Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Neutral Citations
009 INSC 1278
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 30 of the Arbitration Act, 1940
  • Sections 30 and 33 of the Act
  • Section 30 of the Act
  • Section 30 or Section 33 of the Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
009 INSC 1278
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 30 of the Arbitration Act, 1940
  • Sections 30 and 33 of the Act
  • Section 30 of the Act
  • Section 30 or Section 33 of the Act
Smart Summary

Factual and Procedural Background

The appellant-contractor was awarded certain civil works on 22-3-1988 with an original completion date of 28-6-1989. By mutual agreement the period was extended several times, ultimately up to 5-11-1990, and the work was completed on 3-11-1990. After completion, disputes arose regarding payment. Invoking Clause 70 of the contract, the contractor filed claims before a sole arbitrator under the Arbitration Act, 1940 on 21-4-1994; both parties participated fully.

On 30-10-1996 the arbitrator issued a reasoned award allowing various claims, including Claim 5 for losses due to hold-ups and delay. The contractor sought to make the award the rule of court (O.S. No. 184/1996) while the Union of India filed objections (Misc. Suit No. 147/1996) under Section 30 of the 1940 Act. The Civil Judge (Senior Division), Roorkee dismissed the Union’s objections, held that the arbitrator had neither exceeded jurisdiction nor misconducted himself, and made the award a decree.

The Union of India appealed. By judgment dated 10-7-2007 the Division Bench of the High Court of Uttarakhand partly allowed the appeal, setting aside the award in respect of Claim 5 after re-evaluating the evidence. The contractor (now appellant) approached the Supreme Court by special leave; the present decision disposes of that appeal.

Legal Issues Presented

  1. Whether a court, while hearing objections under Section 30 of the Arbitration Act, 1940, can re-appraise evidence and substitute its own conclusions for those of the arbitrator.
  2. Specifically, whether the High Court erred in setting aside Claim 5 of the award on the ground that it was contrary to Clause 11(c) of IAFW-2249 and unsupported by evidence.

Arguments of the Parties

Appellant-Contractor’s Arguments

  • The High Court exceeded its limited jurisdiction under Section 30 by re-appreciating evidence that had already been fully considered by the arbitrator.
  • The Civil Court had rightly found that the arbitrator acted within the scope of the reference, supplied detailed reasons, and committed no legal misconduct.
  • The High Court’s approach violates the settled principle that an arbitrator is the final judge of facts and evidence.

Respondent – Union of India’s Position (as recorded in earlier proceedings)

  • Delay and losses claimed under Claim 5 were attributable to the contractor, who allegedly deployed insufficient manpower and resources.
  • Allowance of Claim 5 was contrary to Clause 11(c) of IAFW-2249, thus beyond the arbitrator’s authority.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
State of Rajasthan v. Puri Construction Co. Ltd. (1994) 6 SCC 485 Court cannot substitute its evaluation for that of the arbitrator; arbitrator is final arbiter on facts and law unless decision is perverse. Relied upon to show that High Court’s re-appreciation of evidence was impermissible.
Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38 Distinguishes between jurisdictional error and error within jurisdiction; courts cannot review merits where arbitrator’s view is possible. Used to reinforce the limited scope of interference.
MCD v. Jagan Nath Ashok Kumar (1987) 4 SCC 497 Appraisement of evidence by arbitrator ordinarily not open to judicial scrutiny; “reasonableness” not to be re-determined by court. Cited to emphasise deference to arbitrator’s factual findings.
Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC 449 Re-appraisal of evidence by courts is unknown to Section 30; interference only if award is perverse or based on wrong legal proposition. Forms core basis for allowing the appeal.
ONGC Ltd. v. SAW Pipes Ltd. (2003) 5 SCC 705 Even a reasoned award can be set aside only if patently illegal; mere error not enough. Quoted to delimit grounds of judicial review.
Kwality Manufacturing Corp. v. Central Warehousing Corp. (2009) 5 SCC 142 Court does not sit in appeal over arbitral findings; investigation confined to Section 30 grounds. Supports view that High Court went beyond statutory limits.
M.P. Housing Board v. Progressive Writers & Publishers (2009) 5 SCC 678 Re-assessment of evidence by court is impermissible. Reinforces prohibition on evidentiary re-evaluation.
Ispat Engg. & Foundry Works v. SAIL (2001) 6 SCC 347 Long-standing principle against re-appraising evidence under Section 30. Cited as further authority.
Champsey Bhara & Co. v. Jivraj Balloo Spg. & Wvg. Co. Ltd. (1922-23) 50 IA 324 (PC) Court has no jurisdiction to review merits of arbitral decision. Referenced within discussion of earlier authorities.
Union of India v. Bungo Steel Furniture (P) Ltd. AIR 1967 SC 1032 Court cannot investigate evidence to find legal error by arbitrator. Quoted to demonstrate settled law.
N. Chellappan v. Kerala SEB (1975) 1 SCC 289 Affirms finality of arbitral determinations on facts. Mentioned as part of the catena of cases.
Olympus Superstructures (P) Ltd. v. Meena Vijay Khetan (1999) 5 SCC 651 Restates limitations on judicial interference with awards. Referred to underline consistency of jurisprudence.

