedings) on the basis that the Defendants failed to serve the Third Party Notice "as soon as reasonably possible" as required by Section 27(1)(b) of the Civil Liability Act, 1961.
The original action began with a Plenary Summons issued in February 1995, with the Statement of Claim filed in March 1995. The Defendants delayed responding until March 1996, partly due to delayed confirmation of insurance cover and administrative errors. The defence was delivered in April 1996, including pleas alleging that the Defendants acted on the advice of Counsel (the Third Party) in issuing proceedings against the Eastern Health Board and that any negligence was attributable to the Third Party.
The Defendants sought particulars from the Plaintiff, which were not provided until January 1997. The Defendants also delayed applying to join the Third Party until July 1997, with the Third Party Notice served in October 1997. The Court considered the delays and explanations provided by the Defendants in relation to the timing of the Third Party Notice service.
Legal Issues Presented
- Whether the Defendants served the Third Party Notice on the Third Party "as soon as reasonably possible" pursuant to Section 27(1)(b) of the Civil Liability Act, 1961.
- The proper interpretation and application of the statutory requirement to serve a Third Party Notice within a reasonable timeframe.
- The consequences of any delay in serving the Third Party Notice, including whether the Court should exercise its discretion to refuse the order for contribution or indemnity.
Arguments of the Parties
Defendants' Arguments
- The Defendants argued entitlement to indemnity or contribution from the Third Party if found liable.
- They contended that delays in serving the Third Party Notice were justified by the need to await replies to particulars from the Plaintiff and a detailed statement from their former associate solicitor, Mr. Murphy.
- The Defendants maintained it was improper to apply to join the Third Party without the statement from Mr. Murphy, who was not a party and could not be compelled to provide it sooner.
- The Defendants relied on prior advice from the Third Party and pleaded negligence against him in the defence as early as April 1996.
Third Party's Arguments
- The Third Party sought to have the Third Party Notice set aside on the basis that it was not served as soon as reasonably possible, contrary to the statutory requirement.
- The Third Party relied on the Defendants' failure to comply with the timing requirements under Section 27(1)(b) and Order 16 of the Rules of the Superior Courts.
Table of Precedents Cited
Precedent | Rule or Principle Cited For | Application by the Court |
---|---|---|
Board of Governors of St. Laurence's Hospital v. Staunton [1990] 2 IR 31 | Interpretation of Section 27(1)(b) Civil Liability Act 1961: Third Party Notice must be served "as soon as reasonably possible". | The Court adopted the Supreme Court's strict interpretation that no Third Party Notice can be served later than "as soon as reasonably possible", leading to the setting aside of the Third Party proceedings due to delay. |
Dillon v. MacGabhann (Morris J., 1995) | Timing to be considered is the date of service of the Third Party Notice. | The Court preferred this view over the alternative that the date of issue of the application is determinative, applying it to assess the delay. |
McElwaine v. Hughes (Barron J., 1997) | Onus on Defendants to prove delay was not unreasonable; some flexibility in "as soon as reasonably possible". | The Court agreed with the onus placement and the need for flexibility but emphasized that delay must still be justified. |
SFL Engineering Limited v. Smyth Cladding Systems Limited (High Court, 1997) | Application of Section 27(1)(b) and procedural rules regarding Third Party Notices. | The Court referenced its own prior reasoning consistent with the current decision. |
Reidy v. National Maternity Hospital (Barr J., 1997) | Requirement of reasonable grounds and expert advice before commencing professional negligence claims. | The Court distinguished this case, noting that expert evidence was not required here, and thus the Defendants should have applied to join the Third Party earlier. |
Court's Reasoning and Analysis
The Court examined the statutory requirement under Section 27(1)(b) of the Civil Liability Act, 1961, which mandates that a Third Party Notice must be served "as soon as reasonably possible" where the person from whom contribution is sought is not already a party to the action. The Court reviewed relevant precedents, notably the Supreme Court decision in St. Laurence's Hospital, which emphasized the strict timing requirement.
The Court considered conflicting High Court views on whether the relevant date for assessing delay is the date of service of the Third Party Notice or the date of issue of the application to serve it, preferring the former as consistent with statutory wording.
The Court analyzed the timeline and reasons for delay: the initial delay awaiting insurer confirmation was considered not unreasonable; however, the subsequent delay between insurer confirmation and serving a Notice for Particulars, and notably the delay between delivering the defence (April 1996) and serving the Third Party Notice (October 1997), was scrutinized critically.
The Court found that the Defendants had sufficient information by April 1996, evidenced by the defence containing allegations of negligence against the Third Party, to justify applying to join the Third Party at that time. The explanations for delay, including awaiting replies to particulars and a statement from Mr. Murphy, were found unsatisfactory. The Court emphasized that Mr. Murphy was not a party and could not be compelled, but the Defendants should not have delayed the application awaiting his cooperation, especially given their prior knowledge and possession of relevant documents, including the Third Party's advice and signed Plenary Summons.
Further unexplained delay occurred between the swearing of the affidavit supporting the application (April 1997) and the hearing date (October 1997). The Court concluded that the Third Party Notice was not served as soon as reasonably possible.
Applying the legal principles and precedents, the Court exercised its discretion to set aside the Third Party proceedings due to the unjustified delay, consistent with the statutory mandate and judicial interpretation.
Holding and Implications
The Court ORDERED that the Third Party proceedings be set aside on the basis that the Third Party Notice was not served as soon as reasonably possible in accordance with Section 27(1)(b) of the Civil Liability Act, 1961.
The direct effect of this decision is that the Defendants are precluded from claiming contribution or indemnity from the Third Party in this action. The Court did not establish any new precedent but reaffirmed the strict statutory requirement and the importance of timely service of Third Party Notices. No broader implications beyond the parties involved were discussed.
Please subscribe to download the judgment.
Comments