  • provisions of Section 127 of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the Act
  • provisions of Section 10(1) of the General Clauses Act, 1904,
  • provisions of Section 127(1)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • provisions of Section 127 of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the Act
  • provisions of Section 10(1) of the General Clauses Act, 1904,
  • provisions of Section 127(1)
Smart Summary

Judicial Opinion Summary

Factual and Procedural Background

The final development plan for Morshi town came into force on 1.9.2005. The petitioners' land was reserved under reservation Nos. 22 and 23 for a garden and a shopping centre respectively. Under Section 127 of the Maharashtra Regional and Town Planning Act, 1966 (the Act), if reserved land is not acquired by agreement within 10 years from the date the final development plan comes into force, the owner or an interested person may serve a purchase notice on the Planning Authority or Appropriate Authority; the authority must then take effective steps for acquisition within 24 months (as amended by the Act of 2015 effective from 29.8.2015), failing which the reservation is deemed released.

The petitioners served an initial purchase notice dated 13.7.2015 on the Municipal Council, which replied on 3.8.2015 that the notice was premature because the 10-year period had not yet expired. Thereafter the petitioners had a legal notice prepared dated 31.8.2015 by their advocate (Shri Mundhada). The Municipal Council's inward register shows reception of a notice on either 1.9.2015 or 2.9.2015 (the opinion records both dates in submissions), and the petitioners contend service occurred on the date of receipt. The petitioners assert no effective acquisition steps were taken by the Municipal Council within 24 months from service of the notice (dated 31.8.2015), and therefore sought a declaration that their land reservations lapsed under Section 127(1) of the Act.

Legal Issues Presented

  1. Whether an owner or a person interested in reserved land is entitled to serve a purchase notice under Section 127(1) of the Act before the completion of the 10-year period from the date the final development plan comes into force.
  2. Whether the relevant date for computing the 10-year period is the date of dispatch of the notice or the date on which the notice is effected/received by the Appropriate Authority (i.e., whether a notice prepared or dispatched before expiry but received on or after the 10th anniversary can be treated as valid).

Arguments of the Parties

Petitioners' Arguments

  • The reservation of the petitioners' land has lapsed under Section 127(1) of the Act because the authority did not acquire the land within the statutory period.
  • Although the notice was prepared on 31.8.2015 (before the 10-year mark), it was served/received by the Municipal Council on 2.9.2015 (or, as argued elsewhere, on the day it was received) and the relevant date for determining the 10-year period is the date of service/effect, not the date of dispatch or preparation.
  • The petitioners relied on authorities (Perfect Machine Tool Company Limited v. State of Maharashtra — 2016 DGLS(SC) 397; Gupta Loom Industries v. The State of Maharashtra — 2016 (6) ALL MR 307; and an unreported judgment dated 22.3.2013 in Writ Petition No. 5531 of 2012) to support the proposition that defects in form or the mode of addressing a notice may be cured if the notice reaches and is acted upon by the appropriate authority.

