AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • (Mah. Act 42 of 2015)
  • Section 127(2) of the Act
  • Section 126 of the Act
  • Section 31(5) of the 1966 Act
  • Mah. Act 42 of 2015 w.e.f 29-8-2015
  • Section 27 of the MRTP Act, 1966
  • Mah. Act 16 of 2009
  • Section 127(1) of the Act
  • Section 127 of the Act, dated 25-6-2009
  • Sections 126 and 127 of the 1966 Act
  • the Act (Maharashtra Regional and Town Planning Act, 1966)
  • Sections 127(1) and (2) of the Act
  • The 1966 Act
  • Section 127 of the MRTP Act, 1966
  • The 1894 Act
  • The Act
  • Section 127 of the Maharashtra Regional and Town Planning Act, 1966
  • Section 6 of the 1894 Act
  • Article 300-A of the Constitution
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • (Mah. Act 42 of 2015)
  • Section 127(2) of the Act
  • Section 126 of the Act
  • Section 31(5) of the 1966 Act
  • Mah. Act 42 of 2015 w.e.f 29-8-2015
  • Section 27 of the MRTP Act, 1966
  • Mah. Act 16 of 2009
  • Section 127(1) of the Act
  • Section 127 of the Act, dated 25-6-2009
  • Sections 126 and 127 of the 1966 Act
  • the Act (Maharashtra Regional and Town Planning Act, 1966)
  • Sections 127(1) and (2) of the Act
  • The 1966 Act
  • Section 127 of the MRTP Act, 1966
  • The 1894 Act
  • The Act
  • Section 127 of the Maharashtra Regional and Town Planning Act, 1966
  • Section 6 of the 1894 Act
  • Article 300-A of the Constitution
Smart Summary

Factual and Procedural Background

The appellant, a partnership firm that jointly owns 3H 90R of land in Survey No. 7/2, Mouja Durgavada, Morshi (Amravati District), found its land reserved for a shopping centre (Reservation 22) and a garden (Reservation 23) in the final development plan that came into force on 1-9-2005. Under Section 127 of the Maharashtra Regional and Town Planning Act, 1966, a landowner may seek de-reservation if, after ten years, the land has not been acquired.

After the ten-year period, the appellant issued:

  • a first notice dated 13-7-2015, which the municipality termed premature; and
  • a second notice dated 31-8-2015, receipt of which is disputed (municipality’s acknowledgement shows 1-9-2015; municipal minutes record 2-9-2015).

Subsequent municipal steps included a 30-11-2015 resolution to acquire the land and forwarding of an acquisition proposal on 14-1-2016 (later re-submitted on 16-12-2016). No acquisition materialised.

The appellant’s writ petition for a declaration that the reservation had lapsed was dismissed by the Bombay High Court (Nagpur Bench) on 5-2-2018, which held the second notice premature and therefore did not examine the adequacy of acquisition steps. The appellant appealed to the Supreme Court.

Legal Issues Presented

  1. Whether the second notice under Section 127, served on 31-8-2015/2-9-2015, was premature because it preceded completion of the prescribed ten-year period.
  2. Whether the municipal authorities took “steps for acquisition” within the 24-month period mandated by Section 127(1) so as to prevent lapsing of the reservation.
  3. Whether publication in the Official Gazette under Section 127(2) is a consequential duty or a discretionary act of the State once the conditions of Section 127(1) are met.

Arguments of the Parties

Appellant’s Arguments

  • The second notice was actually received on 2-9-2015, i.e. after the full ten-year period, as confirmed by the municipal General Body minutes.
  • The municipality failed to take substantive acquisition steps within 24 months; merely forwarding proposals is insufficient under Section 127(1).
  • Once Section 127(1) conditions are met, lapsing is automatic and the State is duty-bound to publish the notification under Section 127(2).

