Factual and Procedural Background

This case concerns the construction of a contract between the General Services Administration (GSA) and American Western Corporation, appellant. On August 22, 1980, GSA awarded a requirements contract to appellant to supply polyethylene plastic bags from August 22, 1980, to July 30, 1981. The contract included an Economic Price Adjustment (EPA) clause allowing price adjustments upward or downward based on a formula, with the Government able to unilaterally reduce prices at any time and the appellant required to submit a written request for increases. The clause did not specify any deadline for asserting price changes.

After the contract award, the Government placed purchase orders that appellant fulfilled, submitting invoices based on original contract prices. Final payment was made by the Government on November 17, 1981. Prior to this, on November 3, 1981, the contracting officer notified appellant of defective bags requiring replacement under a Quality Approved Manufacturer's Agreement, leading to a contract modification in May 1982 and a refund by appellant in June 1982.

Before the contract ended, the price of polyethylene resin declined, entitling the Government to a price reduction under the EPA clause. The Government, unaware, made final payment at original prices. On December 15, 1981, the GSA Inspector General informed the contracting officer about the potential price reduction. On December 31, 1981, the Government notified appellant of its intention to adjust prices downward and demanded payment of $22,521.08 in a March 17, 1981 final decision. Appellant appealed to the GSA Board of Contract Appeals, which upheld the Government's claim by a 2-1 vote.

Legal Issues Presented

  1. Whether the EPA clause is ambiguous regarding the time limit for the Government to assert a price decrease.
  2. Whether the Government's claim for a retroactive price reduction after final payment was made was timely and enforceable.
  3. Whether the appellant was prejudiced by the Government's assertion of the price adjustment claim after final payment, thus barring the Government's claim.

Arguments of the Parties

Appellant's Arguments

  • The EPA clause is ambiguous as to the timing for the Government to assert a price decrease, which should be construed in appellant's favor to bar claims after full contract performance.
  • Price adjustments should only be made during the contract period, citing provisions referring to price indexes tied to months within the contract period.
  • The Government’s claim, made six weeks after final payment, prejudiced appellant because it had already distributed contract proceeds as employee bonuses and would face SEC reporting corrections and potential investor lawsuits.

Amici Curiae Arguments

  • Final payment by the Government bars either party from asserting claims on a Government contract, relying on precedents such as Gulf Western Industries, Inc. v. United States and Dubois Construction Corp. v. United States.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Nager Electric Co., Inc. v. United States, 177 Ct.Cl. 234, 368 F.2d 847 (1966) Where no specific time limit is set in contract clauses, courts imply a reasonable time for asserting claims to avoid unreasonable delay. The court relied on this precedent to hold that omission of a time limit in the EPA clause does not bar the Government from asserting a price reduction after final payment, but requires a reasonable time.
Roberts v. United States, 174 Ct.Cl. 940, 357 F.2d 938 (1966) Contracting officers must make equitable adjustments within a reasonable time to allow contractors an opportunity to appeal before prejudice occurs. The court applied this standard to determine whether the Government acted within a reasonable time in seeking the price reduction and whether appellant was prejudiced.
Merritt-Chapman Scott Corp. v. United States, 174 Ct.Cl. 250, 355 F.2d 622 (1966) Supports the implication of a reasonable time for assertions of claims when no explicit time limit exists. Used to reinforce that the EPA clause’s silence on timing requires a reasonable time standard.
Gulf Western Industries, Inc. v. United States, 226 Ct.Cl. 159, 639 F.2d 732 (1980) Claims must be asserted prior to final payment when contract contains express time limits in Changes clause. The court distinguished this case, noting that the instant contract lacks such express time limits, so the final payment rule does not apply here.
Dubois Construction Corp. v. United States, 120 Ct.Cl. 139, 98 F. Supp. 590 (1951) Government’s counterclaim barred if not asserted before final payment, based on Disputes clause procedures. The court distinguished this case for the same reason as Gulf Western, emphasizing the absence of such procedural clauses in the present contract.
Jo-Bar Mfg. Corp. v. United States, 210 Ct.Cl. 149, 535 F.2d 62 (1976) Supports the principle of express time limits for claims prior to final payment. Cited by Gulf Western and discussed to highlight the contractual basis for the final payment rule, which is absent here.

Court's Reasoning and Analysis

The court first addressed the appellant’s claim of ambiguity in the EPA clause regarding timing for price reductions and found no ambiguity. The clause clearly sets forth rights and a formula for price adjustments but lacks any express time limit for asserting a price decrease. The omission of a time limit does not create ambiguity but requires implying a reasonable time to assert claims.

The court rejected appellant’s argument that references to price indexes tied to months within the contract period imposed a timing restriction, concluding that such provisions relate only to the method of calculation, not timing.

In analyzing the final payment rule cited by amici and appellant, the court distinguished prior cases where express contractual time limits barred claims after final payment. Because the instant contract contains no such express limits, the final payment rule does not apply.