Municipal Council's Arguments

  • The "legal notice" dated 31.8.2015 is not a valid purchase notice as required by Section 127(1) of the Act; Section 127(1) entitles service of a notice only after the completion of the 10-year period following the coming into force of the final development plan.
  • Computation of time for Maharashtra Acts must follow Section 10(1) of the General Clauses Act, 1904, which requires exclusion of the first day in the series when the term "from" is used; thus the 10-year period from 1.9.2005 expires at the end of 1.9.2015. The notice in question was served/received on 1.9.2015 (i.e., before completion of the 10 years) and was therefore premature.
  • Merely because the Municipal Council was considering whether to acquire the land does not convert the petitioners' communication into a valid purchase notice under Section 127(1).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Shantaram Shankar Jamsandekar v. The State of Maharashtra, 2015 (1) Mh.L.J. (719) Where there is inaction by the development authority to acquire land by agreement within 10 years from commencement of the final development plan, a right accrues to owners/interested persons to issue a purchase notice on the planning/development authority. The Court relied on para 12 of this decision to emphasize that the right to issue a purchase notice accrues only after the completion of the 10-year period; consequently an owner must wait for that period before serving a purchase notice.
Perfect Machine Tool Company Limited v. State of Maharashtra, 2016 DGLS(SC) 397 Addresses validity of notices and whether defects in addressing or mode of service are fatal where the Municipal body had notice and acted (context: period of 10 years had already expired in that case). The Court distinguished this case on facts: in Perfect Machine Tool the 10-year period had already expired and the issue involved whether a notice addressed only to the Chief Engineer was valid; the Supreme Court held the notice was not bad in law. The present case was held distinguishable and not applicable.
Gupta Loom Industries v. The State of Maharashtra, 2016 (6) ALL MR 307 Considered whether a notice served on the Municipal Commissioner (but not formally on the Municipal Corporation) was valid where the Municipal Corporation had acted, indicating waiver of alleged defects. The Court held Gupta Loom distinguishable because in that case the Municipal Corporation had acted on the notice (constituting waiver). The present case did not involve such facts and therefore the authority of Gupta Loom did not assist the petitioners.
Unreported judgment dated 22.3.2013 in Writ Petition No. 5531 of 2012 Referenced as an instance where notice-related issues under Section 127 were considered (unreported). The Court observed that this unreported decision did not address the specific question whether a purchase notice can be served before completion of the 10-year period; therefore it was not helpful for the petitioners on the core issue.

Court's Reasoning and Analysis

The Court's analysis proceeded by focusing on the plain text of Section 127(1) of the Act and on statutory time-computation principles. The key steps in the Court's reasoning were:

  1. Identification of the core question: whether an owner/interested person may serve a purchase notice before the completion of the 10-year period after the final development plan comes into force. The Court framed this as the determinative issue.
  2. Application of the General Clauses Act (Section 10(1)) to time computation for a Maharashtra Act: the first day in the series is to be excluded where the term "from" is used. Applying that to the present facts (final plan came into force on 1.9.2005) means the 10-year period expires only at the end of 1.9.2015.
  3. Examination of the sequence of steps taken by the petitioners and their counsel: the first notice dated 13.7.2015 was served before completion of 10 years and was ruled premature by the Municipal Council. Despite that warning, counsel prepared another notice dated 31.8.2015 and dispatched it by registered post; the Municipal Council's acknowledgment shows receipt on 1.9.2015. The Court treated preparation, dispatch and receipt dates together to determine prematurity.
  4. Policy and practical considerations: the Court emphasised that a statutory cut-off (the 10-year benchmark) must be adhered to strictly. Allowing notices prepared and dispatched before expiry but received on or just after the expiry date to be treated as valid would open the door to successive premature notices being validated and would make the cut-off meaningless.
  5. Reliance on precedent: the Court relied on Shantaram Shankar Jamsandekar to support the proposition that the right to issue a purchase notice accrues only after the planning/development authority has remained inactive for ten years. The Court distinguished the authorities cited by the petitioners (Perfect Machine Tool and Gupta Loom) on factual grounds — in those cases the 10-year period had expired or the authority had acted in a way amounting to waiver — and therefore they did not support a contention that a notice served prior to expiry could be validated.
  6. Evaluation of form and substance: the Court also noted that Section 127(1) does not contemplate a mere "legal notice" in the mode used by the petitioners and criticized the advocate for acting prematurely despite being warned.
  7. Conclusion drawn from these steps: because the notice was prepared, dispatched and received before the completion of the 10-year period (as properly computed), it could not be treated as a valid purchase notice under Section 127(1). Accordingly, the petition seeking a declaration of lapse of reservation could not succeed on that basis.

Holding and Implications

Holding: The writ petition is DISMISSED. The Court dismissed the petition with no orders as to costs.

Direct consequences for the parties:

  • The petitioners' claim that their land reservations had lapsed by virtue of Section 127(1) as a result of the notice in question was rejected because the notice was premature.
  • The petitioners remain free to issue a fresh purchase notice to the Municipal Council in accordance with Section 127(1) of the Act — i.e., after the proper completion of the 10-year period and observing the statutory requirements for service.

Broader implications: The Court applied established rules of time-computation and adherence to statutory cut-offs, distinguished the precedents relied upon by the petitioners on factual grounds, and declined to extend or depart from those authorities. The decision enforces strict compliance with the temporal benchmark prescribed by Section 127(1); the opinion did not announce a new legal principle beyond that application.

