Item No. 04 Court No. 1
BEFORE THE NATIONAL GREEN TRIBUNAL
PRINCIPAL BENCH, NEW DELHI
(By Video Conferencing) Original Application No. 125/2017 (With report dated 15.02.2021) Court on its own Motion Applicant Versus
State of Karnataka Respondent Date of hearing: 12.03.2021
CORAM: HON'BLE MR. JUSTICE ADARSH KUMAR GOEL, CHAIRPERSON HON'BLE MR. JUSTICE SHEO KUMAR SINGH, JUDICIAL MEMBER HON'BLE DR. NAGIN NANDA, EXPERT MEMBER
Applicant/ Amicus Curie: Mr. Raj Panjwani, Senior Advocate with Mr. Saransh Jain, Advocate
Respondent(s): Ms. Madhvi Divan, Additional Solicitor General with Mr. KM Darpan, Advocate for State of Karnataka
Mr. Brijendra Chahar, Senior Advocate with Mr. Kashi Vishweshwar, Advocate for BBMP
Mr. Raj Kumar, Advocate for CPCB
Mr. Balaji Srinivasan, Advocate for BWSSB
ORDER
1. The issue for consideration is remedial action for restoration of Bellandur, Agara and Varthur lakes at Bangalore, including preventing discharge and dumping of pollutants, removing encroachments from catchment area and other steps for restoration.
2. The matter has been dealt with by this Tribunal on several occasions in the last almost four years. The Tribunal earlier constituted a Committee headed by Shri Raj Panjwani, Senior Advocate (now assisting the Tribunal
1
as Amicus) to visit the site to assess the factual position and to suggest further course of action.
Report dated 31.5.2018 about the status of degradation of lakes and further orders for remedial action - appointment of monitoring Committee headed by Justice Santosh Hegde
3. Accordingly, the Committee gave its report dated 31.05.2018 which was dealt with by this Tribunal, vide order dated 06.12.2018. While accepting the report, the Tribunal directed preparation of an action plan with timelines and budgetary support under the overall supervision of Additional Chief Secretary, Urban Development Department (UDD), Karnataka and the Bruhat Bengaluru Mahanagara Palike (BBMP). Execution of the action plan was to be overseen by the Monitoring Committee headed by Justice Santosh Hegde, former Judge of the Hon'ble Supreme Court.
Order of the Tribunal dated 21.10.2019 and Supreme Court order dated 22.11.2019
4. The matter was thereafter considered by this Tribunal on 21.10.2019 in the light of reports of the Monitoring Committee dated 27.05.2019 and 20.09.2019. The Tribunal found continuing violation of environmental norms and required the personal presence of the Additional Chief Secretary, Urban Development, Karnataka, Commissioner, BBMP, Commissioner, Bangalore Development Authority (BDA), Chairman, Bangalore Water Supply and Sewerage Board (BWSSB) and the Member Secretary, State PCB with compliance reports and explanation for violation of earlier orders of the Tribunal.
The said order was affirmed by the Hon'ble Supreme Court vide order dated 22.11.2019 in Civil Appeal No. 9666-68 of 2019, State Of Karnataka v. D. Kupendra Reddy.
2
Further order dated 18.12.2019 considering compliance status
5. The matter was thereafter considered on 18.12.2019 in the personal presence of the officers and in the light of status report furnished under 37 headings, including steps for preventing discharge of solid and liquid waste into the lake, removing encroachments, removing illegal construction inside the lake, de-silting and de-weeding etc. The Tribunal discussed all the relevant aspects in paras 14 to 27 of the order and finally issued following directions:
"28. We may now sum up our directions as follows:
i. Timelines for execution of projects for setting up of STPs and laying of sewerage network may not be extended beyond 30.09.2020. If the works remains incomplete even till 30.09.2020, compensation will be liable to be paid @ Rs. 10 lakh per STP per month which may be liable to recovered from the erring officers, apart from adverse entries in their service records and other adverse action.
ii. Bangaluru Water Supply and Sewerage Board (BWSSB) must ensure that no sewage/effluent is discharged into the lakes and till setting up of STPs, interim remediation must be done forthwith. Any default in this regard will result in requirement to pay compensation of Rs. 5 lakh per month per inlet into the lakes from
01.02.2020.
iii. BSWWB may further ensure that treated water is not discharged into the UGB network. Action may be taken against persons responsible for having allowed this to be done earlier resulting into loss of Rs. 2 Lakhs per day i.e. Rs. 60 Lakhs per month and more than Rs. 7 Crore per year without any justification whatsoever.
iv. Sources of discharge of sewage be controlled/regulated and electricity and water supplies to the defaulting establishments be stopped for enforcement of law till remedial steps are taken for compliance.
v. Encroachments which are still continuing be removed by using force wherever necessary. If any injunction has been granted by any Court which is considered erroneous, higher forum can be moved so that law is upheld.
3
vi. Action against erring officers which has not yet been taken must be initiated forthwith as already directed. Failures of officers still in service should be duly reflected in their ACRs.
vii. The State PCB itself may lay down standards for phosphorus instead of waiting for notification by MoEF&CC.
viii. The State of Karnataka may either resolve the issue of fencing with the Defence establishment or put such establishments to notice to place their objections before this Tribunal within one month of such notice after which the State of Karnataka will be at liberty to proceed with the fencing and such Defence establishment will stand restrained from interfering unless otherwise directed by this Tribunal or any other authority.
ix. Compensation already assessed be recovered by adopting coercive measures such as disconnection of electricity and water supplies.
x. Steps be taken expeditiously for de-silting, de- weeding. Analysis of sludge and silt may be carried out before its disposal based on the result of such analysis, the mode of disposal and protocol be determined in accordance with laid down principles under the relevant Rules.
xi. The State PCB may develop a robust water quality monitoring progame for monitoring of water quality of drains leading to the lakes and also undertake water quality monitoring at atleast 5 locations for each lake.
xii. Steps may be taken to explore development of wetlands and bio-diversity parks apart from other remedial action for reducing the pollution load on the recipient water bodies.
xiii. C&D waste processing facility be commissioned expeditiously and steps be taken to ensure that the timeline proposed is adhered to.
xiv. Real time water quality system be commissioned by 31.01.2020 as proposed.
xv. The issue of removing 1.5 km road laid upon the lake bed, within the boundary of Varthur lake, by dumping of C&D debris be finalized as per directions of Justice Hegde Committee in terms of para 26 above.
29. The Monitoring Committee headed by Justice Hegde may also review the progress made in terms of all the issues
4
considered in the order of this Tribunal dated 06.12.2018 and submit its report on or before 06.03.2020 by e-mail at judicial- ngt@gov.in. The Monitoring Committee may also give its findings to the Chief Secretary of Govt. of Karnataka. Considering that the entire exercise requires inter sectional and inter departmental coordination, Chief Secretary, Karnataka may steer the action of different departments and bodies. We extend the tenure of Monitoring Committee till 31.03.2020."
Order dated 13.8.2020 considering further progress
6. The matter was last considered on 13.08.2020 in the light of the report of the Monitoring Committee dated 06.03.2020 and response of the State dated 11.06.2020 and by way of earlier affidavit. The summary of compliance status was filed by the State of Karnataka on 04.08.2020 during the last hearing. The Tribunal considered the compliance status so presented and also the report of the Monitoring Committee and directed that the leftover work may be expeditiously completed, which may be reviewed by the Monitoring Committee and status of compliance as on 31.12.2020 be furnished to this Tribunal by 15.01.2021 with a copy to the Chief Secretary, Karnataka. It was further directed that the Chief Secretary, Karnataka may file consolidated report covering the steps taken by various departments. The concluding part of the above order of the Tribunal is as follows:
"10. The steps taken by the BBMP or other departments can be looked into by the Monitoring Committee. Objections/suggestions of individuals including letter dated 13.02.2020 from A.N. Yellappa Reddy, Chairman, Bangalore Environment Trust need not be considered by the Tribunal as the same can be considered by the Monitoring Committee.
11. In view above, the left-over work may be expeditiously completed which may be reviewed by the Monitoring Committee. The status of compliance as on 31.12.2020 may be compiled by the Monitoring Committee and report furnished to this Tribunal by 15.01.2021 with a copy to the Chief Secretary, State of Karnataka. The Chief Secretary, State of Karnataka may furnish a consolidated report covering the steps taken by all the concerned Departments.
The individual Departments need not file separate reports before
5
this Tribunal once the same are filed before the Monitoring Committee and the Chief Secretary, Karnataka. The Chief Secretary, Karnataka may give its own report by 31.01.2021 by e-mail at judicial-ngt@gov.in preferably in the form of searchable PDF/OCR Support PDF and not in the form of Image PDF."
Latest reports of the Monitoring Committee as on 31.1.2021and the Chief Secretary
7. Accordingly, the Monitoring Committee has filed its report on 15.02.2021 giving the progress upto 31.01.2021 in a tabular form as follows:
Contd. at next page
6
"
| Sl. no | Directions of Hon’ble NGT vide orders dated 06.12.2018, 18.12.2019 and 13.08.2020 | Progress up to 31.01.2021 and Committee observations | 
| 1 | Relevant para | 3 | 
| 1. | Para 28(i) Order dated 18.12.2019: Timelines for execution of projects for setting up of STPs and laying of sewerage network may not be extended beyond 30.09.2020. If the works remains incomplete even till 30.09.2020, compensation will be liable to be paid @ Rs.10 lakh per STP per month which may be liable to recovered from the erring officers, apart from adverse entries in their service records and other adverse action. Further, the NGT vide order dated 13.08.2020 has directed that, the works may be expeditiously completed and to be reviewed by the Monitoring Committee. | In regard to the construction of STPs and their commission, the details are given as under (BWSSB): i. Sarakki – 5 MLD STP Completed and commissioned on 31.03.2020 ii. Agram – 35 MLD STP Completed and commissioned on 31.03.2020 v. Construction of 210 MLD capacity ISPS The work is completed and ready for operation. The water will be at Koramangala at sports complex pumped to 150 MLD STP, once the remaining pipe network is completed, (yet to complete 252 Rmt) | 
| Sl. no | Name of the STP / others | Compliance | 
| Completed and commissioned on 08.11.2019 | ||
| ii. | Chikkabeguru - 5 MLD STP | Completed and commissioned on September 2020. | 
| i. | Hulimavu – 10 MLD STP | |
| iii. | Madivala – 4 MLD STP | 24.5% work completed | 
| iv. | K&C Valley – 150 MLD STP | 90.01 % works completed as on 31.01.2021. Primary treatment is in progress and likely to be completed by 31.03.2021 and expected to treat 83MLD sewage (with this augmentation, 536 MLD (92%) would be treated as against 583 MLD) | 
| vi. | Laying of 800 mm UGD from 210 MLD ISPS to 150 MLD STP | Against the 5315-running meter; 5063 running meter is completed. Likely to be completed by 31.03.2021. | 
| vii. | Waste water wet well – 32.5 MLD Capacity near the premises of 90 MLD Bellanduru Amanikhane STP to augment sewage from the adjoining areas of Bellanduru Amanikhane STP (date fixed for completion 30.09.2020) | The overall progress as on 31.01.2021 is 45.75 % against the planned target of 100.00%. This work will be completed before 31.03.2021. However, the temporary arrangement has been made for pumping sewage to Bellandur Amanikhane STP. | 
7
| 2. | Para No.14 Order Dated 18.12.2019 We also found that timelines fixed by this Tribunal have been unilaterally extended without any valid justification and no action has been taken against the erring officers on a specious plea that it was difficult to fix responsibility. Such approach is hardly compliant with the Rule of Law. We particularly disapprove the timeline for upgradation of STPs with Biological Nutrient Removal (BNR) at 248. MLD STP at K&C Valley. The same must not go beyond 30.09.2020 but preferably be completed before 30.06.2020 although earlier timeline fixed by this Tribunal was 30.06.2019. No substantial work has been done in the last one year on this aspect. | The BWSSB submits that, STPs of 90 MLD at Bellandur Amanikere; 60 MLD at K&C Valley; 5 MLD at Sarakki; 5 MLD at Chikkabegur; 10 MLD Hulimavu; 35 MLD at Agram and 150 MLD at K&C Valley (under construction) are complied with Biological Nutrient Removal treatment. The BWSSB further submits that for the 248 MLD STP at K&C Valley, certain modifications in the process of treatment have been made in consultation with the IISc, Bengaluru, for removal of nutrients. On sample analysis it is found that the biological nitrates have been reduced substantially (nitrogen 6.4 mg per ltr and phosphates 0.85 mg per ltr). It is noted that, the treated water from these STPs is being transmitted to the tanks in Kolar Districts for recharge of ground water for irrigation purpose. However, the upgradation of the system has not been completed but is in process. | 
| 3. | Para 28(ii) Order dated 18.12.2019: Bengaluru Water Supply and Sewerage Board (BWSSB) must ensure that no sewage/effluent is discharged into the lakes and till completing of STPs, interim remediation must be done forthwith. Any default in this regard will result in requirement to pay compensation of Rs.5 lakh per | It is submitted that, the sewage water has been diverted through the peripheral temporary diversion channels and no sewage water enters in these lakes (Agram, Bellanduru and Varthur). Further, the BWSSB has installed aerating systems in these temporary diversion channels at, 1) HAL side and Kempapura inlet, 2) Agaram inlet, 3) Koramangala inlet, 4) Iblur inlet coming under Bellandur Lake, 5) Northern and 6) Sothern side of Varthur lake for inline treatment of sewage. The artificial floating islands have also been installed at certain places. The committee has suggested to augment phytoremediation options at locations, where the water flow is slow or stagnant to enhance the treatment efficacy, which is yet to be implemented. | 
8
| month per inlet into the lakes from 01.02.2020. | ||
| 4. | Para 28(iii) Order dated 18.12.2019: BSWWB may further ensure that treated water is not discharged into the UGD network. Action may be taken against persons responsible for having allowed this to be done earlier resulting into loss of Rs.2 Lakhs per day i.e.Rs.60 Lakhs per month and more than Rs.7 Crore per year without any justification whatsoever. BY BWSSB | There are about 496 buildings having STPs as per the KSPCB records. The BWSSB submits that, wherever there was connectivity with the UGD for flowing of treated water; all have been disconnected (109 buildings). For the remaining areas there is no access to networking of UGD. The BWSSB submits that, treated water was allowed as per the conditions stipulated in the order issued by KSPCB. In view of these facts and circumstances, it is requested by BWSSB not to initiate action against their officials. | 
