The provisions of the contract between the contractor and the township in this case on the matter of extra work, replacements, alterations, and damages, being entirely clear and reasonable, defining as they do the rights and liabilities of the parties to the contract with the especial purpose of safeguarding the township against too high an expenditure and against possible controversies, the contractor may not introduce parol testimony to vary them.
PER CURIAM.
The decree appealed from will be affirmed, for the reasons expressed in the opinion delivered by Vice-Chancellor Fielder in the court of chancery.
For affirmance — THE CHIEF-JUSTICE, TRENCHARD, PARKER, CASE, BODINE, DONGES, HEHER, PERSKIE, VAN BUSKIRK, KAYS, HETFIELD, DEAR, WELLS, DILL, JJ. 14.
For reversal — None.