Respondents’ Arguments

  • Because the acknowledgment shows receipt on 1-9-2015, the notice was premature and therefore invalid under Section 127(1).
  • A land-acquisition proposal was forwarded, demonstrating sufficient steps toward acquisition; allowing lapsing would defeat public-interest planning objectives.
  • Publication under Section 127(2) involves governmental discretion; lapsing is not automatic.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Balaji Associates v. State of Maharashtra, 2018 SCC OnLine Bom 19740 Impugned High Court judgment dismissing writ petition. Reversed; Supreme Court allowed the appeal.
Shrirampur Municipal Council v. Satyabhamabai Bhimaji Dawkher, (2013) 5 SCC 627 “Steps for acquisition” begin only when the State takes active measures culminating in a declaration under Section 6 of the Land Acquisition Act, not by mere resolutions or letters. Relied on to hold that forwarding proposals did not satisfy Section 127(1); therefore reservation lapsed.
Girnar Traders, (2007) 7 SCC 555 Majority view adopted in Shrirampur regarding the threshold for “steps toward acquisition.” Cited approvingly within the Shrirampur extract to reinforce the above principle.
Labour Commissioner v. Burhanpur Tapti Mills Ltd., AIR 1964 SC 1687 Interpretation that “shall” in a statute conveys a mandatory obligation. Used to conclude that the Government is duty-bound (“shall”) to publish the lapsing notification under Section 127(2).

Court's Reasoning and Analysis

1. Date of receipt of the second notice: The Court accepted the municipal General Body’s own minutes, which recorded receipt on 2-9-2015, overruling reliance on the postal acknowledgment. Hence the notice was not premature.

2. Compliance with the 24-month requirement: Although the municipality forwarded an acquisition proposal on 16-12-2016, the Court, guided by Shrirampur Municipal Council, held that mere proposals or resolutions do not constitute “steps for acquisition.” No declaration under Section 6 of the 1894 Act or equivalent concrete action occurred within 24 months.

3. Automatic lapsing and Gazette publication: Reading Section 127(2) in tandem with Section 127(1), and emphasising the word “shall,” the Court held that once reservation lapses, Government publication is a consequential, mandatory act, not discretionary.

4. Expunging adverse remarks: The Court found certain remarks against counsel in the High Court judgment “uncalled for” and ordered them expunged.

Holding and Implications

Appeal Allowed; reservation deemed to have lapsed. The appellant’s land is released from Reservations 22 and 23 and may be developed in accordance with law. The State Government must publish the lapsing notification in the Official Gazette within four months.

Implications: The judgment reinforces that (i) service of notice even a day after the ten-year period suffices; (ii) municipalities must take substantive acquisition steps—not mere administrative correspondence—within 24 months; and (iii) Gazette publication under Section 127(2) is a mandatory follow-up once conditions of Section 127(1) are satisfied. No wider precedent was created beyond applying and affirming existing Supreme Court jurisprudence.

    Balaji Associates Through Its Partners And Others v. State Of Maharashtra And Others

    N.V. Ramana, J.— Leave granted. This appeal, by way of special leave, was filed against the impugned final judgment and order dated 5-2-2018 in Balaji Associates v. State of Maharashtra 2018 SCC OnLine Bom 19740, passed by the High Court of Judicature at Bombay (Nagpur Bench).

    2. The brief facts which are necessary for the disposal of this case are that the appellant is a partnership firm and its partners are the joint owners of the land in Survey No. 7 Sub-division No. 2, for a land admeasuring 3H 90R of Mouja Durgavada, Tq. Morshi, District Amravati, situated in the municipal limits of Nagar Parishad of the city of Morshi (hereinafter referred to as the “disputed land”). The final development plan for the city of Morshi was published on 11-7-2005 which came into force from 1-9-2005. In the aforesaid plan the appellant's land was reserved for shopping centre and garden, by Reservation Nos. 22 and 23 respectively.

    3. Under Section 127 of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as “the Act”), the owners could de-reserve a plot of land by serving a notice, after the lapse of 10 years from the date of such reservation i.e. 10 years from 1-9-2005 herein.

    4. Accordingly, the appellant served the first notice, under Section 127 of the Act, on 13-7-2015 asking the municipality to either acquire the disputed land or permit them to develop the same in accordance with law. The aforesaid first notice was replied as being premature. Moreover, the appellant again on 31-8-2015 sent the second notice under Section 127 of the Act. At the outset we may note that the date of receiving of the second notice is heavily contested, being important we shall take up the same in due course.

