Loading..
Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Smart Summary

High Court of Himachal Pradesh — RFA Nos. 98 to 109 of 2009 (Decision dated 06.01.2016)

Factual and Procedural Background

These connected regular first appeals arise from reference petitions filed by landowners whose land was acquired for the Kol Dam Hydel Project. A notification under Section 4 of the Land Acquisition Act, 1894 was issued on 7.12.2000 (published in the Rajpatra on 12.12.2000 and in newspapers on 14–15.12.2000). Public notice followed on 8.1.2001, and notifications under Sections 6 & 7 were issued on 23.4.2001 (published 12.5.2001). Notices under Section 9 were issued on 12.7.2001. The Land Acquisition Collector awarded a flat rate of Rs. 3,25,528.37 per bigha by an award dated 12.10.2001.

Aggrieved by the Collector's award as inadequate, the claimants filed reference petitions before the Fast Track Court, Mandi. The Reference Court framed issues on 18.6.2004 and, by judgment dated 17.1.2009, enhanced compensation to Rs. 5,00,000 per bigha with statutory benefits. NTPC (the appellant in the RFAs) challenged that judgment, resulting in these consolidated appeals before the High Court.

Legal Issues Presented

  1. Whether the Reference Court correctly assessed and enhanced the compensation awarded by the Collector for land acquired under the Land Acquisition Act, 1894.
  2. Whether the Reference Court properly relied upon the sale deeds and Award No. 2 of 2002 (pertaining to adjoining Mohal Kyan) and other evidence to determine the market value of the acquired land.
  3. Whether the Collector's flat-rate award (Rs. 3,25,528.37 per bigha) was adequate in light of evidence about market values, proximity to industrial installations, and subsequent transactions involving the land or adjacent lands.

Arguments of the Parties

Appellant's (NTPC) Arguments

  • The market value determined by the Collector was correct, adequate and just.
  • The Reference Court erred in relying upon certain sale deeds (Ext. P-1 to Ext. P-9, Ext. PA, Ext. P-10 to Ext. P-14 and Ext. PW-5/A, as identified in the record) while determining market value.
  • Specific sale deeds placed by RW-1 (Ext. RA to Ext. RD) were relied upon by the appellant to support the Collector's valuation; RW-1, however, admitted lack of knowledge regarding the Collector's basis for assessing market value.

Respondents' (Claimants) Arguments

  • The compensation awarded by the Collector was inadequate; the claimants alleged substantially higher market values (one pleaded value being Rs. 25,00,000 per bigha).
  • Factors supporting higher valuation included that the land would be submerged by Kol Dam, the land in Mohal Ropa was irrigated and of better quality, proximity to ACC Cement Plant, and other local market indicators.
  • The Reference Court properly relied upon sale deeds (including private sale deeds and sale to HP PWD) and Award No. 2 of 2002 for adjoining Mohal Kyan to justify enhancement of compensation.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court's analysis proceeded by examining the documentary and oral evidence placed before the Reference Court and by addressing the competing contentions of the parties about market value assessment.

  1. The Court first set out the procedural timeline of acquisition notifications (Section 4 on 7.12.2000; publications and subsequent Section 6/7/9 steps) and the Collector's award dated 12.10.2001 fixing a flat rate of Rs. 3,25,528.37 per bigha.
  2. The Court reviewed the evidence led in the Reference Court: depositions of multiple PW witnesses (PW-1 to PW-7) describing the nature of the land (irrigated, agricultural uses, proximity to ACC Barmana and Dehar Power House), and evidence that land in Mohal Ropa had been sold to HP PWD by private negotiation (sale deeds Ext. P-1 and Ext. PW-5/A) for Rs. 4,62,000 per bigha in 2002.
  3. The Court observed that no sale transaction in Mohal Ropa took place at or about the date of publication of Section 4 notification, but later sales (2002) demonstrated a substantial increase in market value in Mohal Ropa. The Court regarded the sale deeds to HP PWD as being in close proximity to the acquired land and indicative of market movement.
  4. The Court noted Award No. 2 of 2002 (Ext. P-15) for adjoining Mohal Kyan, where compensation was awarded at Rs. 4,35,447.26 per bigha; Mohal Kyan adjoins Mohal Ropa and was factually found to be of lesser quality than Ropa (Ropa being irrigated and superior).
  5. The Court considered the appellant’s reliance on sale deeds Ext. RA–RD (placed by RW-1) but observed that RW-1 admitted he had no knowledge about the basis for the Collector's market valuation. The Court also noted the factual finding that Ropa’s land quality was superior and that the state had purchased Ropa land at a demonstrated price (Ext. P-1/Ext. PW-5/A).
  6. On evaluating the totality of evidence — witness testimony, private sale deeds to HP PWD, Award No. 2 of 2002 for adjoining Mohal Kyan, and comparative quality and proximity considerations (including industrial installations nearby) — the Court concluded that the Reference Court had properly taken relevant transactions and circumstances into account in enhancing compensation.
  7. Given these factual determinations and the assessment of the evidentiary record, the High Court found no reason to interfere with the Reference Court’s well-reasoned award dated 17.1.2009.