Court's Reasoning and Analysis

The Supreme Court observed that the Civil Judge had correctly applied the settled law in making the award a rule of court. The Division Bench of the High Court, however, set aside Claim 5 after independently evaluating the evidence and accepting the Union’s factual assertions. The Supreme Court held that such re-appreciation transgressed the narrow confines of Section 30 of the Arbitration Act, 1940.

The Court canvassed a series of binding precedents establishing that:

  • An arbitrator is the sole judge of the quality and quantity of evidence.
  • Courts may interfere only where the award is totally perverse, based on a manifest error of law, or exceeds the arbitrator’s jurisdiction.
  • Where reasons are given and are plausible, courts cannot test their sufficiency or correctness.

Applying these principles, the Supreme Court found that the arbitrator had provided “elaborate reasons” and had expressly recorded the Union’s defaults—such as delayed payments, late appointment of ATT agency, delayed decisions, and late change in tent-plinth height—which justified Claim 5. These findings were neither perverse nor unsupported by evidence. Consequently, the High Court’s substitution of its own view was legally untenable.

Holding and Implications

Holding: The appeal is allowed; the judgment of the Uttarakhand High Court dated 10-7-2007 is set aside, thereby restoring the Civil Court’s decree making the arbitral award the rule of the court.

Implications: The contractor’s award, including Claim 5, stands enforceable. The decision reaffirms the consistently held principle that courts cannot re-evaluate evidence when reviewing arbitral awards under the 1940 Act, thereby strengthening finality of arbitral processes without creating new substantive precedent.

To access the original judgment, please Sign In or Subscribe.

    Ravindra Kumar Gupta And Company v. Union Of India .

    S.S Nijjar, J.— Leave granted. The challenge in this appeal is to the judgment dated 10-7-2007 of the Division Bench of the High Court of Uttarakhand at Nainital whereby Appeal from Order AO No. 322 of 1998, new No. 242 of 2001 filed by the Union of India challenging the award of the arbitrator has been partly allowed.

    2. The grievance made by the appellant before us is that the High Court travelled beyond its jurisdiction in reappreciating the evidence led by the parties before the arbitrator and by substituting its own conclusions for the conclusions recorded by the arbitrator. It is submitted by the learned counsel for the appellant that the award of the Labour Court had been made the rule of the court by the Court of the Civil Judge, Senior Division, Roorkee (hereinafter referred to as “the civil court”). While considering the objections raised by the Union of India, the civil court took due notice of the evidence led by the parties before the arbitrator. It had been specifically held that the arbitrator has not acted beyond the scope of the reference nor can it be said that the arbitrator has misconducted himself in law or procedure.

    3. We may notice here the relevant facts: the appellant (hereinafter referred to as “the contractor”), was allotted certain civil works on 22-3-1988. Initially, the work was scheduled to be completed on or before 28-6-1989. However, by mutual agreement, the period of contract was extended from time to time and finally till 5-11-1990. The work was completed on 3-11-1990. Disputes arose between the parties after completion of the work regarding the work and payment for the same. The contractor invoked the arbitration clause contained in Clause 70 of the agreement dated 22-3-1988. Necessary claim was filed before the sole arbitrator under the Arbitration Act, 1940 on 21-4-1994. Both the parties participated in the proceedings.

