AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Advocates
Judges
Acts
  • S. 15 of the English Arbitration Act, 1950 or Section 48(5)(b) of the English Arbitration Act, 1996
  • Sections 5 and 34 of the Arbitration and Conciliation Act, 1996 (hereinafter called the 'Act')
  • ARBITRATION ACT 1940
  • S. 30 or S. 33 of the Arbitration Act of 1940.
  • ARBITRATION AND CONCILIATION ACT 1996
  • sub-clause (2)(b) of S. 34 of the new Act.
  • SPECIFIC RELIEF ACT
  • sub-section (2) and sub-section (3). (2)
  • sub-clause (1) of S. 16 to rule
  • S. 75 or 81. Section 75
  • S. 34." Section 16
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Advocates
Judges
Acts
  • S. 15 of the English Arbitration Act, 1950 or Section 48(5)(b) of the English Arbitration Act, 1996
  • Sections 5 and 34 of the Arbitration and Conciliation Act, 1996 (hereinafter called the 'Act')
  • ARBITRATION ACT 1940
  • S. 30 or S. 33 of the Arbitration Act of 1940.
  • ARBITRATION AND CONCILIATION ACT 1996
  • sub-clause (2)(b) of S. 34 of the new Act.
  • SPECIFIC RELIEF ACT
  • sub-section (2) and sub-section (3). (2)
  • sub-clause (1) of S. 16 to rule
  • S. 75 or 81. Section 75
  • S. 34." Section 16
Smart Summary

Factual and Procedural Background

The appellant agreed, through three main agreements dated 9-3-1994, 9-3-1994 and 29-6-1994, to sell six flats in a building called “Wembley” at Vile Parle (East), Bombay, to the respondents for Rs. 76, 72 and 74 lakhs respectively. Possession with amenities was to be delivered by 30-10-1994 and time for payment was stipulated as being of the essence, with 21 % interest payable on default. Each main agreement contained an arbitration clause (Clause 39) of broad scope.

On the same dates the parties executed three separate “Interior Design Agreements”, each for a lump-sum of Rs. 10 lakhs and each containing its own arbitration clause (Clause 5) naming two solicitors as joint arbitrators.

Disputes arose: the respondents alleged lack of construction progress; the appellant alleged payment defaults and purported to terminate the agreements. Correspondence ensued during 1995-1996, culminating in the respondents’ notice of 8-7-1996 proposing arbitration. When no agreement was reached, the respondents moved the Bombay High Court under Section 11 of the Arbitration and Conciliation Act, 1996 (“the Act”). On 13-6-1997 the Chief Justice appointed a retired High Court Judge as sole arbitrator.

The arbitrator proceeded despite several adjournment requests and objections by the appellant, eventually passing three awards on 13-11-1997 granting specific performance of both the main and the Interior Design agreements. The appellant’s objections under Sections 5 and 34 of the Act were dismissed by a Single Judge on 12-1-1998 and by a Division Bench on 2-4-1998. The present Civil Appeals challenge those decisions.

Legal Issues Presented

  1. Whether Clause 39 of the main agreements empowered the arbitrator to decide disputes arising under the separate Interior Design Agreements, whose Clause 5 designated different (named) arbitrators.
  2. Whether failure to raise a jurisdictional plea before the arbitral tribunal under Section 16 precluded the appellant from raising it later under Section 34.
  3. Whether an arbitrator is competent to grant the remedy of specific performance of an agreement for sale of immovable property, or whether such subject-matter is “not capable of settlement by arbitration” under Section 34(2)(b)(i).
  4. Whether the High Court could interfere with the arbitral findings on factual issues such as default, readiness and willingness, and time being of the essence, within the narrow scope of Section 34.

Arguments of the Parties

Appellant’s Arguments

  • The reference, notices and Section 11 order related only to the main agreements; therefore the arbitrator lacked jurisdiction over the Interior Design Agreements, which had a distinct arbitration clause naming different arbitrators.
  • Even if the appellant subsequently remained ex parte, the arbitrator could not assume the respondents’ allegations to be proved.
  • Specific performance is a discretionary remedy reserved to civil courts; hence an arbitral award granting it offends Section 34(2)(b)(i).
  • On merits, the respondents were in default and not ready and willing; termination was valid; at minimum, interest @ 21 % on the balance price was mandatory.

