Loading..
AMICUS AI
Citation Codes
Neutral Citations
2025 INSC 1457
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • the Arbitration Act itself
  • Section 34 Arbitration and Conciliation Act, 1996
  • Section 5 of A&C Act (Arbitration and Conciliation Act)
  • Section(s) 34 and 37 of the A&C Act
  • Section 34(2)(b)(ii) of A&C Act
  • Section 70 of the Contract Act, 1872
  • Arbitration Act, Section 28(3)
  • Section 31(7)(b) of the A&C Act
  • Section 24 of the Act
  • Section 34 and 37 of the A&C Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 31(7)(a) of the A&C Act
  • section 34(2)(b)(ii), A&C Act
  • The Arbitration Act (with consideration of the amendment act of 2015)
  • Section 11(6) of the A&C Act
  • Arbitration and Conciliation (Amendment) Act, section 34
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • section 37, A&C Act
  • Section 34 of the Act 3 (2022) 1 SCC 131 4 (2019) 4 SCC 163
  • Section 34, Section 37 of the A&C Act
  • Section 19 of the A&C Act
  • Section 28(3) of the Act
  • Section 37 of the Arbitration and Conciliation Act, 1996
  • Section 34 and section 37 of the Act
  • section 34, A&C Act
  • section 37 of A&C Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2025 INSC 1457
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • the Arbitration Act itself
  • Section 34 Arbitration and Conciliation Act, 1996
  • Section 5 of A&C Act (Arbitration and Conciliation Act)
  • Section(s) 34 and 37 of the A&C Act
  • Section 34(2)(b)(ii) of A&C Act
  • Section 70 of the Contract Act, 1872
  • Arbitration Act, Section 28(3)
  • Section 31(7)(b) of the A&C Act
  • Section 24 of the Act
  • Section 34 and 37 of the A&C Act
  • Section 5, Subsection 2 of the 1983 Income Tax Act
  • Section 31(7)(a) of the A&C Act
  • section 34(2)(b)(ii), A&C Act
  • The Arbitration Act (with consideration of the amendment act of 2015)
  • Section 11(6) of the A&C Act
  • Arbitration and Conciliation (Amendment) Act, section 34
  • Section 34 of the Arbitration and Conciliation Act, 1996
  • section 37, A&C Act
  • Section 34 of the Act 3 (2022) 1 SCC 131 4 (2019) 4 SCC 163
  • Section 34, Section 37 of the A&C Act
  • Section 19 of the A&C Act
  • Section 28(3) of the Act
  • Section 37 of the Arbitration and Conciliation Act, 1996
  • Section 34 and section 37 of the Act
  • section 34, A&C Act
  • section 37 of A&C Act
Smart Summary

Supreme Court of India – Civil Appellate Jurisdiction

Ramesh Kumar Jain v. Bharat Aluminium Company Limited (BALCO)

Factual and Procedural Background

The respondent, Bharat Aluminium Company Limited (BALCO), invited a tender for mining and transporting 3,70,000 metric tons (MT) of bauxite from Mainpat mines to its Korba Alumina plant. The appellant, Ramesh Kumar Jain, submitted the lowest bid at Rs. 697 per MT. After negotiations, the parties entered into an agreement on 11.12.1999 for mining and transporting 2,22,000 MT of bauxite at Rs. 634.20 per MT. The work was to be completed within 18 months (up to May 2001), later extended to September 2001.

After completion of the agreed quantity, BALCO, by letter dated 05.01.2002, requested the appellant to continue mining and transportation work. The rate for this extra work was to be decided later in consultation with the appellant. The appellant continued work and supplied an additional 1,95,000 MT of bauxite between 16.06.2001 and 31.03.2002.

Disputes subsequently arose regarding payment for this extra work and other claims, leading to invocation of the arbitration clause. The appellant approached the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996 (“A&C Act”) for appointment of an arbitrator. By order dated 12.04.2007 in MCC No. 192 of 2006, the High Court referred the dispute to arbitration in terms of clause J of the agreement.

The sole arbitrator framed 13 issues and, after considering pleadings, evidence and arguments, passed an award on 15.07.2012 in favour of the appellant. The main monetary components of the award (principal plus pre-award interest) were:

  • Claim for extra work of 1,95,000 MT: Rs. 31,85,000 (including interest @10% p.a. from 31.03.2001 till August 2007).
  • Claim for restriction in truck quantity resulting in extra transportation cost: Rs. 1,23,06,058 (including interest @10% p.a. from March 2002 till July 2007).
  • Claim for idle manpower and machinery during a 67‑day strike period: Rs. 71,36,568 (including interest @10% p.a. from 13.03.2001 till 25.08.2007).
  • Interest on delayed payment of the 15th running account bill: Rs. 8,30,157 (interest @18% p.a. for 90 days and thereafter from 01.06.2001 to 31.08.2007).

The total of these claims came to Rs. 2,34,57,783. On this sum, the arbitrator awarded further interest @12% p.a. from 01.09.2007 to 15.07.2012, amounting to Rs. 1,37,22,801, bringing the total award to Rs. 3,71,80,584, together with statutory post-award interest under Section 31(7)(b) of the A&C Act until payment.

BALCO challenged the award under Section 34 of the A&C Act before the Commercial Court, Raipur (MJC No. 33/16). The Commercial Court, by judgment and order dated 02.01.2017, held that the arbitrator had rendered well‑reasoned findings on each claim after considering oral and documentary evidence, and that the award was not arbitrary or capricious, particularly in light of Section 34(2)(b)(ii). It therefore dismissed the Section 34 petition and affirmed the award.

Aggrieved, BALCO filed an appeal under Section 37 of the A&C Act before the High Court of Chhattisgarh (ARBA No. 05 of 2017). By judgment dated 03.05.2023, the High Court allowed the appeal and set aside the arbitral award as well as the Commercial Court’s order, principally on the ground of “patent illegality”.

The appellant (original claimant) then approached the Supreme Court in appeal (arising out of SLP (C) No. 14529 of 2023). The Supreme Court granted leave and proceeded to examine the correctness of the High Court’s judgment.

Legal Issues Presented

  1. Whether interference with the arbitral award by the High Court under Section 37 of the Arbitration and Conciliation Act, 1996 on the ground of “patent illegality” is sustainable when the award has already been affirmed under Section 34 of the Act.

Arguments of the Parties

Appellant’s Arguments

  • The High Court exceeded its limited jurisdiction under Section 37 A&C Act by re‑appreciating facts and evidence and acting as if it were a regular appellate court, contrary to the narrow scope of scrutiny envisaged by the Act. Reliance was placed on Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation.
  • Under Sections 34 and 37, courts do not sit in appeal over arbitral awards and cannot reassess the merits, legality or correctness of factual findings unless the specific statutory grounds are met. Reliance was placed on MMTC Limited v. Vedanta Limited.
  • The arbitral tribunal had given detailed, reasoned findings on each claim, supported by evidence and proper justifications. The Commercial Court had dismissed the Section 34 application as being “without substance”. The High Court could not set aside the award merely because it preferred a different interpretation of the facts under the label of “patent illegality”.
  • Interpretation of contractual terms is primarily for the arbitrator; even an erroneous interpretation does not justify interference under Section 34. Reliance was placed on Hindustan Construction Company Ltd. v. NHAI, MMTC Ltd. (supra), and Associate Builders v. Delhi Development Authority.
  • The arbitral tribunal is “master of the evidence”, and its fact findings, if based on the record, are not to be scrutinized as if in appeal. Reliance was placed on Parsa Kente Collieries Ltd. v. RRVUN Ltd.
  • Where there is material to show that damages have been suffered, but the material does not provide granular detail, the arbitrator is allowed leeway to employ honest guesswork or a rough‑and‑ready method to quantify damages. Reliance was placed on Construction and Design Services v. Delhi Development Authority.
  • On the extra work from July 2001 to March 2002, the High Court erred in assuming that the earlier rate applied. For that later period, BALCO had floated fresh tenders (subsequently withdrawn), and though the appellant was the lowest bidder, BALCO simply requested continuation of work without agreeing on rates—an admitted position evident from letters dated 15.08.2001 and 05.01.2002. Therefore, the arbitrator correctly treated the rate for this extra work as undecided.
  • Regarding the claim for idle machinery and manpower during a strike at BALCO’s plant, the arbitrator considered that the strike was an issue between BALCO’s management and workers, there was no force majeure clause in the contract, and the strike was not an “act of God”. Therefore, the appellant was entitled to compensation for idle resources.

