Smart Summary

Factual and Procedural Background

In January 2011 defendant awarded plaintiff a contract for a multi-phased mechanical systems upgrade at SUNY Stony Brook with an initial price of $13,267,000. The comptroller approved the project in March 2011, plaintiff received notice to proceed in April 2011, work began in May 2011, and substantial completion was originally scheduled for March 1, 2013 (later extended to June 26, 2013). Plaintiff experienced numerous delays which it attributes to defendant's project mismanagement, interference, uncontemplated design changes and errors, work stoppages and defendant's failure to process or respond to change order proposals. Plaintiff completed the project in October 2013 and in November 2013 sought additional remuneration for disputed change orders and delay-related costs, which defendant did not pay.

Plaintiff sued asserting, among other claims, breach of contract for extra work and delay damages. Defendant answered, raised affirmative defenses including plaintiff's failure to comply with contractual notice provisions, and counterclaimed for breach. Following discovery, defendant moved for partial summary judgment seeking dismissal of plaintiff's extra work and delay damages claims. Supreme Court granted the motion and dismissed those claims; plaintiff appealed.

Legal Issues Presented

  1. Whether defendant made a prima facie showing entitling it to summary judgment dismissing plaintiff's extra work claim on the ground that plaintiff failed to comply with the contract's notice provisions.
  2. Whether defendant made a prima facie showing entitling it to summary judgment dismissing plaintiff's delay damages claim based on the contract's "no damages for delay" clause and demonstrating that none of the recognized exceptions applied.

Arguments of the Parties

Appellant's Arguments

  • Plaintiff asserted that project delays were caused by defendant's mismanagement, interference, design changes/errors, work stoppages and failure to process change orders, and sought damages for extra work and delay.
  • Plaintiff argued on appeal that Supreme Court erred because defendant failed to establish prima facie entitlement to summary judgment dismissing those claims.

Respondent's Arguments

  • Defendant argued plaintiff's extra work claim is barred by plaintiff's failure to comply with the contract's notice provisions (sections 2.05(1) and 2.03(1)(b) referenced).
  • Defendant contended the contract's "no damages for delay" clause (section 3.05(7)) barred delay damages and submitted the contract and an affidavit of Donald Chester asserting plaintiff did not provide the required notices and that none of the clause's exceptions applied.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Andrew R. Mancini Assoc., Inc. v Mary Imogene Bassett Hosp., 80 AD3d 933, 935 (2011) Summary judgment standard: movant must make a prima facie showing of entitlement to judgment as a matter of law; evidence viewed in favor of nonmovant. Court applied this standard to evaluate whether defendant established prima facie entitlement to dismiss plaintiff's claims and found defendant had not met the burden.
Alvarez v Prospect Hosp., 68 NY2d 320, 324 (1986) Rule that failure to make a prima facie showing requires denial of the motion regardless of opposing papers. Cited to support that defendant's conclusory submissions required denial of summary judgment if prima facie proof was lacking.
A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d 20, 31 (1998) Contractual notice and reporting provisions in public construction contracts generally serve as conditions precedent to suit or recovery. Used to explain that plaintiff's compliance with notice provisions was a condition precedent and relevant to the extra work claim.
Fahs Rolston Paving Corp. v County of Chemung, 43 AD3d 1192, 1194 (2007) Failure to strictly comply with notice provisions generally constitutes waiver of a claim for additional compensation. Referenced in discussing the legal effect of failing to provide required contractual notices for change orders/extra work.
Phoenix Signal & Elec. Corp. v New York State Thruway Auth., 90 AD3d 1394, 1397 (2011) Support for the principle that failure to strictly comply with contractual notice provisions can waive claims for additional compensation. Used as supporting authority for the rule on notice compliance in public construction contracts.
Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297, 305 (1986) Contract clauses barring recovery for delay are generally valid and prevent recovery for conduct contemplated by the parties. Explained the general enforceability of "no damages for delay" clauses and the need to consider exceptions.
Clifford R. Gray, Inc. v City School Dist. of Albany, 277 AD2d 843, 844 (2000) Enumerates exceptions to "no damages for delay" clauses (bad faith/willful/malicious/gross negligence; uncontemplated delays; delays so unreasonable as to constitute intentional abandonment; breach of a fundamental obligation). Quoted to identify the exceptions that a movant must negate to prevail on a "no damages for delay" defense.
Tougher Indus., Inc. v Dormitory Auth. of the State of N.Y., 130 AD3d 1393, 1393-1394 (2015) As moving party, defendant bears the burden to demonstrate prima facie that none of the exceptions to a "no damages for delay" clause are present. Cited to state defendant's burden in proving the clause barred recovery as a matter of law.
Arnell Constr. Corp. v New York City Sch. Constr. Auth., 177 AD3d 595, 597 (2019) Holding that the mere existence of a "no damages for delay" clause is insufficient standing alone to establish the defense as a matter of law. Applied to conclude Chester's conclusory affidavit did not establish defendant's prima facie entitlement to dismissal under the clause.
Ridley Elec. Co., Inc. v Dormitory Auth. of the State of N.Y., 152 AD3d 1129, 1130 (2017) Referenced for deeming an unchallenged dismissal as abandoned; also cited by comparison regarding sufficiency of proof. Used to (1) deem plaintiff's nonchallenge of certain dismissals abandoned and (2) compare factual showings relevant to summary judgment sufficiency.