| 5. | Para No.16 Order Dated 18.12.2019 We are informed that about 256.7 MLD untreated sewage is entering the lake from five locations which is nothing but a criminal offence which is required to be checked on war footing and violators of law brought to justice, erring officer being appropriately dealt with under the civil, criminal and service law with a view to uphold the Rule of Law. There is large scale breach of public duties by concerned Authorities dealing with the subject and earlier observations of this Tribunal have fallen on deaf ears and blatantly flouted. | The BWSSB submits that to check the flow of sewage water into the lakes, following works have been completed. 1. HAL SWD (Challaghatta Valley) – Totally 23 works are to be taken up for augmenting this flow, out of which 23 works are completed as on 23.12.2020. 2. Koramangala and Agram Valley -Totally 48 works are to be taken up for augmenting this flow out of which 48 works are completed on 23.12.2020. 3. Iblur Catchment area- Completed and Commissioned on 23.12.2020. 4. Kempapura Catchment area- BWSSB has taken up work of laying 300 mm RCC NP3 sewer line for a length of 1000 RMT to convey the sewage generated in the area of Bellanduru Amanekhane STP. The work is completed and commissioned in the month of May 2020. The BWSSB submits that, the combined treatment capacity in the catchment of these lakes will be around 664.50 MLD against the presently measured flow of 553 MLD. Presently, about 453.50 MLD of sewage is being treated. Additional treatment of 83 MLD would be augmented by commissioning of new STP (end of March 2021). Therefore, there will be treatment of 536.50 MLD (92 %) as against the measure flow of 583 MLD. The Committee observes that the BWSSB has to take steps to treat the remaining 8 to 10 % of sewage to stop completely the flowing of sewage into the lakes after rejuvenation. It is submitted here that, as per the earlier recommendations of the Committee, the water level in these lakes will be maintained by supplying treated water from the STPs daily to compensate evaporation and seepage losses. Only the surplus treated water should be allowed to flow to Kolar, Chikkaballapur, Anekal etc. | 
9
| 6. | Para 28(iv) Order dated 18.12.2019: Sources of discharge of Sewage be controlled/ regulated and electricity and water supplies to the defaulting establishments be stopped for enforcement of law till remedial steps are taken for compliance. | The KSPCB has identified 91 units in total that are required to be installation of STP. The details of progress are given as under:- No. of units Installed STP 42 No. of units connected to BWSSB 06 No. of units with STP under construction 07 No. of units issued with Closure orders for either not having STPs or not connected to UGD and letting 10 the raw sewage into the storm water drain Action yet to be taken 26 | 
| 7. | Para 28(v) Order dated 18.12.2019: Encroachments which are still continuing be removed by using force wherever necessary. If any injunction has been erroneous, higher forum can be moved so that law is upheld. | An area of 5.20 Acres in Sy.No.319 was granted to a person from the village of Amani Bellanduru kane during 1976- 77 and a new survey number 477 have been formed. This survey number was the part of Varthur lake. The matter is under process for cancelation of grant and pending before the concerned Assistant Commissioner. The other encroachments are stated as removed. Illegal constructions in Ballandur lake (named as Ambedkar Nagar slum) are yet to be evicted | 
| 8. | Para 28(vi) Order dated 18.12.2019: Action against erring officers which has not yet been taken must be initiated forthwith as already directed. Failures of officers still in service should be duly reflected in their ACRs. | The Additional Chief Secretary, Urban development Department, has submitted the following details in regard to action initiated in the subject matter. The same is produced here for further needful. 1) Bengaluru Development Authority : Sl. No Name of erring officer/ official Designation and Period Rizwan Baig Executive Engineer 1. From 2010 to 2011 & 2015 to 2016 2. S.Mallikarjuna Executive Swamy Engineer from 2010 to 2011 & 2015 to 2016 3. Ravi Narayana Executive Engineer Reddy from 2010 to 2011 & 2015 to 2016 | 
10
| Notices were served to erring officials on 19.02.2020 seeking their replies within 15 days. Replies were received from all the above mentioned officials. On scrutiny of the explanations given by them, the Additional Chief Secretary (ACS), submits that the replies are found acceptable. 2) BBMP : Period from 20.09.2008 to 03.05.2011 Name of erring Sl. No Designation and Period Present Dept officer/ official 1. J.C.Prakash Murthy Assistant Engineer (1.10.2008 to 30.11.2009) PWD 2. H.P.Mohan Kumar Assistant Executive Engineer (2.03.2009 to 3.1.2011) PWD 3. H.Chandrappa Assistant Engineer, K.R.Puram Sub- Division, PWD (2.12.2009 to 11.1.2012) 4. J.C.Prakash Murthy Assistant Executive Engineer, (after promotion) PWD (2.12.2009 to 7.7.2010) The State Government vide No.UDD/91/MNJ/2017, Dated.11.12.2020 directed BBMP to take necessary action on the erring officials as per the directions of the Hon’ble NGT and to submit a compliance report by 20.12.2020. The draft charges memo has been submitted to the concerned Administrative Department i.e., PWD for further necessary action. 3) BWSSB Sl. No. Name Designation 1. Chief Engineer (29.03.2014 to 11.06.2013) & as Chief Engineer 2. S.M. Ramakrishna WWM (I/c) & (11.06.2014 to 31.07.2014) as Chief Engineer WWM 3. S.R. Roopa Kumar Additional Chief Engineer (31.010.2007 to 05.06.2008) 4. S.P. Rudra Murthy Additional Chief Engineer (05.06.2008 to 13.06.2012) 5. V. Mahesh Additional Chief Engineer (27.03.2013 to 10.07.2015) 6. 7. B.M. Purushotham Executive Engineer (29.10.2007 to 23.05.2008) 8. C. Abdul Nazir Executive Engineer (23.05.2008 to 04.01.2012) Executive Engineer (04.01.2012 to 31.08.2012) & from 31.08.2012 9. B.N. Sidda Gangaiah to 15.11.2012 10. C.C. Putta Mallappa Executive Engineer (15.11.2012 to 26.08.2013) 11. B.S.C. Soma Shekar Executive Engineer (26.08.2013 to 07.06.2014) | ||
| S.M. Basavaraju | Chief Engineer (14.11.2006 to 08.04.2013) & 10.05.2013 to 29.03.2014) | 
Chief Engineer (29.03.2014 to 11.06.2013) & as Chief Engineer
2. S.M. Ramakrishna WWM (I/c) & (11.06.2014 to 31.07.2014) as Chief Engineer WWM
3. S.R. Roopa Kumar Additional Chief Engineer (31.010.2007 to 05.06.2008)
4. S.P. Rudra Murthy Additional Chief Engineer (05.06.2008 to 13.06.2012)
5. V. Mahesh Additional Chief Engineer (27.03.2013 to 10.07.2015)
6. K.R. Manjunath Additional Chief Engineer (10.07.2015 to 28.10.2016)
7. B.M. Purushotham Executive Engineer (29.10.2007 to 23.05.2008)
8. C. Abdul Nazir Executive Engineer (23.05.2008 to 04.01.2012) Executive Engineer (04.01.2012 to 31.08.2012) & from 31.08.2012
9. B.N. Sidda Gangaiah to 15.11.2012
10. C.C. Putta Mallappa Executive Engineer (15.11.2012 to 26.08.2013)
11. B.S.C. Soma Shekar Executive Engineer (26.08.2013 to 07.06.2014)
11
| The ACS submits that officers who have worked in the specified period have been identified and show cause notices have been issued to them. The replies obtained from these officers have been reviewed and found to be not acceptable. Hence, the formal approval of the Government has been sought vide letter dated.26.05.2020 for initiating disciplinary proceedings on all the concerned retired officers of BWSSB. In this regard, the State Government in letter dated.27.10.2020 has accorded approval to conduct department enquires on all the concerned retired officers of the Board. As per rule 214 (2)(B)(i) and (ii) of KCSR, action has been initiated to conduct Departmental enquiry and for this purpose show-cause notices have been issued to all the retired officers on 18.12.2020 giving 15 days’ time to submit their replies. All the retired officers have sought many details and additional time for furnishing their replies. After getting their replies, further action will be initiated. | ||
| 9. | Para 28(vii) Order dated 18.12.2019: The State PCB itself may lay down standards for phosphorus instead of waiting for notification. | The KSPCB submits that the Bureau of Indian Standards has issued notification for limiting the Phosphorus content in household laundry detergents powders, household laundry detergents bars and synthetic detergents of washing woollen and silk fabrics. Further they submit that some follow up action has been taken as listed below:- 1. A public notice is issued by KSPCB in this regard in the print media. 2. Letters are addressed to all the State PCB’s to directly implement the order. 3. Letters are addressed to all the soap/detergent manufacturers in the state of Karnataka for the restriction of Phosphorus content. 4. Letter is addressed to MOEF for making a final notification. | 
| 10. | Para 28(viii) Order dated 18.12.2019: The State of Karnataka may either resolve the issue of fencing with the Defence establishment or put such establishments to notice to place their objections before this Tribunal within one month of such notice after which the State of Karnataka will be at liberty to proceed with the fencing and such Defence establishment will stand restrained from interfering unless otherwise | The issue of raising of fencing towards the Defence area have been resolved. The Commissioner, BDA, submits that an estimate is prepared and sent for 4(G) exemption to the Government for the construction of fence. Further, in regard to desilting a portion of the lake, there is a dispute pending with the Defence. | 
12
| directed by this Tribunal or any other authority. | ||
| 11. | Para 28(ix) Order dated 18.12.2019: Compensation already assessed to be recovered by adopting coercive measures such as disconnection of electricity and water supplies. | In regard to this para, the KSPCB submits as under:- Total No. of units issued with notice for EC and Amount. 376 units (Rs.19.85 Crores) No. of units paid EC and Amount 40 units (Rs.2.10 Crores) Action yet to be taken for recovery 336 units M/s. Durga rainbow flat owner’s welfare association has filed an impleading application before the Hon’ble NGT on 30.08.2020. | 
| 12. | Para 28(x) Order dated 18.12.2019: Steps be taken expeditiously for de- silting, de-weeding. Analysis of sludge and silt may be carried out before its disposal based on the result of such analysis, the mode of disposal and protocol be determined in accordance with laid down principles under the relevant Rules. | KSPCB has collected series of samples of Silt/sludge at different depth with grid manner on 25th, 26th & 27th of December 2020. Besides sample collected on 16/09/2020, 18/09/2020, 12/11/2020, 19.12.2020 & 5.1.2021 The CPCB has given a report for Varthur lake based on TCLP and STLC analyses of silt samples. As per the protocol based on TCLP and STLC analyses, the soil is non-hazardous and accordingly the permission is accorded to BDA by KSPCB to dispose silt from the locations showed in the grid map based on local demand. As regards to Bellandur Lake, the analysis of sediment samples for leachability tests is under progress. Desilting of Varthur lake: work order issued on 23.11.2020 to the Agency M/s Star Infra Tech Pvt Ltd. It is submitted that, more soil / silt / sludge samples were collected from the lake bed areas and was analysed. The sediment analysis results based on the screening levels on soil quantity para meters prescribed for agriculture use have been examined by the CPCB and a report is given. Based on the recommendations of CPCB, the KSPCB issued a letter for disposal of the silt for agriculture and other uses. The work of de-silting has commenced by M/s Star Infra Tech Pvt Ltd as per the direction of KSPCB/BDA. Further, the BDA claims that approximately in an area of 100 Acres, silt is removed and stocked in the lake area. This work of removal of silt (100 Acres) is carried out under the 4 (G) exemption. Desilting of Bellandur lake: work order issued on 23.11.2020 to M/s RMN Infrastructure Pvt Ltd. Lake bed pre level survey is done, removal of seepage water and others in the Bellandur lake is completed. BDA claims that under 4(G) exemption, an area of 158 Acres (Bellandur lake) silt is removed and stocked at some places inside the lake. The BDA further submits that the stocked silt will be disposed as per the protocol. | 
13
| 13. | Para 28(xi) Order dated 18.12.2019: The State PCB may develop a robust water quality monitoring program for monitoring of water quality of drains leading to the lakes and also undertake water quality monitoring at atleast 5 locations for each lake. | The KSPCB has a well-equipped laboratory to analyse the samples in house. Samples are being analysed for pH, BOD, COD, TSS, Ammoniacal Nitrogen, Iron and Manganese, Total Nitrogen, Cyanide, Hexavalent Chromium, Cadmium, Copper, Lead, Nickel, Zinc and Total Chromium at KSPCB’s sophisticated Central Laboratory. KSPCB has been advised to undertake water quality monitoring at regular intervals in these lakes and drains (connecting these lakes) and upload (on monthly basis) the water quality information at KSPCB website. | 
| 14. | Para 28(xii) Order dated 18.12.2019: Steps may be taken to explore development of wetlands and biodiversity parks apart from other remedial action for reducing the pollution load on the recipient water bodies. | Provision is made in the estimate for construction of wetland Bellandur and Varthur lakes. Once the identified wetland area within the lake is de-silted, wetland will be developed. Letter has been received from the ADLR (East) dated.06.11.2020 stating that Government land is not available along the periphery of the lake boundary in buffer zone. | 
| 15. | Para 28(xiv) Order dated 18.12.2019: Real time water quality system be commissioned by 31.01.2020 as proposed. | The Board has already installed the Real Time Water Quality Monitoring systems at three locations and continuously monitoring. The results are uploaded on the website. | 
| 16. | Para 28(xv) Order dated 18.12.2019: The issue of removing 1.5 km road laid upon the lake bed, within the boundary of Varthur lake, by dumping of C&D debris be finalized as per directions of Justice Hegde Committee in terms of para 26 above. | The Hon’ble NGT vide order dated 13.08.2020 has held that enquiry should be conducted about the illegality in laying the pipeline by the Minor Irrigation Department. Accordingly, Miner Irrigation department has taken steps as stated in para 21 in this report. | 
| 17. | Para 19(16) of order Order dated 06.12.2018: Post removal of waste from the Lake and from the Rajakaluves, the State ought to prepare a | As regard to removal of waste from the lake area, the desilting work is in progress and once it is completed the left-out waste shall have to be removed. Meanwhile, the BBMP has to prepare a detail project report for the disposal for the same. In regard to removal of waste from the Rajakaluves, the BBMP submits that against approximately 218.0 kms of Rajakaluves (SWD), about 105.149 kms are being maintained. The maintenance includes removal of silt, floating | 
14
| detailed project report with respect to disposal of the same. | tresses, vegetation and other organics and transported to the Anjanapura abandoned stone quarries. A list of drains of 105.149 kms has been provided here as under: 1 MD 428 @ Chainage 2 MD 425 Ramgondanahalli Adarsha Houses 100 0.00m 6 MD 415 Nalluralli Kere 400 7 MD 416 Nalluralli Nalluralli Kere 450 9 16 MD 369 End Point of MD 365 & MD 368 Varthur Kere 500 Kundalahalli Kere 500 Kundalahalli to 18 MD 372 BEML Layout 300 Siddapura 20 MD 375 Siddapura Kere 500 | |||
| Sl. No | Drain No | Drain Name | Length in M | |
| MD 342A | Boganahalli | Panattur Kere | 300 | 
| 3 | MD 428 | Varthur Kere | MD 431 @ Chainage 0.00m | 200 | 
| 4 | MD 413 | Pattanduru Agrahara | Nalluralli Kere | 250 | 
| 5 | MD 414 | Saibaba Hospital | Nalluralli Kere | 450 | 
| Pioneer Software | 
0.00m
MD 431 @ Chainage
3 MD 428 Varthur Kere 200 0.00m
4 MD 413 Pattanduru Agrahara Nalluralli Kere 250
5 MD 414 Saibaba Hospital Nalluralli Kere 450
6 MD 415 Pioneer Software Nalluralli Kere 400
7 MD 416 Nalluralli Nalluralli Kere 450
| 8 | MD 349 | End Point of MD 322 & MD 334 Near ADA Compound Wall | Varthur Kere | 400 | 
| MD 365A | End Point of MD 363 & MD 364 | MD 369 @ chainage 0.00 | 400 | |
| 10 | MD 322 | RHB Colony | Garudacharyapalya Kere | 150 | 