    4. The arbitrator, after elaborate discussion of the entire evidence led by the parties, passed the award dated 30-10-1996. Thereafter, the contractor filed Original Suit No. 184 of 1996 in the civil court with a prayer for making the award of the sole arbitrator the rule of the court. The Union of India also filed Miscellaneous Suit No. 147 of 1996, with a prayer for setting aside the award. Both the suits were heard together by the civil court. In the miscellaneous suit it was pleaded by the Union of India that the award of the arbitrator is infirm being against the law and available evidence. As such the arbitrator has misconducted himself in law.

    5. The main issue between the parties is with regard to Claim 5. It was stated by the Union of India that the arbitrator had acted beyond its jurisdiction by allowing Claim 5 of the contractor, contrary to the provision contained in Clause 11(c) of IAFW 2249, which is part of the agreement dated 22-3-1988. The civil court duly framed issues. It took due notice of the objections raised by the Union of India. It was submitted on behalf of the Union of India, that the arbitrator cannot accept any claim going beyond the scope of the dispute entrusted and referred to him. The civil court specifically observed as follows:

    “In the present case, dispute of loss suffered by the decree-holder for the hold-ups and delay was referred to the arbitrator and the learned arbitrator has decided this dispute within his jurisdiction.”

    It has been specifically observed by the civil court that the parties had placed the case before the arbitrator on the point in issue. It is further observed that the arbitrator has passed the award giving reasons in detail. Therefore, it cannot be said that the arbitrator has acted beyond the scope of reference.

    6. The civil court took due notice of the settled propositions of law that at the time of hearing of objections under Section 30 of the Arbitration Act, 1940 the jurisdiction of the court is limited. It has also been noticed that the court cannot hear the objections against the award as an appellate court, as the arbitrator is the final arbiter of the dispute referred to him. After noticing the legal position and after examining clauses of the agreement, the award has been made the rule of the court.

    7. The findings of the civil court were challenged by the Union of India in appeal before the High Court, which has been partly allowed. In partly allowing the appeal the Division Bench has set aside the findings recorded by the arbitrator by merely stating as follows:

    “So far as the contention of the learned counsel for the appellant that Claim 5 is against Clause 11(c) of IAFW, which is part of the agreement is concerned, we have carefully perused the award given by the arbitrator as well as the impugned judgment of the court below. Claim 5 was for losses due to hold-ups and delay in the work. The Union of India in reply before the arbitrator stated that the delay in execution of work was due to default of the contractor himself. He had not employed sufficient manpower and resources to complete the work in time. There is no reason to disregard this statement on behalf of the appellant Union of India. We find that the arbitrator acted unreasonably and irrationally in ignoring the limits and the provisions of the contract as submitted by the learned counsel for the appellant.”

    8. We are of the considered opinion that the High Court committed a serious error in reappreciating the evidence led by the parties before the arbitrator. This evidence was duly scrutinised and evaluated by the arbitrator. With regard to Claim 5, the arbitrator has given elaborate reasons. Therefore, findings recorded by the arbitrator cannot be said to be either perverse or based on no evidence. A firm finding has been recorded that under Claim 5 there was default and delay on the part of the Union of India with respect to:

    (i) The payment of RARs final bill.
    (ii) Delay in appointing agency for ATT.
    (iii) Delay in giving decision.
    (iv) Increase in height of tent plinth (given late).

    This conclusion has been erroneously substituted by the High Court with its own opinion on appreciation of the evidence. Such a course was not permissible to the High Court while examining objections to the award under Section 30 of the Arbitration Act, 1940.