    5. Thereafter on 22-9-2015, Respondent 2 directed Respondent 3 to initiate the procedure required for acquisition of disputed land. On 30-11-2015 there was a General Body Meeting of the Municipal Council/Nagar Parishad, Morshi wherein it was decided that the disputed land was required for development of garden/park and necessary acquisition needs to be undertaken. For our purposes we need to observe the minutes of the meeting which is as under—

    As per Section 27 of the MRTP Act, 1966, Survey No. 7 of Mouja Durgavada Tq. Morshi, District Amravati reserved for Reservation No. 22 Shopping Centre and 23 Garden as per Development Plan (Excluded Plan) of Morshi City a discussion on the received notice is done in the standing committee meeting of Nagar Parishad Morshi.
    In this matter, Adv. G.K. Mundhada, Khaparde Garden issued a notice under Section 127 of the MRTP Act, 1966 which has inward number 5081 on dated 14-7-2015 and Inward No. 57 on dated 2-9-2015 in Nagar Parishad Office inward record register.
    ***
    Finally, in this meeting after discussion it is decided that the said land is required by the Nagar Parishad. Hence proposal for land acquisition is to be presented in front of Collector, Amravati. Also, the expenditure for said land should be done as per the Government defined guidelines of 13th Finance Commission and 14th Finance Commission.
    Hence the standing committee is giving approval in majority for all the expenses to be incurred in future for acquisition of the said land.
    Resolution approved by Majority.
    (emphasis supplied)

    6. Further on 14-1-2016, Respondent 3 submitted a proposal for acquisition of the disputed land before Respondent 4 (Collector), on the basis of the resolution passed on 30-11-2015. However, Respondent 4 informed Respondent 3 that the aforesaid proposal was not in order and the same needs to be resubmitted. A fresh proposal was submitted by Respondent 3, by letter dated 16-12-2016. It is brought to our attention that nothing has proceeded further and accordingly, acquisition has not taken place till this point of time.

    7. Aggrieved by the fact that the appellant was not allowed to enjoy the benefit of its ownership in the aforesaid disputed land, appellant through its partners filed a writ petition praying therein for a declaration that the reservation of their land has lapsed under Section 127 of the Act and other consequential relief.

    8. The High Court by order dated 5-2-2018 2018 SCC OnLine Bom 19740 dismissed the impugned writ petition on two major premises. First, the High Court was of the opinion that the second notice was sent prematurely thereby the necessary procedures required under Section 127 of the Act for de-reserving the land were not satisfied. Second, as the second notice dated 31-8-2015 was not satisfactory, therefore there was no need for further elaboration on steps taken for acquiring the land, to be followed by the municipality as required under Sections 127(1) and (2) of the Act.

    9. Aggrieved by the aforesaid dismissal, the appellant has approached this Court.

    10. Having observed the facts, we need to briefly notice the appellant's contention herein. The appellant contends that the second notice dated 31-8-2015 was received by the respondent authorities only on 2-9-2015 and not on 1-9-2015. The appellant relied extensively on the minutes of the meeting which records the aforesaid fact and claims that their notice was not premature. Further, the appellant contends that the authorities concerned have not taken adequate steps to acquire the aforesaid land in accordance with the mandate provided under Section 127 of the Act which consequentially entails de-reserving the aforesaid land.

    11. On the other hand, the learned counsel for the respondents contend that on reading of the provisions of Section 127(1) of the Act it is clear that, an owner or a person interested in the land would be entitled to serve a notice only after completion of the period of 10 years from the date on which the Final Developmental Plan comes into force. In this case, since the Final Developmental Plan had come into force on 1-9-2005, the notice dated 31-8-2015 is served on Respondent 3 before the completion of the stipulated period of 10 years from the date of coming into force of the Final Developmental Plan. Therefore, they contend that the High Court has rightly observed the period of 10 years, as mentioned in the aforesaid provision of Section 127 of the Act, is finally yet to complete before service of notice under Section 127 and hence the said notice under Section 127 issued by the appellant on Respondent 3 (Municipal Council, Morshi) would be treated as premature. Also, Respondent 3 has submitted a land acquisition proposal to Respondent 4. Hence, they argue that the High Court has passed order to safeguard the interest of general public at large and has thoroughly and judiciously stated that the provision for lapsing does not become a tool to defeat the very purpose of the Act.