| 11 | MD 322A | Garudacharyapalya Kere | Mahadevpura Kere | 400 | 
| 12 | MD 322C | ITPL Road | Ramakka Layout | 100 | 
| 13 | MD 325 | Outter Ring Road | Doddanenkundi Kere | 300 | 
| 14 | MD 325A | Vinayaka Nagara 8th Cross | MD 325 @ Chainage 0.00 | 500 | 
| 15 | MD 363 | Chinnappanahalli Layout | MD 365 @ Chainage 0.00 | 500 | 
Garudacharyapalya
10 MD 322 RHB Colony 150 Kere
11 MD 322A Garudacharyapalya Kere Mahadevpura Kere 400
12 MD 322C ITPL Road Ramakka Layout 100
13 MD 325 Outter Ring Road Doddanenkundi Kere 300
| 19 | MD 374 | Tuberahalli BEML Layout | MD 375 @ Chainage 0.00m | 230 | 
| End Point of MD 374 & MD 373 | 450 | |||
| 21 | MD 292B | Vijaya Lakshmi Colony via Sai Baba Ashram | Dakshina Pinakini River | 350 | 
| 22 | MD 292 | Patalamma Layout | Dakshina Pinakini River via Sidhartha Layout | 
15
| 23 | MD 292A | Kashi Vishwanatha Temple | Outer Channel of YMC Kere near Railway Culvert | 1050 | 
| 24 | MD 294 | Alembic Glass | MD 388 @ Chainage 0.00m near Channasandra Circle | 1150 | 
| 25 | MD 296 | Channasandra Circle | Dakshina Pinakini River on Chikka Thirupathi Road | 1300 | 
| 26 | MD 388A | Plantation near Gunjar | MD 388 @ Chainage 0.00m | 150 | 
| 27 | MD 387 | End point of MD 385 | MD 382 @ Chainage 1840.00m | 300 | 
| 28 | MD 451A | Gandhipura | MD 451 @ Chainage 560.00m | 360 | 
| 29 | MD 451 | Gandhipura | MD 453 @ Chainage 0.00m @ Immadihalli | 300 | 
| 30 | MD 453 | End Point of MD 451 | MD 454 @Chainage 0.00 | 360 | 
| 31 | BH 628 | Kaikondanahalli Kere | SowlTank | 800 | 
| 32 | BH 627 | Kasavanalli Kere | Kaikondanahalli Kere | 300 | 
| 33 | BH 629 | Arluur Kere | Kaikondanahalli Kere | 500 | 
| 34 | BH 629 | Arluur Kere | Kaikondanahalli Kere | 200 | 
| 35 | BH627A | Bellandur | Ecospace | 500 | 
| 36 | BH-599 | Iblur Lake | Bellandur Lake | 769 | 
| 37 | C 200 | Doordarshan, Jayamahal Extn, | Ulsoor Tank | 4150 | 
| 38 | C-100 | From Palace Grounds, Vasanthnagar | Wind Tunnel Road | 9650 | 
| 39 | C-101 | Sudhamnagar | Inside HAL Airport | 1875 | 
| 40 | C-102 | Sweepers colony, Kadirenapalya | Shastrinagar Joining C-100 | 1600 | 
| 41 | C-103 | Krishnamurthynagar | Kadirenapalya | 1600 | 
| 42 | C-104 | Kadirenapalya | Kadirenapalya tank | 2500 | 
| 43 | C-105 | Hanumannagar | Kodihally, Near Domlur Flyover | 3000 | 
| 44 | C-106 | New Thippasandra | ISRO Complex | 650 | 
| 45 | C-107 | Kaggadasapura Lake | Kaggadasapura Main Road / Doodanekkundi tank | 900 | 
16
| 46 | C-108 | Airport South East Corner | NAL | 600 | 
| 47 | C-109 | Adj. To Airport Compound | Bellandur Lake | 675 | 
| 48 | N4 Drain | Nagammanagar | 3rd Cross Domlur | 1580 | 
| 49 | - | Domlur AK colony | Natasha Apartment | 920 | 
| 50 | C-201 | Ganapathy Temple, near Ulsoor Tank | MEG near Ulsoor Tank | 250 | 
| 51 | C-202 | Richards Town | Gymkhana Club | 1170 | 
| 52 | C-203 | Sagayapuram | Cleve town | 750 | 
| 53 | C-204 | Orion Mall, Marutisevanagar | Ulsoor Tank | 2000 | 
| 54 | - | Upper Byrasandra lake - Baghmane Tech Park | Lower Byrasandra Lake - Baghmane techpark | 560 | 
| 55 | - | Lower Byrasandra Lake - Baghmane techpark | Kaggadasapura Lake | 930 | 
| 56 | - | KrishnaiahnaPalya | Kaggadasapura Lake | 2600 | 
| 57 | - | Kasturinagar Park | Outer Ring Road | 1000 | 
| 58 | - | Kasurinagar Railway track | Outer Ring Road | 600 | 
| 59 | K-100 | K.R.Market | Bellandur Lake | 10200 | 
| 60 | K-200 | Sanatorium | Bellandur Lake | 7600 | 
| 61 | K-103 | Church Street | via Austin town & Vivek nagar joining to K-100 | 3400 | 
| 62 | K-104 | Jayangara 1st Block | Via Lakkasandra joining to K-100 | 1700 | 
| 63 | K-107 | Lang ford town | Jalakanteshwara pura | 770 | 
| 64 | K-108 | Venkatareddy Layout | Willson Garden | 1925 | 
| 65 | K-109 | Kanteerava Stadium | via R.R. Mohan Ray & joining to K-100 | 2000 | 
| 66 | K-110 | Hosur road | Sudhamanagara | 625 | 
| 67 | K-111 | South End road near Jayangara 2nd Block | Lalbgh Tank | 950 | 
| 68 | K-112 | Parvathi Pura | Kumbargundi | 725 | 
| 69 | K-114 | Lang ford road | via St Michael's Church & Joining to K-100 | 1100 | 
| 70 | K-201 | Vanaganahalli | Agara Lake | 1350 | 
| 71 | K-202 | Ellukunte | venkatapura | 950 | 
| 72 | K-203 | Crompton Greeves Road | Ring Road | 1200 | 
| 73 | K-204 | Madivala Tank | Hosur Road | 705 | 
17
74 K-205 Mudduram Nagar Bismillah Nagar 525
| K-206- | Tayappanahalli | Bovi Colony | 1245 | |
| 76 | K-207 | Bairsandra Ext | Bannerugatta road | 1225 | 
77 K-208 Tilaknagar Krishnappa Garden 425
78 K-209 J P Nagara 6th Phase Madiwala Tank 9500
79 K-210 J P Nagara 6th Phase Joining K-200 1700
Total Length 105149 meters
It is stated here that the above details are submitted for the first time now hence Committee could not cross verify at the field level.
Further, the State Government is developing Rajakaluve K-100 for the length of 11.4 kms from Chikkalalbagh to Bellanduru lake. No Objection Certification was given in compliance with IA No.392/2020 in OA No.125/2017 subject to the conditions. Copy of the said letter dated 24.12.2020 was also submitted to the Hon'ble NGT by the Committee. The outcome of the development of this Rajakaluve should be placed before the Hon'ble NGT by the State Government. BBMP is yet to submit the detailed report on the status of the drains (with details of encroachments) and buffer zones.
| 18. | Para 6 of order Order dated 13.08.2020: Details of amount to be recovered from the units operating without STPs and the stage of proceedings pending before the State PCB | KSPCB has identified 91 units for recovery of Rs .271.50 Crores . The stages of proceedings are as under:- No. of units Installed STP 42 No. of units connected to BWSSB 06 No. of units with STP under construction 07 No. of units issued with Closure orders 10 Action yet to be taken 26 No recovery is made from the defaulting units. | 
| 19. | Para 6 of order Order dated 13.08.2020: Vacation of interim order passed by the High Court (present status) | A WP No. 50953/2019 regarding unauthorised occupation of the Bellanduru lake land (Ambedkar Colony) is pending before the Hon’ble High Court. | 
| 20. | Para 6 of order Order dated 13.08.2020: The BDA has wrongly understood that biodiversity parks are to be set up within the lake boundary. Such parks are | The BDA submits that no Bio-Diversity parks are developed within the periphery of the lake after Hon’ble NGT observations. The BDA submits that Government land is not available along the periphery of the lake boundary in buffer zone. BDA submit that Contour Survey is being done for both the lakes to demarcate the area between maximum flood levels and the lake periphery. So, identified/demarcated area which is beyond the maximum water level where water does | 
Details of amount to be No. of units Installed STP 42
recovered from the units No. of units connected to BWSSB 06
operating without STPs and the No. of units with STP under construction 07
stage of proceedings pending No. of units issued with Closure orders 10
before the State PCB Action yet to be taken 26
No recovery is made from the defaulting units.
19. Para 6 of order A WP No. 50953/2019 regarding unauthorised occupation of the Bellanduru lake land (Ambedkar Colony) is pending
Order dated 13.08.2020: before the Hon'ble High Court. Vacation of interim order passed
by the High Court (present
status)
20. Para 6 of order The BDA submits that no Bio-Diversity parks are developed within the periphery of the lake after Hon'ble NGT
Order dated 13.08.2020: observations. The BDA submits that Government land is not available along the periphery of the lake boundary in The BDA has wrongly buffer zone.
understood that biodiversity
parks are to be set up within the BDA submit that Contour Survey is being done for both the lakes to demarcate the area between maximum flood levels lake boundary. Such parks are and the lake periphery. So, identified/demarcated area which is beyond the maximum water level where water does
18
| to be set up along the periphery of the lake boundary. (Possibility of such Biodiversity parks). | not reach to lake periphery, such area may be developed as Bio-diversity parks without compromising total water holding capacity of lake and only on approval from competent Authority. Alternative land for disposal of silt or/and formation of Bio-diversity park in being explored near Defence land abutting to the Bellandur lake and also other open land available with Defence establishment within Bangalore city. Negotiation with Defence authorities are in progress. If it materialises, further action will be taken by following the protocol of disposal as per Rules. | |
| 21. | Para 6 of order Order dated 13.08.2020: Enquiry should be conducted about the illegality in laying the pipeline by the Minor Irrigation Department (Present status). | The Additional Chief Secretary, Urban development Department, has submitted the following details in regard to action initiated against the officials in the subject matter. SL Name of the Erring Designation Period No Official 1. Devaraj B Chief Engineer 23-09-2015 to 31-08-2017 2. M Ravindrappa Superintending 26-06-2014 to 18-11-2019 Engineer 3. S N Krishnappa Executive Engineer 11-06-2015 to 27-08-2018 4. Venkatesh Assistant Executive 27-03-2017 to 04-11-2018 Engineer 5. Lakshmu Assistant Executive 18-07-2016 to 26-03-2017 Engineer 6. Ashok H Bhagi Assistant Engineer 07-12-2016 to 22-07-2019 Officers who have worked in the specified period have been identified and show cause notices were issued to them vide dtd. 04.03.2020, giving 15 days’ time to submit their replies. The replies submitted by them have been reviewed and found unacceptable. Further at Sl. No 04 Shri Venkatesh, Assistant Executive Engineer expired on 04/11/2018. The Additional Chief Secretary submits that a proposal will be sent to DPAR for obtaining formal approval for initiating disciplinary proceedings against the concerned retired officers and after getting approval from DPAR to conduct department enquiry action will be initiated as per rule 214 (2)(B)(i) and (ii) of KCSR. | 
19
| 22. | Para 6 of order Order dated 13.08.2020: Construction of retaining wall should not result in reduction of width of the water bodies/Rajakaluves. | The BBMP submits that the Construction of retaining walls to storm water drains is temporarily suspended in the Bellandur and Varthur catchment areas. To ascertain the actual width of these drains, the help of Cadastral maps is being taken in collaboration of Revenue Department and the Karnataka State Satellite Remotes Sensing Centre. They submit that the exercise will be completed by the end of March 2021. Once these exercises are completed the encroachments shall be identified at field and should be removed. The works of construction of retaining walls should be recommenced accordingly. The excess area outside the retaining walls, tree park should be developed. The BBMP is expected to consider entire lengths of SWDs in the catchment areas. | 
| 23. | Para 6 of order Order dated 13.08.2020: Details of action taken by the BBMP against illegal structures (rajakaluves and 30 meter buffer zone around the lakes) | The BBMP submits a detail of the encroachment removed in Mahadevapura Zone of the catchment of these lakes which were identified in the past. The details are as under:- Details of the Details of the encroach- Balance encroachments Total encroach- ments Encroach ments Sl. removed /resolved by Zone ments Identified removed by to be removed No doing survey in the in each Zone doing survey as on year in the year 24.12.2020 2018-19 on-wards 2016-17 1 Mahadevapura 1101 98 864 139 1a Mahadevapura-New 45 0 0 45 TOTAL 1146 98 864 184 Further, BBMP submits that, following Writ Petitions in the matter of encroachment are filed and pending before the Hon’ble High Court. Sl.no Writ Petition Number Number of cases 1. W.P No.27287/2019 3 cases 2. W.P No.26150/2019 & 26835-26842/19 1 Case 3. W.P No.29873/19 & 29874-876/19 3 Cases 4. W.P No.30399-30414/2019 45 Cases Total 52 Cases The details of encroachments of other zones for the catchment of Varthur, Bellanduru and Agram have not been submitted by the BBMP. The BBMP further submits that 30 meter buffer zone have been demarcated all along the outer boundary of Bellanduru lake with the help of Additional Director of Land Records. In the 30 meter buffer zone of Bellanduru lake, 22 unauthorised structures have been identified. The process up to demolition order, has been completed. Against the demolition order 13 persons have appealed before the Karnataka Administrative Tribunal; one Writ Petition has been | 
20
| filed in the High Court; 4 persons have gone to the City Civil Court. Action has to be initiated against the remaining 4 persons. It is further submitted that along the periphery of the Bellanduru lake 177 mild steel tubular poles and 160 LED lights have been installed and commissioned. 23 poles and 40 LED lights are yet to be installed. As regard to CCTV cameras, 51 numbers have been installed and functioning and 11 numbers are yet to be installed. Further, 30-meter buffer zone has been demarcated along the outer boundary of Varthur lake with the help of Additional Director of Land Records. In this buffer zone, 12 unauthorised structures have been identified. The process up to demolition orders has been completed. Against the demolition order, one person has appealed before the Karnataka Administrative Tribunal; one structure has been demolished and remaining 10 structures are yet to be demolished. It is further submitted that along the periphery of the Varthur lake, 184 poles and 143 LED lights have been installed and commissioned. 16 poles and 57 LED lights are yet to be completed. As regard to CCTV cameras, 24 numbers have been installed and functioning and 26 numbers are yet to be installed. | ||
| 24. | Para 6 of order Order dated 13.08.2020: BBMP should survey and notify the rajakaluves for purposes of buffer zones of 50, 25 and 15 meters | The Storm water drains are classified into the Primary, Secondary and Tertiary SWDs with the buffer zones of 50, 25 and 15 meters respectively on certain technical parameters. The details of length in each category have not been submitted by the BBMP. The Committee has convened several meetings in this regard but no satisfactory desired results are achieved. To ascertain the actual width of these drains and encroachments, the help of Cadastral maps is being taken in collaboration of Revenue Department and the Karnataka State Satellite Remotes Sensing Centre. They submit that the exercise will be completed by the end of March 2021. Once this exercise is completed, the further action of demarcating of encroachments at field should be done and to be removed. The BBMP is expected to consider entire lengths of SWDs in the catchment areas. | 
21
25. Para 8 of order More silt sampling in both lakes have been carried out jointly (by CPCB and KSPCB) and analysed for essential
Order dated 13.08.2020: parameters including heavy metals. The standard protocol for assessing the hazardous (if any) is being followed through We have given due consideration TCLP (Toxicity characteristic leaching procedure) and STLC (Soluble Threshold Limit Concentration) investigations of to the rival opinions. We are of soil samples in Varthur and Bellandur Lakes.
the view that some more
sampling may be got carried out Based on this, CPCB has given a report for Varthur lake. As per the protocol based on TCLP and STLC analyses, the with regard to de-silted soil is non-hazardous and hence permission is accorded to BDA by KSPCB to dispose silt, based on the local demand debris/sludge at appropriate
representative locations for As regards to Bellandur Lake, the analysis of sediment samples for leachability tests is under progress and is expected comprehensive database and to be completed early. Based on the test results CPCB, will submit a report suggesting silt disposal mechanism. thereafter disposal protocol may
be finalized in consultation with
the CPCB. This will avoid
unnecessary delay and cost
(action taken in this regard by
KSPCB for sample analysis).