    Balaji Associates Through Its Partners v. State Of Maharashtra Through Secretary And Others

    1. By this writ petition, the petitioners seek a declaration that the reservation of its land vide reservation Nos. 22 and 23 for garden and shopping centre respectively has lapsed and the petitioner is free to develop his land in the manner permissible to the adjacent land, as per the relevant development plan.

    2. The brief facts that give rise to the petition are that the final development plan for Morshi town was published on 1.9.2005 and the land of the petitioners was reserved vide reservation Nos. 22 and 23 for garden and shopping centre respectively. According to the provisions of Section 127 of the Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as the ‘Act’ for the sake of brevity), if the land reserved for any purpose specified in the plan under the Act is not acquired by an agreement within a period of 10 years from the day on which the final development plan comes into force, the owner or any person interested in the land is entitled to serve a purchase notice along with the documents showing his title or interest in the land on the Planning Authority, the Development Authority or as the case may be on the Appropriate Authority and it is necessary for the Authority to take effective steps for the acquisition of the land within 24 months (as amended by the Act of 2015 with effect from 29.8.2015) or else the land shall be deemed to be released from the reservation. The petitioners served a purchase notice dated 13.7.2015 on the respondent no. 3-Municipal Council, the Planning Authority under Section 127 of the Act. The Municipal Council by the reply dated 3.8.2015 had informed the petitioners that the notice was not in consonance with the provisions of section 127 of the Act, inasmuch as the period of 10 years within which the land of the petitioners should have been acquired by agreement had not expired on the date of the issuance of the notice. The petitioners had then served a legal notice dated 31.8.2015 through their advocate, Shri. Mundhada on the Municipal Council on 1.9.2015. The earlier notice dated 13.7.2015 was also issued by the same advocate, when he was informed that the period of 10 years from 1.9.2005 had not expired and the notice could not have been issued. It appears that the notice dated 31.8.2015 issued through advocate Shri. Mundhada was received by the Municipal Council on 1.9.2015 and the Municipal Council also considered whether the land of the petitioners could be acquired. Since no effective steps have been initiated by the Municipal Council within 24 months from the date of service of the notice dated 31.8.2015, the petitioners have filed the instant petition seeking a declaration that the reservation of their land has lapsed in view of the provisions of Section 127(1) of the Act.

    3. Shri. Dharmadhikari, the learned counsel for the petitioners who is assisted by advocate Shri. Mundhada, who had issued the purchase notice, submitted that the reservation of the land of the petitioners has lapsed in view of the provisions of Section 127(1) of the Act. It is submitted that though the notice was prepared on 31.8.2015 i.e. before the expiry of 10 years from the date of publication of the final development plant on 1.9.2005, the same was served on 2.9.2015 as could be seen from the inward register. It is submitted that even the Municipal Council has proceeded on the basis that the notice was received by the Municipal Council on 2.9.2015. It is submitted that the relevant date for considering the period of 10 years would not be the date on which the notice is dispatched but would be the date on which the notice is effected or served on the Appropriate Authority or the Planning Authority. The learned counsel relied on the judgments in the case of Perfect Machine Tool Company Limited v. State of Maharashtra, reported in 2016 DGLS(SC) 397, Gupta Loom Industries v. The State of Maharashtra, reported in 2016 (6) ALL MR 307 and an unreported judgment dated 22.3.2013 in writ Petition No. 5531 of 2012 to substantiate his submission.