Respondent’s Arguments

  • The contract contained no clause permitting increase in rates except the diesel variation clause. From the outset, the appellant persistently raised unjustified demands for price increases by comparing its contract with a third‑party contract. By letter dated 25.03.2000, BALCO had clarified that rates paid to third parties were irrelevant to the appellant’s contract.
  • The contract required the contractor to inspect the work, site and surrounding area and consider all circumstances before submitting the tender. Nonetheless, the arbitrator, after holding that neither party had agreed to a new rate for the extra work, arbitrarily “guessed” that prices had risen by Rs. 10 per MT without evidentiary support. Additional work was executed at the existing rate; BALCO paid Rs. 657 per MT (including Rs. 23 diesel escalation) throughout, which the appellant accepted without challenge, implying an agreed rate.
  • On the alleged extra distance/route, there was no prescribed route map in the contract. The appellant’s assertion that it was compelled to use a longer route incurring an additional 50 km, for which BALCO was liable under the diesel variation clause, was termed baseless. Clause 2(a) (diesel variation clause) was said to depend on diesel rates and the “average” for the entire contract, not on distance or specific routes chosen by the contractor.
  • Regarding idle machinery and manpower, the arbitrator ignored a specific bar under clause 6 of the contract and, instead of giving a simple, literal meaning to the clause, went beyond the contract’s terms. The arbitrator’s approach was termed “hyper‑technical” and impermissible in contractual interpretation.
  • The arbitrator had acknowledged that the appellant submitted no documentary evidence to substantiate losses due to idle machinery and manpower, yet granted 75% of the claimed amount. The High Court rightly found no evidence that mining had actually come to a standstill or that specific expenses were incurred.
  • The appellant continued to execute 1,95,000 MT from 16.06.2001 to 31.03.2002 and was consistently paid Rs. 657 per MT (inclusive of diesel escalation). This, according to BALCO, showed implied agreement on the existing rate. The appellant’s alleged expectation of Rs. 697 per MT was unfounded, especially since a tender dated 01.01.2001 had been cancelled due to unacceptably high bids.
  • No documentary evidence showed any penalty imposed by BALCO on carrying capacity of trucks. The arbitrator wrongly allowed the claim for extra transportation cost on the basis of an unsubstantiated tabular statement whose factual and numerical basis was unexplained.
  • The contract did not permit the arbitrator to determine rates between the parties or apply quantum meruit to fix a new rate. Awarding an additional Rs. 10 per MT was alleged to be against the “most basic notions of morality and justice” and a rewriting of the contract. Reliance was placed on SsangYong Engineering v. NHAI, MTNL v. TATA Communications, and Alopi Parshad v. Union of India.
  • By awarding above the contractual rate of Rs. 634.20 per MT and treating the extension as if on changed terms, the arbitrator effectively rewrote the contract. Reliance was placed on Satyanarayan Construction Company v. Union of India.
  • The arbitrator’s fixation of Rs. 10 per MT as “reasonable compensation” was said to rest on pure guesswork without evidentiary backing. Reliance was placed on Kailash Nath Associates v. DDA to argue that such guesswork amounts to patent illegality.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
ONGC Limited v. Saw Pipes Limited, (2003) 5 SCC 705 Expanded “public policy of India” under Section 34(2)(b)(ii) A&C Act to include: (a) contravention of fundamental policy of Indian law; (b) interest of India; (c) justice or morality; and (d) “patent illegality”. Provided illustrations of “patent illegality”, including awards contrary to contract terms or statutory provisions. Cited to trace the origin of “patent illegality” as a judicially developed sub‑ground under public policy and to illustrate when an award can be set aside for violating Section 28(2)–(3) or other substantive/statutory provisions.
Associate Builders v. Delhi Development Authority, 2014 SCC OnLine SC 937; (2015) 3 SCC 49 Classified “patent illegality” into: (i) contravention of substantive law of India; (ii) contravention of the Arbitration Act; and (iii) contravention of Section 28(3) (duty to decide in accordance with contract and trade usages). Held that reasonable construction of contract by arbitrator cannot be interfered with unless no fair‑minded person could so construe it. Relied on in discussing limits of “patent illegality” and in holding that the High Court could not substitute its own reasonable interpretation of the contract for that of the arbitrator under Sections 34 and 37.
SsangYong Engg. & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 13 Post‑2015 amendment exposition of “patent illegality” under Section 34(2A); described it as a glaring illegality going to the root of the award, including decisions beyond scope of arbitration, in conflict with substantive law or the Act, or against contractual terms, and awards that are irrational or unreasoned on their face. Used to explain that patent illegality must be fundamental and apparent from the face of the award, and later to state that the High Court’s interference under Section 37, by re‑appreciating evidence and contract interpretation, was contrary to this settled standard.
MMTC Limited v. Vedanta Limited, (2019) 4 SCC 163 Held that interference with an order under Section 37 cannot travel beyond the restrictions in Section 34; courts do not sit in appeal over arbitral awards under these provisions. Applied to affirm that Section 37 confers only a limited appellate remedy, co‑extensive with Section 34, and that the High Court exceeded this limit by re‑examining facts and merits.
Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking, (2023) 9 SCC 85 Reiterated that the scope of appellate scrutiny under Section 37 is co‑extensive with parameters under Section 34 and does not enlarge the appellate court’s jurisdiction. Cited in reinforcing that Section 37 does not permit a broader review than Section 34 and that the High Court’s approach conflicted with this principle.
M/s Hindustan Construction Company Limited v. National Highways Authority of India, 2023 INSC 768 Observed that the standard for scrutinizing arbitral awards is “very narrow” and not equivalent to judicial review, and that reasoned awards, particularly those interpreting contractual terms, should not be interfered with lightly. Relied upon to stress that arbitral awards interpreting contracts, accompanied by reasons, attract a very limited scope of interference under Sections 34 and 37.
Hindustan Construction Company Ltd. v. NHAI, (2024) 2 SCC 613 Referenced for the proposition that interpretation of contractual provisions is primarily a matter for the arbitrator and that an error in interpretation is not, by itself, a ground for interference under Section 34. Employed (along with other precedents) to support the appellant’s contention that the High Court could not overturn the arbitrator’s contractual interpretation merely because another view was possible.
Larsen Air Conditioning and Refrigeration Company v. Union of India and Ors., (2023) 15 SCC 472 Held that the scope of interference in appeal under Section 37 is even narrower where the arbitral award has been upheld, or substantially upheld, under Section 34. Cited to emphasise that, given the Commercial Court had already affirmed the award under Section 34, the High Court’s room for interference under Section 37 was especially limited.
Punjab State Civil Supplies Corporation Limited & Anr. v. M/s Sanman Rice Mills & Ors., 2024 INSC 742 Held that even apparently unreasonable or non‑speaking awards do not warrant interference unless such unreasonableness violates public policy or the fundamental policy of Indian law; courts are not permitted to reappraise evidence merely to arrive at a more plausible view. Used to reinforce the proposition that courts cannot revisit evidence or substitute their own assessment simply because they might find another view more plausible than the arbitrator’s.
Batliboi Environmental Engineers Limited v. Hindustan Petroleum Corporation Limited & Anr., 2023 INSC 850 Recognized that arbitrators are generally the ultimate masters of the quality and quantity of evidence, and that even an award based on little or no evidence may not automatically be invalid if it reflects equitable and fair decision‑making. Cited to support the view that arbitral decisions, including those influenced by equity, should not be overridden under Sections 34 and 37 merely on the ground that the court considers the arbitrator’s approach arbitrary or capricious.
Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation, (2022) 1 SCC 131 Referred to for the limited scope of judicial interference with arbitral awards and the narrow standard applicable under Section 37. Invoked by the appellant to contend that the High Court’s extensive re‑appreciation of evidence exceeded its statutory remit.
Parsa Kente Collieries Ltd. v. RRVUN Ltd., (2019) 7 SCC 236 Affirmed that arbitral tribunals are masters of evidence and of fact finding, and courts should not scrutinize such findings as if sitting in appeal. Used by the appellant, and accepted in the Court’s analysis, to underline that factual determinations by the arbitrator should be respected where based on the record.
Construction and Design Services v. Delhi Development Authority, (2015) 14 SCC 263 Recognized that when there is evidence that damages have been suffered but not enough to permit precise quantification, an arbitrator may resort to honest guesswork or a rough‑and‑ready method to quantify damages. Applied to justify the arbitrator’s use of approximation and percentage‑based assessments in quantifying certain heads of claim, provided they are grounded in some evidence.
Mahanagar Telephone Nigam Limited v. Tata Communications Limited, (2019) 5 SCC 341 Discussed limits of applying quantum meruit, indicating it applies where the price for work has not been fixed in the contract and the contract does not fully govern the field. The High Court relied on this case to hold that the arbitrator exceeded jurisdiction by applying quantum meruit where a contractual rate allegedly existed. The Supreme Court held that this reliance was misplaced because, in the present case, the price for the extra work was consciously left open and not fixed in the contract, so the arbitrator was addressing a contractual vacuum rather than rewriting agreed terms.
Kailash Nath Associates v. Delhi Development Authority and Anr., (2015) 4 SCC 136 Invoked to support the proposition that an arbitrator cannot rewrite an award or go beyond the terms of the contract, and that findings without evidentiary basis can amount to patent illegality. The High Court used this to brand parts of the award as patent illegality due to alleged guesswork and lack of evidence. The respondent similarly relied on it to attack the Rs. 10 per MT award as unsupported guesswork. The Supreme Court, however, found that the arbitrator’s findings were based on evidence and within contractual limits.
Hindustan Construction Company Ltd. v. NHAI (as cited with MMTC and Associate Builders) Cited to reiterate that interpretation of contract is for the arbitrator, and errors in such interpretation do not ordinarily justify setting aside an award under Section 34. Reinforced the Court’s conclusion that the High Court could not interfere merely because it took a different view on contractual interpretation.
Alopi Parshad v. Union of India, AIR 1960 SC 588 Cited by the respondent in support of the contention that the award was against basic notions of morality and justice and that the arbitrator could not alter contractual rates. No independent detailed discussion of this precedent’s reasoning appears; it is noted as part of the respondent’s supporting authorities.
Satyanarayan Construction Company v. Union of India, (2011) 15 SCC 101 Relied upon by the respondent to contend that an arbitrator cannot rewrite the contract, particularly with respect to fixed rates. Cited in the context of arguing that the arbitrator was bound by the contractual rate of Rs. 634.20 per MT and could not award an additional Rs. 10 per MT.
MTNL v. Tata Communications (re‑cited), (2019) 5 SCC 341 Again invoked by the respondent to argue that applying quantum meruit to fix rates was contrary to the contract and basic notions of justice. The Supreme Court ultimately distinguished this precedent on the facts, reiterating that in the present case the contract left the rate for extra work unfinalized.

