ORDER
Shri. G. Dinesh Kumar, Ld. Counsel for the Applicant. Shri. G. Gokul, Ld. Counsel for the Respondent/Liquidator.
IA(IBC)/1016(CHE)2023 has been filed seeking setting aside the order dated 09.03.2021 passed by the Respondent/Liquidator partially admitting the claim of the Applicant.
IA(IBC)/1210(CHE)2023 has been filed seeking condonation of delay in filing the above application.
Common Reply filed by the Respondent vide S.R. No. 3553 dated 23.08.2023 submitting that the orders by the GST Department were passed after the commencement of the liquidation and as such the claims are not maintainable as per Section 33(5) of IBC, 2016. The post demerger liability noted by the CA in the report was admitted although the same was not reflected in the books. It is stated that the movable and immovable properties have already been sold and distribution
-2-
has been made to the stakeholders. Even if the partial claims admitted under Section 53(1)(f) were not paid due to insufficiency of realization proceeds. It is stated that delay has also not been explained properly. We have heard Learned Counsels for the parties.
It is an admitted case of the parties that the amounts / proceeds realized after the sale of movable/immovable assets of the Corporate Debtor have already been distributed to the stakeholders as per Section 53 of IBC. Even the partial claim which was admitted by the Respondent/Liquidator could not be distributed to the Applicant since no funds were available for distribution which was made as per the waterfall mechanism. As to delay, no plausible explanation has been given by the Applicant. Hon'ble NCLAT in the case of "The Deputy Commissioner, Commercial Taxes (Audit), Raichur -Vs- Surana Industries Ltd. (In Liquidation) & Anr. in Company Appeal (AT) (Insolvency) No. 1525 of 2019 dated 07.02.2020" dismissed the application filed by the Applicant in relation to the appeal against the order of the Liquidator and held that the liquidation process is a time bound process and the Liquidator has to conclude the proceedings within one year. Regulation 44(1) of the IBBI (Liquidation Process) Regulations, 2016 also provides for completing the liquidation process within one year from the date of commencement of the liquidation proceedings. Regulation 42(2) provides for seeking extension with the explanation why the liquidation process has not been completed. Hon'ble Supreme Court in the case of "Gaurav Hargovindbhai Dave -Vs- Asset Reconstruction Company (I) Ltd. &
-3-
Another in Civil Appeal No. 4952 of 2019 has held that there is no equity about limitation.
Even if the said application is allowed by condoning the delay, we find that the Applicant is not going to get anything since there are no funds with the Corporate Debtor into liquidation to be distributed to the Applicant.
Considering the above facts and circumstances and the cases supra, both IA(IBC)/1016(CHE)2023 & IA(IBC)/1210(CHE)2023 are dismissed
with no orders as to costs.
Sd/- Sd/-
VENKATARAMAN SUBRAMANIAM SANJIV JAIN
MEMBER (TECHNICAL) MEMBER (JUDICIAL)
VS