Respondents’ Arguments

  • Clause 39 expressly covers disputes “connected with” the subject-matter of the main agreements; the Interior Design Agreements are integrally connected, containing overlapping obligations and executed on the same dates.
  • The appellant never raised a Section 16 plea before the arbitrator; jurisdiction cannot be challenged for the first time after an unfavourable award.
  • An arbitrator can order specific performance; several High Courts have so held and the Act contains no prohibition.
  • The scope of Section 34(2)(b) is narrow; factual re-appraisal or re-appreciation of evidence is impermissible.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Rajinder Krishan Khanna v. Union of India, (1998) 7 SCC 129 Scope of reference can be questioned under Section 34(2)(a)(iv) if objection was raised before the arbitrator. Used to distinguish present facts; here no such objection was raised before the arbitrator.
Renusager Power Co. Ltd. v. General Electric Co., (1984) 4 SCC 679 Wide construction of phrases “connected with, arising out of, or in relation to”. Supported interpretation that Interior Design disputes were “connected” to the main agreements.
Agarwal Engineering Co. v. T.H. Machine Industries, AIR 1977 SC 2122 When two contracts have separate arbitration clauses, each may operate in its distinct sphere absent overlap. Cited to illustrate contrasting situation; present case involved overlapping obligations, hence a single clause applied.
Lakshmi Narain v. Raghbir Singh, AIR 1956 Punj 249 Arbitrator’s power to grant specific performance. Relied upon to affirm arbitral competence to decree specific performance.
Fertiliser Corporation of India v. Chemical Construction Corporation, ILR (1974) Bom 856 (DB) Same principle as above – arbitrator may order specific performance. Supported acceptance of specific performance as an arbitral remedy.
Keventer Agro Ltd. v. Seagram Co. Ltd., Calcutta HC, 27-1-1998 Discretionary remedies like specific performance can be conferred by agreement on an arbitral forum. Quoted with approval; court adopted its reasoning.
PNB Finance Ltd. v. Shital Prasad Jain, AIR 1991 Delhi 13 Contrary view that arbitrator cannot decree specific performance. Expressly overruled as incorrect.
Keir v. Leeman (1846) 9 QB 371 Test of arbitrability: whether the dispute is justiciable and compromiseable. Cited illustratively in discussion on arbitrable subject-matter.
Soilleux v. Herbst (1801) 2 Bos & P 444; Wilson v. Wilson (1848) 1 HL Cas 538; Cahill v. Cahill (1883) 8 App Cas 420 (HL) Examples of disputes properly referable to arbitration even where discretion is involved. Used to support arbitrability of discretionary remedies.

Court's Reasoning and Analysis

Jurisdiction over Interior Design Agreements: The Court analysed Clause 39 of the main agreements, noting its expansive wording encompassing disputes “connected with, arising out of or in relation to” the subject-matter. Schedules to both sets of agreements overlapped (e.g., flooring, fixtures, amenities), showing integral connection. Harmony between Clause 39 and Clause 5 was achieved by construing Clause 5 as operative only when disputes were confined solely to the Interior Design Agreements; where disputes under both contracts co-existed, Clause 39 governed a single reference. The Court further emphasised the appellant’s failure to invoke Section 16 objections during arbitration, though it assumed arguendo that such objections were still open under Section 34.

Section 16 and Timing of Objections: The statutory scheme mandates raising jurisdictional pleas “not later than” the statement of defence (s. 16(2)) or “as soon as” the excess of authority is perceived (s. 16(3)). Although undecided whether non-compliance is fatal, the Court found it unnecessary to rule because the arbitrator indeed possessed jurisdiction.

Arbitrability of Specific Performance: Reviewing Indian case law and the absence of any statutory bar akin to the English Acts, the Court held that specific performance concerns contractual rights and is therefore arbitrable. It approved the Punjab, Bombay and Calcutta views and expressly overruled the Delhi precedent.

Scope of Judicial Review under Section 34: Section 34(2)(b) permits interference only where (i) the subject-matter is non-arbitrable or (ii) the award violates public policy. Factual determinations regarding default, readiness and willingness, or contractual interest did not fall within these limited grounds. No allegation of fraud, corruption or violation of Sections 75/81 existed. Consequently, the arbitral findings were immune from judicial re-appraisal.

Holding and Implications

Holding: Appeals Dismissed; the arbitral awards granting specific performance of both the main and Interior Design Agreements stand confirmed.

Implications: The decision affirms (1) the broad reach of composite arbitration clauses to cover connected agreements, (2) the obligation to raise jurisdictional objections promptly before the tribunal, and (3) the arbitrability of specific performance of contracts concerning immovable property. While resolving the dispute between the parties, the Court set a clarifying precedent on these three issues within Indian arbitration jurisprudence.

    Olympus Superstructures Pvt.Ltd. v. Meena Vijay Khetan and others

    Judgement M. JAGANNADHA RAO, J.:- Leave granted.

    2. These three Civil Appeals are directed against the Judgment of the Bombay High Court in A. Nos. 175-177 of 1988 dated 2-4-98 in Arbitration Petitions 281-283 of 1997. By virtue of this judgment dated 2-4-98, the decision of the learned single Judge in Arbitration Petitions 281-283 of 1997 dated 12-1-1998 was confirmed. The learned single Judge had, by his decision dismissed the objections filed by the appellant under Sections 5 and 34 of the Arbitration and Conciliation Act, 1996 (hereinafter called the 'Act') to the awards and confirmed the three Awards passed by the Arbitrator on 13-11-1997. The learned Chief Justice of the Bombay High Court had appointed a retired Judge of that Court on 13-6-1997 as sole arbitrator and the said arbitrator had passed the three awards on 13-11-1997.