Court’s Reasoning and Analysis

The Court began by reaffirming the Arbitration and Conciliation Act, 1996 as a statute aimed at providing speedy, cost‑effective and efficacious dispute resolution with minimal judicial intervention, a policy reinforced by Section 5, which restricts court interference to situations expressly provided in Part I of the Act.

On Section 34, the Court noted that it confers a narrow supervisory jurisdiction restricted to listed grounds under sub‑sections (2) and (3), including violation of public policy, fundamental policy of Indian law, and basic notions of morality or justice. Following ONGC v. Saw Pipes, it reiterated that “patent illegality” is an additional ground, but that courts under Section 34 do not sit in appeal over arbitral awards and are not to examine the correctness of factual or legal findings unless they fall within the statutorily prescribed grounds.

On Section 37, the Court emphasized that it merely provides a limited appellate remedy against orders under Section 34 and that its scope is co‑extensive with Section 34, not broader. Citing MMTC v. Vedanta and Konkan Railway v. Chenab Bridge Project Undertaking, the Court stressed that an appeal under Section 37 cannot circumvent the restrictions of Section 34. Referring to Hindustan Construction Company Ltd. v. NHAI and Larsen Air Conditioning and Refrigeration Company v. Union of India, it underscored that scrutiny is “very narrow”, especially when the award has already been upheld under Section 34, and that reasoned awards interpreting contracts should not be interfered with lightly.

The Court further cited Punjab State Civil Supplies Corporation Ltd. v. Sanman Rice Mills and Batliboi Environmental Engineers Ltd. v. HPCL to reiterate that even apparently unreasonable or non‑speaking awards are not to be interfered with unless they conflict with public policy or fundamental policy; courts are not permitted to reappraise evidence simply to take a different view. Arbitrators are the masters of fact and evidence, and decisions, even when based on limited evidence or equity, may still be valid.

The Court then examined the development and current contours of “patent illegality”. It recalled that before the 2015 amendment, ONGC v. Saw Pipes broadened “public policy of India” to include patent illegality and gave examples where awards contrary to contract, statutes, or basic procedural protections must be set aside. Associate Builders v. DDA refined patent illegality into three categories: (i) contravention of substantive law; (ii) contravention of the Arbitration Act; and (iii) violation of Section 28(3) (failure to decide in accordance with contract and trade usages), while clarifying that a reasonable contractual construction by an arbitrator cannot be interfered with unless no fair‑minded person could so construe it.

The 2015 amendment, inserting Section 34(2A) and its proviso, statutorily recognized patent illegality as an independent ground for domestic awards but made clear that an award “shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence”. The Court highlighted that the legislative intent was to avoid excessive interference: factual errors or divergent interpretations do not automatically amount to patent illegality; the illegality must go to the heart of the award’s validity, for example where a binding precedent or clear contractual prohibition is ignored, or where findings are based on no evidence, rendering them perverse.

Building on SsangYong Engg. & Construction Co. Ltd. v. NHAI, the Court reiterated that patent illegality denotes glaring, evident defects: awards deciding matters outside the contract or submission; awards contradicting substantive law or the Act; awards against express contractual terms; or awards so irrational or unreasoned that the error is apparent on the face of the award. It emphasized that “no evidence” means truly an absence of any relevant evidence, not merely that evidence is scant or of low probative value. If some evidence exists—even a single witness or some documents—supporting the arbitrator’s conclusions, courts cannot brand the award as patently illegal simply because they would have weighed that evidence differently.

The Court then addressed the arbitrator’s obligation to act in accordance with the contract. While acknowledging that an arbitrator cannot award anything contrary to express contractual stipulations, it clarified that this does not prevent arbitrators from implying terms or filling gaps where the contract is silent, provided they do not contradict express terms. As an example, if a contract is silent on interest for delayed payments, an award of reasonable interest is permissible and consistent with Section 31(7)(a) A&C Act. Likewise, where a party performs extra work at the other’s request and the contract is silent on compensation for such work, the arbitrator may invoke restitutionary principles without violating the contract.

To address cases where contracts are silent but one party has non‑gratuitously conferred a benefit on another, the Court invoked Section 70 of the Indian Contract Act, 1872. It explained that Section 70 creates a statutory, contract‑independent obligation to compensate where a person lawfully does or delivers something for another, not intending it to be gratuitous, and the other enjoys that benefit. The Court observed that this provision corresponds to quantum meruit or unjust enrichment principles and may be applied by arbitral tribunals when its conditions are met.

With these principles in mind, the Court deliberately refrained from revisiting every factual contention, noting that most submissions were factual and that arbitrators are the primary judges of fact. It framed the central inquiry as whether any part of the award was based on no evidence or was contrary to the contract, so as to qualify as patent illegality.

Upon a detailed reading of the arbitral award dated 15.07.2012, the Court found that the arbitrator had relied on both oral and documentary evidence, including testimonies of the appellant (R.K. Jain) and BALCO’s Assistant General Manager/Engineer‑in‑charge (A. Hussain) and various correspondence and affidavits. The arbitrator did not accept the appellant’s claims as “gospel truth”; instead, each claim was tested against the evidentiary record. Some claims were curtailed or denied (e.g., the claim under para 19.3 for removal of extra overburden was rejected), demonstrating a balanced and discriminating assessment rather than capricious acceptance.