    4. The learned counsel for the Municipal Council has strongly opposed the prayers made in the writ petition. It is submitted that the legal notice dated 31.8.2015 is not a purchase notice as required by the provisions of Section 127(1) of the Act. It is stated that only when the land reserved for any purpose specified in the final development plan under the Act is not acquired within 10 years from the date on which the final development plan comes into force, the owner or any person interested in the land is entitled to serve a notice on the Planning Authority or Appropriate Authority. It is submitted that on a reading of the provisions of Section 127(1) of the Act, it is clear that an owner or a person interested in the land would be entitled to serve a notice only after the completion of the period of 10 years from the date on which the final development plan comes into force. It is submitted that since the final development plan had come into force on 1.9.2005, by excluding the said date i.e. 1.9.2005, the period of 10 years would have expired at the end of 1.9.2015. It is submitted that the notice dated 31.8.2015 is served on the Municipal Council on 1.9.2015 i.e. before the completion of the period of 10 years from the date of the coming into force of the final development plan. It is submitted that as per the provisions of Section 10(1) of the General Clauses Act, 1904, when the period of commencement or termination of time is to be computed in respect of a Maharashtra Act, it would be necessary to exclude the first in the series of days or any other period of time, while considering the use of the term “from”. It is submitted that section 127(1) of the Act provides for the acquisition of the land within 10 years “from” the day on which a final development plan comes into force. It is submitted that by excluding the day i.e. the date 1.9.2005 on which the final development plan came into force, if the period of 10 years is to be computed, the said period would expire only at the end of 1.9.2015. It is submitted that the notice dated 31.8.2015 is served on the respondent/Municipal Council by registered post acknowledgment due, as it could be seen from the acknowledgment annexed to the writ petition, on 1.9.2015. It is submitted that neither was the notice prepared after the expiry of the term of 10 years nor was the same served on the Municipal Council after the expiry of the term of 10 years. It is submitted that the petitioners would have a right to serve a purchase notice on the appropriate authority or the planning authority only after ensuring that the said authority has not acquired the land within 10 years. It is submitted that merely because the Municipal Council was considering whether the land of the petitioners could be acquired, it cannot be said that the notice of the petitioners could be a purchase notice, as required by the provisions of Section 127(1) of the Act.

