AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Smart Summary

Factual and Procedural Background

The petitioner, Power Grid Corporation of India Limited (PGCIL), filed a petition seeking approval for the transmission tariff related to the installation of a 400/220kV, 1*315 MVA Transformer at Mapusa (ICT-III) sub-station along with 2 nos. 220kV line bays. The installation was part of the Augmentation of Transformer and Bays in the Western Region, with an anticipated date of commercial operation (DOCO) as 1.10.2013, later commissioned on 1.11.2013. The petition was made under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 ("2009 Tariff Regulations"). The petitioner also requested a provisional tariff pending final tariff determination. The Commission conducted a hearing, considered compliance with procedural requirements, and after a preliminary prudence check, decided to grant provisional tariff subject to future adjustments.

Legal Issues Presented

  1. Whether the petitioner is entitled to provisional transmission tariff under Regulation 5(4) of the 2009 Tariff Regulations for the newly commissioned transformer and line bays at Mapusa sub-station.
  2. Whether the application filed by the petitioner complies with the procedural requirements under the 2009 Tariff Regulations and the 2004 Regulations.
  3. The appropriate quantum of provisional tariff to be granted pending final tariff determination.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Commission examined the petitioner's application for tariff determination under Regulation 5 of the 2009 Tariff Regulations, which permits filing for tariff determination for projects completed or projected to be completed within six months from the date of application. The petitioner complied with the procedural requirements under the 2004 Regulations, including service of notice and publication. The petitioner sought provisional tariff under Regulation 5(4) of the 2009 Tariff Regulations, which allows the Commission discretion to grant provisional tariff up to 95% of the annual fixed cost claimed.

During the hearing, the petitioner updated the Commission on the actual commissioning date and submitted revised certificates and tariff forms. The Commission conducted a preliminary prudence check on the Annual Fixed Charges claimed, considered the cost over-run for final tariff scrutiny, and decided to grant provisional tariff accordingly. The provisional tariff was set lower than the claimed amount, reflecting the Commission's discretion and prudence.

The provisional tariff granted is subject to adjustment as per Regulation 5(3) of the 2009 Tariff Regulations, ensuring reconciliation with the final tariff determination. The Commission also clarified that billing and collection of transmission charges will follow the applicable inter-state transmission charge sharing regulations.

Holding and Implications

The Commission granted provisional transmission tariff to the petitioner for the installation of the transformer and line bays at Mapusa sub-station, effective from the actual date of commercial operation, 1.11.2013. The provisional tariff allowed is Rs. 164.45 lakh for the year 2013–2014, against the claimed Rs. 182.72 lakh.

This decision enables the petitioner to recover transmission charges on a provisional basis pending final tariff determination, ensuring financial viability and continued operation of the transmission asset. The provisional tariff is subject to adjustment upon issuance of the final tariff order, maintaining regulatory oversight and fairness. No new precedent is established by this order.

To access the original judgment, please Sign In or Subscribe.

    Power Grid Corporation Of India Limited v. Madhya Pradesh Power Management Company Ltd.

    In the instant petition the petitioner, Power Grid Corporation of India Limited (PGCIL) has sought approval for transmission tariff for Installation of 400/220kV, 1*315 MVA Transformer at Mapusa (ICT-III) sub-station alongwith 2 nos. 220kV line bays (Ant. DOCO 1.10.2013) under Augmentation of Transformer and Bays in Western Region from DOCO to 31.3.2014, under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (hereinafter referred to as “2009 Tariff Regulations”). Further, the petitioner has requested for grant of provisional tariff as per 2009 Tariff Regulations, pending determination of final transmission tariff.

    2. Regulation 5 of the 2009 Tariff Regulations provides as under:—

    “Application for determination of tariff. (1) The generating company or the transmission licensee, as the case may be, may make an application for determination of tariff in accordance with Central Electricity Regulatory Commission (Procedure for making of application for determination of tariff, publication of the application and other related matters) Regulations, 2004, as amended from time to time or any statutory re-enactment thereof, in respect of the units of the generating station or the transmission lines or sub-stations of the transmission system, completed or projected to be completed within six months from the date of application.