Court's Reasoning and Analysis

The court first reiterated the summary judgment standard: the movant must make a prima facie showing of entitlement to judgment as a matter of law and the evidence must be viewed in the light most favorable to the nonmovant (Andrew R. Mancini; Alvarez). The court then analyzed the contract's notice provisions, noting section 2.05(1) contemplates changes and section 2.03(1)(b) requires a written notice within five working days after being ordered to perform or commencing extra work. The court concluded that, while the contract made notice a condition precedent, defendant's evidentiary showing (a copy of the contract and Donald Chester's affidavit) was conclusory: Chester claimed plaintiff did not provide required notice but his affidavit and the submitted documents did not make clear when plaintiff's notice obligations began to run or whether plaintiff's submissions satisfied the contractual notice requirements. Consequently, defendant failed to establish prima facie entitlement to dismissal of the extra work claim.

Regarding delay damages, the court noted the contract's "no damages for delay" clause (section 3.05(7)) but explained that such clauses are enforceable only absent recognized exceptions (Corinno Civetta; Clifford R. Gray) and that the movant must demonstrate prima facie that none of those exceptions apply (Tougher Indus.). Chester's conclusory assertion that none of the exceptions applied was insufficient (Arnell Constr.). Therefore, defendant did not carry its burden to obtain summary dismissal of the delay damages claim. Based on these deficiencies, the court found Supreme Court erred in granting summary judgment dismissing the extra work and delay claims.

Holding and Implications

The order is modified: Supreme Court's grant of defendant's motion for summary judgment dismissing plaintiff's (1) first cause of action insofar as it sought extra work and (2) second cause of action for delay damages is reversed; the motion is denied to that extent; and, as so modified, the order is affirmed.

Implications: The dismissal of plaintiff's extra work and delay damages claims is reversed and those claims survive summary judgment for further proceedings. The opinion does not announce a new legal rule beyond applying established summary judgment standards and existing authorities concerning contractual notice requirements and "no damages for delay" clauses.

Framan Mechanical, Inc., Appellant, v. State Uni

Egan Jr., J.P.

Before: , Lynch, Devine, Aarons and Colangelo, JJ.

Hodgson Russ LLP, Albany (Scott C. Paton of counsel), for appellant.

Letitia James, Attorney General, Albany (Owen Demuth of counsel), for respondent.

Egan Jr., J.P.

Appeal from an order of the Supreme Court (Platkin, J.), entered December 31, 2018 in Albany County, which, among other things, granted defendant's motion for partial summary judgment.

In January 2011, defendant awarded plaintiff a contract to perform a multi-phased mechanical systems upgrade and renovation (hereinafter the project) of the Life Sciences Building at the State University of New York at Stony Brook, for a contract price of $13,267,000. The comptroller approved the project in March 2011, plaintiff received notice to proceed in April 2011, the project commenced in May 2011 and the deadline for substantial completion was scheduled for March 1, 2013. An extension was later granted, extending the substantial completion deadline to June 26, 2013. Following commencement of the project, plaintiff encountered numerous construction delays that it claims were the result of, among other things, defendant's project mismanagement and interference, uncontemplated design changes and errors, work stoppages and defendant's failure to process and/or respond to change order proposals. Ultimately, plaintiff completed work on the project in October 2013. In November 2013, plaintiff submitted a request seeking additional remuneration from defendant for various outstanding disputed change orders and other costs that it incurred as a result of the numerous project delays. No additional compensation was subsequently forthcoming from defendant.