The court applied the standard from Roberts v. United States requiring that the Government’s price adjustment claim be made within a reasonable time sufficient to allow the contractor to appeal without prejudice. The Government’s claim was made approximately six weeks after final payment but before appellant’s position was prejudiced in the manner contemplated by Roberts.

The court found that appellant’s payment of bonuses to employees did not constitute the kind of legal obligation to creditors that would demonstrate prejudice. Further, appellant’s awareness of the price fluctuations and the Government’s claim for defective bags prior to final payment reduced any claim of surprise or unfairness. The costs of correcting financial statements and potential investor lawsuits were deemed speculative or mere inconvenience, insufficient to establish prejudice.

Accordingly, the court held that the Government acted within a reasonable time and that appellant was not prejudiced by the timing of the Government’s price reduction claim.

Holding and Implications

AFFIRMED.

The court affirmed the decision of the GSA Board of Contract Appeals, entitling the Government to recover $22,521.08 for the price reduction under the EPA clause. The direct effect is that the Government’s retroactive price adjustment claim was valid despite being made after final payment, as no express contractual time limit barred it and the claim was made within a reasonable time without prejudice to appellant. The court did not establish any new precedent but clarified the application of reasonable time and prejudice standards in the absence of express contractual timing provisions.

AMERICAN WESTERN CORPORATION, APPELLANT, v. THE UNITED STATES, APPELLEE.

SKELTON, Senior Circuit Judge.

This case involves the construction of a contract between the General Services Administration (GSA) and the American Western Corporation (appellant). On August 22, 1980, GSA awarded a requirements contract to appellant to supply polyethylene plastic bags for the Government for the period from August 22, 1980, to July 30, 1981. The contract contained an Economic Price Adjustment (EPA) clause which provided that the "price(s) of all items which are purchased under this contract are subject to price adjustment, upward or downward" based upon a formula contained in the clause. The clause provided that, while appellant had to submit a written request for a price adjustment upward, the Government could unilaterally obtain a price reduction. The clause did not fix a time for requesting an increase or for asserting a decrease in prices.

Subsequent to the award of the contract, the Government began placing purchase orders with appellant. After shipping these orders, appellant would submit invoices to the Government based on the original contract prices. All of the purchase orders issued under the contract were shipped, and the Government paid the final invoice on November 17, 1981.

On November 3, 1981, two weeks before the final payment was made, the contracting officer notified appellant that some of the bags shipped under the contract were defective and would have to be replaced under the terms of a Quality Approved Manufacturer's Agreement between the parties. Negotiations ensued which ultimately resulted in a modification of the contract which was executed on May 10, 1982. This modification called for a refund of five percent of the contract price by appellant. Appellant remitted the money owed under the modification on June 18, 1982, and, in addition, offered $8,000 to settle for other defective bags discovered after November 3, 1981.

Prior to the contract's official July 30, 1981, termination date, the price of PE resin — a raw material used in manufacturing polyethylene bags — declined to a point which entitled GSA to obtain a price reduction under the EPA clause. The Government failed to realize this at the time, however, and thus made final payment according to the original contract prices. On or about December 15, 1981, the GSA Inspector General notified the contracting officer that the Government could have obtained a price reduction under the EPA clause. The contracting officer decided to obtain a retroactive price reduction by requesting a refund from appellant, and on December 31, 1981, GSA notified appellant of its intention to adjust the contract price downward. In a final decision dated March 17, 1981, the contracting officer demanded payment from appellant in the amount of $22,521.08. The appellant appealed to the GSA Board of Contract Appeals, which upheld the Government's claim in a 2 to 1 decision.

Appellant initially contends that the Board erred in failing to find that the EPA clause is ambiguous with respect to the time in which the Government must assert its right to a decrease. Because of this alleged ambiguity, appellant argues that we must adopt its construction of the clause, i.e., that the Government may not claim a price reduction after full performance of the contract. We cannot accept appellant's interpretation of the EPA clause because, after careful consideration, we fail to find any ambiguity in the contract. It very clearly states the relative rights of the parties in obtaining price adjustments, and establishes a formula for determining the amount of adjustment available. It merely fails to set a time limit within which the Government must claim a reduction in price. Omission of an express time provision does not of itself create an ambiguity.

Appellant points to certain provisions in the EPA clause that allegedly imply that price adjustments can be made only during the contract period. The clause states, for example, that the price indexes used to determine price adjustments shall be "the indexes for the third, sixth; and ninth succeeding months of the contract period." This provision is directed to the method for determining the amount of adjustment. It clearly was not inserted for the purpose of establishing a time limit for asserting a price reduction and should not be given such an effect. We are unable to find any provision in the EPA clause which could reasonably be construed to impose a time limit on the Government for asserting its right to a price reduction. In the absence of such a time limit, the courts will imply a reasonable time. See, Nager Electric Co., Inc. v. United States, 177 Ct.Cl. 234, 368 F.2d 847, 864 (1966); Roberts v. United States, 174 Ct.Cl. 940, 357 F.2d 938, 946 (1966); Merritt-Chapman Scott Corp. v. United States, 174 Ct.Cl. 250, 355 F.2d 622, 627 (1966).

