    Power Grid Corporation of India Limited

    CENTRAL ELECTRICITY REGULATORY COMMISSION

    NEW DELHI

    Petition No. 681/TT/2020 Coram:

    Shri I. S. Jha, Member Shri Arun Goyal, Member Shri P. K. Singh, Member

    Date of Order: 20.07.2023 In the matter of:

    Approval under Regulation 86 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999 and truing up of transmission tariff from COD to 31.3.2019 under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 and determination of transmission tariff for 2019-24 period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 in respect of transmission assets under "Transmission System associated with North East-Northern/Western Inter Connector-I".

    And in the matter of:

    Power Grid Corporation of India Limited,

    "Saudamini", Plot No. 2, Sector 29, Gurgaon-122001. ….Petitioner Vs.

    1. Assam Electricity Grid Corporation Limited, (Formerly Assam State Electricity Board), Bijulee Bhawan, Paltan Bazar,

    Guwahati-781001, Assam.

    2. Meghalaya Energy Corporation Limited, (Formerly Meghalaya State Electricity Board), Short Round Road, "Lumjingshai", Shillong-793001, Meghalaya.

    3. Government of Arunachal Pradesh, Vidyut Bhawan, Itanagar-791111, Arunachal Pradesh.

    4. Power and Electricity Department, Government of Mizoram, Aizawl, Mizoram.

    Page 1 of 162

    5. Manipur State Electricity Distribution Company Limited, (Formerly Electricity Department, Government of Manipur), Electricity Complex, Patta No. 1293 Under 87(2), Khwai Bazar, Keishampat, District-Imphal West, Manipur-795001.

    6. Department of Power, Government of Nagaland, Kohima, Nagaland.

    7. Tripura State Electricity Corporation Limited, Vidyut Bhawan, North Banamalipur,

    Agartala, Tripura (W)-799001, Tripura.

    8. Himachal Pradesh State Electricity Board Vidyut Bhawan, Shimla-171004 (Himachal Pradesh).

    9. Punjab State Power Corporation Limited, Thermal Shed T-1a, Patiala.

    10. Haryana Power Purchase Centre, IInd Floor, Shakti Bhawan, Sector-6, Panchkula-134109.

    11. Power Development Department, Janipura Grid Station, Jammu (Tawi) 180007.

    12. Uttar Pradesh Power Corporation Limited, 10th Floor, Shakti BhawanExtension, 14, Ashok Marg, Lucknow-226001.

    13. Delhi Transco Limited, Shakti Sadan, Kotla Road (Near ITO), New Delhi.

    14. Chandigarh Administration, Sector -9, Chandigarh.

    15. Uttarakhand Power Corporation Limited, Urja Bhawan, Kanwali Road, Dehradun.

    16. Rajasthan Power Procurement Centre, Vidyut Bhawan, Janpath, Jaipur.

    17. Ajmer Vidyut Vitran Nigam Limited, 400 kV, GSS Building, Ajmer Road, Heerapura, Jaipur.

    Page 2 of 162

    18. Jodhpur Vidyut Vitran Nigam Limited, 400 kV GSS Building, Ajmer Road, Heerapura, Jaipur

    19. Jaipur Vidyut Vitran Nigam Limited, 400 kV GSS Building, Ajmer Road, Heerapura, Jaipur.

    20. Northern Central Railway, Allahabad.

    21. BSES Yamuna Power Limited, Shakti Kiran Building, Karkardooma, Delhi-110092.

    22. BSES Rajdhani Power Limited, BSES Bhawan, Nehru Place, New Delhi

    23. Tata Power Delhi Distribution Limited, 33 kV Sub-station, Building

    Hudson Lane, Kingsway Camp

    North Delhi-110009

    24. New Delhi Municipal Council, Palika Kendra, Sansad Marg, New Delhi-110002.

    25. Madhya Pradesh Power Management Company Limited, Shakti Bhawan, Rampur,

    Jabalpur-482008.

    26. Maharashtra State Electricity Distribution Company Limited, Prakashgad, 4th Floor, Andheri (East),

    Mumbai-400052.

    27. Gujarat Urja Vikas Nigam Limited, Sardar Patel Vidyut Bhawan, Race Course Road, Vadodara-390 007

    28. Electricity Department, Government of Goa,Vidyut Bhawan, Panaji, Near Mandvi Hotel, Goa-403001.

    29. Electricity Department, Administration of Daman & Diu, Daman-396210.

    Page 3 of 162

    30. Electricity Department, Administration of Dadra Nagar Haveli, U.T., Silvassa-396230.

    31. Chhattisgarh State Electricity Board, P.O.Sunder Nagar, Dangania, Raipur, Chhatisgaarh-492013.

    32. Madhya Pradesh Audyogik Kendra, Vikas Nigam (Indore) Limited, 3/54, Press Complex, Agra-Bombay Road, Indore-452008.

    33. Karnataka Power Transmission Corporation Limited, Kaveri Bhavan, Bangalore-560 009.

    34. Transmission Corporation of Andhra Pradesh Limited, Vidyut Soudha, Hyderabad-500082.

    35. Kerala State Electricity Board, Vaidyuthi Bhavanam, Pattom, Thiruvananthapuram-695004.

    36. Tamilnadu Electricity Board, NPKRR Maaligai, 800, Anna Salai, Chennai-600002.

    37. Electricity Department, Government of Pondicherry, Pondicherry-605001.

    38. Eastern Power Distribution Company of Andhra Pradesh Limited, P&T Colony, Seethmmadhara,

    Vishakhapatnam, Andhra Pradesh.

    39. Southern Power Distribution Company of Andhra Pradesh Limited, Srinivasasa Kalyana Mandapam Backside,

    Tiruchanoor Road, Kesavayana Gunta,

    Tirupati-517501, Chittoor District, Andhra Pradesh.

    40. Central Power Distribution Company of Andhra Pradesh Limited, Corporate Office, Mint Compound,

    Hyderabad-500 063, Andhra Pradesh.

    41. Northern Power Distribution Company of Andhra Pradesh Limited, Opp. NIT Petrol Pump, Chaitanyapuri, Kazipet,

    Warangal-506004, Andhra Pradesh.

    Page 4 of 162

    42. Banglore Electricity Supply Company Limited, Corporate Office, K.R. Circle,

    Bangalore-560001, Karnataka.

    43. Gulbarga Electricity Supply Company Limited, Station Main Road, Gulburga, Karnataka.

    44. Hubli Electricity Supply Company Limited, Navanagar, PB Road,

    Hubli, Karnataka.

    45. MESCOM Corporate Office, Paradigm Plaza, Ab Shetty Circle Mangalore-575001, Karnataka

    46. Chamundeswari Electricity Supply Coropration Limited, 927, L J Avenue Ground Floor,

    New Kantharaj Urs Road, Saraswatipuram,

    Mysore-570 009, Karnataka.

    47. Telanagana State Pc Co-Ordination Committee R.No. 547/A Block , Vidyut Soudha, Somajiguda, Khairathabad, Somajiguda, Hyderabad-500082, Andhra Pradesh.

