Loading..
Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Companies Act, 1956
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Companies Act, 1956
Smart Summary

Factual and Procedural Background

The appellants booked a 3-BHK flat in the respondent-developer’s 2008 group-housing project “Parsvnath Paramount” at Subhash Nagar, New Delhi. Between July 2008 and December 2013 they paid approximately 95 % of the total sale price (₹ 1,30,62,971). The Flat Buyer Agreement (10 Oct 2008) promised completion within 30 months plus a 6-month grace period. Possession was never delivered; construction was found stalled in June 2015. After unanswered correspondence, the appellants filed Consumer Case No. 1557/2016 before the National Consumer Disputes Redressal Commission seeking refund with 24 % interest and other compensation.

By order dated 29 September 2022, the Commission directed refund of the entire deposit with 9 % interest and costs of ₹ 1 lakh. Both interest rate and refund directions were challenged before the Supreme Court in the present civil appeal.

Legal Issues Presented

  1. Whether the developer’s delay—attributed to late sanction of layout plans—fell within the force majeure clause, thereby absolving interest liability.
  2. Whether the Commission erred in awarding only 9 % interest instead of a higher rate consistent with the Agreement’s stipulations and principles of parity.

Arguments of the Parties

Appellants’ Arguments

  • The Commission wrongly limited interest to 9 % p.a.; the Agreement allowed the developer to charge 24 % p.a. from purchasers in case of their default, whereas developer’s default attracted only 12 % p.a., showing an unfair imbalance.
  • On the principle of parity and to deter unfair trade practices, at least 24 % interest—or in any event more than 9 %—should be awarded.

Respondent-Developer’s Arguments

  • The delay was not deliberate but caused by delayed approval of plans by the Delhi Development Authority, constituting a force majeure event.
  • Consequently, even 9 % interest should not be imposed.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
DLF Home Developers Ltd. (earlier DLF Universal Ltd.) & Anr. v. Capital Greens Flat Buyers Assn. & Ors., (2021) 5 SCC 537 Delay in sanction of plans does not constitute a valid force majeure defence for builders. The Court relied on this decision to reject the respondent’s force majeure argument regarding delayed plan approval.

Court's Reasoning and Analysis

The Supreme Court found no merit in the developer’s reliance on delayed plan sanction as a force majeure event, citing the DLF Home Developers precedent. It affirmed the Commission’s direction for full refund, noting the project’s inordinate delay and the appellants’ substantial payments without possession.

On interest, the Court observed that the Agreement itself stipulated 12 % p.a. payable by the developer for delay (clause 7(b)). Awarding only 9 % was therefore “lesser than even the one agreed upon.” Given the prolonged deprivation suffered by the appellants, the Court held that interest should at least match the contractual 12 % rate.

Holding and Implications

The appeal was partly allowed. The refund of the entire amount deposited by the appellants is upheld; however, the interest rate is enhanced from 9 % to 12 % per annum, payable from each date of deposit until the date of refund. The developer must pay the unpaid amount within three months.

Implications: The decision reinforces that builders cannot shield themselves behind delayed plan sanctions as force majeure and that interest awarded to consumers should, at minimum, meet contractual promises where the builder is at fault. No new legal precedent was set, but the ruling underscores judicial intolerance toward one-sided real-estate agreements and construction delays.

    VIDYA v. M/S PARSVNATH DEVELOPERS LTD.

    2024 INSC 557

    1

    NON-REPORTABLE

    IN THE SUPREME COURT OF INDIA

    CIVIL APPELLATE JURISDICTION

    CIVIL APPEAL NO. 8985 OF 2022

    VIDYA AND OTHERS …APPELLANT(S)

    VERSUS

    M/S PARSVNATH DEVELOPERS LTD. …RESPONDENT(S)

    J U D G M E N T

    B.R. GAVAI, J.

    1. This appeal challenges the order dated 29thSeptember, 2022 passed by the National Consumer Disputes Redressal Commission, New Delhi (hereinafter referred to as the 'Commission') in Consumer Case No. 1557 of 2016 wherein the Commission partly allowed the complaint preferred by the complainants-appellants herein and directed the sole respondent herein, to refund the entire sum deposited by the complainants-appellants with interest at the rate of 9% per annum from the date of respective deposit till the date of refund, within a period of two months from the date of the said order.