    5. This is a unusual case, where due to the over enthusiasm of an advocate to secure his professional fees, the interest of the client is put at stake. Advocate Shri. Mundhada, who has appeared in this Court in hundreds of cases, only dealing with Section 127 of the Act had served a legal notice on the Municipal Council, dated 31.8.2015 under Section 127 of the Act though the provisions of Section 127(1) of the Act do not contemplate a legal notice. The first legal notice was served on the Municipal Council by Advocate Shri. Mundhada on 13.7.2015. The Municipal Council wrote back to the advocate that the said notice is not in accordance with the provisions of the Act as a period of 10 years had not expired from the date of coming into force of the final development plan on 1.9.2005. For the reasons best known to Advocate Shri. Mundhada, who is working out matters mainly under Section 127 of this Act in this Court, few of them were even listed today before this Court, again prepared a legal notice dated 31.8.2015 before the expiry of the period of 10 years from the date of coming into force of the final development plan and sought to serve the same on the Municipal Council. The said notice is served on the Municipal Council on 1.9.2015 by registered post acknowledgment due. A copy of the acknowledgment is annexed to the writ petition for substantiating the fact that the notice was duly served on the Municipal Council on 1.9.2015. The question that falls for consideration in this case, is whether the owner or an interested person is entitled to serve a notice on the Planning Authority or the Development Authority before the expiry of the period of 10 years from the date of coming into force of the final development plan. On a reading of the provisions of Section 127(1) of the Act, it appears that an owner or a person interested would be required to wait for the completion of 10 years from the date of coming into force of the final development plan to serve a purchase notice on the Planning Authority or the Development Authority. The advocate for the petitioners, Shri. Mundhada had served the notice dated 13.7.2015 before the completion of the period of 10 years. He was clearly made aware of the fact that the notice was premature and it could have been issued to the Municipal Council only after the completion of the period of 10 years. In the recent days some of the counsels are endeavouring to secure big money at a great speed. Hence, without waiting for the completion of the term of 10 years, despite of previous warning, a notice dated 31.8.2015 was prepared by the advocate though it is not necessary for an advocate to serve a purchase notice, and the same was dispatched on 31.8.2015 by registered post acknowledgment due to the Municipal Council. The Municipal Council has received the same on 1.9.2015. It is rightly submitted on behalf of the Municipal Council that for computing the period of time in respect of a provision in the Maharashtra Act the first in the series of days should be excluded while considering the time from the word “from”. If we exclude the day viz. 1.9.2005 while computing the period of 10 years, the period of 10 years would expire only at the end of the day i.e. 1.9.2015. The petitioners however, did not wait for the completion of the period of 10 years, before ensuring that the notice was served on the Municipal Council. The notice is prepared before the expiry of the period of 10 years, dispatched to the Municipal Council before the expiry of the period of 10 years and received by the Municipal Council before the expiry of the period of 10 years. The submission made on behalf of the petitioners that since it is received on the last day i.e. the day on which the period would have expired, the same may be treated as a valid notice. We are afraid that this cannot be done. If it is done in the case of the petitioners, it would be necessary to do it in for several others, who may issue and serve a notice on the planning authority or development authority before the expiry of the period of 10 years and would claim that since the land is not acquired before the expiry of the period of 10 years, the notice i.e. issued prior to the expiry of the period of 10 years and served on the planning authority before the expiry of the same would be valid. In a given case, an owner or interested person may serve a notice 15 days prior to the completion of the period of 10 years or within some other time before the completion of the expiry of the period of 10 years. When a cut-off date/or a benchmark is prescribed for granting a right to a party to do a particular act viz. like service of purchase notice in this case, it would be necessary for the party to adhere to the cut-off date or the benchmark. This is an interesting case where the Municipal Council had informed the advocate, who had served the first notice that it was premature and that his clients should have waited for the completion of 10 years from the date of coming into force of the final development plan but still in great haste and hurry, the notice was again prepared before the expiry of period of 10 years and also served on the respondent-Municipal Council before the expiry of the said period. This is a case where due to the over enthusiasm of an advocate, who was not ready to wait for a very short time, say a couple of days, his clients have to suffer. However, if we issue a declaration in the present case, it would be difficult for us not to grant a similar declaration in cases where there is a short fall in the completion of the period of 10 years. It is held in the judgment in the case of Shri. Shantaram Shankar Jamsandekar v. The State of Maharashtra, reported in 2015 (1) Mh.L.J. (719) that where there is inaction on the part of the development authority to acquire the land by agreement within 10 years from the commencement of the final development plan, a legal right would accrue in favour of the owners or the person interested, to issue a purchase notice on the planning authority or the development authority calling upon them to acquire the land. It is stated in para 12 of the said judgment that the right to issue the purchase notice would accrue if there is inaction on the part of the planning authority or the development authority to acquire the land by agreement within ten years. As a necessary consequence thereof, it would be necessary to hold that it would be necessary for a owner or a person interested to wait for a period of 10 years from the date of coming into force of the final development plan for serving the purchase notice on the planning authority or the development authority. The judgment in the case of Perfect Machine Tool Company Limited v. State of Maharashtra, reported in 2016 DGLS(SC) 397 and relied on by the counsel for the petitioner cannot be applied to the case in hand. In that case, the period of 10 years had expired much before the issuance of the purchase notice. The question in the case before the Hon'ble Supreme Court was whether the notices addressed only to the Chief Engineer of the Development Authority was a valid notice as that was required to be served on the Municipal Corporation. Since the notice was placed before the Municipal Corporation and since the Municipal Commissioner had adequate notice of the same, the Hon'ble Supreme Court had held that the notice cannot be said to be bad-in-law. So also, in the judgment in the case of Gupta Loom Industries v. The State of Maharashtra, reported in 2016 (6) ALL MR 307 the notice was served on the Municipal Commissioner and not served on the Municipal Corporation. In the said judgment, on a consideration of the fact that the notice was addressed to the Municipal Commissioner and the Municipal Corporation and that the Municipal Corporation had acted upon the said notice, the court held that the Municipal Corporation can be said to have waived the alleged defects in the notice. The said cases are clearly distinguishable on facts. In none of the aforesaid reported decisions or in the un-reported decisions dated 22 March 2013 in Writ Petition NO. 5531 of 2012, this court was considering the issue whether the owner or the person interested in the land would be entitled to serve the purchase notice on the development authority or planning authority before the completion of the period of 10 years, within which the land could have been acquired by agreement. The judgments relied on by the counsel for the petitioners are not relevant for deciding the issue involved in this writ petition.

    6. In the result, the writ petition fails and is dismissed with no orders as to costs. The petitioners would be however free to issue a fresh purchase notice on the Municipal Council under the provisions of Section 127(1) of the Act. Order accordingly.