WPMS No. 683 of 2024 Hon’ble Manoj Kumar Tiwari, J. (1) Ms. Pushila Bisht & Ms. Menka Tripathi, Advocates for the petitioners. (2) Mr. Suyash Pant, learned Standing Counsel for the State of Uttarakhand. (3) By means of this writ petition, petitioners have sought the following reliefs:- (i) A writ, order or direction in the nature of mandamus commanding the respondent no. 1 to sign, execute and allow registration of the supplementary lease deed in favour of the petitioner no. 1 within a stipulated period of time. (ii) A writ, order or direction in the nature of mandamus commanding respondents to allow the petitioner no. 1 to undertake mining activity in his own name without any hindrance being caused by the respondents. (4) In sum and substance, case of the petitioners is that petitioner no. 2 was granted a mining lease by the State Government on 18.09.2021. Subsequently, a joint application was made by both the petitioners seeking permission for transfer of the mining lease in favour of petitioner no. 1. The said application is said to be allowed vide order dated 22.12.2023. (5) According to the petitioners, a supplementary lease deed has to be executed between State Government and petitioner no. 1. Before executing supplementary lease deed, ‘No Objection Certificate’ was called from concerned Agencies. Even after grant of No Objection Certificate by the concerned Agencies, |
1
supplementary lease deed has not been executed. This according to petitioners is arbitrary and unjust.
(6) A counter affidavit has been filed by Mr. Laxman Singh, Additional Secretary, Industrial Development (Mining), Government of Uttarakhand, Dehradun. Learned State Counsel has referred to para 7 of the said counter affidavit for contending that complaints were received against the petitioners and a report was called from District Magistrate, Bageshwar, which is awaited.
(7) Learned counsel for petitioners, however, submits that District Magistrate has submitted his report to the State Government, thus, she submits that there is no justification for not executing supplementary lease deed in favour of petitioner no. 1.
(8) If what is stated by learned counsel for the petitioner is correct and the District Magistrate has submitted his report regarding complaints received against petitioners, then State Government is under a duty to take decision in the matter, one way or the other.
(9) Accordingly, writ petition is disposed of with a direction to Secretary, Industrial Development Department to take decision regarding execution of supplementary lease deed, one way or the other, within eight weeks from the date of production of certified copy of this order. Relevant provisions of law/policy shall be borne in mind by the concerned Secretary, while taking the decision.
(Manoj Kumar Tiwari, J.)
03.06.2024