Regarding the claim under para 19.2 (extra transportation cost due to restriction on truck capacity), the Court noted that the claim for Rs. 1,96,11,000 was supported by evidence that, even after a District Transport Officer’s order was stayed by the High Court, BALCO did not permit delivery at the earlier weight of 11 MT. This fact was found to be uncontroverted by BALCO. The arbitrator’s reliance on this and other evidence to partially uphold the claim could not be labelled as mere “guesswork”.

The Court observed that, where the appellant’s evidence was weak or incomplete, the arbitrator had approached quantification with caution, sometimes reducing the claim significantly and applying quantum meruit to strike a fair balance, or rejecting the claim entirely. For instance, in para 19.1 (extra work of 1,95,000 MT), the arbitrator, recognizing the evidence and the open nature of the rate, granted an additional Rs. 10 per MT rather than the full amount claimed. This comported with the permissible use of approximation discussed in Construction and Design Services v. DDA.

In assessing the High Court’s criticism that the award rested on “oral statements” and “guesswork”, the Supreme Court held that such criticism overlooked the evidentiary basis actually discussed in the award. The Court concluded that the award, read as a whole, did not reveal any findings that were arbitrary, capricious or based on no evidence, nor did it show any instance of the arbitrator acting beyond the contractual framework. Consequently, the High Court’s conclusion that the award suffered from patent illegality was found unsustainable.

On the specific issue of quantum meruit and alleged rewriting of the contract, the Court carefully examined the High Court’s reliance on Mahanagar Telephone Nigam Limited v. Tata Communications Limited. It noted that MTNL applies where the contract comprehensively governs the parties’ rights and the consideration for the relevant work is conclusively fixed. In contrast, in the present case, after the expiry of the original contractual period and quantity, the appellant continued to perform additional mining and transport of 1,95,000 MT at BALCO’s request under the letter dated 05.01.2002, which expressly left the rate “to be decided in due course” after consultation. That exercise of fixing the rate was never undertaken.

The Court held that, in such a situation, the arbitrator’s determination of a reasonable additional compensation of Rs. 10 per MT (increasing the operative rate from Rs. 634.20 to Rs. 644.20 per MT) did not amount to rewriting a fixed contractual rate. Instead, the arbitrator was filling a contractual vacuum and enforcing a restitutionary obligation under Section 70, to prevent unjust enrichment of BALCO from admitted extra work performed and accepted without a finalized rate. Therefore, the High Court’s characterisation of this as exceeding jurisdiction or rewriting the contract was rejected.

The Court further clarified that claims based on quantum meruit or unjust enrichment can be decided by an arbitrator where they fall within the scope of the reference, either expressly or by necessary implication. In cases like the present, where extra work is intimately connected with the performance of the contract, such claims are properly arbitrable. While awards under Section 70 must still be grounded in evidence of the benefit’s value or cost, tribunals have discretion to approximate a fair value where exact evidence is unavailable, so long as the figure is reasonable and not plucked “from thin air”.

In its final evaluative remarks, the Court held that the errors identified by the High Court—alleged lack of evidence, percentage‑based allowances, and approximations—did not, individually or collectively, rise to the level of patent illegality requiring annulment of the award. There was a discernible logical path and some evidentiary basis for each part of the award. The arbitrator’s reasoning represented a possible view a reasonable person could take, and the High Court had impermissibly re‑appreciated the evidence and substituted its own view. The High Court, moreover, applied a stricter standard of proof than arbitration law demands, overlooking that arbitrators are not bound by strict rules of evidence under Section 19 of the A&C Act and may draw on their experience. Given that the award’s rationale was traceable and not absurd, judicial interference was unwarranted.

Holding and Implications

Holding: The Supreme Court held that the High Court’s interference with the arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996, on the ground of “patent illegality”, was unsustainable, particularly after the award had been affirmed under Section 34. The Court therefore ALLOWED the appeal, SET ASIDE the High Court’s judgment dated 03.05.2023 in ARBA No. 05 of 2017, and RESTORED the Commercial Court, Raipur’s judgment and order dated 02.01.2017 in MJC No. 33/16, thereby reinstating the arbitral award dated 15.07.2012 in favour of the appellant. Pending applications, if any, were disposed of.

Implications: The direct effect of the decision is that the appellant is entitled to the arbitral award of Rs. 3,71,80,584 with the stipulated interest, and BALCO remains bound by the award as originally affirmed by the Commercial Court. The High Court’s setting aside of the award stands nullified. The judgment applies and consolidates existing principles on the narrow scope of judicial intervention under Sections 34 and 37, the stringent threshold for “patent illegality”, and the permissible use of quantum meruit/Section 70 Contract Act where contracts are silent on compensation for extra work. No broader prospective directions are recorded beyond the resolution of the dispute between the parties.

    RAMESH KUMAR JAIN v. BHARAT ALUMINIUM COMPANY LIMITED (BALCO)

    2025 INSC 1457

    REPORTABLE

    IN THE SUPREME COURT OF INDIA

    CIVIL APPELLATE JURISDICTION

    CIVIL APPEAL NO OF 2025

    (Arising out of SLP (C) No. 14529 of 2023) RAMESH KUMAR JAIN ….APPELLANT

    VERSUS

    BHARAT ALUMINIUM COMPANY

    LIMITED (BALCO) ….RESPONDENT

    J U D G M E N T

    ARAVIND KUMAR, J.

    1. Heard. Leave Granted.

    2. We have been called upon to examine the correctness of the Judgement and order dated 03.05.2023 passed by the High Court of Chhattisgarh at Bilaspur in ARBA No. 05 of 2017 whereby the arbitral award dated 15.07.2012 passed by the sole Arbitrator awarding a sum of Rs. 3,71,80,584 (Three crores seventy- one lacs eighty thousand five hundred eighty-four only) along with the statutory

    Page 1 of 28

    interest to the appellant, affirmed by the Commercial Court by judgement and order dated 02.01.2017 in MJC No. 33/16 while exercising jurisdiction under section 34 Arbitration and Conciliation Act, 1996 (hereinafter "A&C Act") has been set aside by the High Court in exercise of its limited appellate jurisdiction under section 37 of the A&C Act.

    3. The facts shorn of unnecessary details are set forth herein under:

    3.1. The respondent-Bharat Aluminum Company Limited (in short

    "BALCO") invited a tender for the purpose of mining and transporting 3,70,000 Metric Tons (MTs) of Bauxite from Mainpat mines to respondent's Korba Alumina plant. The appellant submitted his bid at Rs. 697/- per metric ton which happened to be the lowest among all the bids received. Therefore, the respondent, after negotiation, entered into an agreement with the appellant for mining and transporting of 2,22,000 MTs of Bauxite from the Mainpat Mines to Alumina plant at rate of Rs.

    634.20 per MT on 11.12.1999. The said work had to be completed within a period of 18 months i.e., by May 2001 but it was extended up to September 2001. After the appellant had completed supplying the agreed quantity of bauxite, the respondent by letter dated 05.01.2002 requested the appellant to continue the work of mining and transporting and the rate for the extra work was agreed to be decided in due course of time after consulting with the appellant. Thereafter, appellant

    Page 2 of 28

    continued the work and supplied total quantity of 1,95,000 MT of Bauxite between 16.06.2001 to 31.03.2002. Subsequently, dispute arose between the parties regarding the payment of extra work performed by the appellant which led to invocation of arbitration clause and the claimant approached the High Court by filing an application seeking appointment of an arbitrator under section 11(6) of the A&C Act. The High Court by way of order dated 12.04.2007 in MCC No. 192 of 2006 referred the said dispute to the Tribunal as per clause J of the agreement between the parties.

    3.2. The sole arbitrator after considering the pleadings filed by the appellant and respondent formulated 13 (Thirteen) issues. The learned sole arbitrator after hearing both the parties at length passed the arbitral award dated 15.07.2012 in favour of the appellant as follows:

    Claim Heading Description Amount Awarded
    Para 19.1 Claim for extra work of 1,95,000 MT allowed @Rs. 10 per metric ton Rs.31,85,000/- (including interest @10% p.a. from 31.03.2001 till Aug 2007
    Para 19.2 Claim for restriction and quantity of Trucks Rs.1,23,06,058/- (including interest

    Page 3 of 28

    resulting in extra cost of transportation @10% p.a. from March 2002 till July 2007)
    Para 19.3 Claim for removal of extra overburden Nil
    Para 19.4 Claim for idle manpower and machinery during the strike period of 67 days Rs.71,36,568/- (including interest @10% p.a. from 13.03.2001 till 25.08.2007
    Para 19.5 Claim on interest on account of delay in respect of 15th R.A. Bill Rs.8,30,157/- (Interest has been awarded @18% p.a. for a period of 90 days and thereafter from 01.06.2001 to 31.08.2007
    TOTAL Rs. 2,34,57,783/-

    3.3. On the above sum, 12% p.a. interest was awarded from 01.09.2007 to 15.07.2012 which came to Rs. 1,37,22,801 (One crore thirty-seven lacs twenty-two thousand eight hundred and one only). Hence, on adding the said sum the total award of Rs. 3,71,80,584 and statutory interest as per section 31(7)(b) of the A&C Act from the date of award till payment by the respondent was ordered by the arbitral tribunal.