This report is submitted to the Hon'ble National Green Tribunal for appropriate order."
22
8. The State of Karnataka has filed its affidavit dated 09.03.2021 with a compliance report in tabular form which is reproduced below:
Contd. at next page
23
" Directions of Hon'ble NGT vide
Sl. orders dated Remarks/explanations on behalf
| Sl. no | Directions of Hon’ble NGT vide orders dated 06.12.2018, 18.12.2019 and 13.08.2020 | Observations ofMonitoring Committee on progress up to 31.01.2021 | Remarks/explanations on behalf of State of Karnataka | 
| 1 | Relevant para | 3 | |
| 26. | Para 28(i) Orderdated 18.12.2019: Timelines for execution of projects for setting up of STPs and laying of sewerage network may not be extended beyond 30.09.2020. If the works remains incomplete even till30.09.2020, compensation will be liable to be paid @ Rs.10 lakh per STP per month which may be liable to recovered from the erring officers, apart from adverse entries in their service records and other adverse action. Further, the NGT vide order dated 13.08.2020 has directed that, the works may be expeditiously completed and to be reviewed by the Monitoring Committee. | In regard to the construction of STPs and their commission, the details are given as under(BWSSB): Name of the STP / others Compliance iii. Sarakki – 5 MLD STP Completed and commissioned on 08.11.2019. iv. Chikkabeguru - 5 MLD STP viii. | i. Sarakki – 5 MLD STP Presently, the treated water is let into Sarakki Lake. Photographs enclosed in Annexure.-R-1 (Vide Pg No. 48 to 51) ___________________ ii. Chikkabeguru – 5 MLD STP Presently, the treated water is let into Chikka Begur Lake. Photographs enclosed in Annexure- R-2 (Vide Pg No. 52 to 55) ___________________ i. Hulimavu – 10 MLD STP Presently the treated water is let into Hulimavu Lake. | 
| Sl. no | |||
| Completed and commissioned on September 2020. | |||
| Hulimavu – 10 MLD STP | Completed and commissioned on 31.03.2020 | 
and 13.08.2020
1 Relevant para 3
26. Para 28(i) Orderdated 18.12.2019: In regard to the construction of STPs and their commission, the details are given as under(BWSSB):
Timelines for execution
of projects for setting up Sl. Name of the STP / others Compliance
of STPs and laying of no
sewerage network may iii. Sarakki - 5 MLD STP Completed and commissioned on 08.11.2019. i. Sarakki - 5 MLD STP
not be extended beyond Presently, the treated water is let into 30.09.2020. If the works Sarakki Lake.
remains incomplete Photographs enclosed in
even till30.09.2020, Annexure.-R-1 (Vide Pg No. 48
compensation will be to 51)
liable to be paid @ Rs.10 lakh per STP per month which may be ___________________ iv. liable to recovered from Chikkabeguru - 5 MLD STP Completed and commissioned on September 2020. ii. Chikkabeguru - 5 MLD
the erring officers, apart STP
from adverse entries in their service records Presently, the treated water is let and other adverse into Chikka Begur Lake. action.
Photographs enclosed in
Further, the NGT vide order dated 13.08.2020 Annexure- R-2 (Vide Pg No. 52
has directed that, the viii. Hulimavu - 10 MLD STP to 55) Completed and commissioned on 31.03.2020 works may be
expeditiously completed ___________________
and to be reviewed by i. Hulimavu - 10 MLD STP
the Monitoring Presently the treated water is let Committee.
into Hulimavu Lake.
24
| Photographs enclosed in Annexure- R-3 (Vide Pg No. 56 to 60) ii.Agaram STP Presently the treated water is let into Agaram Lake. Photographs enclosed in Annexure –R-4 Vide Pg No. 61 to 66) _______________ v. Madiwala STP  Initially, Construction of this STP was taken up by the Karnataka Lake Conservation and Development Authority with funds from KSPCB.  Due to poor progress, this work was handed over to BWSSB.  BWSSB has taken up the up-gradation of this STP and the overall progress as on 22.02.2021 is 33.00 % against the planned target of 100.00%.  Due to Covid-19 pandemic there is delay, however, the work will be completed by December 2021. | ||||
| ix. | Agram – 35 MLD STP | Completed and commissioned on 31.03.2020 | ||
| x. | Madivala – 4 MLD STP | 24.5% work completed | 
to 60) ii.Agaram STP
ix. Agram - 35 MLD STP Completed and commissioned on 31.03.2020 Presently the treated water is let into Agaram Lake.
Photographs enclosed in Annexure -R-4 Vide Pg No. 61 to 66)
_______________
v. Madiwala STP
x.  Initially, Construction of Madivala - 4 MLD STP 24.5% work completed this STP was taken up by the Karnataka Lake
Conservation and
Development Authority
with funds from KSPCB.
 Due to poor progress, this
work was handed over to
BWSSB.
 BWSSB has taken up the up-gradation of this STP and the overall progress as on 22.02.2021 is 33.00 % against the planned target of 100.00%.
 Due to Covid-19 pandemic there is delay, however, the work will be completed by December 2021.
25
|  As an interim measure, toavoid sewage entry into the Madivala lake, the sewage which was earlier augmented to this STP is now diverted to Agarm ISPS by linking this network to ISPS through 900mm dia sewer link line, Photographs enclosed in Annexure R-5 (Vide Pg No. 67- 70) ___________________ iv)In spite of effects of Covid19, pandemic effects, the overall progress as on 22.02.2021 is 91% against the planned target of 100.00%.  Due to Covid 19 pandemic conditions like, Migration of Labour, Shutdown of industries of specialised equipment’s manufacturing units, non- availability of construction materials like cement, steel, aggregates, etc., the shortfall is mainly in civil works and installation of plant and machineries.  At present, the facilities for augmenting the sewage have been completed and intake of sewage has been taken on 31.12.2020 and primary treatment is in progress. | ||||
| xi. | K&C Valley – 150 MLD STP | 90.01 % works completed as on 31.01.2021. Primary treatment is in progress and likely to be completed by31.03.2021and expected to treat 83MLD sewage (with this augmentation, 536 MLD (92%) would be treated as against 583 MLD) | 
the Madivala lake, the
sewage which was earlier
augmented to this STP is
now diverted to Agarm
ISPS by linking this
network to ISPS through
900mm dia sewer link line,
Photographs enclosed in Annexure R-5 (Vide Pg No. 67-
70)
___________________
iv)In spite of effects of Covid19, pandemic effects, the overall progress as on 22.02.2021 is 91% against the planned target of 100.00%.
 Due to Covid 19 pandemic conditions like, Migration of Labour, Shutdown of industries of
xi. specialised equipment's K&C Valley - 150 MLD STP 90.01 % works completed as on 31.01.2021. Primary treatment is in manufacturing units, non- progress and likely to be completed by31.03.2021and expected to treat availability of construction 83MLD sewage (with this augmentation, 536 MLD (92%) would be materials like cement, steel, treated as against 583 MLD) aggregates, etc., the shortfall is
mainly in civil works and
installation of plant and
machineries.
 At present, the facilities for
augmenting the sewage have been
completed and intake of sewage
has been taken on 31.12.2020 and
primary treatment is in progress.
26
|  Action is in progress to commission the balance line of treatment in a phased manner by 31-03-2021. Photographs enclosed in Annexure –R-6 (Vide Pg No. 71 to 83) ________________________ v) The ISPS is ready for operation. The sewage will be pumped after completion of the 150 MLD STP and. Laying of pipe network, which are in progress. Photographs enclosed in Annexure R-7 (Vide Pg No. 84 to 85) _______________________ vi) As the location of the work lies at the end of the valley the SWD carries huge quantity of storm water. Hence, laying of pipelines in the storm water drains (SWD) is very difficult and time consuming At present, 5295 RMT of pipeline work is completed against 5315 RMT (excluding TT & Bend length).  Due to COVID-19 pandemic, the firm lost time to tackle the work in SWD from 23.03.2020 to May 2020. | ||||
| xii. | Construction of 210 MLD capacity ISPS at Koramangala at sports complex | The work is completed and ready for operation. The water will be pumped to 150 MLD STP,once the remaining pipe network is completed, (yet to complete 252 Rmt) | ||
| xiii. | Laying of 1800 mm UGD from 210 MLD ISPS to150 MLD STP | Against the 5315-running meter; 5063 running meter is completed. Likely to be completed by 31.03.2021. | 
 Due to COVID-19 pandemic, the
firm lost time to tackle the work in
SWD from 23.03.2020 to May
2020.
27
 Further, the work was delayed due to the monsoon which set in from June 2020 and lasted up to 10thof December 2020.
 The work will be commissioned on or before31st March 2021. Photographs enclosed in Annexure- R-8 (Vide Pg No. 86 to
92)
_________________________
vii) The overall progress as on 22.02.2021 is 55% against the planned target of 100.00%.  Due to Covid 19 pandemic conditions like, Migration of Labour, non-availability of construction materials like cement, steel, aggregates, etc.,
xiv. there is Delay. Waste water wet well - 32.5 MLD Capacity The overall progress as on 31.01.2021 is 45.75 % against the planned near the premises of 90 MLD target of 100.00%. This work will be completed before 31.03.2021.  Also, the strata met with is in Wet BellanduruAmanikhane STP to augment However, the temporary arrangement has been made for pumping well is hard rock, excavation. In sewage from the adjoining areas of sewage to BellandurAmanikhane STP. hard rock wedging and chiselling BellanduruAmanikhane STP (date fixed for is time consuming.
completion 30.09.2020)
 However, temporary
arrangement has been made for
pumping sewage to
BellandurAmanikhane STP.
 This work will be completed before 31.03.2021.
28
| Photographs enclosed in Annexure-R-9 (Vide Pg No. 93 to 97) | |||
| 27. | Para No.14 Order Dated 18.12.2019 We also found that timelines fixed by this Tribunal have been unilaterally extended without any valid justification and no action has been taken against the erring officers on a specious plea that it was difficult to fix responsibility. Such approach is hardly compliant with the Rule of Law. We particularly disapprove the timeline forupgradation of STPs with Biological Nutrient Removal (BNR) at 248.MLD STP at K&C Valley. The same must not go beyond 30.09.2020 but preferably be completed before 30.06.2020 although earlier timeline fixed by this Tribunal was 30.06.2019. No substantial work has been done in the last one year on this aspect. | The BWSSB submits that, STPs of 90 MLD at BellandurAmanikere; 60 MLD at K&C Valley; 5 MLD at Sarakki; 5 MLD at Chikkabegur; 10 MLD Hulimavu; 35 MLD at Agramand 150 MLD at K&C Valley (under construction) are complied with Biological Nutrient Removal treatment. The BWSSB further submits that forthe 248 MLD STP at K&C Valley, certain modifications in the process of treatment have been made in consultation with the IISc, Bengaluru, for removal of nutrients. On sample analysis it is found that the biological nitrates have beenreduced substantially (nitrogen 6.4 mg per ltr and phosphates 0.85 mg per ltr). It is noted that, the treated water from these STPs isbeing transmitted to the tanks in Kolar Districtsforrecharge of ground waterfor irrigation purpose. However, the upgradation of the system has not been completed but is in process. |  No response was received for the tenders floated due to COVID conditions.  To comply, based on inputs from the IISc, Bengaluru and the consultants viz M/s CH2M Hill India Pvt. Ltd., modifications in the processes have been made to ensure removal of nutrients in the two STP’s i.e. 30 MLD STP & 218 MLD STP.  Samples were collected jointly by CPCB, KSPCB and I.I.Sc. The results furnished by them are annexed.  The treated effluents from all the three above STPs and one more 90 MLD STP at Bellandur Amanikere are eventually conveyed to the Minor Irrigation Jack Well situated near Bellandur Amanikere, from where the effluent is finally discharged into Lakshmi Sagar Lake of Kolar District.  As per the test reports, the Total Nitrogen is 6.4 mg/ltr and the Total Phosphates is 0.85 mg/ltr, which is within the ranges as suggested by Hon’ble NGT Monitoring Committee. | 
97)
27. Para No.14  No response was received for the The BWSSB submits that, STPs of 90 MLD at BellandurAmanikere; 60 MLD at K&C Valley; 5 MLD at Sarakki; 5 MLD at
Order Dated tenders floated due to COVID Chikkabegur; 10 MLD Hulimavu; 35 MLD at Agramand 150 MLD at K&C Valley (under construction) are complied with
18.12.2019 conditions. Biological Nutrient Removal treatment. We also found that  To comply, based on inputs from timelines fixed by this The BWSSB further submits that forthe 248 MLD STP at K&C Valley, certain modifications in the process of treatment have been the IISc, Bengaluru and the Tribunal have been made in consultation with the IISc, Bengaluru, for removal of nutrients. On sample analysis it is found that the biological nitrates consultants viz M/s CH2M Hill unilaterally extended have beenreduced substantially (nitrogen 6.4 mg per ltr and phosphates 0.85 mg per ltr). It is noted that, the treated water from India Pvt. Ltd., modifications in without any valid these STPs isbeing transmitted to the tanks in Kolar Districtsforrecharge of ground waterfor irrigation purpose. However, the the processes have been made to justification and no upgradation of the system has not been completed but is in process. ensure removal of nutrients in the
action has been taken two STP's i.e. 30 MLD STP &
against the erring 218 MLD STP.
officers on a specious
plea that it was difficult  Samples were collected jointly by
to fix responsibility. CPCB, KSPCB and I.I.Sc. The
Such approach is hardly results furnished by them are
compliant with the Rule annexed.
of Law. We particularly
disapprove the timeline  The treated effluents from all the
forupgradation of STPs three above STPs and one more
with Biological Nutrient 90 MLD STP at Bellandur
Removal (BNR) at Amanikere are eventually
248.MLD STP at K&C conveyed to the Minor Irrigation
Valley. The same must Jack Well situated near Bellandur
not go beyond Amanikere, from where the
30.09.2020 but effluent is finally discharged into
preferably be completed Lakshmi Sagar Lake of Kolar
before 30.06.2020 District.
although earlier
timeline fixed by this  As per the test reports, the Total
Tribunal was Nitrogen is 6.4 mg/ltr and the
30.06.2019. No Total Phosphates is 0.85 mg/ltr,
substantial work has which is within the ranges as
been done in the last one suggested by Hon'ble NGT
year on this aspect. Monitoring Committee.