    3. The facts are as follows: There were three main agreements dated 9-3-94, 9-3-94 and 29-6-1994 under which the appellant agreed to sell Flat Nos. 101-102, 201-202 and 301-302 on first, second and third floors of the proposed building Wembley at, Play ground Road, Vile Parle (East) Bombay to the respondents on the terms contained in the agreements. The consideration was Rs. 76, 72 and 74 lakhs respectively. The possession of the flats was to be handed over along with amenities by 30-10-94. The terms of the contract provided the time-schedule for payments by the purchasers and said time was to be the essence of the contract and it was stated that failure to pay would entail termination of the agreement. The purchasers were to pay 21% interest in case of default. There were various other terms. Clause 7 provided that the power of termination should not be exercised by the appellant unless and until the appellant had given to the purchasers 15 days prior notice in writing of the intention to terminate the agreement and given the purchasers opportunity to set right the breaches, if any committed, within the said period. Clause 39 in each agreement contained an arbitration clause which read as follows: "39. All disputes of differences whatsoever which shall at any time hereafter (whether during the continuance and in force of this Agreement or upon or after it discharges or determination) arise between the parties hereto or their respective successors in title and assigns touching or concerning this Agreement or its interpretation or effect or as to the rights, duties and liabilities of the parties and liabilities of the parties hereto or either of them under or by virtue of this Agreement or otherwise as to any other matter in any way connected with arising out of or in relation to the subject matter of this agreement shall in accordance with the subject to the provisions of the Arbitration Act, 1940 or any statutory modification or re-enactment thereof for the time being in force the referred to a single arbitrator if agreed upon by the parties or otherwise to the arbitration of two arbitrators to be appointed by each party to the dispute whose decision in the matters shall be final and binding on the parties hereto." It will have to be noticed that the above clause did not refer to any specific named arbitrator or arbitrators.

    4. Considerable amounts were paid under the above said three main agreements to the appellant. The appellant would contend there was default on part of the respondents while the respondents would contend that there was no progress in the construction.

    5. There were three other separate agreements dated 9-3-94, 9-3-94 and 19-6-94 (hereinafter called the Interior Design Agreements) between the appellant and the same identical purchasers in which the appellant was appointed as 'Interior Designer' for carrying out renovation and interior designing and decorating the respective flats and the exterior area and to provide/install the special amenities in the flats for a lump sum payment of Rs. 10 lakhs each. No amount was, however, paid to the appellant under these three agreements before or at the time of executing of these three agreements. There is again a separate arbitration clause in each of these three agreement. It reads as follows: "5. All disputes and differences which may arise between the parties hereto in connection with this agreement of interpretation and effect thereof or in connection with the rights and obligations of the parties hereto shall be referred to the Joint Arbitration of Shri P. N. Nanavati (Solicitor) and Mr. Rashmi Mehta (Solicitor). If the aforesaid Arbitrators then and in such event such disputes and differences shall be referred to arbitration of two arbitrators, one to be appointed by each of the parties hereto. The Arbitrators so appointed shall appoint an umpire before entering upon the reference. The Arbitrators or the umpire as the case may be shall be governed by the provisions of the Indian Arbitration Act, 1940 or any statutory modification or re-enactment thereof from time to time in force." It will be noticed that this clause required reference to specific named arbitrators.

    6. On 24-4-1995, the respondent wrote to the appellant seeking information as to the stage of the construction and as to when the appellant would be handing over possession of the flats. The appellant replied on 6-6-1995 complaining default on the part of the purchasers as some cheques were dishonoured and stated that he was terminating the three agreements giving 15 days notice. On 22-6-1995 the respondents wrote to the appellant that considerable amounts were paid under each of the main agreements and that the appellant had not cared to inform the respondents about the progress of the construction, that the story of default was false, that the dishonoured cheques had been substituted by Banker's cheques or cash and that the termination was invalid. The respondents were ready and willing to complete the contract. On 21-10-1995 the respondents wrote to the appellant giving details of payments and the mode of payment of the balance under the main and the Interior Design Agreements and stating that 10 lakhs were paid under each of the three Interior Design Agreement, by way of cash to the appellant's solicitor, that only 6 lakhs remained to be paid after the 6th slab was laid and that the termination of the main agreement was bad in law etc. The appellant was called upon to withdraw the contention regarding termination and was asked as to when the 6th of the slabs would be laid so that the payment of Rs. 6 lakhs could be made. The appellant did not send any reply. The respondent then gave a notice on 19-3-1996 making various allegations against the appellant. A reply was sent by the appellant on 27-7-1996 limited to the allegations in the said letter dated 19-3-1996. A final notice was given by the respondents on 8-7-1996 stating that as there were several disputes and differences between the parties in relation to the agreements dated 9-3-1994, 9-3-1994 and 29-6-1994, they should be referred to one out of the three retired Judges whose names were suggested by the respondents. As the appellant failed to reply agreeing for arbitration, one of the respondents moved the Court on 9-8-1996 seeking interim protection before the filing of a regular petition under the Arbitration and Conciliation Act, 1996. Thereafter a regular petition for appointment of arbitrator was moved under S. 11 of the Act on 3-6-1997 and an order dated 13-6-1997 was passed by the learned Chief Justice appointing a sole arbitrator on 7-7-1997. The learned arbitrator fixed a preliminary meeting on 14-7-1997. On that day the arbitrator issued certain directions. On 29-7-1997, the respondents filed their claim before the arbitrator. The appellant took several adjournments on 19-8-1997, 23-9-1997 and 3-10-1997 and raised an objection on 9-10-1997 regarding the continuance of the arbitrator which objection was dismissed on 16-10-1997. On 16-10-1997 the appellant's new counsel sought time to challenge the order of the arbitrator dated 9-10-1997. Adjournment was refused. The arbitrator took up the matter for evidence. On 16-10-1997, the respondents (i.e. claimants before arbitrator) examined their witnesses in chief and the appellant's counsel partly cross-examined them and sought time and the matter was adjourned for 21-10-1997. There were some winding up proceedings against the appellant and a provisional liquidator was appointed on 30-4-1997. On an application by the respondents, the arbitrator, after hearing the counsel for the parties, passed an order on 22-10-1997 that no leave of the company Court was required at the stage of appointment of a provisional liquidator. The appellant's advocate sought further time and the same was refused. The appellant's advocate then filed three IAs for condoning delay in filing the written statement dated 22-10-1997 in all three matters. Delay was condoned. Further adjournment sought by appellant was refused. On 27-10-1997 evidence was recorded but there was no cross-examination by the appellants' counsel and the evidence was closed. On 13-11-1997, the award was passed granting relief of specific performance in respect of the three main agreements and also in respect of the three Interior Design Agreements.