    48. Andhra Pradesh Power Co-ordination Committee, Room No. 547, 5th Floor, Block-A,

    Vidyut Soudha, Somajiguda, Khairathabad, Hyderabad-500 082, Andhra Pradesh.

    49. Bihar State Electricity Board, Vidyut Bhawan, Bailey Road, Patna-800001.

    50. West Bengal State Electricity Distribution Company Limited, Bidyut Bhawan, Bidhan Nagar, Block DJ,

    Sector-II, Salt Lake City, Calcutta-700091.

    51. Grid Corporation of Orissa Limited, Shahid Nagar, Bhubaneswar-751007.

    52. Damodar Valley Corporation, DVC Tower, Maniktala,Civic Centre, VIP Road, Calcutta-700054.

    53. Power Department, Government of Sikkim, Gangtok-737101.

    Page 5 of 162

    54. Jharkhand State Electricity Board, In Front of Main Secretariat, Doranda, Ranchi-834002.

    55. North Bihar Power Distribution Company Limited, Vidyut Bhawan, Bailey Road,

    Patna, Bihar-800001.

    56. South Bihar Power Distribution Company Limited, Vidyut Bhawan, Bailey Road,

    Patna, Bihar-800001.

    57. Tata Steel Limited, Generation Office (W-175) Jamshedpur, Jharkhand.

    58. Maithan Power Limited, MA-5, Gogna Colony, Maithan Dam Post Office, Distt: Dhanbad-828207, Jharkhand.

    59. Ind-Barath Energy (Utkal) Limited, Plot No: 30-A, Road No. 1, Film Nagar, Jubilee Hills, Hyderabad-500033, Andhra Pradesh.

    60. AD Hydro Power Limited, Bhilwara Towers, A-12, Sector-1, Noida-201301, Uttar Pradesh.

    61. Lanco Budhil PowerPrivate Limited, Plot No. 397, Udyog Vihar Phase-III, Gurgaon, Haryana.

    62. Himachal Sorang Power Private Limited, D-7, Sector - I, Lane - 1, 2nd Floor, New Shimla, Shimla-171009, Himachal Pradesh.

    63. MB Power (Madhya Pradesh) Limited, 239, Okhla Industrial Area, Phase-III, New Delhi, 110020.

    64. Himachal Baspa Power Company Limited, Karcham Wangtoo Hep, Sholtu Colony, PO: Tapri, Distt: Kinnaur, 172104, Himachal Pradesh.

    65. Jindal Power Limited, 6thFloor, MTNL Building, 8, Bhikaji Cama Place, New Delhi-110066.

    Page 6 of 162

    66. KSK Mahanadi Power Company Limited, 8-2-293/82/A/431/A Road No 22, Jubilee Hills, Hyderabad, Andhra Pradesh-500033.

    67. PTC India Limited, 2nd Floor, NBCC Tower, 15, Bhikaji Cama Place, New Delhi-110066.

    68. IL&FS Tamil Nadu Power Company Limited, C. Pudhupettai Post, Parangipettai (Via), Chidambaram (Tk), Cuddallore, 608502, Tamil Nadu.

    69. Adani Power Limited, 10 B, Sambhav Press Building, Judges Bungalow Road, Badakdev,

    Ahmedabad-380015.

    70. Torrent Power Limited, Naranpura Zonal Office, Sola Road, Ahmedabad-380013.

    71. Heavy Water Board, Vikram Sarabhai Bhavan, 5th Floor, Anushaktinagar, Mumbai-400094.

    72. ACB India Limited, 7th Floor, Corporate Tower, Ambience Mall, NH-8, Gurgaon-122001, Haryana.

    73. EMCO Energy Limited, Plot No. - F-5, Road No. - 28, Wagle Industrial Area, Thane, Mumbai-400604.

    74. Spectrum Coal and Power Limited, 7thFloor, Corporate Tower, Ambience Mall, NH 8, Gurgaon-122 001, Haryana.

    75. BARC,

    TRP, Post-Ghivali, Distt.-Palghar, BARC Plant Site, 401505, Maharashtra.

    76. Balco, Raipur, Bharat Aluminium Company Limited, Captive Power Plant-II, Balconagar, Korba-495684.

    Page 7 of 162

    77. Dhariwal Infrastructure Limited, C-6 Tadali Growth Centre, M.I.D.C.T, District Chandrapur, Maharashtra-442406.

    78. DB Power Limited, Opp. Dena Bank, C-31, G- Block, 3rd Floor, Naman Corporate Link, Bandar - Kurla Complex, Bandra (East), Mumbai-400051, Maharashtra.

    79. NEEPCO, 15, NBCC Tower, Bhikaji Cama Place, New Delhi.

    80. NHPC Limited, NHPC Office Complex, Sector-33, Faridabad.

    81. NTPC Limited, Core-7, Scope Complex, New Delhi. .…Respondent(s) For Petitioner : Shri S. S. Raju, PGCIL Shri D. K. Biswal, PGCIL

    Shri Ved Prakash Rastogi, PGCIL Shri Amit Yadav, PGCIL

    For Respondents : Shri Manish Kumar Choudhary, Advocate, Bihar Discoms

    Shri Anindya Khare, MPPMCL

    ORDER

    Power Grid Corporation of India Limited has filed the instant petition for truing up of transmission tariff for the period from the date of commercial operation (COD) to 31.3.2019 under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as 'the 2014 Tariff Regulations') and determination of transmission tariff for 2019-24 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 (hereinafter referred to as 'the 2019 Tariff Regulations') in respect of the following transmission assets "Transmission System associated

    Page 8 of 162

    with North East-Northern/ Western Inter Connector-I" in North Eastern Region (hereinafter referred to as the 'transmission project').

    Asset-1: 2nd315 MVA,400/220 kV ICT at Misa;

    Asset-2: 80 MVAR Bus Reactor at Balipara;

    Asset-3: 80 MVAR Bus Reactor at Bongaigaon;

    Asset-4: 400 kV, D/C (Quad) Balipara-Bongaigaon Transmission Line along with associated bays at Bongaigaon Sub-station and Balipara Sub-station including 30% FSC at Balipara and 4 X 63 MVAR, 420 kV LR;

    Asset-5: 200 MVA, 400/132/33 kV ICT - 2 along with associated bays at BNC;

    Asset-6: 80 MVAR Bus Reactor - 1 along with associated bays at Biswanath Chariali;

    Asset-7: 80 MVAR Bus Reactor - 2 along with associated Bays at Biswanath Chariali;

    Asset-8: Augmentation of 400 kV Agra Sub-Station by 1X315 MVA, 400/220/33 kV ICT along with associated bays;

    Asset-9: 400 kV D/C Balipara-Biswanath Chariali # 3 Transmission Line along with associated bays at Balipara and Biswanath Chariali Pooling Station;

    Asset-10: 400 kV D/C Balipara-Biswanath Chariali # 4 Transmission Line along with associated bays at Balipara and Biswanath Chariali Pooling Station;