29
|  The professors of IISc (who are entrusted with the studies of Environmental Impact due to augmentation of treated water from K&C Valley STP’s into Kolar District Lakes have shared the results of the samples collected to at Lakshmi Sagar Lake  As reported by them, the Biological Nutrients in the ultimate discharge point of Lakshmi Sagar Lake are well within the stipulations. | |||
| 28. | Para 28(ii) Order dated 18.12.2019: Bengaluru Water Supply and Sewerage Board (BWSSB) must ensure that no sewage/effluent is discharged into the lakes and till completing of STPs, interim remediation must be done forthwith. Any default in this regard will result in requirement to pay compensation of Rs.5 lakh per month per inlet into the lakes from 01.02.2020. | It is submitted that, the sewage water has been diverted through the peripheral temporary diversion channels and no sewage waterentersin theselakes (Agram, Bellanduru andVarthur). Further, the BWSSB has installed aerating systems in these temporary diversion channels at,1) HAL side and Kempapura inlet, 2) Agaram inlet, 3) Koramangalainlet, 4) Iblur inlet coming under Bellandur Lake, 5) Northern and 6) Sothern side of Varthur lake for inline treatment of sewage. The artificial floating islandshave also been installed at certain places. The committee has suggested to augment phytoremediation options at locations, where the water flow is slow or stagnant to enhance the treatment efficacy, which is yet to be implemented. | BWSSB: The aerating systems in the 6 locations were installed before 31.01.2020. Subsequently, in order to enhance the interim remediation artificial floating islands have also been installed. Photographs and Test Reports enclosed in Annexure R-10 (Vide Pg No. 98 to 103) | 
| 29. | Para 28(iii) Order dated 18.12.2019: | In view of the facts and circumstances explained to the | 
30
| BSWWB may further ensure that treated water is not discharged into the UGD network. Action may be taken against persons responsible for having allowed this to be done earlier resulting into loss of Rs.2 Lakhs per day i.e.Rs.60 Lakhs per month and more than Rs.7 Crore per year without any justification whatsoever. BY BWSSB | There are about 496 buildings having STPs as per the KSPCB records. The BWSSB submits that, wherever there was connectivity with the UGD for flowing of treated water; all have been disconnected (109 buildings). For the remaining areas there is no access tonetworking of UGD. The BWSSB submits that, treated water was allowed as per the conditions stipulated in the order issued by KSPCB. In view of these facts and circumstances, it is requested by BWSSB not to initiate action against their officials. | Monitoring Committee, it is requested not to initiate action against the officials. | |
| 30. | Para No.16 Order Dated 18.12.2019 We are informed that about 256.7 MLD untreated sewage is enteringthe lake from five locations which is nothing but a criminal offencewhich is required to be checked on war footing and violators of lawbrought to justice, erring officer being appropriately dealt with underthe civil, criminal and service law with a view to uphold the Rule ofLaw. There is large scale breach of public duties by concernedAuthorities dealing with the subject | The BWSSB submits that to check the flow of sewage water into the lakes, following works have been completed. 5. HAL SWD (Challaghatta Valley) – Totally 23 works are to be taken up for augmenting this flow, out of which 23 works are completed as on 23.12.2020. 6. Koramangala and AgramValley-Totally 48 works are to be taken up for augmenting this flow out of which 48 works are completed on 23.12.2020. 7. Iblur Catchment area- Completed and Commissioned on 23.12.2020. 8. Kempapura Catchment area- BWSSB has taken up work of laying 300 mm RCC NP3 sewer line for a length of 1000 RMT to convey the sewage generated in the area ofBellanduruAmanekhane STP. The work is completed and commissioned in the month of May 2020. The BWSSB submits that, the combined treatment capacity in the catchment of these lakes will be around 664.50 MLD against the presently measured flow of 553 MLD.Presently, about 453.50 MLD of sewage is being treated. Additionaltreatment of 83 MLD would beaugmented by commissioning of new STP (end of March 2021). Therefore, there will be treatment of 536.50 MLD (92 %) as against the measure flow of 583 MLD. The Committee observes that the BWSSB has to take steps to treat the remaining 8 to 10 % of sewage to stop completely the flowing of sewage into the lakes after rejuvenation. It is submitted here that, as per the earlier recommendations of the Committee, the water level in these lakes will be maintained by supplying treated water from the STPsdaily to compensate evaporation and seepage losses. Only the surplus treated water should be allowed to flow to Kolar, Chikkaballapur, Anekal etc. | The flow in the SWDs was measured in the month of April-2019 and the details of flow are as below: HAL-48.60 MLD Agaram & Koramangala (Y- Junction)-179.50 MLD Total-228.10 MLD The flow details of STPs at K&C Valley, Bellandur on the day of measurement were: 218 MLD-170 MLD 60 MLD-22 MLD 30 MLD-26MLD 90 MLD-30 MLD Total-248 MLD | 
31
and earlier observations After carrying out major of thisTribunal have interlinking/new pipeline works on fallen on deaf ears and the upstream side, the flow was blatantly flouted. measured in the 1stweek of March- 2020. The details are as follows:
HAL-31.4 MLD
Agaram&Koramangala
(Y-Junction)-114.26 MLD
Total-145.66 MLD
The flow details of STPs at K&C
Valley, Bellandur on the day of
measurement were:
218 MLD-180 MLD
60 MLD-51 MLD
30 MLD-30 MLD
90 MLD-70 MLD Total-331 MLD At present, the flow details of STP at K&C valley measurement were:
218 MLD-194 MLD
60 MLD-60MLD
30 MLD- 30MLD
90 MLD -90 MLD
50 MLD-45MLD 2MLD-1.50MLD 1.50MLD-1.50MLD 4MLD-2MLD
5MLD-4.50MLD 10MLD-5MLD
5MLD-2MLD
35MLD-18MLD Total=453.50 MLD.
32
|  As can be seen from the above the flow in the SWD has been reduced to an extent of 159 MLD and is being augmented to STPs  The combined treatment capacity of the above plants will be 664.50 MLD against the measured flow of 583 MLD. Presently, 453.50 MLD of sewage is being treated and 83 MLD will be augmented to new STP which is under construction and will be completed by Last week of March 2021.  The total treated sewage will be 536.50 MLD (92%) by the last week of March 2021 as against the measured flow of 583 MLD (The detail report is enclosed as Annexure- R-11). (Vide Pg No. 104 to 110) | |||
| 31. | Para 28(iv) Order dated 18.12.2019: Sources of discharge of Sewage be controlled/ regulated and electricity and water supplies to the defaulting establishments be stopped for enforcement of law till remedial steps are taken for compliance. | The KSPCB has identified 91 units in total that are required to be installation of STP. The details of progress are given as under: - No. of units Installed STP 42 No. of units connected to BWSSB 06 No. of units with STP under construction 07 No. of units issued with Closure orders for either not having STPs or not connected to UGD and letting the raw 10 sewage into the storm water drain Action yet to be taken 26 | As on 20.03.2020, there were 61 units which had not installed STP, out of which 25 units have installed STP; and the remaining 36 units have not installed STP units. Closure orders have been issued to 10 units which have not installed STP units and closure orders for the remaining units are under consideration. | 
| 32. | Para 28(v) | 
33
| Order dated 18.12.2019: Encroachments which are still continuing be removed by using force wherever necessary. If any injunction has been erroneous, higher forum can be moved so that law is upheld. | An area of 5.20 Acres in Sy.No.319was granted to a person from thevillage of Amani Bellandurukaneduring 1976-77 and a new survey number 477have been formed. This survey number wasthe part of Varthur lake. The matter is under process for cancelation of grant and pending before the concerned AssistantCommissioner.The other encroachments are stated asremoved. Illegal constructions in Ballandur lake (named as Ambedkar Nagar slum) are yet to be evicted | Out of 228 dwellers inAmbedkar Slum, 128 have shifted to Marathahalli. These 128 sheds have been demolished on 16.11.2019. The remaining occupants have filed PIL in the Hon’ble High Court of Karnataka, Bengaluru on 20.11.2019 vide Writ Petition No.50953/2019 (CM-RES) and obtained stay order on 20.11.2019. The Hon’ble High Court of Karnataka, Bengaluru through interim orders has given relief to the petitioners till next date of hearing on13.01.2021. Next Date of hearing is on 08/03/2021 (Copy enclosed). Further action will be taken as per the Order of Hon’ble High Court of Karnataka. | |
| 33. | Para 28(vi) Order dated 18.12.2019: Action against erring officers which has not yetbeen taken must be initiated forthwith as already directed. Failures of officers still in service should be duly reflected in their ACRs. | The Additional Chief Secretary, Urban development Department, has submitted the following details in regard to action initiated in the subject matter. The same is produced here for further needful. 4) Bengaluru Development Authority: Sl. No Name of erring officer/ official Designation and Period RizwanBaig Executive Engineer 4. From 2010 to 2011 & 2015 to 2016 5. S.Mallikarjuna Executive Swamy Engineer from 2010 to 2011 & 2015 to 2016 6. Ravi Narayana Executive Engineer Reddy from 2010 to 2011 & 2015 to 2016 | 
34
Notices were served to erring officials on 19.02.2020 seeking their replies within 15 days. Replies were received from all the above mentioned officials. On scrutiny of the explanations given by them, the Additional Chief Secretary (ACS), submits that the replies are found acceptable.
5) BBMP: Period from 20.09.2008 to 03.05.2011
Name of erring officer/ Designation and Period Present Dept Sl. No official
5. J.C.PrakashMurthy Assistant Engineer(1.10.2008 to30.11.2009) PWD
6. H.P.MohanKumar Assistant ExecutiveEngineer (2.03.2009 to3.1.2011) PWD
7. H.Chandrappa Assistant Engineer,K.R.Puram Sub- Division,(2.12.2009 to PWD
11.1.2012)
8. J.C.PrakashMurthy Assistant ExecutiveEngineer, (after promotion)(2.12.2009 to PWD
7.7.2010)
The State Government vide No.UDD/91/MNJ/2017, Dated.11.12.2020 directed BBMP to take necessary action on the erring officials as per the directions of the Hon'ble NGT and to submit a compliance report by 20.12.2020. The draft charges memo has been submitted to the concerned Administrative Department i.e., PWD for further necessary action.
6) BWSSB
Sl. No. Name Designation
12. S.M. Basavaraju Chief Engineer (14.11.2006 to 08.04.2013) & 10.05.2013 to 29.03.2014)
13. S.M. Ramakrishna Chief Engineer (29.03.2014 to 31.07.2017) as Chief Engineer WWM Some of the retired officers of
14. S.R. Roopa Kumar Additional Chief Engineer (31.010.2007 to 05.06.2008) BWSSB have approached the
15. S.P. Rudra Murthy Additional Chief Engineer (05.06.2008 to 13.06.2012) Hon'ble High Court. In response to
16. V. Mahesh Additional Chief Engineer (27.03.2013 to 10.07.2015) this, the Hon'ble High Court has
17. K.R. Manjunath Additional Chief Engineer (10.07.2015 to 28.10.2016) issued an interim order of stay.
18. B.M. Purushotham Executive Engineer (29.10.2007 to 23.05.2008)
19. C. Abdul Nazir Executive Engineer (23.05.2008 to 04.01.2012) Executive Engineer (04.01.2012 to 31.08.2012) & from 31.08.2012 to
20. B.N. SiddaGangaiah
15.11.2012
21. C.C. PuttaMallappa Executive Engineer (15.11.2012 to 26.08.2013)
22. B.S.C. Soma Shekar Executive Engineer (26.08.2013 to 07.06.2014)
35
| The ACS submits that officers who have worked in the specified period have been identified and show cause notices have been issued to them. The replies obtained from these officers have been reviewed and found to be not acceptable. Hence, the formal approval of the Government has been sought vide letter dated.26.05.2020 for initiating disciplinary proceedings on all the concerned retired officers of BWSSB. In this regard, the State Government in letter dated.27.10.2020 has accorded approval to conduct department enquires on all the concerned retired officers of the Board. As per rule 214 (2)(B)(i) and (ii) of KCSR, action has been initiated to conduct Departmental enquiry and for this purpose show-cause notices have been issued to all the retired officers on 18.12.2020 giving 15 days’ time to submit their replies. All the retired officers have sought many details and additional time for furnishing their replies. After getting their replies, further action will be initiated. | |||
| 34. | Para 28(vii) Order dated 18.12.2019: The State PCB itself may lay down standards for phosphorus instead of waiting for notification. | The KSPCB submits that the Bureau of Indian Standards has issued notification for limiting the Phosphorus content in household laundry detergents powders, household laundry detergents bars and synthetic detergents of washing woollen and silk fabrics. Further they submit that some follow up action has been taken as listed below:- 5. A public notice is issued by KSPCB in this regard in the print media. 6. Letters are addressed to all the State PCB’s to directly implement the order. 7. Letters are addressed to all the soap/detergent manufacturers in the state of Karnataka for the restriction of Phosphorus content. 8. Letter is addressed to MOEF for making a final notification. |  BIS has released revised standards on the Phosphorus content in soaps/detergents during August, 2020.  Follow up action has been taken by the Board as also noted by the Monitoring Committee. Public notice/letters attached as Annexures-R-12. (Vide Pg No. 111 to 114) | 
| 35. | Para 28(viii) Order dated 18.12.2019: The State of Karnataka may either resolve the issue of fencing with the Defence establishment or put such establishments to notice to place their objections before this Tribunal within one month of such notice after which the State of Karnataka will be at liberty to proceed with the fencing and such Defence establishment will stand restrained from | The issue of raising of fencing towards the Defence area have beenresolved. The Commissioner, BDA, submits that an estimate is prepared and sent for 4(G) exemption to the Government for the construction of fence. Further, in regard to de-silting a portion of the lake, there is a dispute pending with the Defence. | The Finance Department approved the proposal of BDA for undertaking the left over fencing work under 4(G) exemption and issued orders vide FD 57 EXP -12/2021 dated05.02.2021. Commissioner, BDA has written a letter No BDA/Com/EM/T- 296/2020-21, Dated08.02.2021 to Lt. Gen, Commandant & Colonel Commandant ASC, ASC Centre & College, Bangalore and also had a meeting with him. During the meeting, the Commissioner requested for permission to make use of the defence area for desilting in the defence portion of lake and also | 
approval of the Government has been sought vide letter dated.26.05.2020 for initiating disciplinary proceedings on all the
concerned retired officers of BWSSB. In this regard, the State Government in letter dated.27.10.2020 has accorded approval to
conduct department enquires on all the concerned retired officers of the Board. As per rule 214 (2)(B)(i) and (ii) of KCSR, action
has been initiated to conduct Departmental enquiry and for this purpose show-cause notices have been issued to all the retired
officers on 18.12.2020 giving 15 days' time to submit their replies. All the retired officers have sought many details and additional
time for furnishing their replies. After getting their replies, further action will be initiated.
34. Para 28(vii) The KSPCB submits that the Bureau of Indian Standards has issued notification for limiting the Phosphorus content in household  BIS has released revised
Order dated laundry detergents powders, household laundry detergents bars and synthetic detergents of washing woollen and silk fabrics. standards on the Phosphorus
18.12.2019: content in soaps/detergents during The State PCB itself
Further they submit that some follow up action has been taken as listed below:- August, 2020. may lay down standards
for phosphorus instead
of waiting for 5. A public notice is issued by KSPCB in this regard in the print media.  Follow up action has been taken
notification. 6. Letters are addressed to all the State PCB's to directly implement the order. by the Board as also noted by the
7. Letters are addressed to all the soap/detergent manufacturers in the state of Karnataka for the restriction of Phosphorus Monitoring Committee. Public content. notice/letters attached as
8. Letter is addressed to MOEF for making a final notification. Annexures-R-12. (Vide Pg No. 111 to 114)
35. Para 28(viii) The issue of raising of fencing towards the Defence area have beenresolved. The Commissioner, BDA, submits that an estimate is The Finance Department approved
Order dated prepared and sent for 4(G) exemption to the Government for the construction of fence. Further, in regard to de-silting a portion of the proposal of BDA for undertaking
18.12.2019: the lake, there is a dispute pending with the Defence. the left over fencing work under 4(G) The State of Karnataka exemption and issued orders vide FD
may either resolve the 57 EXP -12/2021 dated05.02.2021.
issue of fencing with the
Defence establishment Commissioner, BDA has written a
or put such letter No BDA/Com/EM/T-
establishments to notice 296/2020-21, Dated08.02.2021 to Lt.
to place their objections Gen, Commandant & Colonel
before this Tribunal Commandant ASC,
within one month of ASC Centre & College, Bangalore
such notice after which and also had a meeting with him.
the State of Karnataka
will be at liberty to During the meeting, the
proceed with the fencing Commissioner requested for
and such Defence permission to make use of the
establishment will stand defence area for desilting in the
restrained from defence portion of lake and also
36
| interfering unless otherwise directed by this Tribunal or any other authority. | sought approval for depositing the desilted muck in the low-lying areas of the defence land. Lt. Genhas agreed in principle to allow only non- hazardous silt to be deposited in the defence land where it will be beneficial in development of army training areas & reclaiming of low- lying land. On receipt of a formal permission from the defence authority, the work of chain link fencing and de-silting in the defence area will be taken up and completed. | ||
| 36. | Para 28(ix) Order dated 18.12.2019: Compensation already assessed to be recovered by adopting coercive measures such as disconnection of electricity and water supplies. | In regard to this para, the KSPCB submits as under:- Total No. of units issued with notice for EC and Amount. 376 units (Rs.19.85 Crores) No. of units paid EC and Amount 40 units (Rs.2.10 Crores) Action yet to be taken for recovery 336 units M/s. Durga rainbow flat owner’s welfare association has filed an impleading application before the Hon’ble NGT on 30.08.2020. | Where recovery is due, action is being taken to request the Deputy Commissioners concerned to recover the amounts from the concerned as arrears of land revenue. ANNEXURE-R-13 (Vide Pg No. 115 to129) | 
| 37. | Para 28(x) Orderdated 18.12.2019: Steps be taken expeditiously for de- silting,de-weeding. Analysis of sludge and silt may be carried out before its disposal based on the result of such analysis, the mode of disposal and protocol be determined in accordance with laid | KSPCB has collected series of samples of Silt/sludge at different depth with grid manner on 25th, 26th& 27th of December 2020. Besides sample collected on 16/09/2020, 18/09/2020, 12/11/2020, 19.12.2020 & 5.1.2021 The CPCB has given a report for Varthur lakebased on TCLP and STLC analyses of silt samples. As per the protocol based on TCLP and STLC analyses, the soil is non-hazardous and accordingly the permission is accorded to BDA by KSPCB to dispose silt from the locations showed in the grid map based on local demand. As regards to Bellandur Lake, the analysis of sediment samples for leachability tests is under progress. | KSPCB has collected series of samples of silt/sludge at different depths on 25th, 26th& 27th of December 2020. Besides sample collection done on 16/09/2020, 18/09/2020&12/11/2020 (Annexure-14). (Vide Pg. No. 130- 145) The CPCB has given a report stating that other than the areas where the heavy metals are found to be managed as per the Hazardous Waste | 
this Tribunal or any of the defence land. Lt. Genhas
other authority. agreed in principle to allow only non-
hazardous silt to be deposited in the
defence land where it will be
beneficial in development of army
training areas & reclaiming of low-
lying land.
