Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Docket Number
Attorney(S)
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Docket Number
Attorney(S)
Judges

CALIFORNIA MANUFACTURERS ASSOCIATION et al., Petitioners, v. PUBLICUTILITIES COMMISSION et al., Respondents; PACIFIC GAS AND ELECTRICCOMPANY, Real Party in Interest.OWENS-CORNING FIBERGLAS CORPORATION, Petitioner,

OPINION

CLARK, J.

(1) In these two proceedings we review Public Utilities Commission Decision No. 87585 as modified on petition for rehearing by Decision No. 87996. The decisions granted Pacific Gas and Electric Company increased revenue of $58,444,000 to offset an increase in its cost of purchasing gas. The increase in revenue is not challenged; petitioners challenge the method by which the commission allocates the increase among utility users.

In the original proceedings, Commissioner Dedrick did not participate, and Commissioner Symons filed a dissenting opinion. Commissioner Dedrick voted to modify and deny rehearings, and Commissioner Sturgeon, who had been part of the majority in the original decisions, joined Commissioner Symons, in dissenting from the order denying rehearing.

In the companion opinion of California Manufacturers Assn. v. Public Utilities Com., ante, page 251, [ 155 Cal.Rptr. 664, 595 P.2d 98], decided today, we conclude the commission decisions must be annulled because the rate designs adopted — assertedly to further conservation goals — are supported by neither the findings nor the evidence. In the instant decisions, the commission again adopts a rate design assertedly to further the same goals. However, the findings and evidence are substantially the same as in the former two cases and fail for the same reasons.

The commission's decisions are annulled. On remand the commission shall determine an appropriate method to spread the rate increase to which the utility is entitled. Having ascertained an appropriate rate spread, the commission shall order refunds and surcharges, if appropriate, all in compliance with Public Utilities Code section 1705

Bird, C.J., Mosk, J., Richardson, J., Manuel, J., Newman, J., and Caldecott, J., concurred.

Assigned by the Chairperson of the Judicial Council.

Use AI to get other relevant cases.

Comments

CALIFORNIA MANUFACTURERS ASSN. v. PUBLIC UTIL. COM
(May 16, 1979)