    Asset-11: 2X80 MVAR, 400 kV Switchable Line Reactors for 400 kV D/C Agra-Sikar Transmission Line at Agra Sub-station;

    Asset-12: 63 MVAR Line Reactor (to be used as Bus Reactor) connected to 400 kV Lower Subansiri-BNC-I line bay alongwith associated bays at BNC Sub-station;

    Asset-13: 63 MVAR line reactor (to be used as Bus Reactor) connected to 400 kV Lower Subansiri-BNC-III line bay alongwith associated bays at BNC Sub-station;

    Asset-14: Loop In and Loop Out (LILO) of 400 kV Ranganadi-Balipara-I T/L at Biswanath Chariali PS alongwith associated bays at Biswanath Chariali Pooling Station;

    Page 9 of 162

    Asset-15: Loop In and Loop Out (LILO) of 400 kV Ranganadi-Balipara-II Transmission Line at Biswanath Chariali Pooling Station alongwith associated bays at Biswanath Chariali Pooling Station;

    Asset-16: 132 kV D/C BNC (PG) - BNC (AEGCL) Transmission Line alongwith associated bays at BNC (AEGCL) and BNC Pooling Station (PGCIL);

    Asset-17: 200 MVA, 400/132/33 kV ICT- I at Biswanath Chariali Pooling Station;

    Asset-18: ± 800 kV HVDC Biswanath Chariali - Agra Pole-1 (1500 MW HVDC Terminals at Biswanath Chariali and Agra each along with the ± 800 kV Hexa Lapwing Transmission Line);

    Asset-19: ±800 kV Biswanath Chariali-Agra HVDC Pole-II (1500 MW HVDC Terminal at Biswanath Chariali and Agra) along with Earth Electrode line and Earth Electrode Station for both BNC and Agra;

    2. The Petitioner has made the following prayers in the instant petition:

    "1) Approve the trued up Transmission Tariff for 2014-19 block and transmission tariff for 2019-24 block for the assets covered under this petition as per para 10.2 and 11.1 above.

    2) Admit the capital cost claimed and additional capitalization incurred during 2014- 19 and also allow the projected additional capitalization during 2019-24.

    3) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission as provided in Tariff Regulation 2014 and Tariff regulations 2019 as per para 10.2 and 11.1 above for respective block.

    4) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 70 (1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, and other expenditure ( if any) in relation to the filing of petition.

    5) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the respondents in terms of Regulation 70 (3) and (4) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,

    2019.

    6) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2019-24 period, if any, from the respondents.

    Page 10 of 162

    7) Allow the Petitioner to file a separate petition before Hon'ble Commission for claiming the overall security expeses and consequetional IOWC on that security expenses as mentioned at para 11.1 above.

    8) Allow the Initial spares claimed as project as a whole.

    9) Allow the Petitioner to claim the capital spares at the end of tariff block as per actual.

    10) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the respondents, if GST on transmission is levied at any rate in future. Further, any taxes including GST and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries.

    and pass such other relief as Hon'ble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice". (In this order, Asset-1 to Asset-19 have been referred to as "transmission assets"

    while turing up the tariff of 2014-19 period. In 2019-24 tariff period, Asset-1 to Asset-17 have been referred to as 'Combined Asset' and Asset-18 and Asset-19 have been referred individually.)

    Background

    3. The brief facts of the case are as follows:

    (a) Investment Approval (IA) for transmission project was accorded in the 219thmeeting of the Board of Directors of the Petitioner's company held on 24.2.2009 and conveyed vide Memorandumn Ref. No. C/CP/NER-NR.WR Intr-I dated 27.2.2009 at an estimated cost of ₹1113019 lakh including IDC of ₹106605 lakh based on 4thquarter, 2008 price level.

    (b) Revised Cost Estimate (RCE-I) of the transmission project was accorded by the Board of Directors of the Petitioner's company in its 323rdmeeting held on 30.11.2015 at an estimated cost of ₹1376271 lakh including IDC of ₹174732 lakh based on April, 2015 price level and communicated vide Memorandum No. C/CP/RCE:NE-NR/WR Interconnector-I dated 9.12.2015).

    (c) Revised Cost Estimate-II (RCE-II) for the transmission project was accorded by Board of Directors of the Petitioner's company in its 363rd

    Page 11 of 162

    meeting held on 7.3.2019 and communicated vide Memorandum No. C/CP/RCE-II/PA1819-12-0AY-RTE023 dated 28.3.2019 at an estimated cost of ₹1471910 lakh including IDC of ₹176395 lakh based on March, 2018 price level.

    (d) The scope of work covered under the transmission project is as follows:

    Transmission Lines Part-A: North East - Northern/Western Interconnector-I:

    (i) Biswanath Chariali - Agra ±800 kV, 6000 MW HVDC bipole line (This includes four (4) number of corridors with ± 800 kV HVDC towers in the chicken neck area. One corridor has been utilized by stringing of the Biswanath Chariyali - Agra HVDC bipole line while only towers will be erected in the other three corridors (No Stringing)*. Further, this includes Earth Electrode line at Biswanath Chariyali end and at Agra end.)

    (ii) Balipara-Biswanath Chariali 400 kV D/C line

    (iii) LILO of Ranganadi-Balipara 400 kV D/C line at Biswanath Chariali (Pooling Point)

    (iv) Biswanath Chariali - Biswanath Chariali (AEGCL) 132 kV D/C line

    Part-B: Transmission System for immediate evacuation of power from Kameng HEP

    (i) Kameng-Balipara 400 kV D/C line

    (ii) Balipara-Bongaigaon 400 kV D/C (Quad conductor) with 30% Fixed Series Compensation at Balipara end

    Part-C: Transmission System for immediate evacuation of power from Lower Subansiri HEP

    (i) Lower Subansiri-Biswanath Chariali (Pooling Point) - 2 numbers 400 kV D/C lines with twin lapwing conductor

    Sub-stations Part-A: North East-Northern/Western Interconnector - I

    (i) Establishment of 400/132 kV Pooling Station at Biswanath Chariali with 2x200 MVA, 400/132/33 kV transformers alongwith associated line bays;

    Page 12 of 162

    (ii) HVDC rectifier module of 3000 MW at Biswanath Chariali and inverter module of 3000 MW capacity at Agra;

    (iii) Augmentation of 400 kV Agra Sub-Station by 4x105 MVA, 400/220/33 kV transformer along with associated bays

    (iv) Extension of 400 kV line bays at Balipara Sub-station

    (v) Extension of 132 kV line bays at Biswanath Chariali (AEGCL)

    Part-B: Transmission System for immediate evacuation of power from Kameng HEP

    (i) 2nd315 MVA, 400/220 kV ICT at MISA

    (ii) Extension of 400 kV line bays at Bongaigaon and Balipara Sub- stations

    Part-C: Transmission System for immediate evacuation of power from Lower Subansiri HEP