On receipt of a formal permission
from the defence authority, the work
of chain link fencing and de-silting in
the defence area will be taken up and
completed.
36. Para 28(ix) In regard to this para, the KSPCB submits as under:- Where recovery is due, action is
Order dated being taken to request the Deputy
18.12.2019: Total No. of units issued with notice for EC and Amount. 376 units (Rs.19.85 Crores) Commissioners concerned to recover Compensation already No. of units paid EC and Amount 40 units (Rs.2.10 Crores) the amounts from the concerned as assessed to be recovered Action yet to be taken for recovery 336 units arrears of land revenue. by adopting coercive M/s. Durga rainbow flat owner's welfare association has filed an impleading application before the Hon'ble NGT on 30.08.2020. ANNEXURE-R-13 (Vide Pg No.
measures such as 115 to129)
disconnection of electricity and water supplies.
37. Para 28(x) KSPCB has collected series of samples of Silt/sludge at different depth with grid manner on 25th, 26th& 27thof December 2020. KSPCB has collected series of
Orderdated 18.12.2019: Besides sample collected on 16/09/2020, 18/09/2020, 12/11/2020, 19.12.2020 & 5.1.2021 samples of silt/sludge at different Steps be taken depths on 25th, 26th& 27thof
expeditiously for de- The CPCB has given a report for Varthur lakebased on TCLP and STLC analyses of silt samples. As per the protocol based on December 2020. Besides sample silting,de-weeding. TCLP and STLC analyses, the soil is non-hazardous and accordingly the permission is accorded to BDA by KSPCB to dispose silt collection done on 16/09/2020, Analysis of sludge and from the locations showed in the grid map based on local demand. As regards to Bellandur Lake, the analysis of sediment samples 18/09/2020&12/11/2020 silt may be carried out for leachability tests is under progress. (Annexure-14). (Vide Pg. No. 130-
before its disposal based 145)
on the result of such analysis, the mode of The CPCB has given a report stating disposal and protocol be that other than the areas where the determined in heavy metals are found to be accordance with laid managed as per the Hazardous Waste
37
down principles under Management rules and the balance the relevant Rules. silt can be used over the agricultural land.
Varthur Lake:
De-silting of Varthur lake: work order issued on 23.11.2020 to the Agency M/s Star Infra Tech Pvt Ltd.It is submitted that, more On a pilot basis, silt was soil / silt / sludge samples were collected from the lake bed areas and was analysed. The sediment analysis results based on the screening levels on soil quantity parameters prescribed for agriculture use have been examined by the CPCB and a report is given. removed under 4 (G) Based on the recommendations of CPCB, the KSPCB issued a letter for disposal of the silt for agriculture and other uses. The work exemption over an area of 100 of de-silting has commenced by M/s Star Infra Tech Pvt Ltd as per the direction of KSPCB/BDA.Further, the BDA claims that acres and stacked in the lake approximately inan area of 100 Acres, silt is removed and stocked in the lake area. This work of removal of silt(100 Acres) is area. carried out under the 4 (G)exemption. Work order was issued on
23.11.2020 to M/s Star
Infratech Pvt. Ltd.
Silt has been removed over an
area of 128 acres for an
average depth of 1 metre. The
total quantity of silt removed
and stacked till 22.02.2021 is
approximately 8.75 lakhs
cubic metre.
The KSPCB has sent a letter
dated.12.02.2021 which is
received on 22.02.2021
informing the steps for
disposal of the silt in Varthur
lake (copy of the letter is
enclosed herewith at page
no.7). Action is being taken to
stack the useful silt on the lake
boundary for interested
farmers to collect the required
quantity till a certain time.
38
| Desilting of Bellandur lake: work order issued on 23.11.2020 to M/s RMN Infrastructure Pvt Ltd. Lake bed pre level survey is done, removal of seepage water and others in the Bellandurlakeis completed. BDA claims that under 4(G) exemption,an area of 158 Acres(Bellandur lake) silt is removed and stocked at some places inside the lake.The BDA further submits that the stocked silt will be disposed as per the protocol. | Thereafter, it will be transported to the designated place. Photographs enclosed herewith as Annexure R-15 (Vide Pg No. 146 to 152) Bellandur Lake: On a pilot basis, silt was removed under 4 (G) exemptions over an area of 158 acres and stacked in the lake area. Work order was issued on 23.11.2020 to M/s RMN Infrastructure Pvt. Ltd. Silt has been removed for an average depth of 1 metre over an area of 65 acres. The total quantity of silt removed and stacked till 22.02.2021 is approximately 9.2 lakhs cubic metre. The stacked and recently removed silt /muck will be disposed of as per the protocol. The letter from KSPCB is awaited. Photographs enclosed herewith as Annexure R-15 (Vide Pg No. 153 to 157) | ||
| 38. | Para 28(xi) Orderdated 18.12.2019: | The KSPCB has a well-equipped laboratory to analyse the samples in house. Samples are being analysed for pH, BOD, COD, TSS, Ammoniacal Nitrogen, Iron and Manganese, Total Nitrogen, Cyanide, Hexavalent Chromium, Cadmium, Copper, Lead, Nickel, Zinc and Total Chromium at KSPCB’s sophisticated Central Laboratory. KSPCB has been advised to undertake water quality | The KSPCB has a well-equipped laboratory to analyze the samples in house. Samples are being | 
39
| The State PCB may develop a robust water quality monitoring program for monitoring of water quality of drains leading to the lakes and also undertake water quality monitoring at atleast 5 locations for each lake. | monitoring at regular intervals in these lakes and drains (connecting these lakes) and upload (on monthly basis) the water quality information at KSPCB website. | analyzed for pH, BOD, COD, TSS, Ammoniacal Nitrogen, Iron and Manganese, Total Nitrogen, Cyanide, Hexavalent Chromium, Cadmium, Copper, Lead, Nickel, Zinc and Total Chromium at KSPCB’s sophisticated Central Laboratory, out of which 6 are heavy metals. (Annexure-R-7). (Vide Pg No. 158 to 188) | |
| 39. | Para 28(xii) Orderdated 18.12.2019: Steps may be taken to explore development of wetlands and biodiversity parks apart from other remedial action for reducing the pollution load on the recipient water bodies. | Provision is made in the estimate for construction of wetland Bellandur and Varthur lakes. Once the identified wetland area within the lake is de-silted, wetland will be developed. Letter has been received from the ADLR (East) dated.06.11.2020 stating that Government land is not available along the periphery of the lake boundary in buffer zone. | Identified wetland will be developed after desilting. | 
| 40. | Para 28(xiv) Order dated 18.12.2019: Real time water quality system be commissioned by 31.01.2020 as proposed. | The Board has already installed the Real Time Water Quality Monitoring systems at three locations and continuously monitoring. The results are uploaded on the website. | The Board has already installed the Real Time Water Quality Monitoring systems at 3 locations and continuously monitoring. The results are uploaded on the website. (Annexure—R-18). (Vide Pg. No. 189-191) | 
| 41. | Para 28(xv) Orderdated 18.12.2019: The issue of removing 1.5 km road laid upon the lake bed, within the boundary of Varthur lake, by dumping of C&D debris be finalized | The Hon’ble NGT vide order dated 13.08.2020has held that enquiry should be conducted about the illegality in laying the pipeline by the Minor Irrigation Department. Accordingly, Miner Irrigation department has taken steps as stated in para 21 in this report. |  Show cause notices were issued to them vide dated. 04.03.2020, giving 15 days’ time to submit their replies. The replies submitted by them have been reviewed and found unacceptable.  A proposal will be sent to DPAR for obtaining formal approval for | 
40
| as per directions of Justice Hegde Committee in terms of para 26 above. | initiating disciplinary proceeding sagainst the concerned retired officer and after approval from DPAR to conduct Departmental Enquiry, action will be initiated as per rule 214(2)(B)(i) and KCSR.  Disciplinary Proceedings has been initiated against the serving official by issuing a Show Cause Notice along with article of charges under rule 12(1)(A) of KCS (CCA)rules dated 05.02.2021 to erring officials who are responsible for the execution of the work. Further, ShriVenkatesh, Assistant Executive Engineer at Sl. No 04 expired on 04/11/2018. | ||
| 42. | Para 19(16) of order Order dated 06.12.2018: Post removal of waste from the Lake and from the Rajakaluves, the State ought to prepare a detailed project report with respect to disposal of the same. | As regard to removal of waste from the lake area, the desilting work is in progress and once it is completed the left-out waste shall have to be removed. Meanwhile, the BBMP has to prepare a detail project report for the disposal for the same. In regard to removal of waste from the Rajakaluves, the BBMP submits that against approximately 218.0 kms of Rajakaluves(SWD),about 105.149kmsare being maintained. The maintenance includes removal of silt, floating tresses, vegetation and other organics and transported to the Anjanapura abandoned stone quarries. A list of drains of 105.149kmshas been provided here as under: Sl.No Drain No Drain Name Length in M MD 428 @ Chainage 2 MD 425 RamgondanahalliAdarsha Houses 100 0.00m MD 431 @ Chainage 3 MD 428 VarthurKere 200 0.00m 4 MD 413 PattanduruAgrahara NalluralliKere 250 5 NalluralliKere MD 415 7 MD 416 Nalluralli NalluralliKere 450 |  The details of remaining length of drains with encroachments are being surveyed. The help of Karnataka State Remote Sensing Centre has been taken in identifying the details of SWD widths as per revenue maps. The work is in progress. | 
Committee in terms of officer and after approval from
para 26 above. DPAR to conduct Departmental
Enquiry, action will be initiated as
per rule 214(2)(B)(i) and KCSR.
 Disciplinary Proceedings has been
initiated against the serving
official by issuing a Show Cause
Notice along with article of
charges under rule 12(1)(A) of
KCS (CCA)rules dated
05.02.2021 to erring officials who
are responsible for the execution
of the work. Further,
ShriVenkatesh, Assistant
Executive Engineer at Sl. No 04
expired on 04/11/2018.
42. Para 19(16) of order As regard to removal of waste from the lake area, the desilting work is in progress and once it is completed the left-out waste shall  The details of remaining length of
Order dated have to be removed. Meanwhile, the BBMP has to prepare a detail project report for the disposal for the same. drains with encroachments are
06.12.2018: being surveyed. The help of Post removal of waste In regard to removal of waste from the Rajakaluves, the BBMP submits that against approximately 218.0 kms of Karnataka State Remote Sensing from the Lake and from Rajakaluves(SWD),about 105.149kmsare being maintained. The maintenance includes removal of silt, floating tresses, vegetation Centre has been taken in the Rajakaluves, the and other organics and transported to the Anjanapura abandoned stone quarries. A list of drains of 105.149kmshas been provided identifying the details of SWD State ought to prepare a here as under: widths as per revenue maps. The
detailed project report work is in progress.