    (2) The generating company or the transmission licensee, as the case may be, shall make an application as per Appendix I to these regulations, for determination of tariff based on capital expenditure incurred duly certified by the auditors or projected to be incurred up to the date of commercial operation and additional capital expenditure incurred duly certified by the auditors or projected to be incurred during the tariff period of the generating station or the transmission system:

    Provided that in case of an existing project, the application shall be based on admitted capital cost including any additional capitalization already admitted up to 31.3.2009 and estimated additional capital expenditure for the respective years of the tariff period 2009–14:

    Provided further that application shall contain details of underlying assumptions for projected capital cost and additional capital expenditure, where applicable.

    (4) Where application for determination of tariff of an existing or a new project has been filed before the Commission in accordance with clauses (1) and (2) of this regulation, the Commission may consider in its discretion to grant provisional tariff upto 95% of the annual fixed cost of the project claimed in the application subject to adjustment as per proviso to clause (3) of this regulation after the final tariff order has been issued:

    Provided that recovery of capacity charge and energy charge or transmission charge, as the case may be, in respect of the existing or new project for which provisional tariff has been granted shall be made in accordance with the relevant provisions of these regulations.”

    3. As per Regulation 5(4) of the 2009 Tariff Regulations, the Commission may in its discretion grant provisional tariff, if an application has been filed under Regulation 5(1) and (2) of the 2009 Tariff Regulations. Regulation 5(1) of the 2009 Tariff Regulations provides that the application for tariff should be made in accordance with the Central Electricity Regulatory Commission (Procedure for making of application for determination of tariff, publication of the application and other related matters) Regulations, 2004 (hereinafter referred to as “2004 Regulations”). Regulation 5(2) of 2009 Tariff Regulations provides that the application shall be made as per Appendix to the 2009 Tariff Regulations.

    4. The petitioner has made the application as per the Appendix to the 2009 Tariff Regulations. The petitioner has also complied with the requirements of 2004 Regulations, such as service of the copy of the application on the beneficiaries, publication of notice and web hosting of the application, etc.

    5. During hearing on 11.3.2014, the representative of the petitioner submitted that the petition was filed on 17.9.2013 with anticipated date of commercial operation as 1.10.2013 The asset has been commissioned on 1.11.2013 and revised management certificate alongwith revised tariff forms have been submitted vide affidavit dated 16.12.2013 He requested to allow provisional tariff as determination of final tariff would take some time. He also submitted that rejoinder to the reply of MSEDCL, Respondent No. 2, would be filed. The Commission directed the petitioner to file rejoinder to the reply of MSEDCL, by 25.3.2014 After carrying out a preliminary prudence check of the Annual Fixed Charges claimed and taking into consideration the cost over-run, which shall be looked into at the time of final tariff, the Commission has decided to grant the following provisional tariff to the petitioner:—

    (Rs. in lakh)

    Particulars Anticipated DOCO/DOCO Annual transmission charges claimed for the year 2013–2014 Annual transmission charges allowed for the year 2013–2014 Installation of 400/220kV, 1*315 MVA Transformer at Mapusa (ICT-III) sub-station alongwith 2 nos. 220 kV line bays 1.11.2013 182.72 164.45

    6. The provisional tariff allowed in this order shall be applicable from the date of commercial operation (DOCO) of the transmission system and the billing, collection and disbursement of the transmission charges shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time.

    7. The provisional transmission charges allowed in this order shall be subject to adjustment as per Regulation 5(3) of the 2009 Tariff Regulations.

    Use AI to get other relevant cases.

    Comments

    Power Grid Corporation Of India Limited v. Madhya Pradesh Power Management Company Ltd.
    (May 13, 2014)