    Page 4 of 28

    3.4. Being aggrieved by the arbitral award, the respondent preferred an objection petition under section 34 of the A&C Act bearing no. MJC No. 33/16 before the Commercial court. On meticulous consideration the civil court came to the conclusion that the sole arbitrator had given a well-reasoned findings on each claim after considering the oral and documentary evidence which could not be regarded as arbitrary or capricious especially in the light of section 34(2)(b)(ii) of A&C Act and therefore, refused to interfere and affirmed the arbitral award dated 15.07.2002 by way of judgement and order dated 02.01.2017.

    3.5. The respondent being not satisfied with the findings of civil court invoked the limited appellate jurisdiction of the High Court under Section 37 of A&C Act by preferring ARBA No. 05 of 2017 against judgement and order dated 02.01.2017. The said appeal came to be allowed by the impugned judgement and the arbitral award dated 15.07.2012 affirmed by civil court by order dated 02.01.2017 has been set aside.

    3.6. Aggrieved by the same, the appellant, the original claimant, is in appeal before us.

    REASONING ASSIGNED UNDER THE IMPUGNED JUDGEMENT

    4. At the outset, before examining the submissions made by the learned Senior counsels appearing on behalf of the parties, we deem it apt and appropriate to examine the reasonings given by the high court for setting aside the concurrent

    Page 5 of 28

    findings in favour of the appellant. Hence the same has been encapsulated hereinbelow.

    5. The first and foremost reason given by the High Court is that fixation of additional cost from Rs. 634.20 PMT to the tune of Rs. 644.20 PMT by addition of Rs. 10/- per metric ton for the extra work determined by the sole arbitrator on the basis of principle of "quantum meruit" was without jurisdiction since the letter dated 05.01.2002 whereunder the appellant was obligated to perform extra work of excavation did not fix any rate. Therefore, in the absence of the agreement, the arbitrator could not have fixed the rate, as such it amounted to rewriting of the contract. The High Court further relied upon the decision of this court in Mahanagar Telephone Nigam Limited v. Tata Communications Limited1 to arrive at an conclusions that principle of "quantum meruit" could not have been applied since its application is limited to cases wherein the price has not been fixed by the contract but in the instant case since previously the rate was accepted and work was done, fixation of amount of compensation additionally by Rs. 10/- PMT was erroneous which falls under the realm of exceeding jurisdiction or rewriting of the contract which according to the High Court tantamounts to "patent illegality".

    6. Another reason assigned by the High Court for allowing the appeal of the respondent was that the learned arbitrator had assessed the damages only on the basis of oral statement and on the guess work, therefore, the same was not sustainable and according to the High Court it also fell within the sweep of

    1 (201 9) 5 SCC 341

    Page 6 of 28

    patent illegality. Further, the High Court while considering the award with respect to extra cost for transportation borne due to restriction on carrying capacity of trucks relied upon the specific statement made by the claimant during the trial in respect of Question No. 45 to arrive at conclusion that respondent was not prima facie responsible for any reduction in weight, hence the loss caused on transportation cannot be attributed to the respondent. It was held that arbitrator had merely relied upon the tabular statement given by the appellant without examining the basis of rate and calculation on which the loss was determined. Hence, it was of the opinion that claim of appellant was not based on the evidence and facts relied upon. Therefore, in the absence of any documentary evidence on record to show that appellant was restricted to carry only 10.2 MT, the award on the basis of alleged loss was only a guess work. In this regard, the High Court placed reliance on the decisions of this court rendered in Kailash Nath Associates v. Delhi Development Authority and Anr.2 to hold that Arbitrator cannot rewrite the award and the part of findings of the arbitrator which is without any evidence and beyond the terms of contract would be a patent illegality.

    7. The High court further concluded that the tribunal in respect of idle machinery and idle manpower merely relied upon the tabular chart tendered by the appellant which was only a self-declaratory opinion and not based on evidence of facts.

    2 (2015) 4 SCC 136

    Page 7 of 28

    SUBMISSIONS ON BEHALF OF THE PARTIES

    8. Learned Senior Counsel Shri Mukul Rohatgi appearing on behalf of the appellant submitted that the High Court exceeded its jurisdiction in reappraising the factual matrix and arriving at a different conclusion to that of the arbitrator. The High Court was acting as an appellate court while the jurisdiction in section 37 of A&C Act is restricted by virtue of the act and the lens of scrutiny under the said provision is very narrow. The High Court went into the merits of the case and has re-appreciated and re-examined the documents and evidence on record which was impermissible under section 37 of the A&C Act. To buttress the said contention, the learned senior counsel relied upon the law laid down by this court in Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation3.

    9. The learned senior counsel further submitted that under section 34 and section 37 of the Act, the court does not sit in appeal and it cannot go into the merits of the matter. Hence, in the present case, the High court acted in excess of jurisdiction conferred upon it by law. In this regard reliance was placed upon the case of MMTC Limited v. Vedanta Ltd.4

    10. The Learned senior counsel vehemently submitted that arbitral tribunal has given detailed reasons for the conclusion that it had reached while passing the award. Further, the claims awarded by the arbitral tribunal have been supplemented with proper reasons and justifications. The award was upheld by the commercial court, Raipur and the application under section 34 of the Act

    3 (2022) 1 SCC 131

    4 (2019) 4 SCC 163

    Page 8 of 28

    was dismissed as "being without substance". Hence, it was not proper for the High Court to set aside the award in the name of patent illegality, merely because the reason that the High Court's interpretation of facts were different than that of the arbitral tribunal.

    11. He further submitted that Interpretation of the contract is a matter for the arbitrator to determine based on evidence and communications and an error in interpretation is not a basis for interference under section 34 of A&C Act. To back his contention, he placed reliance upon Hindustan Construction Company Ltd. v. NHAI5, MMTC Ltd. (supra) and Associate Builders v. Delhi Development Authority6.

    12. The learned senior counsel while placing reliance upon Parsa Kente Collieries Ltd. v. RRVUN Ltd.7 vehemently submitted that arbitral tribunal is the master of evidence and findings of facts which are arrived at by the arbitrators based on evidence on record and not to be scrutinized, as if the court was sitting in appeal.

    13. He further submitted that as long as there is material available before the arbitrator to show damages have been suffered, but such material does not give him an insight into the granular details, the arbitrator is permitted the leeway to employ honest guesswork and/or a rough and ready method for quantifying the damages. To buttress the said contention, the learned senior counsel relied upon

    Construction and Design Services v. Delhi Development Authority8.

    5 (2024) 2 SCC 613

    6 (2015) 3 SCC 49

    7 (2019) 7 SCC 236

    8 (2015) 14 SCC 263

    Page 9 of 28

    14. He also submitted that High court with respect to extra work from July 2001 to March 2002, was factually not correct in stating that earlier rate was agreed between the parties. For the subsequent period from July 2001 onwards, the respondent had taken out fresh tenders which were later withdrawn despite the petitioner being the lowest bidder. Nonetheless the respondent requested the petitioner to continue the work but the rates were never agreed between the parties which is an admitted fact as evident from the letters dated 15.08.2001 and 05.01.2002.

    15. He also submitted that the tribunal considered the fact that the strike at respondent's plant was an issue between the management and workers of the respondent. Since there was no Force Majeure clause in the contract and the strike was not an Act of God, the petitioner was entitled for compensation with respect to idle machinery and manpower.