with respect to disposal Sl.No Drain No Drain Name Length in M
of the same. 1 MD 342A Boganahalli PanatturKere 300 MD 428 @ Chainage
2 MD 425 RamgondanahalliAdarsha Houses 100 0.00m
MD 431 @ Chainage
3 MD 428 VarthurKere 200 0.00m
4 MD 413 PattanduruAgrahara NalluralliKere 250
5 MD 414 Saibaba Hospital NalluralliKere 450
6 MD 415 Pioneer Software NalluralliKere 400
7 MD 416 Nalluralli NalluralliKere 450 End Point of MD 322 & MD 334 Near ADA Compound
8 MD 349 VarthurKere 400 Wall
41
| 9 | MD 365A | End Point of MD 363 & MD 364 | MD 369 @ chainage 0.00 | 400 | 
| 10 | MD 322 | RHB Colony | GarudacharyapalyaKer e | 150 | 
| 11 | MD 322A | GarudacharyapalyaKere | MahadevpuraKere | 400 | 
| 12 | MD 322C | ITPL Road | Ramakka Layout | 100 | 
| 13 | MD 325 | Outer Ring Road | DoddanenkundiKere | 300 | 
| 14 | MD 325A | VinayakaNagara 8th Cross | MD 325 @ Chainage 0.00 | 500 | 
| 15 | MD 363 | Chinnappanahalli Layout | MD 365 @ Chainage 0.00 | 500 | 
| 16 | MD 369 | End Point of MD 365 & MD 368 | VarthurKere | 500 | 
| 17 | MD 371 | Tules CADCAM Technology | KundalahalliKere | 500 | 
| 18 | MD 372 | BEML Layout | Kundalahalli to Siddapura | 300 | 
| 19 | MD 374 | Tuberahalli BEML Layout | MD 375 @ Chainage 0.00m | 230 | 
| 20 | MD 375 | End Point of MD 374 & MD 373 | SiddapuraKere | 450 | 
| 21 | MD 292B | Vijaya Lakshmi Colony via Sai Baba Ashram | DakshinaPinakini River | 350 | 
| 22 | MD 292 | Patalamma Layout | DakshinaPinakini River via Sidhartha Layout | 500 | 
| 23 | MD 292A | Kashi Vishwanatha Temple | Outer Channel of YMC Kere near Railway Culvert | 1050 | 
| 24 | MD 294 | Alembic Glass | MD 388 @ Chainage 0.00m near Channasandra Circle | 1150 | 
| 25 | MD 296 | Channasandra Circle | DakshinaPinakini River on ChikkaThirupathi Road | 1300 | 
| 26 | MD 388A | Plantation near Gunjar | MD 388 @ Chainage 0.00m | 150 | 
| 27 | MD 387 | End point of MD 385 | MD 382 @ Chainage 1840.00m | 300 | 
| 28 | MD 451A | Gandhipura | MD 451 @ Chainage 560.00m | 360 | 
| 29 | MD 451 | Gandhipura | MD 453 @ Chainage 0.00m @ Immadihalli | 300 | 
42
| 30 | MD 453 | End Point of MD 451 | MD 454 @Chainage 0.00 | 360 | 
| 31 | BH 628 | KaikondanahalliKere | SowlTank | 800 | 
| 32 | BH 627 | KasavanalliKere | KaikondanahalliKere | 300 | 
| 33 | BH 629 | ArluurKere | KaikondanahalliKere | 500 | 
| 34 | BH 629 | ArluurKere | KaikondanahalliKere | 200 | 
| 35 | BH627A | Bellandur | Ecospace | 500 | 
| 36 | BH-599 | Iblur Lake | Bellandur Lake | 769 | 
| 37 | C 200 | Doordarshan, JayamahalExtn, | Ulsoor Tank | 4150 | 
| 38 | C-100 | From Palace Grounds, Vasanthnagar | Wind Tunnel Road | 9650 | 
| 39 | C-101 | Sudhamnagar | Inside HAL Airport | 1875 | 
| 40 | C-102 | Sweepers colony, Kadirenapalya | Shastrinagar Joining C-100 | 1600 | 
| 41 | C-103 | Krishnamurthynagar | Kadirenapalya | 1600 | 
| 42 | C-104 | Kadirenapalya | Kadirenapalya tank | 2500 | 
| 43 | C-105 | Hanumannagar | Kodihally, Near DomlurFlyover | 3000 | 
| 44 | C-106 | New Thippasandra | ISRO Complex | 650 | 
| 45 | C-107 | Kaggadasapura Lake | Kaggadasapura Main Road / Doodanekkundi tank | 900 | 
| 46 | C-108 | Airport South East Corner | NAL | 600 | 
| 47 | C-109 | Adj. To Airport Compound | Bellandur Lake | 675 | 
| 48 | N4 Drain | Nagammanagar | 3rd Cross Domlur | 1580 | 
| 49 | - | Domlur AK colony | Natasha Apartment | 920 | 
| 50 | C-201 | Ganapathy Temple, near Ulsoor Tank | MEG near Ulsoor Tank | 250 | 
| 51 | C-202 | Richards Town | Gymkhana Club | 1170 | 
| 52 | C-203 | Sagayapuram | Cleve town | 750 | 
| 53 | C-204 | Orion Mall, Marutisevanagar | Ulsoor Tank | 2000 | 
| 54 | - | Upper Byrasandra lake - Baghmane Tech Park | Lower Byrasandra Lake - Baghmanetechpark | 560 | 
| 55 | - | Lower Byrasandra Lake - Baghmanetechpark | Kaggadasapura Lake | 930 | 
| 56 | - | KrishnaiahnaPalya | Kaggadasapura Lake | 2600 | 
| 57 | - | Kasturinagar Park | Outer Ring Road | 1000 | 
| 58 | - | Kasurinagar Railway track | Outer Ring Road | 600 | 
| 59 | K-100 | K.R.Market | Bellandur Lake | 10200 | 
| 60 | K-200 | Sanatorium | Bellandur Lake | 7600 | 
43
via Austin town
61 K-103 Church Street &Viveknagar joining to 3400 K-100
Via Lakkasandra
62 K-104 Jayangara 1st Block 1700 joining to K-100
63 K-107 Lang ford town Jalakanteshwarapura 770
64 K-108 Venkatareddy Layout Willson Garden 1925 via R.R. Mohan Ray &
65 K-109 Kanteerava Stadium 2000 joining to K-100
66 K-110 Hosur road Sudhamanagara 625
67 K-111 South End road near Jayangara 2nd Block Lalbgh Tank 950
68 K-112 Parvathi Pura Kumbargundi 725 via St Michael's Church &
69 K-114 Lang ford road 1100 Joining to K-100
70 K-201 Vanaganahalli Agara Lake 1350
71 K-202 Ellukunte venkatapura 950
| 72 | K-203 | Crompton Greeves Road | Ring Road | 1200 | 
| 73 | K-204 | Madivala Tank | ||
| 74 | K-205 | Mudduram Nagar | Bismillah Nagar | 525 | 
75 K-206- Tayappanahalli Bovi Colony 1245
76 K-207 Bairsandra Ext Bannerugatta road 1225
77 K-208 Tilaknagar Krishnappa Garden 425
78 K-209 J P Nagara 6th Phase Madiwala Tank 9500
79 K-210 J P Nagara 6th Phase Joining K-200 1700
TotalLength 105149 meters
It is stated here that the above details are submitted for the first time now hence Committee could not cross verify at the field level. Further, the State Government is developing RajakaluveK-100 for the length of 11.4 kms from Chikkalalbagh to Bellanduru lake. No Objection Certification was given in compliance with IA No.392/2020 in OA No.125/2017 subject to the conditions. Copy of the said letter dated 24.12.2020 was also submitted to the Hon'ble NGT by the Committee. The outcome of the development of this Rajakaluve should be placed before the Hon'ble NGT by the State Government.
BBMP is yet to submit the detailed report on the status of the drains (with details of encroachments) and buffer zones
43. Para 6 of order KSPCB has identified 91 units for recovery of Rs.271.50 Crores . The stages of proceedings are as under:-  KSPCB has identified 91 Units for
Orderdated 13.08.2020: violation of non-installation of
44
Details of amount to be No. of units Installed STP 42 STP and assessed Environmental recovered from the units No. of units connected to BWSSB 06 Compensation of Rs 271.50 operating without STPs No. of units with STP under construction 07 Crores. and the stage of No. of units issued with Closure orders 10 proceedings pending Action yet to be taken 26  Out of 91 Units, 42 Units have before the State PCB installed STP, 6 units have
No recovery is made from the defaulting units. connected to BWSSB / UGD and 16 units STP are under
construction. Accordingly 55 units
are at different stages of
compliance and 27 Units have not
complied. Closure Orders have
been issued for these 27.
44. Para 6 of order A WP No. 50953/2019 regarding unauthorised occupation of the Bellanduru lake land (Ambedkar Colony)is pending before the  The Hon'ble High court extended
Order dated Hon'ble High Court. the stay order till the next date of
13.08.2020: hearing on13.01.2021. Next Date Vacation of interim of hearing is on order passed by the 08/03/2021Further action will be High Court (present taken after vacation of the stay status) order.
45. Para 6 of order The BDA submits that no Bio-Diversity parks are developed within the periphery of the lake after Hon'ble NGT observations. The  Setting up of Bio-diversity park in
Orderdated 13.08.2020: BDA submits that Government land is not available along the periphery of the lake boundary in buffer zone. both the lakes within the area The BDA has wrongly available between boundary of
understood that BDA submit that Contour Survey is being done for both the lakes to demarcate the area between maximum flood levels and the lake and Full Tank Level (FTL) is biodiversity parks are to lake periphery. So, identified/demarcated area which is beyond the maximum water level where water does not reach to lake being explored. be set up within the lake periphery, such area may be developed as Bio-diversity parks without compromising total water holding capacity of lake and only boundary. Such parks on approval from competent Authority.  Proposal submitted to Karnataka
are to be set up along Tank Conservation Development
the periphery of the lake Alternative land for disposal of silt or/and formation of Bio-diversity park in being explored near Defence land abutting to the Authority (KTCDA) for their boundary. (Possibility Bellandur lakeand also otheropen land available with Defence establishment within Bangalore city. Negotiation with Defence opinion which will be submitted of such Biodiversity authorities are in progress. If it materialises, further action will be taken by following the protocol of disposal as per Rules. to Hon'ble NGT for parks). consideration.
 The Full Tank Level will be
maintained through the
arrangement of sluice gates at
Bellandur and Varthur lake.
45
| 46. | Para 6 of order Order dated 13.08.2020: Enquiry should be conducted about the illegality in laying the pipeline by the Minor Irrigation Department (Present status). | The Additional Chief Secretary, Urban development Department, has submitted the following details in regard to action initiated against the officials in the subject matter. SL Name of the Erring Designation Period No Official 7. Devaraj B Chief Engineer 23-09-2015 to 31-08- 2017 8. M Ravindrappa Superintending Engineer 26-06-2014 to 18-11- 2019 9. S N Krishnappa Executive Engineer 11-06-2015 to 27-08- 2018 10. Venkatesh Assistant Executive Engineer 27-03-2017 to 04-11- 2018 11. Lakshmu Assistant Executive Engineer 18-07-2016 to 26-03- 2017 12. Ashok H Bhagi Assistant Engineer 07-12-2016 to 22-07- 2019 Officers who have worked in the specified period have been identified and show cause notices were issued to them vide dtd. 04.03.2020, giving 15 days’ time to submit their replies. The replies submitted by them have been reviewed and found unacceptable. Further at Sl. No 04 Shri Venkatesh, Assistant Executive Engineer expired on 04/11/2018. The Additional Chief Secretary submits that a proposal will be sent to DPAR for obtaining formal approval for initiating disciplinary proceedings against the concerned retired officers and after getting approval from DPAR to conduct department enquiry action will be initiated as per rule 214 (2)(B)(i) and (ii) of KCSR. | |
| 47. | Para 6 of order Orderdated 13.08.2020: Construction of retaining wall should not result in reduction of width of the water bodies/Rajakaluves. | The BBMP submits that the Construction of retaining wallsto storm water drains is temporarily suspended in the Bellandur and Varthur catchment areas. To ascertain the actual width of these drains, thehelp of Cadastral maps is being taken in collaboration of Revenue Department and the Karnataka State Satellite Remotes Sensing Centre. They submit that the exercise will be completed by the end of March 2021. Once these exercises are completed the encroachments shall be identified at field and should be removed.The works of construction of retaining walls should be recommenced accordingly. The excess area outside the retaining walls, tree park should be developed. The BBMP is expected to consider entire lengths of SWDs in the catchment areas. |  As per the instructions of the monitoring committee, the entire length of SWDs in the Catchment area is taken up for survey. | 
| 48. | Para 6 of order Orderdated 13.08.2020: Details of action taken by the BBMP against | The BBMP submits a detail of the encroachment removed in Mahadevapura Zone of the catchment of these lakes which were identified in the past.The details are as under:- | It is submitted that the regard to in regard to the encroachments pertaining to Bellandur lake, Out of 22 encroachments, 18 cases are | 
46
| illegal structures (rajakaluves and 30 meter buffer zone around the lakes) | Details of the encroach- Total encroach- ments removed Zone ments Identified by doing in each Zone survey in the year 2016-17 1 Mahadevapura 1101 1a Further, BBMP submits that, following Writ Petitions in the matter of encroachment are filed and pending before the Hon’ble High Court. Sl.no Writ Petition Number Number of cases 5. W.P No.27287/2019 3 cases 6. W.P No.26150/2019 & 26835-26842/19 1 Case 7. W.P No.29873/19 & 29874-876/19 3 Cases 8. W.P No.30399-30414/2019 45 Cases Total 52 Cases The details of encroachments of other zones for the catchment of Varthur, Bellanduru and Agram have not been submitted by the BBMP. The BBMP further submits that30 meter buffer zone have been demarcated all along the outer boundary of Bellandurulake with the help of Additional Director of Land Records. In the 30 meter buffer zone of Bellanduru lake, 22 unauthorised structures have been identified. The process up to demolition order, has been completed. Against the demolition order 13 persons have appealed before the Karnataka Administrative Tribunal; one Writ Petition has been filed in the High Court;4 persons have gone to the City Civil Court. Action has to be initiated against the remaining 4 persons. It is further submitted that along the periphery of the Bellanduru lake 177 mild steel tubular poles and 160 LED lights have been installed and commissioned.23 poles and 40 LED lights are yet to be installed. As regard to CCTV cameras, 51 numbers have been installed and functioning and 11 numbers are yet to be installed. Further, 30-meter buffer zone has been demarcated along the outer boundary of Varthur lake with the help of Additional Director of Land Records. In this buffer zone,12unauthorised structures have been identified. The process up to demolition orders has been completed. Against the demolition order, one person has appealed before the Karnataka Administrative Tribunal; one structure has been demolished and remaining 10 structures are yet to be demolished. | pending in KAT and Hon’ble High court and City Civil Court. The remaining four encroachments will be removed by 15.03.2021. It is further submitted that along the periphery of the Bellanduru lake. The remaining 23 poles and 40 LED lights and 11 CC TV Camera installation works will be completed before 15.04.2021. Regarding encroachments pertaining to Varthur lake, out of 12 encroachments, 1 case is pending in KAT and 1 demolition is completed. The remaining 10 encroachments will be removed within 15.03.2021. Along the periphery of the Varthur lake, the remaining 16 poles and 57 LED lights and 26 CCTV camera installation works will be completed before 15.04.2021. | |||
| Sl. No | Details of the encroachments removed /resolved by doing survey in the year 2018-19 on-wards | Balance Encroach ments to be removed as on 24.12.2020 | |||
| 98 | 864 | 139 | |||
| Mahadevapura-New | 45 | 0 | 0 | 45 | |
| TOTAL | 1146 | 98 | 864 | 184 | 
(rajakaluves and 30 encroach- Balance court and City Civil Court. The
Total encroach- encroachments removed
meter buffer zone Sl. ments removed Encroach ments remaining four encroachments will around the lakes) Zone ments Identified /resolved by doing No
by doing to be removed as be removed by 15.03.2021.
in each Zone survey in the year survey in the on 24.12.2020 2018-19 on-wards
year 2016-17 It is further submitted that along the
1 Mahadevapura 1101 98 864 139 periphery of the Bellanduru lake. The 1a Mahadevapura-New 45 0 0 45 remaining 23 poles and 40 LED lights and 11 CC TV Camera
TOTAL 1146 98 864 184 installation works will be completed before 15.04.2021.
Further, BBMP submits that, following Writ Petitions in the matter of encroachment are filed and pending before the Hon'ble High Court.
Sl.no Writ Petition Number Number of cases
5. W.P No.27287/2019 3 cases
6. W.P No.26150/2019 & 26835-26842/19 1 Case
7. W.P No.29873/19 & 29874-876/19 3 Cases
8. W.P No.30399-30414/2019 45 Cases
Total 52 Cases Regarding encroachments pertaining to Varthur lake, out of 12
encroachments, 1 case is pending in The details of encroachments of other zones for the catchment of Varthur, Bellanduru and Agram have not been submitted by the KAT and 1 demolition is completed.
BBMP.
The remaining 10 encroachments will be removed within 15.03.2021. The BBMP further submits that30 meter buffer zone have been demarcated all along the outer boundary of Bellandurulake with the help of Additional Director of Land Records. In the 30 meter buffer zone of Bellanduru lake, 22 unauthorised structures have been identified. The process up to demolition order, has been completed. Against the demolition order 13 persons have appealed before the Karnataka Administrative Tribunal; one Writ Petition has been filed in the High Court;4 persons have gone to the City Civil Court. Action has to be initiated against the remaining 4 persons.
It is further submitted that along the periphery of the Bellanduru lake 177 mild steel tubular poles and 160 LED lights have been installed and commissioned.23 poles and 40 LED lights are yet to be installed. As regard to CCTV cameras, 51 numbers have been installed and functioning and 11 numbers are yet to be installed.
Along the periphery of the Varthur
lake, the remaining 16 poles and 57
Further, 30-meter buffer zone has been demarcated along the outer boundary of Varthur lake with the help of Additional Director LED lights and 26 CCTV camera
of Land Records. In this buffer zone,12unauthorised structures have been identified. The process up to demolition orders has been installation works will be completed
completed. Against the demolition order, one person has appealed before the Karnataka Administrative Tribunal; one structure has before 15.04.2021.
been demolished and remaining 10 structures are yet to be demolished.