    7. The appellant challenged the three awards under S. 34 by filing three applications in December, 1997 and these were dismissed by a learned single Judge on 12-1-1998 and by the Division Bench on 2-4-1998. It is against these judgments that the present appeals have been filed.

    8. Learned counsel for the appellant Sri H. L. Tiku raised various contentions. He contended that the reference to arbitration was based upon the three main agreements dated 9-3-1994, 9-3-1994 and 29-6-1994 and therefore the arbitrator could not have decided the disputes regarding the three other Interior Design agreements dated 9-3-1994, 9-3-1994 and 29-6-1994 and there was neither a prayer nor a reference of the disputes under the three latter Interior Design agreements. It was pointed out that the arbitration clauses in the main agreements could not supersede the separate arbitration clauses under the Interior Design Agreements which provided for named arbitrators. Merely, because the appellant remained ex parte before the arbitrator after a stage, the arbitrator could not assume the correctness of the pleas of the respondents and he ought to have insisted on proof of the pleas raised by the respondents. A point was raised in the grounds in this Court that an arbitrator could not grant specific performance of an agreement and hence S. 34(2)(b)(i) of the Act was attracted. It was also contended that in respect of the main agreements, the respondents had committed default, that respondents were not ready and willing, that the termination of the main agreement by the appellant was valid and that, on facts, an award for specific performance could not have been granted. In any event, as provided in the agreements, the respondents should have been directed to pay interest on the balance at consideration 21%.

    9. On the other hand, the learned senior counsel for the respondents-Sri D. R. Dhanuka and Sri K. K. Venugopal pointed out that under the arbitration clause contained in the main agreements, it was permissible to refer to arbitrator not only disputes and differences under the main agreements but also in respect of "connected" matters, that the appellant never raised any point relating to jurisdiction under S. 16 of the Act, that the arbitrator could not decide the dispute concerning the Interior Design Agreements and that the point was not also raised before the learned single Judge. For the first time the point was raised before the Division Bench. The same could not be permitted to be raised after the award. An arbitrator could grant specific performance of an agreement of sale. So far as the other points raised on the merits of the award were concerned, the same could not have been raised in view of the narrow scope of objections permitted by sub-clause (2)(b) of S. 34 of the new Act. It was contended that the challenge to the award was rightly rejected by the High Court. It was prayed that the appeals be dismissed.

    10. On these contentions, the following points arise for consideration: (1) Whether the appellant is right in contending that the arbitration Cl. 39 in the main agreement did not permit the arbitrator to deal with the disputes relating to the Interior Design Agreement which contained a different arbitration clause and whether the award, in respect of the Interior Design Agreement was void? (2) Whether the appellants who did not raise any question of jurisdiction under S. 16 of the Act in relation to the disputes under the Interior Design Agreements, could have raised a question of jurisdiction of the arbitrator or of his power to deal with issues arising under the said agreements at the stage of S. 34? (3) Whether an arbitrator is not entitled to pass an award directing specific performance of an agreement of sale and the subject-matter of the dispute is not capable of arbitration under S. 34(2)(b)(i) of the Act? (4) Whether the appellant could question factual findings relating to default, time being essence, readiness and willingness etc. before the arbitrator under S. 34 of the Act? Points 1 and 2:

    11. From the facts mentioned, it would be noticed that there were two sets of agreements, namely the main set of three agreements dated 9-3-1994, 9-3-1994 and 29-6-1994 and the three other agreements of the same dates dealing with Interior Designing. Each of main agreements contained an arbitration clause (Clause 39) of a general nature which did not specify any particular arbitrator's name while the Interior Design Agreements in each case contained a separate arbitration clause (Clause 5) mentioning the name of specified arbitrators. It was the case of the appellant that the notice given on 8-7-1996, the petition under S. 11 of the Act for appointment of an arbitrator and the reference covered only disputes and differences arising under the main agreements and there was no reference in respect of the disputes and differences arising out of Interior Design Agreements. It is contended for the appellant that the order appointing the arbitrator dated 13-6-1997 specifically dealt with disputes and differences under the main agreements only and not those under the Interior Design Agreements.

