Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Attorney(S)
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Attorney(S)
Judges
Smart Summary

Factual and Procedural Background

The defendant was the original contractor for the construction of a large building and is referred to as "the owner" in the subcontract. W.L. Clark and Company, as subcontractors, agreed to perform the mason work for $73,000 under the supervision of an architect. Article 5 of the subcontract authorized the architect to certify expenses incurred by the owner in completing the work should the subcontractor default. Clark and Company ceased work on April 5, 1901, and the defendant, following the architect's direction, completed the work to the architect's satisfaction by September 1, 1901. The architect certified that the expenses incurred in completion exceeded the unpaid balance by $4,411.14, including a $5,300 commission claimed by the defendant for supervisory services. The plaintiff, as assignee of the subcontract, sued to recover the balance due. The case was initially heard in the Municipal Court and then on appeal in the Superior Court, where the judge ruled for the defendant, upholding the architect’s certificate as conclusive. The plaintiff alleged exceptions and the case was argued before the Supreme Judicial Court of Massachusetts.

Legal Issues Presented

  1. Whether the architect’s certificate, including the allowance of a $5,300 commission for supervisory services, was within the scope of the contract and thus conclusive upon the parties.
  2. Whether the architect had authority under Article 5 of the subcontract to audit and certify expenses claimed as commissions or supervisory fees.
  3. Whether the court could revise or disregard the architect’s certificate absent fraud or palpable mistake.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Audette v. L' Union St. Joseph, 178 Mass. 113 Enforcement of certificates by an arbitrator absent fraud or palpable mistake. Supported the binding nature of the architect’s certificate under the contract.
Flint v. Gibson, 106 Mass. 391 Similar principle regarding arbitration and conclusive certificates. Reinforced the validity of the architect’s certification as final.
Palmer v. Clark, 106 Mass. 378 Authority of arbitrators and binding effect of their awards. Used to affirm the conclusive effect of the architect’s certificate.
Robbins v. Clark, 129 Mass. 145 Arbitration and finality of awards absent fraud. Supported the court’s deference to the architect’s certification.
White v. Middlesex Railroad, 135 Mass. 216, 220 Binding effect of arbitrator’s determinations. Confirmed the finality of the architect’s certificate.
Mittenthal v. Mascagni, 183 Mass. 19, 23 Limits on court revision of arbitrator’s awards. Applied to uphold the architect’s certificate in the absence of fraud.
New England Trust Co. v. Abbott, 162 Mass. 148, 154 Authority of arbitrators and conclusiveness of their awards. Supported the architect’s conclusive certification.
Norcross v. Wyman, 187 Mass. 25 Finality of arbitrator’s decisions unless fraud or mistake is shown. Used to uphold the architect’s certificate.
Martinsburg Potomac Railroad v. March, 114 U.S. 549 Federal precedent on arbitration and conclusive awards. Supported the principle that certificates are binding absent fraud.
Sharpe v. San Paulo Railway, L.R. 8 Ch. 597, 607 Arbitration principles regarding finality of awards. Confirmed the binding nature of the architect’s certificate.
Korf v. Lull, 70 Ill. 420 Authority and conclusiveness of arbitrator’s decisions. Reinforced the finality of the architect’s certification.
Dingley v. Greene, 54 Cal. 333 Arbitration awards binding absent fraud or mistake. Supported the court’s refusal to revise the architect’s certificate.

Court's Reasoning and Analysis

The court analyzed the subcontract’s Article 5, which empowered the architect to audit and certify expenses incurred by the owner in completing the work after the subcontractor default. The court distinguished this provision from those that attempt to oust courts of jurisdiction entirely, recognizing it as a valid delegation of authority to the architect to make conclusive determinations on specified expenses. The court held that the architect’s certificate is binding absent fraud or palpable mistake, a standard supported by multiple precedents.

Regarding the $5,300 commission claimed by the defendant for supervisory services, the court reasoned that this claim fell within the class of expenses contemplated by the contract as subject to the architect’s certification. The architect had jurisdiction to allow or disallow such claims, and the court declined to substitute its judgment for that of the architect, as the certificate was made in good faith and without fraud. The court expressly refrained from assessing whether the amount allowed was reasonable, emphasizing the finality of the architect’s decision on such matters.

The court also noted that expenses not related to completing the contract were outside the architect’s auditing authority and thus subject to court determination, but these were not at issue.

Holding and Implications

Exceptions overruled.

The court held that the architect’s certificate, including the allowance of the $5,300 commission for supervisory services, was within the scope of the subcontract and conclusive upon the parties. Consequently, the court affirmed the judgment for the defendant, upholding the finality of the architect’s certification absent fraud or palpable mistake. This decision directly affects the parties by enforcing the contractual arbitration clause and confirms that the court will not revise such certifications when made in good faith. No new precedent beyond the application of existing arbitration principles was established.

CHARLES M. WHITE vs. EDWARD A. ABBOTT.