The amici, American Transparents Plastic Corporation and Chicago Transparent Products, Inc., argue that final payment by the Government bars the assertion of a claim by either party to a Government contract. As authority for this proposition, the amici cite the cases of Gulf Western Industries, Inc. v. United States, 226 Ct.Cl. 159, 639 F.2d 732 (1980), and Dubois Construction Corp. v. United States, 120 Ct.Cl. 139, 98 F. Supp. 590 (1951).

In Gulf Western the contract contained a Changes clause which provided that the contracting officer could receive and act upon any claim asserted prior to final payment, if the facts justified such action. The court denied the contractor's claim challenging defective specifications because the claim was not made until after final payment. The decision was clearly based upon the language in the Changes clause, which set forth an express time limit. This was also the case in Jo-Bar Mfg. Corp. v. United States, 210 Ct.Cl. 149, 535 F.2d 62 (1976), cited by the court in Gulf Western.

In Dubois the Government's counterclaim for defective work by the contractor was barred because it was not asserted until after full performance and final payment. The contract in that case contained a Disputes clause which required all disputes concerning questions of fact to be decided by the contracting officer. The court's denial of the Government's claim was clearly based upon the Government's failure to follow the procedure set out in the Disputes clause.

The final payment rule enunciated in the above cases was predicated upon express contractual provisions. In the instant case no such provisions are found in the agreement. The contract simply contains a provision allowing the Government to make a unilateral price adjustment, with no express time limit. In such case, the final payment rule does not apply. As the Court of Claims stated in Nager Electric, supra:

Those specific clauses (Disputes clauses) usually have built-in time limits, and where no specific period is established in the contract the contractor (or Government) cannot delay unreasonably. 368 F.2d at 864.

This rule was applied in Roberts v. United States, supra, where the contract stated simply that when a change causes a decrease in the amount due on the contract, "equitable adjustment shall be made." The court held that this provision imposed a duty upon the contracting officer to "make such an adjustment within a reasonable time." 357 F.2d at 946.

The issue, then, resolves itself into a determination of whether the Government acted within a reasonable time in adjusting the contract price downward. Both the parties and the Board look to the Roberts case to make this determination. Roberts held that the adjustment should be made within such a time as to allow the contractor an opportunity to appeal (1) while the facts supporting the claim are readily available and (2) before the contractor's position is prejudiced by final settlement with his subcontractors, suppliers, and other creditors. If the adjustment is not made within a reasonable time, the Government may be held to be estopped by an act of waiver. There is no problem here with (1) because the facts supporting a claim for price adjustment under the EPA clause are readily available by reference to a monthly publication of the U.S. Department of Labor, and to the formula set out in the contract. However, under (2) the appellant asserts that it was prejudiced by the Government's claim asserted six weeks after final payment because it had distributed some of the proceeds from the contract as bonuses to employees. It also claims prejudice from the fact that it will have to file corrected financial statements with the SEC if the Government's claims are allowed, and because appellant will be exposed to potential lawsuits from investors who relied upon the inaccurate financial statements.

To begin with, as appellant concedes, bonus payments to employees are not the same as the payments to subcontractors and creditors contemplated in Roberts. There is no evidence of record that appellant was legally obligated to pay bonuses to its employees, as would be the case of payments to creditors. Additionally, appellant was aware of the price fluctuations in the cost of PE resin, as the Board found. Although it was under absolutely no obligation to inform the Government of these changes, it at least knew that there was a possibility that the GSA might make a claim for a price reduction. It was also aware before final payment on November 17, 1981, that the Government was asserting a claim based upon defective bags. It, therefore, knew that it might eventually receive less than the original contract price. Without calling the prudence of appellant into question for paying the bonuses, it is clear that it might have avoided its predicament by waiting until all disputes concerning the contract were settled before making the bonus payments. Moreover, the cost of filing a corrected financial statement with the SEC does not rise to the level of prejudice contemplated by Roberts. Inconvenience does not equal prejudice. Finally, the possibility of suits by disgruntled investors is too speculative to afford a basis for a finding of prejudice. We hold that the appellant was not prejudiced by the Government's assertion of a claim for price adjustment on December 31, 1981, and that the Government's claim was, therefore, made within a reasonable time.

We have considered the remaining contentions of appellant and the amici, and have determined that they are without merit. The decision of the GSA Board of Contract Appeals entitling the Government to recoup its overpayment of $22,521.08 is affirmed.

AFFIRMED.