    12. Before we go into the interpretation of the arbitration clauses, we have to refer to the conduct of the appellant which is very much relevant for purposes of S. 16 of the Act. The respondents had referred in their claim statement before the arbitrator dated 29-7-1997 to the disputes and differences arising under the main agreements as well as under the Interior Designer Agreements. The appellant filed its written statement dated 22-10-1997 but no objection was raised that the disputes and differences contained in the three Interior Design Agreements were not intended to be referred to the arbitrator or that the same could not be decided by the arbitrator appointed under the main agreement. The appellants' counsel had cross-examined the respondents' witnesses up to a stage and even then no such objection as to scope of reference was raised. The arbitrator referred in his award to the sole contention of the appellant before him so far as the Interior Design Agreements were concerned and that was that the said agreements were void inasmuch as no amount was paid at the time of the agreements (though Rs. 10 lakhs each was agreed to be paid). That was the only contention concerning these three Interior Design Agreements. No dispute as to the power of the arbitrator to deal with disputes under these three agreements was raised. That means that the appellant accepted that disputes under these agreements were also covered by the reference. In the objections to the award filed in the Court under S. 34 no such point was raised except a general ground (j) that the entire proceedings of arbitration were illegal and bad in law, null and void and that the award was liable to be set aside. In the order of the learned single Judge in para 5 it was stated that only 3 points were raised and we find that this was not one of those points argued before the learned single Judge. For the first time this point relating to the scope of the reference was raised/argued before the Division Bench and the same was rejected.

    13. In our view, learned senior counsel for the respondents are right in contending that if parties before the arbitrator had any objections to the arbitrator's jurisdiction, the same must be raised before the arbitrator as provided in sub-clauses (2) and (3) of S. 16. (We are, however, not deciding the consequences of not raising the said question at that stage). Section 16 of the Act reads as follows: "16. Competence of arbitral Tribunal to rule on its jurisdiction- (1) The arbitral Tribunal may rule on its own jurisdiction, including ruling on any objections with respect to the existence or validity of the arbitration agreement, and for the purpose,- (a) an arbitration clause which forms part of a contract shall be treated as an agreement independent of the other terms of the contract; and (b) a decision by the arbitral that the contract is null and void shall not entail ipso jure the invalidity of the arbitration clause. (2) A plea that the arbitral Tribunal does not have jurisdiction shall be raised not later than the submission of the statement of defence; however, a party shall not be precluded from raising such a plea merely because that he has appointed, or participated in the appointment of, an arbitrator. (3) A plea that the arbitral Tribunal is exceeding the scope of its authority shall be raised as soon as the matter alleged to be beyond the scope of its authority is raised during the arbitral proceedings. (4) The arbitral Tribunal may, in either of the cases referred to in sub-section (2) or sub-section (3), admit a later plea, if it considers the delay justified. (5) The arbitral Tribunal shall decide on a plea referred to in sub-section (2) or sub-section (3) and, where the arbitral Tribunal takes a decision rejecting the plea, continue with the arbitral proceedings and make an arbitral award. (6) A party aggrieved by such an arbitral award may make an application for setting aside such an arbitral award in accordance with S. 34." Section 16 is based on Art. 16 of the UNCITRAL Model Law. Sub-clause (1) of S. 16 corresponds to sub-clause (1) of Art. 16. Sub-clauses (2) and (3) of S. 16 of the Act correspond substantially to sub-clause (2) of Art. 16. The words 'not later than' and 'as soon as may be' in sub-clause (2) of Art. 16 of the Model Law occur in sub-clauses (2) and (3) of S. 16 of the Act.

    14. It will be noticed that under the Act of 1996 the arbitral Tribunal is now invested with power under sub-clause (1) of S. 16 to rule on its own jurisdiction including ruling on any objection with respect to the existence or validity of the arbitration agreement and for that purpose, the arbitration clause which forms part of the contract shall be treated as an agreement independent of other terms of the contract and any decision by the arbitral Tribunal that the contract is null and void shall not entail ipso jure affect the validity of the arbitration clause. This is clear from sub-clause (b) of S. 16(1) which states that a decision by the arbitral Tribunal that the main contract is null and void shall not entail ipso jure the invalidity of the arbitration clause.

    15. In the present context sub-clauses (2) and (3) of S. 16 are relevant. They refer to two types of pleas and the stages at which they can be raised. Under sub-clause (2) a plea that the arbitral Tribunal does not have jurisdiction shall be raised not later than submissions of the statement of defence; however, a party shall not be precluded from raising such a plea merely because he has appointed or participated in the appointment of, an arbitrator. Under sub-clause (3) a plea that the arbitral Tribunal is exceeding the scope of its authority shall be raised as soon as the matter alleged to be beyond the scope of its authority, is raised during the arbitral proceedings. These limitations in sub-clauses (2) and (3) are subject to the power given to the arbitrator under sub-clause (4) of S. 16 that the Tribunal may, in either of the cases referred to in sub-section (2) or sub-section (3) admit a later plea if it considered the delay justified. Sub-section (5) requires the arbitral Tribunal to decide on the pleas referred to sub-section (2) or sub-section (3) at that stage itself. It is further provided that if either of the pleas is rejected and the arbitral Tribunal holds in favour of its own jurisdiction, the Tribunal will continue with the arbitral proceedings and proceed to make the arbitral award. Then comes sub-clause (6) which states that the party aggrieved by such an arbitral award may make an application for setting aside such an arbitral award in accordance with S. 34.