    16. Per Contra, Learned Senior Counsel Shri Ranjith Kumar appearing for the respondent submits that there was no clause for in the contract for increasing the rate except for the diesel variation clause. He further contended that petitioner from the beginning of the contract, started protesting and raising unnecessary demands for increasing the price of the contract by comparing it with the contract awarded by the respondent to a third party. The respondent through its letter dated 25.03.2000 had already informed the petitioner that it should not be of his concern who the respondent pays or at what rate, for the bauxite purchased from outside.

    17. He further contended that it was specifically mentioned in the contract that the contractor should investigate and inspect the work, site and surrounding area

    Page 10 of 28

    and keep all circumstances in mind before submitting the tender. He also submitted that the Sole arbitrator after holding that neither party has agreed to the rate, has proceeded to guess that the prices have arisen by Rs. 10/- without any evidence or materials to support such findings. He further contended that additional work was executed at existing rate, and that the additional work was executed at existing rate, and that the claimant had accepted the amount and did not challenge the same. The respondent paid the petitioner Rs. 657/- throughout the period and the rate was impliedly agreed between the parties.

    18. With reference to route map, the learned senior counsel contended that there was no specific route map prescribed in the contract for transportation of the bauxite. The petitioner contended that they had to carry the bauxite from the longest route which was costing them additional 50 KM distance for which the respondent was liable to pay as per the diesel variation clause, which is completely baseless. It was an admitted fact that the petitioner was not bound by the contract to follow any particular route. Further, bare perusal of clause 2(a) of the contract i.e., the diesel variation clause shows that it depends on the rate of the diesel and not on the distance and the word 'average' has been mentioned for the entire contract irrespective of the route which the contractor choses for transportation.

    19. He further submits that the Learned sole arbitrator without appreciating the specific bar under clause 6 and without giving a simple meaning to the terms therein, went beyond the terms of the contract to allow the claim for idle machinery. The arbitrator adopted a hyper-technical approach which is not permissible while interpreting the terms of the contract.

    Page 11 of 28

    20. He has also submitted that the arbitrator after holding that the petitioner had not submitted any documentary evidence on record in respect of the claim for alleged loss due to idle machinery and manpower, however erroneously granted 75% of the alleged amount claimed. The High Court rightly held that there is no evidence to show that the mining process came to stand still and there is no document to show the expenses incurred by the petitioner.

    21. He submitted that petitioner continued to work and execute a quantity of 1,95,000 MT from 16.06.2001 to 31.03.2002 and respondent was paying the petitioner at the existing rate plus Rs. 23/- as diesel escalation. The respondent paid the petitioner Rs. 657/- inclusive of diesel rate throughout the period and the rate was impliedly agreed between the parties. The contention of the petitioner that they were expecting a payment of Rs. 697/- PMT is baseless for the reason that the tender 01.01.2001 was cancelled because the bidders offered a very high rate which was not acceptable to the respondent.

    22. He further submitted that there was no documentary evidence on record to show that the penalty was imposed by the respondent over the carrying capacity. The Arbitrator wrongly allowed the claim for extra cost of transportation to be borne by the respondent in the absence of any evidence. Only an unsubstantiated tabular statement was placed on record by the petitioner and the basis on which the facts and figures were arrived at therein was absent since there was no evidence.

    23. He vehemently submitted that the contract does not permit the Ld. Arbitrator to decide the rates between the parties. It could not have applied the principle of quantum meruit and fixed the rates between the parties. The Award, is thus,

    Page 12 of 28

    against the most basic notions of morality and justice. To buttress his submissions, he placed reliance upon SsangYong Engineering v. NHAI9, MTNL v. TATA Communications10, and Alopi Parshad v. Union of India11.

    24. He also submitted that Ld. Arbitrator has re-written the contract since the rates were fixed at Rs. 634.20/- PMT and the extension of contract was on the same terms and conditions. Once the rates are fixed, the arbitrator could not award an additional amount. To back the said contention, he has placed reliance upon

    Satyanarayan Construction Company v. Union of India12.

    25. He lastly submitted that Ld. Arbitrator while awarding a sum of Rs. 10/- as a reasonable compensation to the petitioner has not been relied upon any evidence and merely a guesswork. He has placed reliance upon Kailash Nath Associates v. DDA13, to buttress the said contention.

    POINT FOR OUR CONSIDERATION

    26. Having heard the learned senior counsels at length on behalf of both the parties and after examining the material on record, we are of the considered opinion that the core issue that arises for our consideration is: Whether interference with the arbitral award by the High Court under Section 37 of the Arbitration and Conciliation Act, 1996 on the ground of patent illegality is sustainable when

    9 (2019) 15 SCC 131

    10 (2019) 5 SCC 341

    11 AIR 1960 SC 588

    12 (2011) 15 SCC 101

    13 (2015) 4 SCC 136

    Page 13 of 28

    once the award has been affirmed under section 34 of the Arbitration and Conciliation Act, 1996?

    DISCUSSION & OUR ANALYSIS

    27. The Arbitration and Conciliation Act, 1996 avows to provide a speedy, cost- effective & efficacious mode of alternative dispute resolution with a policy of minimal judicial intervention. The same is apparent from the legislative intent explicitly mandated under section 5 of A&C Act which envisages an embargo upon the judiciary to interfere in arbitral proceedings save in circumstance expressly stipulated under Part I of the Act. Hence, it is clear that judicial interference is circumscribed with only exception being the statutorily mandated remedies which we find under section(s) 34 and 37 of the A&C Act.

    28. The bare perusal of section 34 mandates a narrow lens of supervisory jurisdiction to set aside the arbitral award strictly on the grounds and parameters enumerated in sub-section (2) & (3) thereof. The interference is permitted where the award is found to be in contravention to public policy of India; is contrary to the fundamental policy of Indian Law; or offends the most basic notions of morality or justice. Hence, a plain and purposive reading of the section 34 makes it abundantly clear that the scope of interference by a judicial body is extremely narrow. It is a settled proposition of law as has been constantly observed by this court and we reiterate, the courts exercising jurisdiction under section 34 do not sit in appeal over the arbitral award hence they are not expected to examine the legality, reasonableness or correctness of findings on facts or law unless they come under any of grounds mandated in

    Page 14 of 28

    the said provision. In ONGC Limited. v. Saw Pipes Limited14, this court held that an award can be set aside under Section 34 on the following grounds: "(a) contravention of fundamental policy of Indian law; or (b) the interest of India; or (c) justice or morality, or (d) in addition, if it is patently illegal."

    29. When it comes to section 37 of the A&C Act it provides for a limited appellate remedy against an order either setting aside or refusing to set aside an arbitral award passed by civil court in exercise of its power under section 34. This court in MMTC Ltd. v. Vedanta Ltd.15, at Paragraph 14 observed that interference with an order made under section 37 cannot travel beyond the restrictions laid down in section 34. Further in Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking16 this court at Paragraph 18 observed that the scope of appellate scrutiny under section 37 is necessarily co-extensive with the parameters mandated under section 34 of the Act and hence the said provision does not enlarge the jurisdiction of the appellate court. Even this court has observed in M/s. Hindustan Construction Company Limited v. M/s. National Highways Authority of India17, wherein one of us (Justice Aravind Kumar) was part of the bench at Paragraph 26 that the standard of scrutiny of an arbitral award is very narrow and it is not the judicial review of an award. Further in Paragraph 27 it was observed that awards which contains reasons, especially when they interpret contractual terms, ought not to be interfered with lightly. This court has also observed in Larsen Air Conditioning and

    14 (2003) 5 SCC 705

    15 (2019) 4 SCC 163

    16 (2023) 9 SCC 85

    17 2023 INSC 768

    Page 15 of 28

    Refrigeration Company v. Union of India and Ors.18 at Paragraph 15 that the scope of interference in exercise of appellate power under section 37 is even narrower to review the findings of the awards, if it has been upheld or substantially upheld under section 34. Hence, it is very well settled that arbitral awards are not liable to be set aside merely on the ground of erroneous in law or alleged misappreciation of evidence and there is a threshold that the party seeking for the award to be set aside has to satisfy, before the judicial body could enter into the realm of exercising its power under section(s) 34 & 37. It is also apt and appropriate to note that re-assessment or re-appreciation of evidence lies outside the contours of judicial review under section(s) 34 and 37. This court in Punjab State Civil Supplies Corporation Limited & Anr. v. M/s. Sanman Rice Mills & Ors.19, at Paragraph 12 observed that even when the arbitral awards may appear to be unreasonable and non-speaking that by itself would not warrant the courts to interfere with the award unless that unreasonableness has harmed the public policy or fundamental policy of Indian law. It might be a possibility that on re-appreciation of evidence, the courts may take another view which may be even more plausible but that also does not leave scope for the courts to reappraise the evidence and arrive at a different view. This court in Batliboi Environmental Engineers Limited v. Hindustan Petroleum Corporation Limited & Anr.20 held that the arbitrator is generally considered as ultimate master of quality and quantity of evidence. Even an award which is based on little or no evidence would not be held to be invalid

    18 (2023) 15 SCC 472

    19 2024 INSC 742

    20 2023 INSC 850

    Page 16 of 28

    on this score. At times, the decisions are taken by the arbitrator acting on equity and such decisions can be just and fair therefore award should not be overridden under section 34 and 37 of the A&C Act on the ground that the approach of the arbitrator was arbitrary or capricious.

