ORAL ORDER
(PER : HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE SUNITA AGARWAL)
Having heard the learned senior advocate Mr. S.I.Nanavati assisted by the learned advocate Mr. Mrugen Purohit for the petitioners and Mr. G.H.Virk, the learned Government Pleader for the respondent Nos.1 to 6 and perused the record, pertinent is to note that the present petition has been filed by the Gram Panchayat, namely Kathda Gram Panchayat, Taluka Mandvi, through its Sarpanch to raise the issue with regard to utilisation of the gaucher land for a project, which is inter alia of National importance, for extension of Mandvi Airstrip, for which budgetary sanction was granted in the year 2019.
Page 1 of 3
2. In the affidavit filed on behalf of the respondents, it is categorically stated that an area of approximately 9.15 lakhs sq.mtrs. for village Kathda and 21.75 lakhs sq.mtrs. for village Bhambdhai has been allotted by the Collector, Kachchh as Gaucher land, in the alternative to the Gaucher land qua the utilised 8.50 lakhs sq.mtrs. Gaucher land for Kathda and 15,02,200 sq.mtrs. Gaucher land for Mandavi, which according to the respondent State is the nearest possible lands available for identification of as Gaucher land.
3. The only issue raised before us by the petitioner, which is Gram Panchayat, is that the lands identified to be given in exchange for village Kathda is far away from the existing land and it is not possible for the villagers to use it for the purposes.
4. Taking note of the above, suffice it to record that the petitioner No.1 in the present petition is Kathda Gram Panchayat, which is holder of the lands of the village panchayat in the entire village Kathda. If any alternative land is available with the Gram Panchayat for identification as a Gaucher land, it would be open for the Gram Panchayat to make a resolution and place it before the Collector. There is no need for us to adjudicate on the issue of identification of the alternative land as Gaucher land for the simple reason that the entire land in the village-in-question is well within the jurisdiction of the Gram Panchayat being vested in it.
5. As regards the grievance of the Gram Panchayat for identification for utilisation of the land-in-question, which is currently being used as a Gaucher land, pertinent is to note that the project-in-question is of National importance inter alia for defence
Page 2 of 3
purposes. The piece of current gaucher land is adjacent to the existing Airstrip.
6. In this scenario, we dispose of the present petition with the only observation that it would be wiser for the Gram Panchayat to make a resolution for identification of the alternative Gaucher land out of the lands available in its jurisdiction or make a request to the Collector to identify any alternative land for the purpose. All other petitioners impleaded in the petition alongwith the Gram Panchayat, are not permitted to raise any issue with regard to the identification of gaucher land, inasmuch as, the Gram Panchayat itself has come up to this Court as petitioner No.1.
7. The decision on the resolution of the Gram Panchayat, if any, shall be taken as early as possible.
8. With the above, the present petition stands disposed of.
(SUNITA AGARWAL, CJ )
(D.N.RAY,J)
C.M. JOSHI
Page 3 of 3