    (i) Extension of 400 kV line bays at Biswanath Chariali Pooling Sub- station

    Reactive Compensation A. Line Reactors

    Sl. No. Name of Line Line Reactor
    1. 2x400 kV D/C L. Subansiri- Biswanath Chariali line 2x63 MVAR* at Biswanath Chariyali end on each ckts (total 4 numbers of reactors out of which 2 numbers of reactors are being utilized as bus reactors)**
    2. 400 kV, D/C (Quad Moose) Balipara-Bongaigaon line 1x63 MVAR at both end on each ckt. (total 4 numbers of reactors)
    3. 400 kV D/C Balipara-Biswanath Chariali line resulting from LILO of Ranganadi-Balipara 400 kV D/C line at Biswanath Chariali 1x50 MVAR Existing Fixed line reactor in each circuit at Balipara end to be made switchable at the present location itself.
    4. Agra-Sikar 400 kV D/C line 2x80 MVAR line reactors in place of 2x50 MVAR existing line reactors at Agra end.***

    *Switchable line reactor

    **As agreed during 6th NER Standing Committee Meeting held on 3.10.2016.

    *** As agreed during 33rd SCM of NR held on23.12. 2013.

    Page 13 of 162

    B. Bus Reactors

    Sl. No. Name of Sub-station Bus Reactor
    1. Biswanath Chariali 2x80 MVAR
    2. Bongaigaon 1x80 MVAR
    3. Balipara 1x80 MVAR
    4. Lower Subansiri 1x80 MVAR*
    5. Kameng 1x80 MVAR*

    * These reactors would be a part of generation switchyard

    (e) As per IA dated 24.2.2009, the transmission assets were scheduled to be put into commercial operation within 54 months for Part-A and 48 months for Part-B and C from the date of IA. Therefore, the scheduled date of commercial operation (SCOD) of the transmission assets for Part-A was 1.8.2013 while for Part-B and Part-C it was 26.3.2013. The details of transmission tariff approved for 2014-19 tariff period in respect of the transmission assets are as follows:

    Asset nomenculature in previous petition Asset No. Name of Asset COD Description of the Petition No. and date of order by which tariff for 2014-19 tariff period allowed Remarks
    Asset 1 2nd 315 MVA, 400/220 kV ICT at Misa 1.7.2012 Vide order dated 11.3.2016 in Petition No. 391/TT/2014 Covered under instant petition for true-up of 2014-19 tariff period and determination of tariff of 2019-24 tariff period
    Asset 2 80 MVAR Bus Reactor at Balipara 1.10.2012 Vide order dated 28.1.2016 in Petition No. 131/TT/2015
    Asset 3 80 MVAR Bus Reactor at Bongaigaon 1.3.2013 Vide order dated 18.2.2016 in Petition No. 217/TT/2015
    Asset 4 400 kV, D/C (Quad) Balipara- Bongaigaon Transmission Line along with associated bays at Bongaigaon Sub- station and Balipara Sub- station including 30% FSC at Balipara and 4x63 MVAR, 420 kV LR 7.11.2014 Vide order dated 14.7.2016 in Petition No. 65/TT/2015
    Asset-I 5 200 MVA, 400/132/33 kV ICT- 1.10.2015

    Page 14 of 162

    Asset Asset Name of Asset COD Description of the Remarks nomenculature No. Petition No. and date in previous of order by which

    petition tariff for 2014-19

    tariff period allowed

    2 along with associated bays at

    BNC

    80 MVAR Bus Reactor-1 along Asset-II 6 with associated 3.10.2015 Bays at Biswanath

    Chariali

    80 MVAR Bus Reactor-2 along Asset-III 7 with associated 26.2.2016 Bays at Biswanath

    Chariali

    Augmentation of

    400 kV Agra Sub-

    Station by 1X315

    Asset-IV 8 10.12.2015

    MVA, 400/220/33

    kV ICT along with Vide order dated associated bays. 26.5.2016 in Petition 400 kV D/C No. 259/TT/2015

    Balipara-

    Biswanath Chariali

    #3 Transmission

    Asset-Va 9 Line along with 12.10.2015 associated bays at

    Balipara and

    Biswanath Chariali

    PS.

    400 kV D/C Balipara- Biswanath Chariali #4 Transmission Asset-Vb 10 Line along with 1.10.2015 associated bays at

    Balipara and

    Biswanath Chariali

    PS.

    2X80 MVAR, 400

    kV Switchable Line Reactors for 400 Asset-I 11 kV D/C Agra-Sikar 1.8.2017 Transmission Line Vide order dated at Agra Sub- 25.6.2019 in Petition station. No. 242/TT/2018

    63 MVAR Line Reactor (to be Asset-II 12 21.7.2017 used as Bus

    Reactor)

    Page 15 of 162

    Asset Asset Name of Asset COD Description of the Remarks nomenculature No. Petition No. and date in previous of order by which

    petition tariff for 2014-19

    tariff period allowed

    connected to 400 kV Lower

    Subansiri-BNC-I line bay alongwith associated bays at BNC sub-station.

    63 MVAR line reactor (to be used as Bus Reactor) connected to 400 Asset-III 13 kV Lower 11.12.2017 Subansiri-BNC-III

    line bay alongwith

    associated bays at

    BNC sub-station.

    Loop-In-and-Loop-

    Out (LILO) of 400

    kV Ranganadi-

    Balipara-I

    Transmission Line

    Asset-I 14 at Biswanath 28.10.2015 Chariali Pooling

    Station alongwith

    associated bays at

    Biswanath Chariali

    Pooling Station.

    Loop-In-and-Loop-

    Out (LILO) of 400

    kV Ranganadi-

    Balipara-II

    Transmission Line Vide order dated Asset-II 15 at Biswanath 27.10.2015 17.12.2019 in Petition Chariali Pooling No. 363/TT/2018

    Station alongwith

    associated bays at

    Biswanath Chariali

    Pooling Station.

    132 kV D/C BNC

    (PG)-BNC (AEGCL)

    Transmission Line

    alongwith

    Asset-III 16 1.10.2015

    associated bays at

    BNC (AEGCL) and

    BNC Pooling

    Station (PGCIL)

    200 MVA,

    Asset-IV 17 400/132/33 kV ICT-I 19.12.2015 at Biswanath

    Page 16 of 162

    Asset Asset Name of Asset COD Description of the Remarks nomenculature No. Petition No. and date in previous of order by which

    petition tariff for 2014-19

    tariff period allowed

    Chariali Pooling Station

    ± 800 kV HVDC Biswanath Chariali- Agra Pole-1 (1500

    MW HVDC

    Terminals at Asset-V 18 Biswanath Chariali 1.11.2015 and Agra each

    along with the ±

    800 kV Hexa

    Lapwing

    Transmission Line)

    ± 800 kV

    Biswanath Chariali-

    Agra HVDC POLE-

    II (1500 MW HVDC

    Terminal at

    Biswanath Chariali Asset-VI 19 2.9.2016 and Agra) along with Earth

    Electrode line and Earth Electrode Station for both BNC and Agra.

