Reshma Constructions v. State of Goa: Interpretation of Section 85 of the Arbitration and Conciliation Act, 1996 on Pending Proceedings

Reshma Constructions v. State of Goa: Interpretation of Section 85 of the Arbitration and Conciliation Act, 1996 on Pending Proceedings

Introduction

The case of Reshma Constructions, Goa v. State Of Goa adjudicated by the Bombay High Court on March 12, 1998, addresses a pivotal question in Indian arbitration law: the applicability of the newer Arbitration and Conciliation Act, 1996 ("the new Act") to arbitral proceedings that were initiated under the Arbitration Act, 1940 ("the old Act") and were still pending when the new Act became effective.

Parties Involved:

  • Petitioner: Reshma Constructions, Goa
  • Respondent: State of Goa

Background: Reshma Constructions was contracted to construct the Canal Head Regulator of Chapoli Minor Irrigation Tank at Canacona. A dispute arose when the State of Goa allegedly failed to settle dues owed to Reshma Constructions, prompting the invocation of an arbitration clause stipulated in the contract.

Summary of the Judgment

The Bombay High Court was tasked with determining whether the Arbitration and Conciliation Act, 1996, should govern the arbitration proceedings that commenced under the Arbitration Act, 1940, and were pending at the time of the new Act's enforcement. The trial court had previously dismissed the petitioner's application to apply the new Act, holding that, according to Section 85 of the new Act, pending arbitrations should be governed by the old Act unless the parties agreed otherwise after the new Act came into force.

The High Court overturned this decision, interpreting the saving clause of Section 85 to allow for the applicability of the new Act to pending arbitrations based on the parties' existing agreement. The Court found that the agreement between Reshma Constructions and the State of Goa contained provisions that effectively embraced the new Act, thereby mandating its application to the ongoing arbitration. Consequently, the High Court set aside the trial court's order, declared the previous proceedings closed, and allowed the respondent the opportunity to exercise rights under Sections 33 and 34 of the new Act within the prescribed limitation periods.

Analysis

Interpretation of Section 85

Central to this judgment was the interpretation of Section 85 of the Arbitration and Conciliation Act, 1996. This section serves as a transitional provision, repealing previous arbitration laws while preserving their applicability to ongoing proceedings unless the parties involved explicitly agree to the contrary.

Section 85 (2)(a): "The provisions of the said enactments shall apply in relation to arbitral proceedings which commenced before this Act came into force unless otherwise agreed by the parties but this Act shall apply in relation to arbitral proceedings which commenced on or after this Act comes into force."

The High Court emphasized that the phrase "unless otherwise agreed by the parties" pertains to the intention of the parties regarding which Act governs the arbitration, rather than the timing of when such an agreement is made. This interpretation ensures that existing agreements encompassing future statutory modifications are respected, aligning with the legislative intent to provide flexibility and uphold contractual autonomy.

Legislative Intent and Purpose of the New Act

The Court delved into the objectives outlined in the Statement of Objects and Reasons of the Arbitration and Conciliation Act, 1996, highlighting the legislative intent to create a fair, efficient, and flexible arbitration framework. By allowing parties to dictate procedural aspects and minimizing court intervention, the Act aims to facilitate smoother arbitration processes and provide finality to arbitral awards.

Effect of Existing Agreements

The existing arbitration agreement between Reshma Constructions and the State of Goa included a clause specifying adherence to the Arbitration Act, 1940, "or any statutory modification or re-enactment thereof and the rules made thereunder and for the time being in force." The High Court interpreted this provision as encompassing the new Act, thereby mandating its application to the ongoing arbitration despite its commencement under the old Act.

Impact on Procedural Rights

By applying the new Act, the respondent retains the right to seek corrections or interpretations of the arbitral award under Section 33 and can move to set aside the award under Section 34 within the statutory limitation periods. The Court acknowledged that procedural steps taken under the old Act, such as the respondent's objections and challenges, were valid but emphasized adherence to the new statutory framework post the Act's applicability.

Impact

This judgment has significant implications for the landscape of arbitration in India:

  • Clarification on Transitional Provisions: It provides clarity on how the new Arbitration and Conciliation Act, 1996, interacts with ongoing arbitrations initiated under previous laws.
  • Emphasis on Contractual Autonomy: Reinforces the principle that parties' agreements dictate procedural governance, even in the face of legislative changes.
  • Facilitation of Legal Harmonization: Ensures that the objectives of the new Act—promoting fair and efficient arbitration—are upheld in existing proceedings.
  • Influence on Future Agreements: Encourages parties to draft arbitration clauses with foresight, considering potential statutory evolutions to avoid ambiguities.

Future cases will likely reference this judgment when addressing similar issues of statutory applicability and the interpretation of transitional clauses in arbitration agreements.

Complex Concepts Simplified

Section 85: Repeal and Saving Clause

Repeal: Section 85 formally revokes the Arbitration (Protocol and Convention) Act, 1937, the Arbitration Act, 1940, and the Foreign Awards (Recognition and Enforcement) Act, 1961.

Saving Clause: Despite the repeal, any arbitration proceedings that began before the new Act's enforcement continue under the old Act unless the parties agree to apply the new Act.

“Unless Otherwise Agreed by the Parties”

This phrase means that parties involved in arbitration can mutually decide to adhere to the provisions of the new Act instead of the old Act for their pending arbitration proceedings. The agreement reflects the parties' intent regarding which set of rules should govern their arbitration.

Statutory Limitation Periods

Under the new Act, Sections 33 and 34 impose time limits within which parties must seek corrections, interpretations, or set aside arbitral awards:

  • Section 33: Parties have 30 days from receiving the award to request corrections or interpretations.
  • Section 34: Parties have three months from receiving the award—or from the disposal of any Section 33 request—to apply for setting aside the award.

These limitation periods are crucial for ensuring timely resolution and finality in arbitration proceedings.

Conclusion

The Reshma Constructions, Goa v. State Of Goa judgment serves as a landmark interpretation of the transitional provisions within the Arbitration and Conciliation Act, 1996. By affirming that existing arbitration agreements can dictate the applicability of the new Act to ongoing arbitrations, the High Court upheld the principles of contractual autonomy and legislative intent to facilitate efficient and fair arbitration processes.

This decision not only clarifies the relationship between old and new arbitration laws but also underscores the importance of carefully drafted arbitration clauses in contracts. As arbitration continues to evolve in India, such judicial interpretations will be pivotal in shaping the procedural and substantive contours of dispute resolution.

In essence, the judgment reinforces the balance between statutory frameworks and party autonomy, ensuring that legal transitions enhance rather than impede the arbitration mechanism.

Case Details

Year: 1998
Court: Bombay High Court

Judge(s)

R.M.S Khandeparkar, J.

Advocates

S.G Dessai, Senior Advocate with R.B De SaV.B Nadkarni, Advocate General with S. Vahidulla, Additional Government Advocate

Comments