    30. Hence, in the light of the aforesaid discussion, we would deal with the submissions made by the learned senior counsels on behalf of the parties. But there is yet another aspect that warrants our attention before delving into the analysis of submission and that is the setting aside of the impugned order by the High Court by placing reliance on the ground of "patent illegality"

    therefore, it becomes imperative to understand the true import of the said term before we move further.

    31. Prior to 2015 amendment, the ground of "patent illegality" emerged as result of judicial interpretation in ONGC Ltd. (supra) while interpreting "public policy" mandated under section 34(2)(b)(ii) of A&C Act wherein this court for the first time read patent illegality as a sub-ground to set aside the award on the broader purport of "public policy". In Paragraph 22 of the decision this court observed: Therefore, in a case where the validity of award is challenged, there is no necessity of giving a narrower meaning to the term "public policy of India". On the contrary, wider meaning is required to be given so that the

    "patently illegal award" passed by the arbitral tribunal could be set aside." This court went on to illustrate what would constitute patent illegality at Paragraph 22 and we extract the same for easy reference:

    "……Take for illustration a case wherein there is a specific provision in the contract that for delayed payment of the amount due

    Page 17 of 28

    and payable, no interest would be payable, still however, if the arbitrator has passed an award granting interest, it would be against the terms of the contract and thereby against the provision of Section 28(3) of the Act which specifically provides that "Arbitral Tribunal shall decide in accordance with the terms of the contract". Further, where there is a specific usage of the trade that if the payment is made beyond a period of one month, then the party would be required to pay the said amount with interest at the rate of 15 per cent. Despite the evidence being produced on record for such usage, if the arbitrator refuses to grant such interest on the ground of equity, such award would also be in violation of sub-sections (2) and

    (3) of Section 28. Section 28(2) specifically provides that the arbitrator shall decide ex aequo et bono (according to what is just and good) only if the parties have expressly authorised him to do so. Similarly, if the award is patently against the statutory provisions of substantive law which is in force in India or is passed without giving an opportunity of hearing to the parties as provided under Section 24 or without giving any reason in a case where parties have not agreed that no reasons are to be recorded, it would be against the statutory provisions. In all such cases, the award is required to be set aside on the ground of "patent illegality"."

    32. In Associate Builders v. Delhi Development Authority21, this court attempted to filter out what contemplated patent illegality in paras 42.1 to 42.3 under the following three subheads: firstly, contravention of the substantive law of India; secondly, contravention of the Arbitration Act itself and thirdly, contravention of Section 28(3) of the Arbitration Act which mandates the Arbitral Tribunal to decide the case in accordance with the terms of the contract, taking into account the usages of the trade applicable to the transaction. With regard to the third sub-head Justice R.F. Nariman, observed by stating that: if an arbitrator construes a term of the contract in a reasonable manner, it will not mean that

    21 2014 SCC OnLine SC 937

    Page 18 of 28

    the award can be set aside on this ground. Construction of term of a contract is primarily for an arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something that no fair minded or reasonable person could do.

    33. In 2015, by way of the Arbitration and Conciliation (Amendment) Act a new sub-section (2A) to section 34 of A&C Act was inserted which in addition to statutorily recognizing the 'patent illegality' ground for setting aside a domestic arbitral award made it an independent and distinct ground from 'public policy' under section 34. The proviso to the newly inserted clause further provided that an award "shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence". The legislative intent behind insertion of this proviso was to avoid excessive intervention to arbitral award by the courts under the ground of 'patent illegality'. However, the Amendment clarified that "an erroneous application of the law" or "re- appreciation of evidence" does not fall under patent illegality. Hence, the courts are not to treat every factual error or every divergent interpretation as an illegality. The illegality must be of a kind that strikes at the heart of the award's validity. For instance, if an arbitrator ignores a binding precedent or a clear prohibition in the contract, that may be patent illegality. Likewise, a finding based on no evidence at all can be said to be perverse and thus patently illegal. But where there is some evidence and a reasonably plausible inference has been drawn by the arbitrators, the courts should ordinarily refrain themselves from supplanting the views arrived by the arbitrator as that would be the true import of the legislative intent inherent in the Amendment Act.

    Page 19 of 28

    34. Thereafter, this court elucidated the meaning of the expression 'patent illegality' in Ssangyong Engg. & Construction Co. Ltd. v. NHAI22 while taking into consideration the amendment act of 2015 and held it as a glaring, evident illegality that goes to the root of the award. This includes: (a) an award deciding matters outside the scope of the arbitration (beyond the contract or submission); (b) an award contradicting the substantive law of India or the Arbitration Act itself; (c) an award against the terms of the contract; and (d) an award so unreasoned or irrational that it manifests an error on its face.

    35. Considering the aforesaid precedents, in our considered view, the said terminology of 'patent illegality' indicates more than one scenario such as the findings of the arbitrator must shock the judicial conscience or the arbitrator took into account matters he shouldn't have, or he must have failed to take into account vital matters, leading to an unjust result; or the decision is so irrational that no fair or sensible person would have arrived at it given the same facts. A classic example for the same is when an award is based on "no evidence" i.e., arbitrators cannot conjure figures or facts out of thin air to arrive at his findings. If a crucial finding is unsupported by any evidence or is a result of ignoring vital evidence that was placed before the arbitrator, it may be a ground the warrants interference. However, the said parameter must be applied with caution by keeping in mind that "no evidence" means truly no relevant evidence, not scant or weak evidence. If there is some evidence, even a single witness's testimony or a set of documents, on which the arbitrator could rely

    22 (2019) 15 SCC 13

    Page 20 of 28

    upon or has relied upon to arrive at his conclusions, the court cannot regard the conclusion drawn by the arbitrator as patently illegal merely because that evidence has less probative value. This thin line is stood crossed only when the arbitral tribunal's conclusion cannot be reconciled with any permissible view of the evidence.

    36. Having discussed the said law, we move ahead to another limb of the submission which was espoused by the respondent particularly with reference to obligations of the arbitrator to decide the dispute in accordance with the terms of the contract. It is a fundamental principle that the arbitrator cannot award anything that is contrary to the contract. The arbitrator is bound by clear stipulations inter se the parties, and an award ignoring such stipulations would violate public policy by undermining freedom of contract. However, that does not mean that not every award which gives a benefit not expressly mentioned in the contract is in violation. The arbitral tribunal in exercise of their power can very well interpret the implied terms or fill gaps where the contract is silent, so long as doing so does not contradict any express term. For example, if a contract is silent on interest on delayed payments, an arbitrator awarding reasonable interest is not contradicting the contract rather it is a power exercised by the arbitrator to fulfill the gap on the basis of equity which also mandated under Section 31(7)(a) of the A&C Act. Similarly, if a contract does not say either way about compensating extra work done at request, the arbitrator can imply a term or use principles of restitution to award a reasonable sum, without violating the terms of contract. The thin line is whether an express prohibition or restrictions in the contract is breached by the award? If the

    Page 21 of 28

    answer is in affirmative, the award is liable to struck down. However, where the contract is simply silent on a legitimate claim which is inherently linked to the natural corollary of contractual obligation of the parties the arbitrator will be well within his powers to interpret the contract in the light of principles of the contractual jurisprudence and apply the equity to that situation. A contrary interpretation would lead to opening a floodgate whereby a party who may have dominant position would intentionally not ink down the natural obligation flowing from the contract and subsequently; after obtaining the benefit the party would agitate absence of express terms to sway away from even discharging his alternative obligation of compensating the party at loss. Hence the question which arises in such situations is, can the party who bears the brunt and suffers the loss due to silence under the contract regarding the natural contractual obligation which arises in usual course of business be left in limbo? In our view, that is the very purpose why section 70 of the Contract Act, 1872, has been an intrinsic part of our Contract Act. The said provision creates a statutory right independent of contract, often termed quantum meruit or unjust enrichment remedy. For ready reference the said provision has been extracted hereinbelow:

    "70. Obligation of person enjoying benefit of non-gratuitous act. Where a person lawfully does anything for another person, or delivers anything to him, not intending to do so gratuitously, and such other person enjoys the benefit thereof, the latter is bound to make compensation to the former in respect of, or to restore, the thing so done or delivered."