    Kameng-Balipara 400 kV D/C line Vide order dated 31.8.2021 in Petition alongwith No. 121/TT/2019 and trued up vide - 20 30.3.2018

    associated bays order dated 7.10.2022 in Petition No. and 1x80 MVAr 165/TT/2022.

    Bus Reactor

    Lower Subansiri-

    Biswanath Chariali

    (Pooling Point)-2

    numbers 400 kV

    D/C lines with twin

    Lapwing conductor Under implementation and petition will be filed under - 21

    along with 2019 Tariff Regulations.

    associated bays

    and 1x80 MVAr

    Bus Reactor and

    4x63 MVAr Line

    Reactor

    (f) The Petitioner has submitted that entire scope of work defined under the transmission project consists of 21 number of transmission assets

    Page 17 of 162

    (Asset-1 to Asset-21 as enumerated above), out of which Asset-1 to Asset-19 are covered in the instant petition. Asset-20, as detailed above in the table, has already been trued up vide order dated 7.10.2022 in Petition No. 165/TT/2022 while Asset-21, as detailed above in the table, is still under implementation.

    4. The Respondents are distribution licensees, power departments, power utilities and transmission licensees, who are procuring transmission services from the Petitioner, mainly beneficiaries of the Northern Eastern Region.

    5. The Petitioner has served the petition on the Respondents and notice regarding filing of this petition has also been published in the newspapers in accordance with Section 64 of the Electricity Act, 2003. No comments or suggestions have been received from the general public in response to the aforesaid notices published in the newspapers by the Petitioner. A combined reply has been filed on behalf of Bihar State Electricity Board (BSEB), North Bihar Power Distribution Company Limited (NBPDCL), South Bihar Power Distribution Company Limited (SBPDCL), Respondent Nos. 49, 55 and 56 (collectively referred to as "Bihar Discoms" vide affidavit dated 20.7.2021 and M.P. Power Management Company Limited (MPPMCL), Respondent No. 25 vide affidavit dated 18.2.2021. The Bihar Discoms have raised the issue of Return on Equity (RoE), GST, floating rate of interest, filing fee and expenses and sharing of transmission charges. MPPMCL has raised the issue of RoE, effect of GST and Initial Spares. The Petitioner has filed its rejoinders to the reply of Bihar Discoms and MPPMCL vide affidavits dated 18.8.2021 and 8.7.2021, respectively. The issues raised by the Respondents and the clarifications given by the Petitioner have been considered in the relevant portions of this order.

    Page 18 of 162

    6. The hearing in this matter was held on 28.6.2022 through video conference and order was reserved.

    7. During the course of hearing on 28.6.2022, the Petitioner informed that it has filed an appeal, being Appeal No. 188 of 2020, before the Appellate Tribunal for Electricity (APTEL) against the Commission's order dated 25.6.2019 in Petition No. 242/TT/2018 on the issue of payment of Incidental Expenses During Construction (IEDC) on account of time over-run. The APTEL vide judgment dated 13.9.2021, remanded the matter back to the Commission observing that the Commission has already decided that time over-run is not attributable to the Appellant (Petitioner in the instant matter) due to uncontrollable factors as specified in Regulation 12 of the 2014 Tariff Regulations, IEDC should have been allowed as per actuals after due prudence check. The Petitioner vide affidavit dated 8.3.2021 has given details of IEDC in Form-12A in respect of the transmission assets covered in the present petition and has requested to consider the same for determination of tariff.

    8. Having heard the representatives of the Petitioner and MPPMCL, learned counsel for Bihar Discoms and having perused the material on record, we proceed to dispose of the petition.

    9. This order is issued considering the submissions made by the Petitioner in the petition vide affidavit dated 20.3.2020 and affidavits dated 8.3.2021, 5.8.2021 and 4.7.2022, replies filed by Bihar Discoms and MPPMCL vide affidavits dated 20.7.2021 and 18.2.2021, respectively, and rejoinder of the Petitioner vide affidavits dated 18.8.2021 and 8.7.2021, respectively.

    Page 19 of 162

    10. It has been placed before us that MPPMCL has been raising the same issue of RoE in other petitions as well despite clear findings of the Commission rejecting the contentions of MPPMCL. The contentions of MPPMCL regarding RoE have been rejected by the Commission in other petitions including Petition No. 348/TT/2019. As MPPMCL has not challenged the findings, the same have attained finality. In view of these, the pleas raised by MPPMCL regarding grossing up of RoE are rejected. Therefore, MPPMCL's submissions, Petitioner's clarifications thereto and the Commission's findings on the issue of RoE have not been repeated here. Other issues of MPPMCL and the Petitioner's clariofications are dealt in the relevant portions of the order.

    11. Bihar Discoms has raised the issue of MAT rate and RoE in the instant petition. BSPHCL, the successor of BSEB, Respondent No. 49 raised the issue of MAT rate and RoE earlier in other petitions. The Commission rejected the contentions of BSPHCL in those petitions, including in Petition No. 476/TT/2019 vide order dated 28.5.2021. BSPHCL has not challenged those findings and the same have attained finality. As such, the issue of MAT and RoE raised by the Bihar Discoms in the instant petition are rejected. The issues which are specific to the instant petition and not dealt by the Commission earlier are considered in the relevant paragraphs of this order.

    12. Bihar Discoms have submitted that truing up of transmission tariff for 2014- 19 tariff period is being carried out on account of actual ACE during 2014-19 period, change in MAT rate as well as floating rate of interest during 2014-19. Para

    10.3 of the petition contains the summarised trued up annual transmission tariff for

    Page 20 of 162

    2014-19 period and details are provided in Enclosure-4 attached with the petition. Bihar Discoms have further submitted that on perusal of summary of tariff of Enclosure-4, heading under depreciation and O&M Expenses while arriving at final revised AFC based on truing up but details of these two heads are not mentioned in para 6.6 of the petition.

    13. In response, the Petitioner has submitted that the truing up of transmission tariff for 2014-19 tariff period is being carried out as per the 2014 Tariff Regulations and the calculation for depreciation and O&M Expenses has already been submitted in prescribed forms i.e. in Form-10A and Form-2.

    14. We have considered the submissions of the Petitioner and Bihar Discoms. The contensions raised by Bihar Discoms regarding depreciation and O&M Expenses for truing up of tariff of 2014-19 tariff period and the clarifications given by the Petitioner are dealt in the relevant portions of this order.