    9. The law with regard to scope and ambit of the jurisdiction of the courts to interfere with an arbitration award has been settled in a catena of judgments of this Court. We may make a reference here only to some of the judgments. In State of Rajasthan v. Puri Construction Co. Ltd. (1994) 6 SCC 485 this Court observed as follows:

    “26. The arbitrator is the final arbiter for the dispute between the parties and it is not open to challenge the award on the ground that the arbitrator has drawn his own conclusion or has failed to appreciate the facts. In Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38 it has been held by this Court that there is a distinction between disputes as to the jurisdiction of the arbitrator and the disputes as to in what way that jurisdiction should be exercised. There may be a conflict as to the power of the arbitrator to grant a particular remedy. One has to determine the distinction between an error within the jurisdiction and an error in excess of the jurisdiction. Court cannot substitute its own evaluation of the conclusion of law or fact to come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. (emphasis in original) Whether a particular amount was liable to be paid is a decision within the competency of the arbitrator. By purporting to construe the contract the court cannot take upon itself the burden of saying that this was contrary to the contract and as such beyond jurisdiction. If on a view taken of a contract, the decision of the arbitrator on certain amounts awarded is a possible view though perhaps not the only correct view, the award cannot be examined by the court. Where the reasons have been given by the arbitrator in making the award the court cannot examine the reasonableness of the reasons. If the parties have selected their own forum, the deciding forum must be conceded the power of appraisement of evidence. The arbitrator is the sole judge of the quality as well as the quantity of evidence and it will not be for the court to take upon itself the task of being a Judge on the evidence before the arbitrator.
    27. In MCD v. Jagan Nath Ashok Kumar (1987) 4 SCC 497, it has been held by this Court that appraisement of evidence by the arbitrator is ordinarily never a matter which the court questions and considers. It may be possible that on the same evidence the court may arrive at a different conclusion than the one arrived at by the arbitrator but that by itself is no ground for setting aside the award. It has also been held in the said decision that it is difficult to give an exact definition of the word ‘reasonable’. Reason varies in its conclusions according to the idiosyncrasies of the individual and the time and circumstances in which he thinks. In cases not covered by authority, the verdict of a jury or the decision of a Judge sitting as a jury usually determines what is ‘reasonable’ in each particular case. The word reasonable has in law prima facie meaning of reasonable in regard to those circumstances of which the actor, called on to act reasonably knows or ought to know. An arbitrator acting as a Judge has to exercise a discretion informed by tradition, methodised by analogy, disciplined by system and subordinated to the primordial necessity of order in social life. Therefore, where reasons germane and relevant for the arbitrator to hold in the manner he did, have been indicated, it cannot be said that the reasons are unreasonable.”

    10. In Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC 449 this Court upon analysis of numerous earlier decisions, held as follows:

    “36. Be it noted that by reason of a long catena of cases, it is now a well-settled principle of law that reappraisal of evidence by the court is not permissible and as a matter of fact exercise of power by the court to reappraise the evidence is unknown to proceedings under Section 30 of the Arbitration Act. In the event of there being no reasons in the award, question of interference of the court would not arise at all. In the event, however, there are reasons, the interference would still be not available within the jurisdiction of the court unless of course, there exist a total perversity in the award or the judgment is based on a wrong proposition of law. In the event however two views are possible on a question of law as well, the court would not be justified in interfering with the award.
    37. The common phraseology ‘error apparent on the face of the record’ does not itself, however, mean and imply closer scrutiny of the merits of documents and materials on record. The court as a matter of fact, cannot substitute its evaluation and come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. If the view of the arbitrator is a possible view the award or the reasoning contained therein cannot be examined.”

    11. This view has been reiterated by this Court in ONGC Ltd. v. SAW Pipes Ltd. (2003) 5 SCC 705 as follows:

    “53. In the light of the aforesaid decisions, in our view, there is much force in the contention raised by the learned counsel for the appellant. However, the learned Senior Counsel Mr Dave submitted that even if the award passed by the Arbitral Tribunal is erroneous, it is settled law that when two views are possible with regard to interpretation of statutory provisions and/or facts, the court would refuse to interfere with such award.
    54. It is true that if the Arbitral Tribunal has committed mere error of fact or law in reaching its conclusion on the disputed question submitted to it for adjudication then the court would have no jurisdiction to interfere with the award. But this would depend upon reference made to the arbitrator: (a) if there is a general reference for deciding the contractual dispute between the parties and if the award is based on erroneous legal proposition, the court could interfere; (b) it is also settled law that in a case of reasoned award, the court can set aside the same if it is, on the face of it, erroneous on the proposition of law or its application; and (c) if a specific question of law is submitted to the arbitrator, erroneous decision in point of law does not make the award bad, so as to permit its being set aside, unless the court is satisfied that the arbitrator had proceeded illegally.”