Plaintiff thereafter commenced this action asserting causes of action for, as relevant here, breach of contract, seeking damages for extra work and delay damages. Defendant answered, asserting numerous affirmative defenses, including plaintiff's failure to comply with the contract's notice provisions, and counterclaimed for breach of contract. Following discovery, defendant moved for partial summary judgment dismissing, as relevant here, that part of plaintiff's first cause of action as sought damages for extra work and the second cause of action for delay damages. Supreme Court granted defendant's motion, finding that plaintiff's extra work claim was barred as a result of its failure to abide by the contract's notice provisions, and its claim for delay damages was precluded given the inclusion of a "no damages for delay" clause in the contract. Supreme Court further concluded that the contract delays for which plaintiff was seeking damages were "within the contemplation of a prime contractor on a large commercial construction project." Plaintiff appeals.

Subsequently, SPJ Piping Corp. and Roland's Electric, Inc., two of plaintiff's subcontractors for the project, commenced separate actions against plaintiff to recover damages for extra work. Plaintiff served defendant with a third-party complaint and a second third-party complaint, respectively, in the context of these separate actions. To the extent that plaintiff sought recovery for the same extra work as alleged in its complaint, both third-party actions were severed, transferred to Albany County and joined with this action for the purposes of disclosure and trial.

Plaintiff's first cause of action for breach of contract also stated a claim for the unpaid contract balance and its third and fourth causes of action asserted quasi-contractual claims for unjust enrichment and quantum meruit. Supreme Court also granted summary judgment dismissing plaintiff's third and fourth causes of action, and, to the extent that plaintiff does not challenge these dismissals on appeal, we deem any such challenge to be abandoned (see Ridley Elec. Co., Inc. v Dormitory Auth. of the State of N.Y., 152 AD3d 1129, 1130 [2017]). Plaintiff's breach of contract claim seeking damages for the unpaid contractual balance is not at issue on appeal.

Plaintiff claims that Supreme Court erred in granting defendant's motion for partial summary judgment dismissing its claims for extra work and delay damages as defendant failed to establish its prima facie entitlement to summary judgment. We agree. "The proponent of a summary judgment motion must make a prima facie showing of entitlement to judgment as a matter of law, tendering sufficient evidence to demonstrate the absence of any material issues of fact, and the evidence produced by the movant must be viewed in the light most favorable to the nonmovant, affording the nonmovant every favorable inference" (Andrew R. Mancini Assoc., Inc. v Mary Imogene Bassett Hosp., 80 AD3d 933, 935 [2011] [internal quotation marks and citations omitted]). "Failure to make such prima facie showing requires a denial of the motion, regardless of the sufficiency of the opposing papers" (Alvarez v Prospect Hosp., 68 NY2d 320, 324 [1986] [citation omitted]).

When dealing with public construction contracts, contractual notice and reporting provisions generally serve as conditions precedent to suit or recovery (see A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d 20, 31 [1998]; Fahs Rolston Paving Corp. v County of Chemung, 43 AD3d 1192, 1194 [2007]). As relevant here, section 2.05 (1) of the contract provides that defendant "reserves the right at any time during [the project] to add, modify or change the work covered by the [c]ontract." In the event that defendant ordered plaintiff to perform extra work, pursuant to section 2.03 (1) (b) of the contract, plaintiff was required to comply with any such order and, thereafter, "[f]ile with [defendant] and [the contract consultant], within five (5) working days after being ordered to perform the work claimed by it to be extra work or within five (5) working days after commencing performance of the extra work, . . . a written notice of the basis of its claim and request a determination thereof." Thus, the "[f]ailure to strictly comply with [the relevant notice] provisions generally constitutes waiver of a claim for additional compensation" or extra work (Fahs Rolston Paving Corp. v County of Chemung, 43 AD3d at 1194; see Phoenix Signal & Elec. Corp. v New York State Thruway Auth., 90 AD3d 1394, 1397 [2011]).