    16. Section 34 of the Act deals with the filing of an application for setting aside the award and reads as follows. Sub-clauses (1) and (2) are relevant for our purpose and they read as follows: "34. Application for setting aside arbitral award- (1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-section (3). (2) An arbitral award may be set aside by the Court only if- (a) the party making the application furnishes proof that-

    (i) a party was under some incapacity, or

    (ii) the arbitration agreement is not valid under the law to which the parties have subjected it or failing any indication thereon, under the law for the time being in force; or

    (iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

    (iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or

    (v) the composition of the arbitral Tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this part; or (b) the Court finds that-

    (i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force; or

    (ii) the arbitral award is in conflict with the public policy of India. Explanation.- Without prejudice to the generality of sub-clause (ii) of Cl. (b), it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the public policy of India if the making of the award was induced or affected by fraud or corruption or was in violation of S. 75 or S. 81."

    17. Section 34 of the Act is based on Art. 34 of the UNCITRAL Model Law and it will be noticed that under the 1996 Act the scope of the provisions for setting aside the award is far less the same under S. 30 or S. 33 of the Arbitration Act of 1940.

    18. It will be noticed that under sub-clause 2(a)(iv) of S. 34, the arbitral award may be set aside by the Court if the award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitrator or if it contains a decision on matters beyond the scope of the submission to arbitration. The proviso to Cl. (iv) deals with severability.

    19. The word 'terms of the submission to arbitration' in S. 34(2)(a)(iv) in our view, refer to the terms of the arbitration clause. This appears to be the meaning of the word if one refer to S. 28 which uses the word 'dispute submitted to arbitration' and to S. 43(3) which uses the word 'submit' future dispute to arbitration.

    20. A question arises whether in view of the provisions of S. 16(2) which uses the word 'not later than,' any such objection as contained in S. 16(2) not raised before the arbitrator can be permitted to be raised for the first time under S. 34. Similarly a question arises whether in view of the proviso of S. 16(3) which uses the word 'as soon as' any objection as contained in S. 16(3), cannot be raised for the first time under S. 34.

    21. It may be argued on one side that the time limits set in arbitration. Cls. (2) and (3) of S. 16 are mandatory and do not permit the said question to be raised at a later point of time even under S. 34. An opposite view could be that these being jurisdictional issues, the fact that they were not raised earlier could not preclude the question being raised under S. 34 inasmuch as consent, express or implied could not confer jurisdiction.

    22. We do not think it necessary to decide this question in view of the fact that though S. 16 was referred to during the course of the hearing, the learned senior counsel for respondents had argued on merits that the arbitrator had jurisdiction to decide the disputes/differences concerning the Interior Design agreements also and that even if the appellant could be permitted to raise these issues at the stage of S. 34, there was no substance in the said contentions.

    23. We shall, therefore, proceed to decide the question of jurisdiction on the assumption that the appellant is not precluded from raising these questions at the stage of S. 34 though these issues have not been raised before the arbitration as per sub-clauses (2) and (3) of S. 16.

    24. Before we do so, we shall advert to a recent decision of this Court in Rajinder Krishan Khanna v. Union of India, (1998) 7 SCC 129 wherein this Court referred to S. 16 and S. 34(2)(a)(iv) of the Act. In that case a reference was made to arbitrators when the appeal was being heard by this Court. The appellant was the claimant. The opposite party raised a specific plea before the arbitrators that they had no jurisdiction to decide about the value of the potentiality of the land and that the claim petition before the arbitrator could not have included the above claim, which was outside the reference and outside the writ petition and the civil appeal from which the reference arose by consent. It was argued for the appellant in reply that the respondents did not have a specific issue framed by the arbitrators in regard to the scope of the reference and the respondents were estopped from contending that the arbitrators could not have dealt with the question. This Court held that this case was not a case where no objection was raised by the respondent before the arbitrators as to the scope of the reference. A specific objection was raised in the written statement of the respondents that the potentiality of the land was not one of the questions referred to the arbitrators. This Court held that the fact that an issue was not framed by the arbitrators that the item was not covered by the reference did not raise any estoppel. The said question as to the scope of the reference could therefore be permitted to be raised under S. 34(2)(a)(iv) in the objections to the award. It is true that on the facts of the case before us, the objection as to the scope of the reference was not raised in the written statement of the appellant. But as already stated, we are not deciding the question whether the appellant is precluded at the stage of S. 34 from raising the question relating to the scope of the reference. We shall assume, for the purpose of this case, that the said contention can still be raised under S. 34(2)(a)(iv). We shall accordingly deal with the merits of the question of jurisdiction of the arbitrator.

    25. It is true that there are two agreements in each of the three appeals before us. One is the main agreement relating to construction of flats and the arbitration Cl. 39 there is general and does not refer to any named arbitrator. It is also true that there is a separate arbitration Cl. 5 in the Interior Design Agreement which gives the names of specific arbitrators. But it must be noticed that Cl. 39 permits reference to arbitration not only of issues arising under the main agreement but also those disputes or differences which are "connected" with disputes arising under the main agreement. The following words in the main agreement are important. "Otherwise as to any other method in any way connected with, arising out of or in relation to the subject-matter of this agreement." In other words, Cl. 39 refers to the 'subject-matter' of the main agreement and also to 'any other matters' and these 'any other matters' if they are "connected" with or arise out of or are in relation to the subject-matter of the main agreement, the disputes and differences concerning those 'other matters' can also be referred to arbitration under Cl. 39 of the main agreement. In other words, parties intended arbitration in respect of the main disputes and connected disputes before one arbitral Tribunal.