    12. Having heard the arguments, we need to observe Section 127 of the Act, which reads as under—

    “127. Lapsing of reservations.— dated 25-6-2009[(1) If any land reserved, allotted or designated for any purpose specified in any plan under this Act is not acquired by agreement within ten years from the date on which a final regional plan, or final development plan comes into force 1894 (1 of 1894), dated 25-6-2009[or, if a declaration under sub-section (2) or (4) of Section 126 is not published in the Official Gazette within such period, the owner or any person interested in the land may serve notice, along with the documents showing his title or interest in the said land, on the Planning Authority, the Development Authority or, as the case may be, the appropriate authority to that effect; and if within 2015 (Mah. Act 42 of 2015)[twenty-four months]] from the date of the service of such notice, the land is not acquired or no steps as aforesaid are commenced for its acquisition, the reservation, allotment or designation shall be deemed to have lapsed, and thereupon the land shall be deemed to be released from such reservation, allotment or designation and shall become available to the owner for the purpose of development as otherwise, permissible in the case of adjacent land under the relevant plan.
    dated 25-6-2009[(2) On lapsing of reservation, allocation or designation of any land under sub-section (1), the Government shall notify the same, by an order published in the Official Gazette.]”

    13. The statutory provision is clear and categorical. Section 127(1), mandates that for an owner whose land is reserved, allotted or designated, in terms of final regional plan or developmental plan, needs to serve a notice to inform the municipality and seek its response concerning its interest in acquiring the land, if he wants his property to be de-reserved. As provided under the section, the time-limit to serve such notice accrues from the end date of stipulated period of ten years. Once such notice is served, the municipality has 24 months to acquire or take steps for acquisition of land. If municipality does not take the required measures in accordance with the aforesaid provision, then the land would be de-reserved and the owner can develop the same in accordance with law. Under sub-section (2) of Section 127 of the Act, the Government is required to publish the de-reserved plots in the Official Gazette.

    14. It is the contention of the respondents that the second notice was premature as the notice under Section 127 of the Act is required to be served after completion of the stipulated time. They place their reliance on the acknowledgment signed by the Municipality, while receiving the post which records the event of receival as 1-9-2015. While the appellant rely on the minutes of the meeting of the General Body, to point the factual discrepancy, wherein the letter is stated to have been received only on 2-9-2015.

    15. In our considered opinion, the writ courts, usually, should not indulge themselves in such factual findings. However, this case has been dragged too long and any further delay would unduly affect the right to enjoy property and benefits thereof. In any case, this case turns on the aspect of admission on the part of the respondents, that the second notice was received on 2-9-2015. There is no gainsaying that the respondents have not denied that their own General Body Meeting Resolution has accepted that the date of receival was 2-9-2015. In this context we need to accept the same. We may note that the High Court has ignored the aforesaid aspect, to rely exclusively on the acknowledgment. In the aforestated circumstances, reliance on the acknowledgment would not be safe. Having come to this understanding, we can conclude that the second notice can be said to have reached the municipality on 2-9-2015, after the expiry of the stipulated period.

    16. Having decided the first aspect, we need to now turn our attention to a different aspect under Section 127(1) of the Act, regarding the satisfaction of the actions undertaken by the municipality, to acquire or steps taken for acquiring, within the stipulated period of 24 months from the service of notice. We may note that the aforesaid time period of 24 months under Section 127 of the Act, given to the municipal authorities, was increased from 6 months to 12 months by an amending Act in 2009 (Mah. Act 16 of 2009); further, this time period was increased from 12 months to 24 months in 2015 (Mah. Act 42 of 2015 w.e.f 29-8-2015). From the aforesaid amendments, it can be noted that the legislative intent was to provide sufficient time for the municipalities to acquire the land as per the Developmental Plan needed for effective town planning.

    17. In any case, the respondents herein have admitted that the fresh proposal was forwarded from the office of Respondent 3 on 16-12-2016, and the same is currently being processed through the Office of Land Acquisition Officer, Amaravati. From the aforesaid narration, there is no gainsaying that the appellant has been denied its right to enjoy benefits of its possession by this protracted litigation. Mere forwarding of the proposal, would not be sufficient under Section 127(1) of the Act, as the provision concerned distinguishes between “step of acquisition of land” from “step for acquisition of land”.

