Ferrick v. City of New York, Appellate Division, First Department — May 23, 1985

Factual and Procedural Background

The plaintiff alleged that in June 1979 he was arrested and assaulted by two transit police officers in a subway station at 42nd Street and Lexington Avenue. In January 1980 the plaintiff was acquitted, after a jury trial, of charges of disorderly conduct and resisting arrest. The plaintiff commenced this action seeking damages in June 1980.

In January 1983 the New York City Transit Authority and the individual defendants moved for summary judgment dismissing the complaint on the ground that a timely notice of claim had not been served — the notice of claim had been served more than 90 days after the June 1979 incident. At Special Term the defendants' motion was denied on the ground that it was an omnibus motion that failed to distinguish among the various claims and causes of action and because the notice of claim for malicious prosecution did not accrue until the plaintiff's acquittal and therefore was timely as to that claim.

Legal Issues Presented

  1. Whether the notice of claim was timely as to the plaintiff's malicious prosecution claim, given that malicious prosecution does not accrue until termination in the plaintiff's favor (here, the acquittal in January 1980).
  2. Whether an omnibus summary judgment motion that does not distinguish among multiple claims or causes of action is a proper basis for dismissal.
  3. Whether a notice of claim requirement applies as a condition precedent to tort actions against individual transit officers as well as against the Transit Authority.

Arguments of the Parties

Appellants (New York City Transit Authority and individual defendants)

  • Moved for summary judgment dismissing the complaint on the ground that the plaintiff failed to serve a timely notice of claim — the notice of claim was served more than 90 days after the June 1979 incident.

Respondent (Plaintiff)

  • Substantially conceded that the notice of claim was untimely as to the assault, false arrest and false imprisonment claims.
  • Contended (implicitly or by the court's treatment) that the malicious prosecution claim did not accrue until the plaintiff's acquittal in January 1980, and thus the notice of claim was timely as to malicious prosecution.
  • Requested that any dismissal be directed only as to the Transit Authority and not as to the individual officers.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
McElveen v. Police Dept., 70 A.D.2d 858 Supports the proposition that a malicious prosecution claim accrues upon termination favorable to the plaintiff (i.e., after dismissal/acquittal), affecting notice-of-claim timeliness. The court cited McElveen to support treating the malicious prosecution notice as timely because the claim accrued only at the plaintiff's January 1980 acquittal.
Diemer v. Diemer, 8 N.Y.2d 206 (cited as "cf.") Referenced for comparison or related authority (court cites it with "cf." in the opinion). The court cited Diemer by way of comparison; the opinion does not elaborate further on its specific application beyond the citation.
Colena v. City of New York, 68 A.D.2d 898, 900 Contains a contrary approach regarding notice-of-claim timeliness as applied in similar circumstances. The court declined to follow Colena to the extent it would require a contrary result, stating that following Colena would "exalt form over substance."

Court's Reasoning and Analysis

The court's analysis proceeded from two interrelated procedural and accrual considerations.

  1. On the procedural posture of the Special Term motion: Special Term denied the defendants' summary judgment motion in part because it was an omnibus motion that failed to distinguish among the various claims or causes of action. The court accepted that procedural ground for denial: an undifferentiated omnibus motion does not adequately address discrete claims requiring separate analysis.
  2. On the accrual and timeliness issue: the court recognized that malicious prosecution is a cause of action that cannot accrue until the criminal proceedings terminate in the plaintiff's favor. Because the plaintiff was acquitted in January 1980, the malicious prosecution claim did not accrue until that time. Accordingly, a notice of claim served after that date but within the applicable statutory period would be timely as to malicious prosecution even though the underlying arrest and assault occurred in June 1979.
  3. The court noted that the plaintiff had essentially conceded that notices were untimely as to the assault, false arrest and false imprisonment claims; the remaining live accrual question concerned malicious prosecution.
  4. The court addressed conflicting authority: it relied on McElveen (and cited Diemer by comparison) to support deeming the malicious prosecution notice timely, and expressly declined to follow Colena insofar as Colena would produce a contrary result — characterizing adherence to Colena as elevating form over substance.
  5. Finally, the court explained that service of a notice of claim is a condition precedent to commencing a tort action against both the Transit Authority and the individual officers, citing Public Authorities Law § 1212 and General Municipal Law § 50-e. Thus, any deficiency in notice would affect actions against the individual officers as well as the Authority.