47
| It is further submitted that along the periphery of the Varthur lake, 184 poles and 143 LED lights have been installed and commissioned. 16 poles and 57 LED lights are yet to be completed. As regard to CCTV cameras, 24 numbers have been installed and functioning and 26 numbers are yet to be installed. | |||
| 49. | Para 6 of order Order dated 13.08.2020: BBMP should survey and notify the rajakaluves for purposes of buffer zones of 50, 25 and 15 meters | The Storm water drains are classified into the Primary, Secondary and Tertiary SWDs with the buffer zones of 50, 25 and 15 meters respectively on certain technical parameters. The details of length in each category have not been submitted by the BBMP. The Committee has convened several meetings in this regard but no satisfactory desired results are achieved. To ascertain the actual width of these drains and encroachments, the help of Cadastral maps is being taken in collaboration of Revenue Department and the Karnataka State Satellite Remotes Sensing Centre. They submit that the exercise will be completed by the end of March 2021. Once this exercise is completed, the further action of demarcating of encroachments at field should be done and to be removed. The BBMP is expected to consider entire lengths of SWDs in the catchment areas. | As per the instructions of the Monitoring Committee, the entire length of SWDs in the Catchment area is undertaken for survey. | 
| 50. | Para 8 of order Order dated 13.08.2020: We have given due consideration to the rival opinions. We are of the view that some more sampling may be got carried out with regard to de-silted debris/sludge at appropriate representative locations for comprehensive database and thereafter disposal protocol may be finalized in consultation with the CPCB. This will avoid unnecessary delay and cost (action taken in this regard by KSPCB for sample analysis) | More silt sampling in both lakes have been carried out jointly (by CPCB and KSPCB) and analysed for essential parameters including heavy metals. The standard protocol for assessing the hazardous (if any) is being followed through TCLP (Toxicity characteristic leaching procedure) and STLC (Soluble Threshold Limit Concentration) investigations of soil samples in Varthur and Bellandur Lakes. Based on this, CPCB has given a report for Varthur lake. As per the protocol based on TCLP and STLC analyses, the soil is non- hazardous and hence permission is accorded to BDA by KSPCB to dispose silt, based on the local demand As regards to Bellandur Lake, the analysis of sediment samples for leachability tests is under progress and is expected to be completed early. Based on the test results CPCB, will submit a report suggesting silt disposal mechanism. | Comments from the CPCB with regard to disposal Protocol is awaited. | 
48
Consideration of status report, objections of the Amicus and further directions
9. We have heard leaned Amicus Curie Shri Raj Panjwani, Senior Advocate and Ms. Madhvi Divan, learned ASG appearing for the State of Karnataka.
10. Shri Raj Panjwani submitted that progress in the matter has been very slow and at a snail pace. The problem is continuing for the last about four years. The Tribunal has been monitoring the matter for the last more than two years with the assistance of Monitoring Committee, headed by a former Supreme Court judge. On significant aspects, the State Authorities have not come up to the expectations. Inter alia it is pointed out:
(I) Against item nos. 8 and 16, there is practically no progress in taking action against erring officers
(II) Against item no. 6, action taken against industrial units for discharging the industrial waste without treatment by not installing requisite STPs is inadequate. Out of 61 defaulting units, action has been taken only against 10, while compliance is only by 25. Action is yet to be taken against 26.
(III) Against item No. 18, the progress shown is inadequate. Though compensation of Rs. 271.50 crores has been assessed against the defaulting units, no recovery has been made even though non-compliance is continuing. The State PCB ought to take coercive measure of disconnecting electricity supply, if the assessed compensation is not paid without valid reason, to enforce the "Polluter Pays' principle.
(IV) Against item No. 11, there is similar position with regard to recovery of compensation. Instead of disconnecting
49
electricity/water supply, the State is merely referring to the matter to the Deputy Commissioner, with no progress.
(V) Against Item No. 17, on the subject of removal of the waste and encroachments, there is no action taken with reference to 79 drains mentioned therein. It is further mentioned that the State Government is developing Rajakaluve K-100 for the length of 11.4 kms from Chikkalalbagh to Bellanduru lake. I.A. No. 392/2020 filed by the State before this Tribunal was disposed of on 15.12.2020 with the observation that the issue should be first looked into by the Monitoring Committee. The Monitoring Committee has left the issue to be gone into by this Tribunal, in absence of entire information being available with the Committee. Learned Amicus Curiae submitted that in the garb of development of the Rajakaluve in question the width and capacity of the drains should not be reduced.
(VI) Under Item No. 12, on the subject of desilting, progress shown is that a part of the silt has been removed and stacked.
Learned Amicus submitted that the silt can be used in the abandoned mines consistent with the SOP with underneath lining or can also be used on the embankment of flyovers as per CPCB guidelines on the subject. Safeguards be taken to prevent silt re-entering the lake till it is removed.
(VII) Under Item No. 10, on the issue of desilting of the lake falling in the defence area, the progress is that non-hazardous silt can be deposited on the defence land for development of army training areas and reclaiming of low-lying land.
50
Learned Amicus submitted that reclaiming of low-lying land will alter the character of the wetland, against established environmental norms. The low-lying land in question is wetland and needs to be maintained as such.
(VIII) Progress against item No. 20 with reference to setting up of bio-diversity park is not satisfactory. It is pointed out that the BDA has again taken a wrong stand for demarcating area between maximum flood level and the lake periphery instead of doing so along the periphery of the lake boundary i.e. ensuring that area of lake is not used in the process. The proposal of the BDA appears to be to develop the bio-diversity park within the boundary of the lake and the full tank level which will adversely affect the lake.
(IX) The progress against Item No. 23 with reference to removing the illegal encroachments in the catchment areas of the lakes is not satisfactory. It is mentioned that the BBMP has still not given details of the encroachments. It is only submitted that certain cases are pending before the Karnataka Administrative Tribunal (KAT), the High Court and the City Civil Court.
(X) Huge amount of C&D waste has been dumped and road made inside the lake itself which has to be undone, as directed earlier.
(XI) Compensation amount determined by the Tribunal needs to be credited to a separate account and utilised for restoration and if necessary, recovered from the polluters/erring officers
51
11. Learned ASG, without joining issue with the above submissions of learned Amicus, which are otherwise well founded, submitted that substantial progress has taken place and the same is continuing. Further steps are being taken and even after filing of progress report, closure orders have been passed against 26 industrial units. Boundaries are being constructed. There are constraints in the form of interim orders by various Courts. She has assured that further steps will be taken expeditiously and points made by learned Amicus will be addressed in the course of further working.
Analysis and further Directions
12. We have given due consideration to the issue. We do find some progress but we agree with learned Amicus that the progress is very slow and inadequate. The remaining work needs to be executed on war footing by remedying the deficiencies pointed out above by learned Amicus. We also permit learned Amicus to file a supplementary note directly to the Chief Secretary or to this Tribunal. If filed with the Tribunal, the same may be forwarded to the Chief Secretary, Karnataka for being addressed in positive spirit, in the light of observations already made and assurance of learned ASG.
13. Remedial steps to be taken so far for restoration of pristine ecology of the lakes in question have been discussed in earlier orders dated 6.12.2018, 21.10.2019, 18.12.2019 and 13.8.2020 and comments on some of the issues have been made hereinabove. Justice Hegde Committee has monitored the execution of the action plan on the subject for the last more than two years. We place on record our gratitude to Justice Hegde for the outstanding contribution in the matter.
52
14. However, monitoring by a Tribunal or Tribunal appointed Committee cannot be for indefinite period and ownership of execution of action plan for restoration of pristine ecology of the lakes/wetlands must be finally owned and taken over by the State authorities, headed by the Chief Secretary. Governance deficit has to be made up by further action in mission mode. The road-map has already been laid down by the orders of this Tribunal. We may note that apart from the present matter, issues of solid and liquid waste disposal generally and of polluted river stretches, water bodies, lakes and wetlands have been dealt with by this Tribunal in the light of Hon'ble Supreme Court decisions.1 Copies of such orders have been duly sent to the Chief Secretary, Karnataka and Chief Secretary also appeared in person twice before this Tribunal for interaction on these issues in OA 606/2018. There are 17 polluted river stretches in Karnataka including Tungabhadra which has been identified by the State to be model of compliance. Detailed guidelines have been laid down on all aspects of restoration of lakes and water bodies and several issues are overlapping with restoration of polluted river stretches. Specific directions cover the present matter on subjects of preventing discharge of sewage and effluents and solid waste, removing encroachments from catchment areas, desilting and deweeding, maintaining lake free from any constructions inside and all other matters covered by different headings of the progress report quoted
1
(2000) 2 SCC 679 Almitra Patel, Tribunal orders in OA 606/2018, last order 2.7.2020: Solid Waste (2017) 5 SCC 326 Paryavaran Suraksha, Tribunal last order dated 22.2.2021 in OA 593/2017: Liquid waste, including 351 polluted river stretches (OA 673/2018), coastal pollution (OA829/19), re-use of treated water (OA148/2016). (2017) 5 SCC 805, Tribunal order dated 27.8.2020, OA 351/2019, Raja Muzaffar Bhat v J & K: Wetlands and lakes: M.K. Balakrishnan and Ors. v. UOI, Tribunal order dated 18.11.2020 Lt Col Sarvadaman OA 325/2015, Water bodies, (1997) 1 SCC MC Mehta v. Kamal Nath, (2001) 6 SCC 496 Hinch Lal Tiwari vs. Kamala, (2006) 3 SCC 549 Intellectual Forum vs. State of AP
53
above. In the present context, we may specifically note need to remedy foaming and fire incidents, attributed to detergents containing Phosphates, sewage entering the lake needs to be diverted and treated sewage utilised for non-potable use. The lake is to be maintained with required oxygen levels for survival of aquatic life.
15. Protection of lakes and water bodies and preventing pollution is part of 'public trust' doctrine obligating the State authorities to take stern measures for enforcing the basic constitutional right of citizens to clean environment. Without this being done in a meaningful manner, there can be no sustainable development. There is need for stringent enforcement by way of adverse measures, including recovery of compensation for continuing violation and adverse entries in the record of defaulting officers. Accountability for those who are entrusted the responsibility to comply with these directions must be fixed on the principle of good governance, to enforce rule of law to protect rights of citizens.
16. Inspite of the fact that Water (Prevention and Control of Pollution) Act, 1974 was enacted 47 years back, to give effect to the decision in Stockholm Conference in the year 1972, the water pollution remains rampant. Though a serious criminal offence under the law of the land, the authorities have failed to take stringent action against the violators. In a way the State-authorities, who are constitutionally under obligation to ensure treatment of sewage before the same is discharged into the water bodies, have to take the blame. The adverse effect of water pollution on health and environment is well known. Water bodies, including lakes and wetlands, have great role in sustaining aquatic life, attract migratory and other birds, add to the natural aesthetics, help
54
harvesting rain water, maintain micro climate, recharge ground water and perform other ecological services.
The Hon'ble Supreme Court in its judgment in Paryavaran Suraksha vs. Union of India & Ors., (2017) 5 SCC 326 discussed the need to remedy water pollution and fixed a firm deadline of 31.03.2018 by which all necessary CETPs/STPs/ETPs should be in place failing which coercive action, including prosecution of State authorities was mandated. It also indicated sources of funding. The said direction continues to be violated. This situation can hardly be held to be conducive to the environmental rule of law. The sewage treatment is less than 50% (the sewage generation from the urban population of the country is reported to be about 70000 MLD and treatment capacity about 27000 MLD)2which is a matter of serious concern. The Tribunal has issued repeated directions on the subject. Till it is remedied, the goal of sustainable development is far cry. Similarly, directions have been given for protection of water bodies and wetlands, referred to earlier in para 14, supra.
The environmental law principles, which this Tribunal is mandated to apply under sections 20 and 15 of the NGT Act, 2010, are - 'sustainable development', 'precautionary' and 'polluter pays'. These principles, accepted in Stockholm conference, have been held to be part of right to life under article 21 of the Constitution in Vellore Citizens' Welfare Forum v. Union of India, (1996) 5 SCC 647. In Hanuman Laxman, (2019) 15 SCC 401, (paras 142-156), significance of environmental rule of law has been highlighted to achieve sustainable development goals for prosperity, health and well-being. This requires filling of gap between law and enforcement. In T.N. Godavarman Thirumulpad v. Union of India, (2002) 10 SCC 606,
2
As per report of the CPCB dated 30.09.2020 quoted in the order of this Tribunal dated 05.02.2021 in OA 95/2018, Aryavart Foundation v. M/s Vapi Green Enviro Ltd. & Ors.
55
at page 621, it was observed that the State has to forge in its policy to maintain ecological balance and hygienic environment. Article 21 protects right to life as a fundamental right. Enjoyment of life and its attainment including the right to life with human dignity encompasses within its ambit, the protection and preservation of environment, ecological balance free from pollution of air and water and providing sanitation, without which life cannot be enjoyed. Any contra acts or actions would cause environmental damage. Therefore, hygienic environment is an integral facet of right to healthy life and it would be impossible to live with human dignity without a humane and healthy environment. Environmental protection has now become a matter of grave concern for human existence. Promoting environmental protection implies maintenance of the environment as a whole comprising the man-made and the natural environment. Therefore, there is constitutional imperative on the Central Government, State Governments and bodies like municipalities, not only to ensure and safeguard proper environment but also an imperative duty to take adequate measures to promote, protect and improve the man-made environment and natural environment.
17. Accordingly, there is need for further continuous action and effective monitoring at the highest level in the Government. Consistent with earlier orders on the subject, such monitoring needs to be taken over by the Chief Secretary, Karnataka who may take over the record from the Monitoring Committee and take stock of all the left-over issues, with the assistance of other identified authorities and experts (which may include Indian Institute of Science, Bangaluru). He may inter alia interact with the State Lake Conservation and Development Authority and Forest, Ecology and Environment Departments. First meeting may be held latest by March 31, 2021. Thereafter, review meetings may be held atleast once in a month to
56
monitor further progress and completion of targets, already fixed or which may be further fixed. It will be open to all persons interested in restoration and maintenance of the lakes in question to give their suggestions and offer assistance which may be duly considered by the Chief Secretary, Karnataka on its merits. All pending projects for setting up of STPs, fencing of lake, removal of encroachments, etc. may be executed expeditiously. Particular attention may be given to preventing formation of foam and fire incidents. Directions in earlier orders and current order be duly carried out and overseen by the Chief Secretary, as already mentioned, atleast once a month. In pursuance of order of this Tribunal dated 18.11.2020 in OA 325/2015, Lt. Col. Sarvadaman Singh Oberoi v. Union of India & Ors., the steps for protection of water bodies have been directed to be taken and quarterly reports sent by the Chief Secretaries of States to the Secretary Ministry of Jal Shakti. Similarly, a quarterly report is to be given by the Chief Secretaries in respect of steps taken for protection of lakes and wetlands to the National Wetlands Authority, as earlier directed in OA 351/2019, Raja Muzaffar Bhat, supra, vide order dated 27.8.2020 and also placed on the website of the State Wetland Authority, for information of all the stake holders. The lakes in question are undoubtedly of great significance for the Bengaluru city and are glory and pride of the city. We do hope the administration will appreciate the need for stringent action and efforts for maintaining the said Lakes.
18. Before parting, we place on record our deep appreciation for the invaluable services rendered by learned Amicus. The application is disposed of accordingly.
57
A copy of this order be forwarded to the Secretary, MoEF&CC as Chairperson of National Wetland Authority and to Secretary, MoJS, GoI, CPCB and the Chief Secretary, Karnataka by e-mail for compliance. Adarsh Kumar Goel, CP
S.K. Singh, JM
Dr. Nagin Nanda, EM
March 12, 2021
Original Application No. 125/2017
DV
58
						
					
Comments