    18. In this context, we may refer to Shrirampur Municipal Council v. Satyabhamabai Bhimaji Dawkher (2013) 5 SCC 627, wherein a three-Judge Bench of this Court has observed that:

    “42. We are further of the view that the majority in Girnar Traders (2007) 7 SCC 555 had rightly observed that steps towards the acquisition would really commence when the State Government takes active steps for the acquisition of the particular piece of land which leads to publication of the declaration under Section 6 of the 1894 Act. Any other interpretation of the scheme of Sections 126 and 127 of the 1966 Act will make the provisions wholly unworkable and leave the landowner at the mercy of the Planning Authority and the State Government.
    43. The expression “no steps as aforesaid” used in Section 127 of the 1966 Act has to be read in the context of the provisions of the 1894 Act and mere passing of a resolution by the Planning Authority or sending of a letter to the Collector or even the State Government cannot be treated as commencement of the proceedings for the acquisition of land under the 1966 Act or the 1894 Act. By enacting Sections 125 to 127 of the 1966 Act, the State Legislature has made a definite departure from the scheme of acquisition enshrined in the 1894 Act. But a holistic reading of these provisions makes it clear that while engrafting the substance of some of the provisions of the 1894 Act in the 1966 Act and leaving out other provisions, the State Legislature has ensured that the landowners/other interested persons, whose land is utilised for execution of the development plan/town planning scheme, etc. are not left high and dry. This is the reason why time-limit of ten years has been prescribed in Section 31(5) and also under Sections 126 and 127 of the 1966 Act for the acquisition of land, with a stipulation that if the land is not acquired within six months of the service of notice under Section 127 or steps are not commenced for acquisition, reservation of the land will be deemed to have lapsed. Shri Naphade's interpretation of the scheme of Sections 126 and 127, if accepted, will lead to absurd results and the landowners will be deprived of their right to use the property for an indefinite period without being paid compensation. That would tantamount to depriving the citizens of their property without the sanction of law and would result in violation of Article 300-A of the Constitution.”
    (emphasis supplied)

    In line with the observations of this Court, we hold that the authorities have not taken sufficient steps towards acquisition in this case. As the 24 months' time period stipulated under the law has elapsed, therefore the necessary procedures under Section 127(1) of the Act, stand satisfied for de-reserving the disputed land.

    19. The respondents have finally argued that the fulfilment of requirements under Section 127(1) of the Act does not automatically de-reserve the land, rather it's a discretion, under sub-section (2) of Section 127 of the Act, bestowed on the Government to choose the land to be de-reserved and publish the same in the Official Gazette. Such mandatory reading of the sub-section (2) of Section 127 of the Act, would give unfettered power in the hands of the State to pick and choose. This Court needs to effectively balance the power of eminent domain and the constitutional right of property, which mandates a rational reading of the law, wherein the declaration in the Official Gazette is only consequential and the State needs to follow, if the conditions under Section 127(1) stands satisfied. The usage of “On lapsing of reservation, allocation or designation of any land under sub-section (1)” in the sub-section (2) of Section 127, clearly points towards the aforesaid interpretation. Moreover, the usage of “shall”, also indicates the imperative nature of the sub-section, which makes the Government duty-bound to publish the same. [Refer Labour Commr. v. Burhanpur Tapti Mills Ltd. AIR 1964 SC 1687] In this case, we are of the opinion that the requirements under Section 127(1) are fully satisfied.

    20. Our attention has been drawn to certain adverse remarks passed by the High Court against the advocate, who appeared before it for the appellant herein, as contained in line numbers 1 to 7 and 76 to 79 of para 5 of the impugned judgment 2018 SCC OnLine Bom 19740. In our considered opinion, such adverse remarks were uncalled for, unnecessary and therefore, the same stand expunged from the record.

    21. In the light of the aforesaid observations, the inevitable conclusion is that the reservation of the appellant's land in question has lapsed and the land has become available to the appellant to be developed as otherwise permissible. Appeal, therefore deserves to be allowed and is accordingly allowed in terms of prayer. The State Government is directed to notify the lapsing of the reservation by an order to be published in the Official Gazette as per the requirements of Section 127(2) of the Act which shall be done as expeditiously as possible and preferably within a period of 4 months from today.

    22. The appeal stands allowed in the abovesaid terms. No order as to costs.