Holding and Implications

Holding: The appeals are dismissed. The High Court found no merit in the appeals challenging the Reference Court's judgment dated 17.1.2009 and declined to interfere with the enhancement of compensation to Rs. 5,00,000 per bigha (with statutory benefits) made by the Reference Court.

Direct consequences for the parties: The Reference Court award enhancing compensation (dated 17.1.2009) stands. Pending applications, if any, were ordered to be disposed of and the Court ordered that there would be no costs.

Broader implications: The opinion does not set out or discuss any new legal principle or broader precedent beyond its application of the factual evidence in this cluster of matters. The judgment affirms the Reference Court's factual evaluation of sale transactions, award(s) for adjoining mohal and other local circumstances in assessing market value for compensation purposes.


Judge: The Hon'ble Mr. Justice Rajiv Sharma. Date of decision: 06.01.2016. This summary is based exclusively on the text of the provided opinion and does not add or infer information beyond that text.

    NTPC v. SANT RAM

    H

    ig h Co ur t o f H

    .P

    .

    IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA.

    RFA No. 98 of 2009

    with

    RFA Nos. 99 to 109 of 2009.

    Reserved on: 04.01.2016.

    Decided on: 06.01.2016.

    1. RFA No. 98 of 2009 NTPC Ltd. ……Appellant. Versus

    Kirpa and others …….Respondents.

    2. RFA No. 99 of 2009 NTPC Ltd. ……Appellant. Versus

    Raghu & ors. ….Respondents.

    3. RFA No. 100 of 2009 NTPC Ltd. ……Appellant. Versus

    Sher Singh & ors. ….Respondents.

    4. RFA No. 101 of 2009 NTPC Ltd. ……Appellant. Versus

    Sarvan Kumar & ors. ….Respondents.

    5. RFA No. 102 of 2009 NTPC Ltd. ……Appellant. Versus

    Sita Ram & ors. ….Respondents.

    6. RFA No. 103 of 2009 NTPC Ltd. ……Appellant. Versus

    Kanshi Ram & ors. ….Respondents.

    7. RFA No. 104 of 2009 NTPC Ltd. ……Appellant. Versus

    Parwati & ors . ….Respondents.

    8. RFA No. 105 of 2009 NTPC Ltd. ……Appellant. Versus

    Prabha Devi & ors. ….Respondents.

    9. RFA No. 106 of 2009 NTPC Ltd. ……Appellant. Versus

    1

    2

    Parma Nand & ors. ….Respondents.

    10. RFA No. 107 of 2009 NTPC Ltd. ……Appellant. Versus

    Sunder Ram & ors. ….Respondents.

    11. RFA No. 108 of 2009 NTPC Ltd. ……Appellant. Versus

    Sant Ram & ors. ….Respondents.

    12. RFA No. 109 of 2009 NTPC Ltd. ……Appellant. Versus

    Prem Lal & ors. ….Respondents. Coram

    The Hon'ble Mr. Justice Rajiv Sharma, Judge. Whether approved for reporting? Yes.

    For the appellant(s): Mr. Neeraj Gupta, Advocate.

    For the respondents: Mr. N.K. Sood, Sr. Advocate with Mr. Aman Sood and Mr. Varun Rana, Advocates for respondents No. 1 to 3.

    ----------------------------------------------------------------------------------------------

    Justice Rajiv Sharma, J.

    Since common questions of law and facts are involved in these regular first appeals, the same were taken up together for hearing and are being disposed of by a common judgment.

    2. These regular first appeals are directed against the common judgment of the learned Presiding Officer, Fast Track Court, Mandi, Distt. Mandi, H.P., dated 17.1.2009 in Ref. Petition Nos. 78 of 2002, 74 of 2005, 82 of 2002, 76 of 2005, 79 of 2002, 75 of 2005, 83 of 2002, 77 of 2005, 81 of 2002, 132 of 2005, 80 of 2002, 133 of 2005, 89 of 2002, 134 of 2005, 88 of 2002, 135 of 2005, 87 of 2002, 137 of 2005, 84 of 2002, 136 of 2005, 85 of 2002, 138 of 2005, 86 of 2002, 139 of 2005.