    37. The close scrutiny of the aforesaid provision reveals that it comes into play when one party confers a benefit on another in circumstances not governed by

    Page 22 of 28

    a contract, without intent to act gratuitously. Hence in such situation, the party taking the benefit is bound to pay compensation to the party who had gratuitously taken the benefits and the courts including arbitral tribunals, can award compensation under Section 70 if the conditions are met.

    38. Coming to submissions of the parties, we refrain ourselves from meticulously examining each submission made by the parties since most of the submissions raised are purely factual in nature and as observed hereinabove, the arbitrator is considered as the master on question of facts and even an erroneous interpretation of facts would not lead us to invoke our extra-ordinary jurisdiction, the only caveat being the said interpretation of facts is patently illegal that is it is based on no evidence or beyond the scope of contract.

    39. Keeping the said position in mind, we have first meticulously examined the arbitral award dated 15.07.2012 passed by the Learned arbitrator with sole intent to analyze whether there is any part of the award which is based on no evidence or is alien to the terms of contract. However, the perusal of the award as a whole, in our view, does not reveal any findings arrived by the tribunal which seems unreasonable or capricious, rather, the arbitrator has scrutinized the material on record: oral evidence of Shri R.K. Jain, the claimant and Shri A. Hussain, the then Assistant General Manager & Engineer-in-charge, who was overseeing the performance of the contract in question, adduced during cross-examination by the Respondent; and documentary evidence in the form of affidavits and correspondence letters to arrive at individual findings of each claim. The sheer application of mind at the behest of the arbitrator is apparent from the very fact that the claims asserted by the appellant were not accepted

    Page 23 of 28

    by the arbitrator as a gospel truth but were put on pedestal of evidentiary proof. The respondent has argued that the arbitrator has based its findings based on the calculation sheets and guesswork. We would have agreed with the respondent had there been no evidence available before the arbitrator to arrive at such findings but the same is not true since the arbitrator after considering the evidence on record has given its finding. For instance, the claim under Para

    19.2 to the tune of Rs. 1,96,11,000 towards extra transportation cost incurred by the appellant on the premise of restricting the capacity of the truck was proved by the fact that after the District Transport Officer order was stayed by the High Court, the respondent did not allow the appellant to deliver at the weight of 11 MT which was not controverted by the respondent. Also, the arbitrator was conscious to draw adverse conclusions against the appellant, where he failed to sufficiently satisfy the basis of the claim and the arbitrator in such cases has either reduced the said claim substantially while applying the principle of quantum meruit (as evident from claim under Para 19.1 for executing the extra work) while balancing the interest of both the parties to the arbitral proceedings or has completely denied it (as evident from claim under Para 19.3 for removal of extra burden). Hence, in our view, the overall analysis of the arbitral award does not reveal any arbitrary exercise of power or findings which is based on lack of evidence as such to fall within the sweep of "patent illegality" as held by the impugned judgement. In our assessment, the High Court allowed itself to be deviated by things that are in truth within a range of normalcy in arbitral adjudication.

    Page 24 of 28

    40. With regard to application of principle of quantum meruit the respondent had argued the Ld. Arbitrator had erroneously applied the said principle when the rates were already fixed between the parties. Even the High court observed in the impugned judgement that the said exercise tantamount to rewriting of contract. The Impugned judgement has proceeded on an erroneous understanding of the decision of this Court in Mahanagar Telephone Nigam Limited v. Tata Communications Limited23. We say so because the said decision is applicable to situations where the contract between the parties fully governs the field and the consideration for the very work in dispute stands conclusively determined by express contractual terms. However, in the present case, after the currency of the earlier two contract the appellant continued to mine and transport the additional work of supplying the additional Bauxite to the tune 1,95,000 MT at the behest of the respondent, but the price thereof was left open to be finalized in due course of time by mutual consensus as is evident from the bare reading of Letter dated 05.01.2002 (Annexure P4) addressed by the respondent to the claimant, which exercise was never undertaken. In such a factual matrix, the arbitral tribunal cannot be said to have rewritten or varied the contract rather the arbitrator addressed a vacuum in the contractual arrangement by determining reasonable compensation in terms of Section 70 of the Contract Act, 1872, to obviate the possibility of unjust enrichment. The quantification of additional compensation at Rs. 10/- PMT i.e., from Rs. 634.20/- PMT to Rs. 644.20/- PMT represents an assessment of reasonable

    23 (2019) 5 SCC 341

    Page 25 of 28

    value for the extra work performed and does not amount to substitution of any agreed contractual rate as no such sum was mutually inked down by both the parties. Therefore, we disagree with said view of the High court as the arbitral award did not rewrite the contract but merely enforced a restitutionary obligation arising from admitted extra work directed and accepted by the respondent, where the aspect of consideration was consciously left open and later misused by the respondent to sway away from discharge of its usual contractual obligation. Hence, the High Court, in exercise of limited jurisdiction under Section 37, impermissibly re-appreciated facts and substituted its own interpretation, contrary to settled law under Associate Builders, Ssangyong Engineering and MMTC (referred to supra).

    41. Further, we have no hesitation to hold that claims in the nature of quantum meruit or unjust enrichment can be decided by the arbitrator provided they fall within the scope of disputes referred either explicitly or by necessary implication. For instance, in a situation like the present, claim for payment for such work has been entertained as it relates to the performance of the contract. The measure of compensation under Section 70 is typically the value of the benefit obtained by the other party or the cost incurred by the claimant in doing the act (whichever is reasonable to avoid unjust enrichment). The law does not permit arbitrary awards under Section 70. The award must still be grounded in evidence of the benefit's value or the expense incurred. Nonetheless, tribunals have a degree of discretion to approximate a fair value, especially when exact evidence is hard to come by, so long as the final figure is reasonable and not pulled from thin air.

    Page 26 of 28

    42. The errors pointed out in the impugned judgement, i.e., lack of evidence, percentage-based guess allowances, etc. do not, singly or cumulatively, amount to patent illegality warranting annulment. There were at least some evidence and logical rationale for each award element. The arbitrator's approach was certainly a possible view a reasonable man might take. The High Court, unfortunately, re-appreciated the evidence and came to a different view, which is impermissible. The High Court's scrutinized the award from a stricter standard of proof than arbitration law demands. Arbitrators are not bound by the strict rules of evidence as per Section 19 of the A&C Act and may draw on their knowledge and experience. It is settled that a court should not interfere simply because the arbitrator's reasoning is brief or because the arbitrator did not cite chapter and verse of the contract as long as the path can be discerned by which the arbitrator arrived at his conclusions. Here, the path is discernible and not absurd.

    CONCLUSION

    43. In light of the foregoing analysis, we are of the considered view that impugned

    judgement dated 03.05.2023 passed in ARBA No. 05 of 2017 cannot be sustained and the appeal deserves to be allowed. Accordingly, the appeal stands allowed and the aforesaid impugned judgement is set aside. 44. Consequently, the judgement and order dated 02.01.2017 passed by Commercial Court, Raipur in MJC No. 33/16 which affirmed the arbitral award

    Page 27 of 28

    passed by the sole arbitrator dated 15.07.2012 is restored. Pending applications, if any, stands disposed of.

    .……………………………., J.

    [ARAVIND KUMAR]

    .……………………………., J.

    [N.V. ANJARIA]

    New Delhi;

    December 18th, 2025.

    Page 28 of 28