    Truing up of Annual Fixed Charges for 2014-19 Tariff Period

    15. The details of the trued-up transmission charges claimed by the Petitioner in respect of the transmission assets for 2014-19 tariff period are as follows:

    (₹ in lakh) Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 117.51 125.66 127.00 127.31 127.39 Interest on Loan 120.38 119.30 109.46 98.07 86.23 Return on Equity 133.05 143.13 144.59 144.93 145.41 Interest on Working Capital 14.20 14.79 14.82 14.77 14.72 O&M Expenses 102.51 105.91 109.43 113.08 116.81

    Total 487.65 508.79 505.30 498.16 490.56 (₹ in lakh)

    Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 48.06 50.27 51.57 51.60 51.60

    Page 21 of 162

    Asset-2 Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Interest on Loan 49.37 47.56 44.47 39.87 35.28 Return on Equity 53.59 56.31 57.73 57.77 57.92 Interest on Working Capital 6.81 6.99 7.10 7.11 7.13 O&M Expenses 60.30 62.30 64.37 66.51 68.71

    Total 218.13 223.43 225.24 222.86 220.64 (₹ in lakh)

    Asset-3

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 31.36 36.01 39.50 39.50 39.50 Interest on Loan 33.81 36.38 36.80 32.27 28.49 Return on Equity 34.97 40.33 44.22 44.23 44.34 Interest on Working Capital 5.64 6.04 6.33 6.35 6.38 O&M Expenses 60.30 62.30 64.37 66.51 68.71

    Total 166.08 181.06 191.22 188.86 187.42 (₹ in lakh)

    Asset-4

    2014-15 2018-19

    Particulars (pro-rata 2015-16 2016-17 2017-18 145 days)

    Depreciation 2380.84 6117.41 6178.09 6205.00 6220.10 Interest on Loan 3389.82 8165.41 7544.47 6794.43 6187.55 Return on Equity 1769.77 4582.81 4649.95 4681.59 4711.12 Interest on Working Capital 188.71 473.62 463.57 449.02 437.47 O&M Expenses 274.06 712.77 736.32 760.90 786.15

    Total 8003.20 20052.02 19572.40 18890.94 18342.39 (₹ in lakh)

    Asset-5

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 183 days)

    Depreciation 54.16 116.15 125.06 128.25 Interest on Loan 83.24 167.90 165.55 157.57 Return on Equity 45.25 100.60 112.16 116.61 Interest on Working Capital 6.79 14.19 14.78 14.96 O & M Expenses 46.73 96.55 99.76 103.07

    Total 236.17 495.39 517.31 520.46 (₹ in lakh)

    Asset-6

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 181 days)

    Depreciation 34.17 75.75 83.25 85.07 Interest on Loan 52.90 109.38 108.70 102.60 Return on Equity 28.72 66.32 75.67 78.14 Interest on Working Capital 4.37 9.34 9.83 9.92

    Page 22 of 162

    Asset-6 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 181 days)

    O&M Expenses 30.81 64.37 66.51 68.71

    Total 150.97 325.16 343.96 344.44 (₹ in lakh)

    Asset-7

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 35 days)

    Depreciation 7.04 79.11 85.03 86.41 Interest on Loan 10.97 117.08 115.77 109.46 Return on Equity 5.92 68.13 75.37 77.26 Interest on Working Capital 0.88 9.64 10.03 10.08 O&M Expenses 5.96 64.37 66.51 68.71

    Total 30.77 338.33 352.71 351.92 (₹ in lakh)

    Asset-8

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 113 days)

    Depreciation 100.02 350.70 375.74 381.09 Interest on Loan 144.36 477.32 466.79 436.71 Return on Equity 78.69 285.17 314.55 321.76 Interest on Working Capital 10.73 36.65 38.02 38.00 O& M Expenses 59.61 199.55 206.16 213.01

    Total 393.41 1349.39 1401.26 1390.57 (₹ in lakh)

    Asset-9

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 172 days)

    Depreciation 102.70 226.75 230.63 241.99 Interest on Loan 147.36 306.08 281.09 272.23 Return on Equity 82.00 183.99 188.82 203.98 Interest on Working 24.12

    10.88 23.61 23.47

    Capital

    O&M Expenses 58.56 128.74 133.02 137.42

    Total 401.50 869.17 857.03 879.74 (₹ in lakh)

    Asset-10

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 183 days)

    Depreciation 329.71 689.28 714.23 738.67 Interest on Loan 453.33 886.99 824.02 780.74

    Page 23 of 162

    Asset-10 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 183 days)

    Return on Equity 254.10 541.17 569.59 600.46 Interest on Working Capital 28.50 58.30 58.40 59.00 O&M Expenses 83.76 173.06 178.81 184.74

    Total 1149.40 2348.80 2345.05 2363.61 (₹ in lakh)

    Asset-11

    2017-18 2018-19

    Particulars (pro-rata

    242 days)

    Depreciation 46.26 73.39 Interest on Loan 53.42 79.68 Return on Equity 34.83 56.57 Interest on Working Capital 2.88 4.50 O&M Expenses 0.00 0.00

    Total 137.39 213.14 (₹ in lakh)

    Asset-12

    2017-18 2018-19 Particulars (pro-rata 254 days)

    Depreciation 81.66 124.58 Interest on Loan 107.26 153.63 Return on Equity 66.33 103.63 Interest on Working Capital 7.86 11.73 O&M Expenses 46.28 68.71

    Total 309.39 462.28 (₹ in lakh)

    Asset-13

    2017-18 2018-19 Particulars (pro-rata 111 days)

    Depreciation 35.72 124.95 Interest on Loan 46.87 155.95 Return on Equity 28.98 103.59 Interest on Working Capital 3.43 11.79 O&M Expenses 20.23 68.71

    Total 135.23 464.99

    Page 24 of 162

    (₹ in lakh) Asset-14 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 156 days)

    Depreciation 49.48 126.80 131.82 134.43 Interest on Loan 75.31 182.15 175.65 165.95 Return on Equity 40.04 102.08 105.94 108.48 Interest on Working Capital 10.12 24.80 25.37 25.79 O&M Expenses 114.57 277.71 286.94 296.45

    Total 289.52 713.54 725.72 731.10 (₹ in lakh)

    Asset-15

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 157 days)

    Depreciation 165.00 416.05 432.11 450.14 Interest on Loan 231.15 545.08 500.51 475.84 Return on Equity 126.34 317.97 330.07 347.86 Interest on Working Capital 15.26 37.23 37.11 37.63 O&M Expenses 58.53 140.97 145.65 150.48

    Total 596.28 1457.30 1445.45 1461.95 (₹ in lakh)

    Asset-16

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 183 days)

    Depreciation 66.52 146.08 155.63 161.50 Interest on Loan 100.04 203.82 190.97 180.64 Return on Equity 53.48 116.83 124.12 129.56 Interest on Working Capital 8.62 18.09 18.42 18.70 O&M Expenses 64.32 132.91 137.32 141.91

    Total 292.98 617.73 626.46 632.31 (₹ in lakh)

    Asset-17

    2015-16 2018-19

    Particulars (pro-rata 2016-17 2017-18 104 days)

    Depreciation 37.56 141.08 145.88 151.78 Interest on Loan 54.71 195.92 187.29 180.35 Return on Equity 30.11 112.99 116.83 123.51 Interest on Working Capital 4.29 15.69 15.87 16.18 O&M Expenses 26.55 96.55 99.76 103.07

    Total 153.22 562.23 565.63 574.89

    Page 25 of 162

    (₹ in lakh) Asset-18 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 152 days)