    3

    3. "Key facts" necessary for the adjudication of these regular first appeals are that the notification under Section 4 of the Land Acquisition Act, 1894 (hereinafter referred to as the Act) was issued on 7.12.2000. It was published in the Rajpatra on 12.12.2000. It was also published in the Newspapers "Amar Ujala" and "The Tribune" on 14.12.2000 and 15.12.2000, respectively. Public notice was issued on 8.1.2001. Consequently, notification under Sections 6 & 7 of the Act were issued on 23.4.2001 and published in Rajpatra on 12.5.2001. It was also published in two newspapers i.e. "Divya Himachal" and "Indian Express" on 2.5.2001. Notices under Section 9 of the Act were issued to the interested holders on 12.7.2001. The Land Acquisition Collector awarded a flat rate of Rs. 3,25, 528.37/- per bigha to the respondents claimants on 12.10.2001.

    4. The claimants, feeling aggrieved by the award dated 12.10.2001, filed reference petitions before the learned Presiding Officer, Fast Track Court, Mandi, Distt. Mandi, H.P. According to them, they were given inadequate compensation by the learned Collector. The value of their land was Rs. 25,00,000/- per bigha. The land acquired from the claimants would be submerged in the water by Kol Dam. The land adjacent to Sundernagar Tatapani road is rich in minerals. The sale transactions of Mohal Dhawal, which land is not similar to the acquired land was wrongly considered to work out the market value of the land by the Collector. The sale transaction of Mohal Kyan which land is same vis-a-vis land of Mohal Ropa and higher in value were wrongly ignored by the Collector while assessing the market value of the land.

    4

    5. The appellants contended that the market value worked out by the Collector was correct, adequate and just. The Collector while working out the market value of the land of this Mohal has taken into consideration all aspects and surrounding circumstances.

    6. The issues were framed by the learned Reference Court on 18.6.2004. The learned Reference Court enhanced the compensation from Rs. 3,25,528.37/- per bigha to Rs. 5,00,000/- per bigha, with statutory benefits. Hence, these regular first appeals.

    7. Mr. Neeraj Gupta, Advocate, has vehemently argued that the Reference Court has wrongly relied upon sale deeds Ext. P-1 to Ext. P-9, Ext. PA, Ext. P-10 to Ext. P-14 and Ext. PW-5/A, while determining the market value of the acquired land. According to him, the transactions pertaining to contiguous Mohals Kyan and Dhawal were required to be taken into consideration by the learned Reference Court. He has supported the award made by the Collector. On the other hand, Mr. N.K.Sood, Sr. Advocate, has supported the award dated 17.1.2009.

    8. I have heard learned Advocates for the parties and gone through the award and records of the case(s) carefully.

    9. PW-1 Khazana Ram deposed that their land was acquired by the Kol Dam Project. It was situated in Mohal Ropa. The possession of the land was taken about 4-5 years back i.e. in December, 2000. The land was irrigated. There is BBMB Power House, Slapper and ACC Cement Plant at Barmana, in close vicinity of the acquired land. The price of the land was 10- 11 lacs per bigha. They have been awarded compensation of the land at the rate of Rs. 3.20 lacs per bigha. Kyan Mohal is adjacent to their Mohal, having

    5

    common boundary and having land of lesser quality than their land and for Mohal Kyan compensation has been awarded at the rate of Rs. 6 lac per bigha. In his cross-examination, he admitted that Kol Dam authorities started visiting their area about 10-11 years back. He denied the suggestion that in the year 2000, the land prices in their Mohal was not more than Rs. 15-20,000/- per bigha. The ACC Cement Plant, Barmana is at a distance of about 2 ½ - 3 kms from their Mohal.

    10. PW-2 Ganpat Ram deposed that they were having four gharats (water mill) in village Ropa belonging to Kirpa Ram, Raghu Ram, Sher Singh and Sarvan Kumar etc. They have not been paid any compensation for loss of income and only price of structures has been paid. Paddy, ginger and vegetables etc. are sown in the area. Their land is near to ACC Barmana, Dehar Power Plant. The price of land in their area is Rs. 10-12 lacs per bigha. In the adjoining Mohal, compensation was awarded at the rate of Rs. 5 lacs per bigha. They should be paid compensation on the value of land of Kyan.

    11. PW-3 Lekh Ram deposed that he has purchased land in village Kyan vide sale deed Ext. PA for sale consideration of Rs. 1,20,000/-. He had enquired about the land price at village Ropa and was told that the value of the land was Rs. 8 lacs per bigha and then he went to village Kyan and found the rate of Rs. 40,000/- per biswa. He, therefore, purchased 3 biswas of land for Rs. 1,20,000/-.

    12. PW-4 Sarvan deposed that in village Ropa, Government purchased land from him. 15 families sold land to the Government at the rate of Rs. 4,62,000/- per bigha for the construction of the road. The

    6

    agreement was executed in December, 2002 and the same was made in 2003. They were demanding price at the rate of Rs. 10,00,000/- per bigha but for want of budget, Government insisted at the rate of Rs. 4,62,000/-. The Government purchased 8-10 bighas of land.