Holding and Implications

Holding: The court treated the malicious prosecution claim as having accrued only upon the plaintiff's January 1980 acquittal and therefore the notice of claim as to malicious prosecution was deemed timely. The court also declined to follow Colena v. City of New York insofar as that case would compel a contrary result. Additionally, the court confirmed that service of a notice of claim is a condition precedent to tort actions against both the Transit Authority and the individual officers (citing Public Authorities Law § 1212 and General Municipal Law § 50-e).

Implications:

  • The direct effect on the parties is that the plaintiff's malicious prosecution claim survives the timeliness attack because it accrued at the January 1980 acquittal; by contrast, the plaintiff conceded the assault, false arrest and false imprisonment claims were untimely.
  • The court's refusal to follow Colena indicates the panel's unwillingness to apply that contrary approach in this case; beyond that refusal the opinion does not announce any broad new rule or purport to establish a sweeping precedent beyond the resolution of these issues.
  • No additional remedies or dispositions are described in the opinion excerpt; the opinion emphasizes technical and procedural considerations (omnibus motions, accrual rules, and statutory notice prerequisites) as dispositive of the timeliness inquiry presented.

Concurrence: Kupferman, J.P., Ross, Lynch, Kassal and Rosenberger, JJ., concurred.

JORDAN FERRICK, Respondent, v. CITY OF NEW YORK, Respondent, and NEW YORK CITY TRANSIT AUTHORITY et al., Appellants.

The underlying action, seeking to recover damages, arises out of an incident in June 1979, when the plaintiff was allegedly arrested and assaulted by two transit police officers in a subway station at 42nd Street and Lexington Avenue. In January 1980, the plaintiff was acquitted after a jury trial of charges of disorderly conduct and resisting arrest.

In June 1980, the action was commenced. In January 1983, the Transit Authority and the individual defendants moved for summary judgment dismissing the complaint on the ground that a timely notice of claim was not served, the notice of claim having been served over 90 days after the incident, in 1979.

The court, at Special Term, denied the motion to dismiss on the ground that it was an omnibus motion and did not distinguish among the various claims or causes of action and that the notice of claim for malicious prosecution was timely, inasmuch as that claim did not accrue until dismissal of the charges against the plaintiff.

Of course, there was no prejudice to the Transit Authority with respect to the notice of claim, and so we deal merely with the technical question.

The plaintiff has substantially conceded that the notice of claim was untimely as to the assault, false arrest and false imprisonment claims. While the claim for malicious prosecution could not accrue until after the acquittal in January 1980, it was implicit in this situation and, therefore, should be deemed timely. ( See, McElveen v. Police Dept., 70 A.D.2d 858; cf. Diemer v. Diemer, 8 N.Y.2d 206.) To the extent that Colena v. City of New York ( 68 A.D.2d 898, 900) is to the contrary, we believe it would exalt form over substance and, therefore, do not follow it.

The plaintiff asked that insofar as we may dismiss, it be directed only as to the Transit Authority and not as to the individual officers. However, service of a notice of claim is a condition precedent to the commencement of a tort action against them as well as the Transit Authority. (Public Authorities Law § 1212; General Municipal Law § 50-e.)

Concur — Kupferman, J.P., Ross, Lynch, Kassal and Rosenberger, JJ.

Use AI to get other relevant cases.

Comments

FERRICK v. CITY OF NEW YORK
(May 23, 1985)