Executability of a Specific-Plot Allotment Decree Despite Alleged Merger and Subsequent Construction; Court-May Order Removal of Non-Integral Encroachment

Executability of a Specific-Plot Allotment Decree Despite Alleged Merger and Subsequent Construction; Court-May Order Removal of Non-Integral Encroachment

Case: Prakash Namdeorao Dhage v. Ganpati s/o Yadavrao Kumbhare (connected appeals)
Citation: 2025 INSC 1226
Court: Supreme Court of India
Date: 09 October 2025
Coram: Vikram Nath, J. and Sandeep Mehta, J.

1. Introduction

The dispute arose from a long-running conflict between a co-operative housing society (Southern Nagpur Co-operative Society Limited) and its member, Ganpati Yadavrao Kumbhare, concerning allotment of a specific plot in the society’s layout. The respondent-member initially pursued claims over Plot Nos. 3 and 4, later amending the dispute to claim Plot No. 5A.

The core controversy in the Supreme Court was not the original entitlement (already crystallized by prior awards), but whether the decree directing allotment of Plot No. 5A had become inexecutable because the society asserted that Plot No. 5A had “lost identity” by alleged merger with Plot Nos. 4 and 4A and because constructions/third-party transfers had allegedly intervened.

Key Parties

  • Appellant (in main appeals): Southern Nagpur Co-operative Society Limited
  • Respondent: Ganpati Yadavrao Kumbhare (member seeking allotment/possession of Plot No. 5A)
  • Intervenors/third parties: (i) Prakash Namdeorao Dhage; (ii) various shop owners; (iii) certain society members claiming shares/interest in Plot No. 5A

Issues

  • Whether the decree/award directing allotment of Plot No. 5A was inexecutable due to alleged loss of identity/merger of the plot and subsequent construction/transfers.
  • Whether third-party shop owners/intervenors could resist execution and/or were affected by directions concerning Plot No. 5A.
  • What practical directions were warranted on the facts, including the existence of a covered passage/structure on the land shown in the photograph.

2. Summary of the Judgment

The Supreme Court declined to interfere with the High Court’s order upholding the appellate court’s reversal of the executing court. Relying significantly on the admitted factual position reflected in a photograph, the Court held that a substantial portion of the disputed land remained open and that the construction on it was essentially a covered passage to a community hall, not integral to the main building.

Accordingly, the Court directed:

  • Removal of the covered passage/structure standing on Plot No. 5A.
  • Allotment and delivery of clear and vacant possession of Plot No. 5A to the respondent.
  • Protection for intervening shop owners: they were stated to be occupants on Plot Nos. 4 and 4A (not Plot No. 5A) and were not to be affected.
  • Intervention applications rejected, while clarifying non-disturbance of shop owners on Plot Nos. 4 and 4A.

3. Analysis

3.1 Precedents Cited

No prior judicial precedents are cited or discussed in the provided judgment text. The decision is driven primarily by:

  • the procedural history and prior finality of the award/decree directing allotment of Plot No. 5A,
  • the nature and timing of objections raised in execution, and
  • concrete, admitted factual material (notably the photograph) demonstrating the continuing physical availability of the plot substantially in open condition.

As a result, the judgment’s value lies less in doctrinal exposition through earlier case-law and more in the Supreme Court’s practical articulation of when “inexecutability” arguments should fail on facts—particularly where alleged constructions are non-integral and removal would enable compliance.

3.2 Legal Reasoning

(A) Finality of entitlement vs. execution-stage obstruction

The respondent’s entitlement to Plot No. 5A had already been adjudicated in the co-operative fora: the Cooperative Court awarded allotment (31.03.2000) and the Cooperative Appellate Court dismissed the challenge (20.04.2002). The society’s later attempt to defeat implementation through execution objections was treated as lacking merit when compared against the continuing feasibility of compliance.