    13. PW-5 Sant Ram deposed that he remained Pradhan w.e.f. 1985 to 22.1.2006. According to him, the acquired land falls in his Panchayat. In the year 1998-99, there was an agreement between HP PWD and the villagers for selling the land to HP PWD and they were demanding Rs. 10 lacs per bigha in Mohal Ropa. Their land in Mohal Ropa is irrigated one and they have been growing vegetables etc and finally in the year 1999, the land was agreed to be sold for Rs. 4,62,000/- per bigha. He proved sale deed vide Ext. PW-5/A.

    14. PW-6 Sarvan Kumar and PW-7 Sher Singh deposed that they were earning Rs. 4,000/- to 5,000/- per month from the Gharats (water mill). The acquired land price was Rs. 10 lacs per bigha.

    15. RW-1 Partap Singh deposed that he remained Tehsildar at Sundernagar w.e.f. March, 2000 to November, 2002. He proved Notifications Ext. RW-1/A to Ext. RW-1/O, Notices under Section 9 of the Act Ext. R-1 to R-3 and sale deeds Ext. RA to RD. In his cross-examination, he deposed that he has no knowledge on what basis the market value of the acquired land was assessed by the Collector.

    16. It is admitted case of the parties that no sale transaction has taken place in Mohal Ropa at or about the time of publication of Notification under Section 4 of the Act and the Collector had awarded flat rate of Rs. 3,25,828.37 paise per bigha. It has come on record that ACC Cement plant is

    7

    at a distance of 2 ½ -3 km. from the acquired land. Power House Dehar is also situated at a distance of 2.5-3 kms from the acquired land.

    17. It is duly proved that the villagers of Ropa have sold their land to HP PWD vide sale deeds Ext. P-1 and Ext. PW-5/A dated 25.10.2002 for consideration of Rs. 4,62,000/- per bigha by private negotiations. The sale deeds were executed by HP PWD in the year 2002. It establishes that in Mohal Ropa, the market value of land has substantially increased. In this case, the notification has been issued under Section 4 of the Act on 7.12.2000. The sale deeds Ext. P-1 and Ext. PW-5/A were in close proximity of acquired land of notification issued under Section 4 of the Act.

    18. Mr. N.K.Sood, Sr. Advocate, has drawn the attention of the Court to Award No. 2 of 2002 vide Ext. P-15. Award No. 2 of 2002 pertains to the acquisition of land in village Kyan for Kol Dam Hydel Project. The compensation was awarded at the rate of Rs. 4,35,447.26 paise per bigha. The notification under Section 4 of the Act, as noticed hereinabove, by acquiring the land of Village Ropa, was also published on 11.12.2000. Mohal Kyan is adjoining to Mohal Ropa. It has also come on record that village Ropa is having better quality of land, since it is irrigated vis-à-vis Mohal Kyan. The HP PWD has already purchased land at village Ropa for a consideration of Rs. 4,62,000/- per bigha. The land of Mohal Kyan was though sold in small plots, in the year 2000, but for approximate price of Rs. 40,000/- 50,000/- per biswa. The learned Reference Court has correctly taken into consideration the sale transactions made vide sale deeds Ext. P-1 and Ext. PW-5/A and award No. 2 of 2002 Ext. P-15, while determining the market value of the acquired land of the claimants.

    8

    19. Mr. Neeraj Gupta, Advocate, has placed strong reliance upon sale deeds Ext. RA to Ext. RD. These sale deeds were placed on record by RW-1 Partap Singh. RW-1 Partap Singh, in his cross-examination, has admitted that he has no knowledge on what basis the market value of the acquired land was assessed by the Collector. Sale deed Ext. RA pertains to Mohal Kyan, Ext. RB pertains to Mohal DPF Dhawal, Ext. RC pertains to village Kyan and Ext. RD pertains to Mohal Kyan. The Court has already noticed that the land of village Ropa was superior vis-à-vis Kyan. Village Ropa and Kyan share common boundary. The land at village Ropa itself has been purchased by the State Government for consideration of Rs. 4,62,000/- vide sale deed Ext. P-15, which also pertains to village Kyan. This land was also acquired for the construction of Kol Dam. The Reference Court has correctly assessed the market value of the land. There is no occasion for this Court to interfere with the well reasoned award of the Reference Court dated

    17.1.2009.

    20. Accordingly, there is no merit in these appeals and the same are dismissed. Pending application(s), if any, shall also stand disposed of. No costs.

    January 06, 2015, ( Rajiv Sharma ),

    (karan) Judge.