With regard to delay damages, a contract clause that bars a contractor from recovering damages for delay in the performance of a contract by a contractee are generally valid and enforceable and "will prevent recovery of damages resulting from a broad range of reasonable and unreasonable conduct by the contractee if the conduct was contemplated by the parties when they entered into the agreement" (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297, 305 [1986]). However, where, as here, a construction contract contains a "no damages for delay" clause, various exceptions exist and a contractor may still recover damages for "(1) delays caused by the contractee's bad faith or its willful, malicious, or grossly negligent conduct, (2) uncontemplated delays, (3) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee, and (4) delays resulting from the contractee's breach of a fundamental obligation of the contract" (Clifford R. Gray, Inc. v City School Dist. of Albany, 277 AD2d 843, 844 [2000] [internal quotation marks and citation omitted]). Accordingly, as the moving party, it was defendant's burden to demonstrate "prima facie that none of the exceptions to the damages for delay clause are present" (Tougher Indus., Inc. v Dormitory Auth. of the State of N.Y., 130 AD3d 1393, 1393-1394 [2015] [internal quotation marks and citations omitted]).

Section 3.05 (7) of the contract provided a "no damages for delay clause," which states, in relevant part, that "[i]f [plaintiff] shall claim to have sustained any damages by reason of delays, extraordinary or otherwise, or hindrances which it claims to be due to any action, omission, direction or order by [defendant] . . ., [plaintiff] shall be entitled only to an extension of time . . . and shall not have or assert any claim or prosecute any suit, action, cause of action or proceeding against [defendant] based upon such delays or hindrances, unless such delays or hindrances were caused by [defendant's] bad faith or its willful, malicious, or grossly negligent conduct, or uncontemplated delays, or delays so unreasonable that they constitute an intentional abandonment of the contract by [defendant], or delays resulting from [defendant's] breach of fundamental obligation of the contract."

Said exceptions were explicitly incorporated into the parties' contract. --------

In support of its motion for partial summary judgment, defendant submitted a copy of the contract and the affidavit of Donald Chester, the associate project coordinator for defendant. In his supporting affidavit, Chester avers that he reviewed the records maintained by defendant, including a two-page spreadsheet that plaintiff provided in response to defendant's bill of particulars specifically listing its disputed change order proposals, "and can verify that [plaintiff] did not provide contractually required notice for any of the [c]hange [o]rder proposals" that it submitted. However, upon review, it is not evident from Chester's affidavit or other documentary evidence filed in support thereof as to when plaintiff's obligation to provide such contractual notice for each of its claims began to run and whether its submissions in this regard satisfied its notice obligations. In other words, although the terms of the contract make plain that the parties contemplated the possibility of change orders, extra work and potential acts or omissions by the contractee, and made plaintiff's provision of proper contractual notice a condition precedent to suit, it cannot be determined from defendant's submissions, other than Chester's conclusory assertion, whether plaintiff complied with the applicable notice provisions.

Chester further avers that the "no damages for delay" clause set forth in section 3.05 (7) served to bar plaintiff's claim for delay damages. However, the mere existence of a "no damages for delay clause," standing alone, is insufficient to establish the applicability of the defense as a matter of law (see Arnell Constr. Corp. v New York City Sch. Constr. Auth., 177 AD3d 595, 597 [2019]). Although Chester provides a conclusory blanket assertion that none of the exceptions to enforcement of the "no damages for delay" clause were applicable, said assertion was insufficient in and of itself to establish defendant's prima facie entitlement to summary judgment dismissing plaintiff's second cause of action for delay damages (see id. at 597-598; compare Ridley Elec. Co., Inc. v Dormitory Auth. of the State of N.Y., 152 AD3d 1129, 1131-1132 [2017]; Fahs Rolston Paving Corp. v County of Chemung, 43 AD3d at 1194). Accordingly, based on the foregoing, we find that Supreme Court erred in granting summary judgment dismissing plaintiff's first causes of action seeking damages for extra work and second cause of action for delay damages.

Lynch, Devine, Aarons and Colangelo, JJ., concur.

ORDERED that the order is modified, on the law, without costs, by reversing so much thereof as granted defendant's motion for summary judgment dismissing plaintiff's (1) first cause of action to the extent that it sought extra work and (2) second cause of action for delay damages; motion denied to that extent; and, as so modified, affirmed.