    Depreciation 17572.10 43496.71 44571.50 39495.13 Interest on Loan 13588.80 33611.39 32656.08 28979.47 Return on Equity 13261.54 32834.94 33678.35 30010.93 Interest on Working Capital 1073.79 2660.89 2690.24 2393.72 O&M Expenses 928.24 2357.44 2487.53 2295.16

    Total 46424.47 114961.37 116083.70 103174.41 (₹ in lakh)

    Asset-19

    2016-17 2018-19

    Particulars (pro-rata 2017-18

    211 days)

    Depreciation 6359.69 11659.93 10450.71 Interest on Loan 2953.57 5797.79 6015.78 Return on Equity 4935.08 9063.24 8153.98 Interest on Working Capital 342.59 638.02 593.33 O&M Expenses 611.62 1145.05 1082.72

    Total 15202.55 28304.03 26296.52

    16. The details of the trued-up Interest on Working Capital (IWC) claimed by the Petitioner in respect of the transmission assets for 2014-19 tariff period are as follows:

    (₹ in lakh) Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    O&M Expenses 8.54 8.83 9.12 9.42 9.73 Maintenance Spares 15.38 15.89 16.41 16.96 17.52 Receivables 81.28 84.80 84.22 83.02 81.76

    Total of Working Capital 105.20 109.52 109.75 109.40 109.01 Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of working Capital 14.20 14.79 14.82 14.77 14.72

    (₹ in lakh) Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    O&M Expenses 5.03 5.19 5.36 5.54 5.73 Maintenance Spares 9.05 9.35 9.66 9.98 10.31 Receivables 36.36 37.24 37.54 37.14 36.77

    Total of Working Capital 50.44 51.78 52.56 52.66 52.81

    Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of working Capital 6.81 6.99 7.10 7.11 7.13

    Page 26 of 162

    (₹ in lakh) Asset-3

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    O&M Expenses 5.03 5.19 5.36 5.54 5.73 Maintenance Spares 9.05 9.35 9.66 9.98 10.31 Receivables 36.36 37.24 37.54 37.14 36.77

    Total of Working Capital 50.44 51.78 52.56 52.66 52.81

    Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of working Capital 6.81 6.99 7.10 7.11 7.13

    (₹ in lakh) Asset-4

    2014-15 2018-19 Particulars (pro-rata 2015-16 2016-17 2017-18 145 days)

    O&M Expenses 57.50 59.40 61.36 63.41 65.51 Maintenance Spares 103.49 106.92 110.45 114.14 117.92 Receivables 3357.68 3342.00 3262.07 3148.49 3057.06

    Total of Working Capital 3518.67 3508.32 3433.88 3326.04 3240.49

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 475.02 473.62 463.57 449.02 437.47

    (₹ in lakh) Asset-5

    2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 183 days)

    O&M Expenses 7.79 8.05 8.31 8.59 Maintenance Spares 14.02 14.48 14.96 15.46 Receivables 78.72 82.57 86.22 86.74

    Total of Working Capital 100.53 105.10 109.49 110.79

    Rate of Interest on working 13.50 13.50 13.50 13.50 capital (in %)

    Interest of working Capital 13.57 14.19 14.78 14.96

    (₹ in lakh) Asset-6

    2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 181 days)

    O&M Expenses 5.19 5.36 5.54 5.73 Maintenance Spares 9.35 9.66 9.98 10.31 Receivables 50.88 54.20 57.33 57.41

    Total of Working Capital 65.42 69.22 72.85 73.45

    Rate of Interest on working capital 13.50 13.50 13.50 13.50 (in %)

    Interest of working Capital 8.83 9.34 9.83 9.92

    Page 27 of 162

    (₹ in lakh) Asset-7

    2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 35 days)

    O&M Expenses 5.19 5.36 5.54 5.73 Maintenance Spares 9.35 9.66 9.98 10.31 Receivables 53.62 56.39 58.79 58.66

    Total of Working Capital 68.16 71.41 74.31 74.70

    Rate of Interest on working 13.50 13.50 13.50 13.50 capital (in %)

    Interest of working Capital 9.20 9.64 10.03 10.08

    (₹ in lakh) Asset-8

    2015-16 2016-17 2017-18 2018-19 Particulars (pro-rata

    113 days)

    O&M Expenses 16.09 16.63 17.18 17.75 Maintenance Spares 28.97 29.93 30.92 31.95 Receivables 212.38 224.90 233.54 231.76

    Total of Working Capital 257.44 271.46 281.64 281.46

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 34.75 36.65 38.02 38.00

    (₹ in lakh) Asset-9 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 172 days)

    O&M Expenses 10.38 10.73 11.09 11.45 Maintenance Spares 18.69 19.31 19.95 20.61 Receivables 142.39 144.86 142.84 146.62

    Total of Working Capital 171.46 174.90 173.88 178.68

    Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50

    Interest of working Capital 23.15 23.61 23.47 24.12

    (₹ in lakh) Asset-10 2015-16 Particulars (pro-rata 183 2016-17 2017-18 2018-19 days)

    O&M Expenses 13.96 14.42 14.90 15.40 Maintenance Spares 25.13 25.96 26.82 27.71 Receivables 383.13 391.47 390.84 393.94

    Total of Working Capital 422.22 431.85 432.56 437.05

    Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50

    Interest of working Capital 57.00 58.30 58.40 59.00

    Page 28 of 162

    (₹ in lakh) Asset-11 2017-18 2018-19 Particulars (pro-rata 242 days)

    O&M Expenses 0.00 0.00 Maintenance Spares 0.00 0.00 Receivables 34.40 35.69

    Total of Working Capital 34.40 35.69

    Rate of Interest on working capital 12.60 12.60 (in %)

    Interest of working Capital 4.33 4.50

    (₹ in lakh) Asset-12 2017-18 2018-19 Particulars (pro-rata 254 days)

    O&M Expenses 5.54 5.73 Maintenance Spares 9.98 10.31 Receivables 74.10 77.05

    Total of Working Capital 89.62 93.09

    Rate of Interest on working capital (in %) 12.60 12.60

    Interest of working Capital 11.29 11.73

    (₹ in lakh) Asset-13 2017-18 2018-19 Particulars (pro-rata 111 days)

    O&M Expenses 5.54 5.73 Maintenance Spares 9.98 10.31 Receivables 74.11 77.50

    Total of Working Capital 89.63 93.54

    Rate of Interest on working capital (in %) 12.60 12.60

    Interest of working Capital 11.29 11.79

    (₹ in lakh) Asset-14 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 156 days)

    O&M Expenses 22.40 23.14 23.91 24.70 Maintenance Spares 40.32 41.66 43.04 44.47 Receivables 113.21 118.92 120.95 121.85

    Total of Working Capital 175.93 183.72 187.90 191.02

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 23.75 24.80 25.37 25.79

    Page 29 of 162

    (₹ in lakh) Asset-15 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 157 days)

    O&M Expenses 11.37 11.75 12.14 12.54 Maintenance Spares 20.46 21.15 21.85 22.57 Receivables 231.68 242.88 240.91 243.66