Contract, Building contracts. Architect. Arbitrament and Award. If a contract for the mason work of a building, between a subcontractor, called in the contract "the contractor," and the principal contractor for the construction of the building, called in the contract "the owner," provides that if the architect shall certify that the contractor has refused, neglected or failed to perform the work called for by the contract the owner may terminate the employment of the contractor and enter the premises and complete the work, and that in such case the contractor shall not be entitled to receive any further payment under the contract until the work shall be wholly finished, at which time if the unpaid balance to be paid under the contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor, but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner, and that expenses "either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties," and if the subcontractor ceases to furnish labor and materials upon the building and the principal contractor, called the owner, by direction of the architect enters upon the premises and completes the work to the satisfaction of the architect, and the architect makes a certificate that he has audited and certified the expense, and includes therein a sum of $5,000 claimed as a commission by the principal contractor for his services in making the arrangements and supervising the work, this as matter of law is an expense within the meaning of the contract and the architect's certificate upon it is conclusive.

KNOWLTON, C.J.

The defendant was the original contractor for the construction of a large building, and in the subcontract hereafter described is called "the owner." W.L. Clark and Company, as subcontractors, agreed with him to do the mason work for the sum of $73,000, under the direction and superintendence of one Safford as architect. The fifth article of this subcontract is as follows: "Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty, after two days' written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work comprehended under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor, but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architects, whose certificate thereof shall be conclusive upon the parties." The plaintiff sues as assignee of this subcontract, to recover the balance due thereon.

On April 5, 1901, Clark and Company ceased to furnish labor and materials upon the building, and the defendant, by the direction of the architect, entered upon the premises to complete the work. This was done to the satisfaction of the architect, about September 1, 1901. On January 10, 1902, the architect made a certificate, under the fifth clause of the contract, that he had audited and certified the expense incurred by "the owner" in completing the contract. According to this certificate, this expense of completion exceeded the unpaid balance by $4,411.14. One item of expense included in the certificate was $5,300, claimed as a commission and allowed to the defendant for his services in making the arrangements and supervising the work. The principal question is whether this item should be reduced, or stricken out, or allowed to stand.

The validity of the provision contained in Article 5, authorizing the architect to certify the amount of expense incurred by the owner, has not been questioned in the argument before us, and we are of opinion that it is not like those agreements which cannot be enforced because they purport to oust the courts of jurisdiction by submitting the determination of all rights under the contract to an arbitrator, but is one of a different class. Audette v. L' Union St. Joseph, 178 Mass. 113. Flint v. Gibson, 106 Mass. 391. Palmer v. Clark, 106 Mass. 378. Robbins v. Clark, 129 Mass. 145. White v. Middlesex Railroad, 135 Mass. 216, 220. Mittenthal v. Mascagni, 183 Mass. 19, 23. New England Trust Co. v. Abbott, 162 Mass. 148, 154. Norcross v. Wyman, 187 Mass. 25. A certificate made under such a contract, in the absence of fraud, or of such palpable mistake as prevents the arbitrator from the exercise of his judgment upon the matters submitted to him, is binding upon the parties. See cases above cited. Also, Martinsburg Potomac Railroad v. March, 114 U.S. 549; Sharpe v. San Paulo Railway, L.R. 8 Ch. 597, 607; Korf v. Lull, 70 Ill. 420; Dingley v. Greene, 54 Cal. 333. In the present case, both the auditor and the judge before whom the case was tried in the Superior Court, have found that the "architect and the defendant acted in good faith without fraud, in all that pertained to the presentation of the defendant's claim, auditing and certifying the same." The judge also ruled that "as to all expense incurred for the purpose of completing the contract, the decision of the architect, acting in good faith, without fraud on his part or on the part of the defendant, and his certificate thereof are conclusive, and not subject to revision by the court."

The plaintiff contends that the allowance for services was not expense within the meaning of the contract, and that therefore the architect could not certify it. Of course he could not create for himself jurisdiction, and he had no authority to allow as expense a claim which was outside the class which he was appointed to consider. Claims were within his jurisdiction for examination if they were of the class intended to be submitted to him, upon which his certificate was to be conclusive. We are of opinion that within the class designated, which fairly may be called claims for expense under the contract, he could make a certificate that would be conclusive. We are of opinion that the defendant's claim of a compensation for services belonged to the class of claims for expenses to be passed upon by him. We therefore hold, as matter of law, that it was within his jurisdiction, to be allowed or disallowed, in whole or in part, under his appointment. We do not pass upon the question whether the sum of $5,300 allowed by the architect was more than properly should be allowed for overseeing the work, because the architect's conclusion upon the amount is final.

Because it was within the class of claims which he was authorized to audit and certify, his certificate is conclusive and this court has no power to disregard it. Other claims, which were disallowed by the Superior Court as not within his authority to audit and certify, we have no occasion to consider.

Exceptions overruled.

Use AI to get other relevant cases.

Comments

WHITE v. ABBOTT
(May 18, 1905)