(B) “Loss of identity/merger” and “subsequent construction” as grounds of inexecutable decree

The society argued (i) Plot No. 5A ceased to exist due to merger with Plot Nos. 4 and 4A allegedly in 1985, and (ii) substantial construction/transfers made execution impossible, especially vis-à-vis non-parties.

The Supreme Court did not accept these claims as a bar to execution on the facts before it. Critically, the Court found—based on the photograph relied on by both sides—that a substantial open portion remained and that the only relevant construction on Plot No. 5A was a covered passage providing access to a community hall.

(C) Practical enforceability: removal of a non-integral structure

The judgment is notable for its remedial, implementation-focused approach: instead of treating “some construction exists” as making the decree inexecutable, the Court assessed whether the structure was integral to the main building. Finding it was not integral, the Court ordered its removal to enable delivery of “clear and vacant possession” of Plot No. 5A.

(D) Third-party occupants and the limits of collateral resistance

The Court insulated shop owners/intervenors from adverse impact by recording that their shops were on Plot Nos. 4 and 4A—not the disputed Plot No. 5A. This served two functions:

  • It neutralized the society’s “third-party rights make execution impossible” narrative, at least as to these intervenors.
  • It narrowed the execution remedy strictly to Plot No. 5A (removal of the passage + delivery of possession), thereby reducing collateral disruption.

3.3 Impact

  • Execution jurisprudence (fact-driven): The judgment strengthens a practical proposition: a decree for delivery/allotment of a specific plot will not be treated as inexecutable merely because the judgment-debtor alleges merger or points to later developments, if the land is substantially available and compliance can be achieved by removing a non-essential obstruction.
  • Deterrence against strategic “impossibility” defenses: The Court’s emphasis on the admitted photographic position and its directive to remove an obstructing structure signals intolerance toward prolonged non-compliance—especially where the decree-holder has been waiting decades.
  • Targeted relief to avoid third-party hardship: By explicitly excluding shop owners on Plot Nos. 4 and 4A from the order’s effect, the Court illustrates a template for enforcing decrees while minimizing spillover onto persons not truly occupying the decretal property.
  • Co-operative housing disputes: The ruling underscores that society-level resolutions and post-award layout changes (asserted without clear approval/validation in the proceedings) are unlikely to defeat an allotment award at the execution stage when physical feasibility is demonstrated.

4. Complex Concepts Simplified

  • “Inexecutable decree”: A decree is inexecutable if it cannot be implemented in law or in fact (e.g., the subject matter no longer exists). Here, the Court found execution possible because the plot substantially existed and only a removable passage obstructed it.
  • “Plot has lost its identity”: This typically means boundaries/plot existence have been altered so the original parcel cannot be identified. The Court effectively treated this claim as unpersuasive on the admitted physical depiction of the site.
  • “Executing court”: The court that enforces a decree. It generally implements what has been decreed rather than re-litigating the merits. In this case, execution was revived/affirmed by higher courts to ensure the award’s benefit is realized.
  • “Intervention”: A request by a non-party to participate. Even though interventions were rejected, the Court still clarified that certain intervenors (shop owners) would not be affected because they were not on Plot No. 5A.

5. Conclusion

The Supreme Court’s decision in Prakash Namdeorao Dhage v. Ganpati s/o Yadavrao Kumbhare consolidates an execution-centric principle: an allotment decree for a specific plot should be enforced where the plot remains substantially available, and alleged obstacles—especially non-integral constructions—can be removed to deliver clear possession. The Court also demonstrates a calibrated approach to third-party concerns by explicitly insulating occupants on other plots from the execution directions. Overall, the judgment prioritizes real-world enforceability and curbs prolonged resistance to long-standing decrees in co-operative society allotment disputes.

Case Details

Year: 2025
Court: Supreme Court Of India

Judge(s)

Justice Vikram NathJustice Sandeep Mehta

Advocates

CHAND QURESHI

Comments