    12. In Kwality Mfg. Corpn. v. Central Warehousing Corpn. (2009) 5 SCC 142 it was held:

    “10. At the outset, it should be noted that the scope of interference by courts in regard to arbitral awards is limited. A court considering an application under Section 30 or 33 of the Act, does not sit in appeal over the findings and decision of the arbitrator. Nor can it reassess or reappreciate evidence or examine the sufficiency or otherwise of the evidence. The award of the arbitrator is final and the only grounds on which it can be challenged are those mentioned in Sections 30 and 33 of the Act. Therefore, on the contentions urged, the only question that arose for consideration before the High Court was, whether there was any error apparent on the face of the award and whether the arbitrator misconducted himself or the proceedings.”

    13. Again it is reiterated in the judgment of M.P Housing Board v. Progressive Writers and Publishers (2009) 5 SCC 678 as follows:

    “28. The finding arrived at by the arbitrator in this regard is not even challenged by the Board in the proceedings initiated by it under Section 30 of the Act. It is fairly well settled and needs no restatement that the award of the arbitrator is ordinarily final and the courts hearing applications under Section 30 of the Act do not exercise any appellate jurisdiction. Reappraisal of evidence by the court is impermissible.”

    14. In this case, the Supreme Court noticed the earlier judgment in Ispat Engg. & Foundry Works v. SAIL (2001) 6 SCC 347 wherein it was held as follows:

    “4. Needless to record that there exists a long catena of cases through which the law seems to be rather well settled that the reappraisal of evidence by the court is not permissible. This Court in one of its latest decisions (Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC 449) upon consideration of decisions in Champsey Bhara & Co. v. Jivraj Balloo Spg. & Wvg. Co. Ltd. (1922-23) 50 IA 324, AIR 1923 PC 66, Union of India v. Bungo Steel Furniture (P) Ltd. AIR 1967 SC 1032, (1967) 1 SCR 324, N. Chellappan v. Kerala SEB (1975) 1 SCC 289, Sudarsan Trading Co. v. Govt. of Kerala (1989) 2 SCC 38, State of Rajasthan v. Puri Construction Co. Ltd. (1994) 6 SCC 485 as also in Olympus Superstructures (P) Ltd. v. Meena Vijay Khetan (1999) 5 SCC 651 has stated that reappraisal of evidence by the court is not permissible and as a matter of fact, exercise of power to reappraise the evidence is unknown to a proceeding under Section 30 of the Arbitration Act. This Court in Arosan Enterprises (1999) 9 SCC 449 categorically stated that in the event of there being no reason in the award, question of interference of the court would not arise at all. In the event, however, there are reasons, interference would still be not available unless of course, there exist a total perversity in the award or the judgment is based on a wrong proposition of law. This Court went on to record that in the event, however, two views are possible on a question of law, the court would not be justified in interfering with the award of the arbitrator if the view taken recourse to is a possible view. The observations of Lord Dunedin in Champsey Bhara (1922-23) 50 IA 324, AIR 1923 PC 66 stand accepted and adopted by this Court in Bungo Steel Furniture AIR 1967 SC 1032, (1967) 1 SCR 324 to the effect that the court had no jurisdiction to investigate into the merits of the case or to examine the documentary and oral evidence in the record for the purposes of finding out whether or not the arbitrator has committed an error of law. The court as a matter of fact, cannot substitute its own evaluation and come to the conclusion that the arbitrator had acted contrary to the bargain between the parties.”

    15. In our opinion, the impugned judgment of the High Court does not fall within the limited jurisdiction available to the Court for interference in the award of an arbitrator.

    16. For the aforesaid reasons the appeal is allowed. The impugned judgment of the High Court is set aside.

    Use AI to get other relevant cases.

    Comments

    Ravindra Kumar Gupta And Company v. Union Of India .
    (Dec 3, 2009)