    1

    2

    2. The facts, in brief, giving rise to the present appeal are as under:

    2.1. M/s Parsvnath Developers Limited (hereinafter referred to as the 'Developer'), a company registered under the Companies Act, 1956, and engaged in the business of development and construction of inter alia residential projects as well as projects for the Delhi Metro Rail Corporation, launched a group housing project (hereinafter referred to as 'the project') titled 'Parsvnath Paramount' at Subhash Nagar (near Subhash Nagar Metro Station), New Delhi in the year 2008 and widely publicized the same.

    2.2. Upon gaining knowledge of the project, the complainants-appellants booked a 3BHK flat in the said project and to that end, deposited a sum of Rs.16,03,066/- on 15thJuly, 2008. Subsequently, the complainants- appellants paid second instalment of an identical sum on 14thAugust, 2008.

    2.3. Subsequently, the complainants-appellants and the respondent-Developer entered into a Flat Buyer Agreement (hereinafter referred to as 'the Agreement') on 10thOctober, 2008 and in furtherance of the same, the complainants-

    3

    appellants were allotted Flat No. 301 situated in Tower 3 of the project, which had an approximate area of 1805 sq. ft. The total payable price of the flat was determined to be Rs. 1,28,24,525/- calculated at the rate of Rs. 7105/- per sq. ft. of the saleable/super built-up area. An additional sum of Rs. 3,00,000/- was to be paid for the mandatory covered car parking space in the concerned tower. Clause 11(a) of the Agreement clarified that the construction of the flat would be completed within a period of 30 months of commencement of construction of the particular Tower in which the flat was located, with a further grace period of 6 months.

    2.4. The complainants-appellants opted for a 'Construction Linked Payment Plan' under which 25% of the sale price was payable within 30 days of booking, 60% of the sale price and the additional sum for the covered car parking space was payable in 6 installments and 15% of the sale price was payable in another 3 installments. In pursuance of the same, the complainants-appellants paid a total sum of Rs.1,30,62,971/- in the intervening period between 15thJuly, 2008 and 21stDecember, 2013, as per the demand of the respondent-Developer. The aforesaid amount deposited by

    4

    the complainants-appellants amounted to about 95% of the total sale price of the flat.

    2.5. In the meanwhile, the respondent-Developer unilaterally transferred the said Flat No. 301 situated in Tower 3, which had been initially allotted to the complainants-appellants, to Flat No. 702 situated in Tower 2, admeasuring 1942 sq. ft., in April, 2011.

    2.6. Subsequently, the respondent-Developer raised a demand for the payment of VAT amounting to Rs. 60,141/- which was duly paid by the complainants-appellants on 29th January, 2014. A second payment of an identical sum was made on 13thMarch, 2014.

    2.7. In the interregnum, the period of 36 months set out in the Agreement, including the grace period of 6 months, had expired.

    2.8. On failure of the respondent-Developer to handover the possession of the flat within the expected deadline, despite timely payments, the complainants-appellants made several attempts to contact the respondent-Developer to enquire about the progress of the project but received no substantial update. Thereafter, the complainants-appellants visited the

    5

    site in June, 2015 and discovered that no construction work was ongoing.

    2.9. Aggrieved by the halt in construction, the complainants- appellants in a letter dated 15thJune, 2015, addressed to the respondent-Developer, enquired about the time-frame within which the construction would be completed and possession would be handed over to them. Further, the complainants- appellants enquired about the manner in which they would be compensated on account of the delay in delivery of possession.

    2.10. The respondent-Developer in subsequent letters dated 29thJune, 2015 and 5thJuly, 2015 informed the complainants-appellants that the delay in construction was on account of technical issues and recession in the real- estate sector owing to which construction for the project had suffered. However, the respondent-Developer, assured the complainants-appellants that they had persisted with the construction and the same would be completed at the earliest and the complainants-appellants would be informed about the tentative date for making an offer of possession, thereafter. So far as the compensation claimed for was

    6

    concerned, the same was to be governed by the terms and conditions laid down in the Agreement. However, the respondent-Developer failed to directly address the specific queries that had been raised by the complainants-appellants.

