Interest on Delayed Local Currency Payments: Supreme Court Establishes Right to Reasonable Compensation in Absence of Specified Rate

Interest on Delayed Local Currency Payments: Supreme Court Establishes Right to Reasonable Compensation in Absence of Specified Rate

Introduction

The case of Oriental Structural Engineers Pvt. Ltd. (S) v. State Of Kerala (S) (2021 INSC 269) adjudicated by the Supreme Court of India on April 22, 2021, addresses critical issues pertaining to contractual obligations and the entitlement of contractors to interest on delayed payments. The dispute arose from a contract awarded by the State of Kerala to Oriental Structural Engineers for the upgradation of two stretches of State Highway. Central to the case was whether the contractor was entitled to receive interest on delayed payments made in local currency, especially when the contract did not explicitly specify the rate of interest.

Summary of the Judgment

The Supreme Court upheld the Arbitral Tribunal's decision granting interest to Oriental Structural Engineers on delayed payments in local currency. The State of Kerala had contended that the absence of a specified interest rate in the contract's appendix implied a zero or nil rate. However, the Supreme Court found this interpretation flawed, emphasizing that unless an express exclusion is present, contractors are entitled to reasonable compensation for delayed payments. The Court also addressed the contention regarding alleged waiver of interest claims by the contractor through specific communications but concluded that such waivers were either coerced or limited in scope. Ultimately, the Court sustained the entitlement to interest but adjusted the rate to a reasonable 8% simple interest per annum.

Analysis

Precedents Cited

Legal Reasoning

The Supreme Court meticulously analyzed the contractual terms, particularly focusing on Sub-Clause 60.8 which provided for interest on delayed payments but left the rate unspecified for local currency transactions. The State of Kerala's argument hinged on the assumption that the blank space for the interest rate implicitly indicated a zero rate. However, the Court rejected this interpretation, emphasizing that such an omission should not be construed against the contractor without clear express terms.

Furthermore, the Court examined the contractor's communications that the State used to argue waiver of interest claims. Recognizing that these communications were either coerced or limited to specific instances, the Court found them insufficient to indicate a blanket waiver of rights.

Drawing on precedents, the Court underscored that interest serves as compensatory damages for the deprivation of funds and should be awarded unless explicitly excluded by contract. The Tribunal's discretion to set a reasonable interest rate, in absence of a specified rate, was deemed within legal bounds. The Court adjusted the Tribunal's awarded rate to 8% simple interest per annum, deeming it just and equitable.

Impact

This judgment reinforces the principle that contractors can claim reasonable interest on delayed payments even when contracts lack explicit terms on the rate, provided there is no clear exclusion. It sets a precedent ensuring that omissions in contractual documents do not unfairly disadvantage parties relying on the contractual framework for remedies. This decision is particularly significant for public contracts where delays in payment can be frequent, thereby ensuring contractors are adequately compensated without necessitating explicit contractual provisions for every eventuality.

Complex Concepts Simplified

Patent Illegality

Patent illegality refers to scenarios where an arbitral award is so flawed that it violates the fundamental principles of justice, ethics, or public policy. In such cases, the award can be set aside by higher courts. This concept ensures that arbitral decisions remain within the bounds of legality and fairness.

Section 34 of the Arbitration and Conciliation Act, 1996

Section 34 deals with the setting aside of arbitral awards by courts. Grounds for setting aside include incapacity of parties, invalid arbitration agreement, lack of proper notice, or if the award deals with matters beyond the arbitration agreement. The Supreme Court evaluated whether the lower courts' decisions met these criteria.

Interest Pendente Lite

Interest pendente lite refers to interest accruing during the pendency of litigation, intended to compensate the party for the time value of money lost due to delays. In arbitration, similar principles apply, allowing for interest awards to mitigate financial losses resulting from delayed payments.

Conclusion

The Supreme Court's decision in Oriental Structural Engineers Pvt. Ltd. v. State Of Kerala serves as a landmark ruling affirming the right of contractors to receive reasonable interest on delayed payments, even in the absence of explicit contractual terms specifying the rate. By rejecting the State's inference of a zero rate due to a blank space and emphasizing the compensatory nature of interest, the Court reinforced fair contractual interpretation principles. This judgment not only upholds the contractor's entitlement under the existing contractual framework but also delineates the boundaries within which arbitral tribunals operate when determining equitable interest rates. Consequently, this ruling provides clarity and assurance to parties in similar contractual relationships, promoting fairness and mitigating disputes arising from payment delays.

Case Details

Year: 2021
Court: Supreme Court Of India

Judge(s)

Surya KantAniruddha Bose, JJ.

Advocates

DEVENDRA SINGHG. PRAKASH

Comments