    26. As to the meaning of the words "connected with, arising out of or in relation thereto," we may refer to Renusager Power Co. Ltd. v. General Electric Co. (1984) 4 SCC 679 It was held that these words "are of the widest amplitude and content and include even questions as to the existence and effect (scope) of the arbitration agreement.

    27. Question is whether the disputes and differences arising under the Interior Design Agreement are integrally "connected with" the disputes and differences arising from the main contract? In our view, they are. The main agreement refers to the payment of the last instalment of Rs. 17 lakhs against 'taking of possession' of the flats. Therefore the main agreements extended up to the time of taking of possession by the purchasers. Para 8 of the main agreement states that the fixtures, fittings and amenities to be provided by the Developers in the said building and the flat/unit are those that are set out in Annexure E annexed to the main agreement. Now Annexure E refers not only to the building but to the type of doors, corridors, fixtures, the nature of the flooring, the bathroom tiles and fittings, the Kitchen, the W.C. and the nature of the Electric Wiring. When we come to the Interior Design Agreement, Annexure A itself refers to the element of designs, Interior finishes/fittings/services and deals with the Walls, Balcony, type of Main Door and Internal Doors, External Doors. It also deals with the type of staircase, the flooring (Italian marbles for Hall room, Bed rooms and passages), Toilet (Italian Marbles, Designed Basin, Ceiling Valve plastering, Bath tub/Ja cuzzi all hardware fitting inclusively Germany range), Marble skirting, Lobby and Entrance (Italian Marble Flooring), Plumbering, Gas system, Electrical (Heavy Duty ISI quality concealed copper wiring) etc.

    28. Thus it will be noticed that there are several items in Schedule E of the main agreement which overlap the items in Schedule A of the Interior Design Agreement. In view of the overlapping, in our opinion it has to be said that several items in the Schedule A of the Interior Design Agreement are in modification/substitution of the items in the main agreement. Therefore the coverage of the two agreements makes it clear that the execution of the Interior Design Agreement is 'connected with' the execution of the main agreement. It may also be noted that the date of the main agreement and the Interior Design Agreement is the same in each of the three cases and Cl. 3 of the Interior Design Agreement states specifically that 'the work of the said renovation, designing and installation shall commence from the execution thereof' which means that the execution of the Interior Design Agreement and the main agreement is to be simultaneous.

    29. But then, we have to explain the purpose of the arbitration agreement contained in Cl. 5 of the Interior Design Agreement? Is it wholly superfluous?

    30. If there is a situation where there are disputes and differences in connection with the main agreement, and also disputes in regard to "other matters" "connected" with subject-matter of the main agreement then in such a situation, in our view, we are governed by the general arbitration Cl. 39 of the main agreement under which disputes under the main agreement and disputes connected therewith can be referred to the same arbitral Tribunal. This Cl. 39 no doubt does not refer to any named arbitrators. So far as Cl. 5 of the Interior Decorator Agreement is concerned, it refers to disputes and differences arising from the agreement which can be referred to named arbitrators and said Cl. 5, in our opinion, comes into play only in a situation where there are no disputes and differences in relation to the main agreement and the disputes and differences are solely confined to the Interior Design Agreement. That, in our view, is the true intention of parties and that is the only way by which the general arbitration provision in Cl. 39 of the main agreement and the arbitration provision for named arbitrator contained in Cl. 5 of the Interior Design Agreement can be harmonised or reconciled. Therefore, in a case like the present where the disputes and differences cover the main agreement as well as the Interior Design Agreement,- (that there are disputes arising under the main agreement and the Interior Design Agreement is not in dispute) - it is the general arbitration Cl. 39 in the main agreement that governs because the questions arise also in regard to disputes relating to the overlapping items in the schedule to the main agreement and the Interior Design Agreement, as detailed earlier. There cannot be conflicting awards in regard to items which, overlap in the two agreements. Such a situation was never contemplated by the parties. The intention of the parties when they incorporated Cl. 39 in the main agreement and Cl. 5 in the Interior Design Agreement was that the former clause was to apply to situations when there were disputes arising under both agreements and the latter was to apply to a situation where there were no disputes or differences arising under the main contract but the disputes and differences were confined only to the Interior Design Agreement. A case containing two agreements with arbitration clauses arose before this Court in Agarwal Engineering Co. v. T. H. Machine Industries, AIR 1977 SC 2122. There were arbitration clauses in two contracts one for sale of two machines to the appellant and the other appointing the appellant as sales representative. On the facts of the case, it was held that both the clauses operated separately and this conclusion was based on the specific clause in the sale contract that it was the "sole repository" of the sale transaction of the two machines. Krishna Iyer, J. held that if that were so, then there was no jurisdiction for travelling beyond the sale contract. The language of the other agreement appointing the appellant as sales representatives was prospective and related to a sales agency and 'later purchases,' other than the purchases of these two machines. There was therefore no overlapping. The case before us and the above case exemplify contrary situations. In one case the disputes are connected and in the other they are distinct and not connected. Thus, in the present case, Cl. 39 of the main agreement applies. Points 1 and 2 are decided accordingly in favour of the respondents. Point 3:

    31. This point becomes relevant because if the arbitrators cannot grant specific performance, a point can be raised under S. 34(2)(b)(i) that the subject-matter of the dispute is not capable of arbitration.