    2.11. Subsequently, the complainants-appellants addressed two further letters to the respondent-Developer on 28thOctober, 2015 and 6thJanuary, 2016, respectively, once again raising queries as to when the construction would be completed and the possession would be handed over to them, whether the construction would be completed at all and the manner in which the complainants-appellants would be compensated for the delay in conclusion of the project. However, the respondent-Developer did not respond to the said letters.

    2.12. Aggrieved thereby, the complainants-appellants filed a complaint before the Commission being Consumer Case No. 1557 of 2016 praying for a refund of the entire amount paid by them as per the current market value along with interest at the rate of 24% per annum, thereon, from the date of booking the flat till the date of payment as well as compensation amounting to Rs. 1,37,36,350/- along with

    7

    interest at the rate of 24% per annum thereon, among other reliefs.

    2.13. The learned Commission, by the impugned order, partly allowed the said Consumer Case No. 1557 of 2016 in the afore-stated terms, with costs of Rs. 1 lakh.

    3. Being aggrieved thereby, the present appeal.

    4. We have heard Shri Sanjay Jain, learned counsel appearing on behalf of the complainants-appellants and Shri Jayant Muth Raj, learned Senior Counsel appearing on behalf of the respondent-Developer.

    5. Shri Jain, learned counsel appearing for the complainants-appellants submitted that the learned Commission erred in awarding the interest only at the rate of 9% per annum. He submitted that the Agreement provided that, in case there is delay in payment by the flat purchaser, the respondent-Developer was entitled to condone the same by charging interest at the rate of 24% per annum of the amount in default. He further submitted that the proforma agreement was fully tilted in favour of the respondent- Developer. The Agreement provided that, in case of delay in completion of the project by the respondent-Developer, it was

    8

    liable to pay interest only at the rate of 12% per annum. It is submitted that there is no logic in making the flat purchaser liable for payment of interest at the rate of 24% per annum whereas the respondent-Developer was liable to pay interest only at the rate of 12% per annum.

    6. Shri Jain therefore submitted that, applying the principle of parity, the learned Commission ought to have awarded the interest at the rate of 24% per annum. It is submitted that, in any case the interest at the rate of only 9% per annum is not sustainable in law.

    7. Per contra, Shri Jayant Muth Raj, learned Senior Counsel appearing on behalf of the respondent-Developer submitted that the delay in completion of the project was not deliberate. He submitted that, since there was a delay in sanctioning of the plans by the Delhi Development Authority, the project could not be completed. It is therefore submitted that the case was duly covered under the force majeure clause and as such, interest even at the rate of 9% was not liable to be imposed upon the respondent-Developer.

    8. We have perused the order passed by the learned Commission. Insofar as the contention of the respondent-

    9

    Developer that since there was a delay in sanctioning the layout plans, it was covered under force majeure clause is concerned, this Court, in the case of DLF Home Developers Limited (earlier known as DLF Universal Limited) and Another v. Capital Greens Flat Buyers Association and Others1 has held to the contrary. Therefore, the contention in that regard is without substance. We find that the learned Commission has rightly directed the respondent-Developer to refund the entire amount deposited by the complainants- appellants. However, we find that, insofar as award of interest at the rate of 9% per annum is concerned, the learned Commission was not justified in the facts of the case to award a lesser interest than even the one agreed upon in the Agreement. Undisputedly, the facts of the case show that the project was delayed inordinately. The complainants- appellants were made to suffer for long, for no fault of them. In spite of making the entire payment, they were deprived of the possession within the stipulated time.

    1 (2021 ) 5 SCC 537

    10

    9. In our view, the learned Commission, at least, ought to have awarded interest at the rate of 12% per annum in view of clause 7(b) of the Agreement.

    10. In the result, the appeal is partly allowed. The direction made by the learned Commission for refund of the entire amount deposited by the complainants-appellants is upheld. However, the direction with regard to interest is modified to the extent that it shall be paid at the rate of 12% per annum from the date of respective deposit till the date of refund. The unpaid amount in terms of the aforesaid shall be paid within a period of three months from the date of this judgment.

    11. Pending application(s), if any, shall stand disposed of.

    ..............................J.

    (B.R. GAVAI)

    ..............................J.

    (SANDEEP MEHTA)

    NEW DELHI;

    JULY 29, 2024