    32. One of the points raised in the grounds in this Court is that the grant of specific performance is discretionary and the discretion to grant or not to grant specific performance has been conferred by the Specific Relief Act, 1963 on the Civil Court and hence the arbitrator cannot be deemed to have been empowered to grant such a relief.

    33. We may point out that the Punjab High Court in Lakshmi Narain v. Raghbir Singh, AIR 1956 Punj 249 the Bombay High Court in Fertiliser Corporation of India v. Chemical Construction Corporation, ILR (1974) Bom 856/858 (DB) and the Calcutta High Court in Keventer Agro Ltd. v. Seegram Comp. Ltd. (Apo 498 of 1997 and Apo 449 of (401)) (dated 27-1-1998) have taken the view that an arbitrator can grant specific performance of a contract relating to immovable property under an award. No doubt, the Delhi High Court in M/s. PNB Finance Limited v. Shital Prasad Jain, AIR 1991 Delhi 13 has however held that the arbitrator cannot grant specific performance. The question arises as to which view is correct.

    34. In our opinion, the view taken by the Punjab, Bombay and Calcutta High Courts is the correct one and the view taken by the Delhi High Court is not correct. We are of the view that the right to specific performance of an agreement of sale deals with contractual rights and it is certainly open to the parties to agree - with a view to shorten litigation in regular Courts - to refer the issues relating to specific performance to arbitration. There is no prohibition in the Specific Relief Act, 1963 that issues relating to specific performance of contract relating to immovable property cannot be referred to arbitration. Nor is there such a prohibition contained in the Arbitration and Conciliation Act, 1996 as contrasted with S. 15 of the English Arbitration Act, 1950 or Section 48(5)(b) of the English Arbitration Act, 1996 which contained a prohibition relating to specific performance of contracts concerning immoveable property.

    35. It is stated in Halsburys' Laws of England 4th Ed., (Arbitration Vol. 2 para 503) as follows: "Nature of the dispute or difference: The dispute or difference which the parties to an arbitration agreement agree to refer must consist of a justiciable issue triable civilly. A fair test of this is whether the differences can be compromised lawfully by way of accord and satisfaction (Cf. Bacon's Abidgement and Award A)." Reference is made thereto certain disputes like criminal offences of a public nature, disputes arising out of illegal agreements and disputes relating to status, such as divorce, which cannot be referred to arbitration. It has, however, been held that if in respect of facts relating to a criminal matter, (say) physical injury, if there is a right to damages for personal injury, then such a dispute can be referred to arbitration (Keir v. Leeman) (1846) 9 QB 371. Similarly, it has been held that a husband and wife may, refer to arbitration the terms on which they shall separate, because they can make a valid agreement between themselves on that matter (Soilleux v. Herbst) (1801) 2 Bos and p. 444; Wilson v. Wilson (1848) 1 HL Cas 538; (Cahill v. Cahill) (1883) 8 App Cas 420 (HL).

    36. Further, as pointed in the Calcutta case, merely because there is need for exercise of discretion in case of specific performance, it cannot be said that only the Civil Court can exercise such a discretion. In the above case, Ms. Ruma Pal, J. observed: "merely because the sections of the Specific Relief Act confer discretion on Courts to grant specific performance of a contract does not mean that parties cannot agree that the discretion will be exercised by forum of their choice. If the converse were true, then whenever a relief is dependent upon the exercise of discretion of a Court by statute e.g. the grant of interest or costs, parties should be precluded from referring the dispute to arbitration." We agree with this reasoning. We hold on Point 3 that disputes relating to specific performance of a contract can be referred to arbitration and S. 34(2)(b)(i) is not attracted. We overrule the view of the Delhi High Court. Point 3 is decided in favour of respondents. Point 4:

    37. This point concerns the issues between the parties on the merits of the award relating to default, time being exercise, readiness and willingness etc. These are all issues of fact. If we examine S. 34(2) of the Act, the relevant provisions of which have already been extracted under Points 1 and 2, it will be seen that under sub-clause (b) of S. 34(2), interference is permissible by the Court only if

    (i) the subject-matter of the dispute is non-capable of settlement by arbitration under the law for the time being in force, or

    (ii) the arbitral amount is in conflict with the public policy in India. The Explanation to the provisions says that without prejudice to the generality of sub-clause (ii) of Cl. (b), it is declared for the avoidance of any doubt, that an award is to be created as in conflict with the public policy of India if the making of the award was induced or affected by fraud, or corruption or was in violation of S. 75 or 81. Section 75 deals with confidentiality while S. 81 deals with admissibility of evidence in other proceedings. We do not have any such situation before us falling within S. 34(2)(b)(ii). The factual points raised in the case before us, to which we have referred to earlier, do not fall within S. 34(2)(b)(ii). Coming to S. 34(2)(b)(i) we have already held that the subject-matter of the dispute is not incapable of settlement by arbitration under the law for the time being in force. Nor is any point raised that the arbitral award is in conflict with the public policy of India. We are, therefore, of the view that the merits of the award, on the facts of the case do not fall under S. 34(2)(b) of the Act. Point 4 is held accordingly against the appellant.

    38. For the aforesaid reasons, the appeals fail and are dismissed but in the circumstances without costs. Appeals dismissed.

    Use AI to get other relevant cases.

    Comments

    Olympus Superstructures Pvt.Ltd. v. Meena Vijay Khetan and others
    (Nov 5, 1999)