    Total of Working Capital 263.51 275.78 274.90 278.77

    Rate of Interest on working capital (in %) 13.50 13.50 13.50 13.50

    Interest of working Capital 35.57 37.23 37.11 37.63

    (₹ in lakh) Asset-16 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 183 days)

    O&M Expenses 10.72 11.08 11.44 11.83 Maintenance Spares 19.30 19.94 20.60 21.29 Receivables 97.66 102.96 104.41 105.39

    Total of Working Capital 127.68 133.98 136.45 138.51

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 8.62 18.09 18.42 18.70

    (₹ in lakh) Asset-17 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 104 days)

    O&M Expenses 7.79 8.05 8.31 8.59 Maintenance Spares 14.02 14.48 14.96 15.46 Receivables 89.87 93.71 94.27 95.82

    Total of Working Capital 111.68 116.24 117.54 119.87

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 4.28 15.69 15.87 16.18

    (₹ in lakh) Asset-18 2015-16 2018-19 Particulars (pro-rata 2016-17 2017-18 152 days)

    O&M Expenses 186.26 196.45 207.29 218.84 Maintenance Spares 335.27 353.62 373.13 393.92 Receivables 18630.87 19160.23 19347.28 19675.37

    Total of Working Capital 19152.40 19710.30 19927.70 20288.13

    Rate of Interest on working capital (in 13.50 13.50 13.50 13.50 %)

    Interest of working Capital 1073.79 2660.89 2690.24 2738.90

    Page 30 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2016-17 (pro-rata 211 days) 2017-18 2018-19
    O&M Expenses 88.17 95.42 103.24
    Maintenance Spares 158.70 171.76 185.83
    Receivables 4383.04 4717.34 5014.75
    Total of Working Capital 4629.91 4984.52 5303.82
    Rate of Interest on working capital (in %) 12.80 12.80 12.80
    Interest of working Capital 342.59 638.02 678.89

    Capital Cost as on 1.4.2014/ COD

    17. Asset-1 to Asset-3 were put into commercial operation in 2009-14 tariff period and Asset-4 to Asset-19 in 2014-19 tariff period. The Petitioner has submitted the details of apportioned approved cost as per FR, RCE-I and RCE-II, admitted the capital cost as on COD and Additional Capital Expenditure (ACE) vide order dated 11.3.2016 in Petition No. 391/TT/2014 for Asset-1; vide order dated 28.1.2016 in Petition No.131/TT/2015 for Asset-2; vide order dated 18.2.2016 in Petition No. 217/TT/2015 for Asset-3; vide order dated 14.7.2016 in Petition No. 65/TT/2015 for Asset-4, vide order dated 26.5.2016 in Petition No. 259/TT/2015 for Asset-5 to Asset-10; vide order dated 25.6.2019 in Petition No. 242/TT/2018 for Asset-11 to Asset-13 and vide order dated 17.12.2019 in Petition No. 363/TT/2018 for Asset- 14 to Asset-19 as follows:

    (₹ in lakh) Expenditure Capital ACE 2014-2019 (as allowed) FR RCE-I RCE-II Estimated

    up to COD/ cost

    Apportioned Apportioned Apportioned completion Assets 31.3.2014 allowed as

    approved approved approved cost

    (as on COD/

    cost cost cost (as allowed)

    claimed) 31.3.2014 2014-15 2015-16 2016-17 2017-18 2018-19

    Commission's order dated 11.3.2016 in Petition No. 391/TT/2014

    Asset-1 3015.76 2692.86 2734.02 2121.32 2118.89 397.09 0.00 0.00 0.00 0.00 2515.98

    Commission's order dated 28.1.2016 in Petition No. 131/TT/2015

    Asset-2 1119.87 1073.94 1048.02 892.38 892.38 35.70 14.43 0.00 0.00 0.00 942.51

    Commission's order dated 18.2.2016 in Petition No. 217/TT/2015

    Asset-3 875.50 843.88 915.15 572.15 557.88 43.64 39.33 0.00 0.00 0.00 640.85

    Commission's order dated 14.7.2016 in Petition No. 65/TT/2015

    Asset-4 102220.99 115967.79 119828.33 113537.96 111684.25 3215.98 1067.56 0.00 0.00 0.00 115967.79

    Commission's order dated 26.5.2016 in Petition No.259/TT/2015

    Asset-5 2430.98 2850.65 3076.94 2266.61 2266.61 0.00 232.00 348.11 0.00 0.00 2846.72 Asset-6 1333.64 1917.41 2065.05 1448.53 1448.53 0.00 199.00 269.88 0.00 0.00 1917.41

    Page 31 of 162

    Expenditure Capital ACE 2014-2019 (as allowed) FR RCE-I RCE-II Estimated

    up to COD/ cost

    Apportioned Apportioned Apportioned completion Assets 31.3.2014 allowed as

    approved approved approved cost

    (as on COD/

    cost cost cost

    claimed) 31.3.2014 2014-15 2015-16 2016-17 2017-18 2018-19

    (as allowed)

    Asset-7 1333.64 1923.49 2079.54 1560.06 1552.77 0.00 32.46 337.99 0.00 0.00 1923.22 Asset-8 5352.49 7846.08 9947.34 6396.80 6295.39 0.00 1239.99 233.50 75.30 0.00 7844.18 Asset-9 5228.96 5252.39 4292.55 4247.93 0.00 404.94 394.55 0.00 0.00 5047.42

    14496.41

    Asset-10 13749.77 14750.56 12609.13 12564.93 0.00 737.60 447.24 0.00 0.00 13749.77

    Commission's order dated 25.6.2019 in Petition No. 242/TT/2018

    Asset-11 0.00 1452.05 1465.98 1308.94 1060.19 0.00 0.00 0.00 93.54 59.96 1213.69 Asset-12 1169.00 2710.32 2910.32 2420.64 2335.00 0.00 0.00 0.00 118.09 207.93 2661.02 Asset-13 1169.00 2710.32 2910.32 2444.45 2318.91 0.00 0.00 0.00 104.41 238.45 2661.77

    Commission's order dated 17.12.2019 in Petition No. 363/TT/2018

    Asset-14 2297.93 2231.37 0.00 295.87 120.35 75.28 87.69 2810.56

    10155.26 11767.82 13210.96

    Asset-15 7005.64 6949.22 0.00 927.82 269.19 335.25 92.42 8573.90 Asset-16 2281.57 3252.78 3617.44 2565.59 2548.98 0.00 291.80 193.09 158.65 79.02 3271.54 Asset-17 2395.22 3175.08 3421.57 2601.95 2567.54 0.00 239.28 120.07 75.10 206.13 3208.12 Asset-18 641074.53 871003.91 887106.06 806800.85 799945.79 0.00 19337.31 27534.72 15422.38 11989.58 874229.78 Asset-19 194699.17 254374.87 259005.37 209794.48 208789.61 0.00 0.00 15175.16 11413.34 4805.74 240183.85

    TOTAL 985123.03 1304541.98 1335345.36 1182937.96 1172376.17 3692.41 25059.39 45443.85 27871.34 17766.92 1292210.08

    *No provision in FR included for RCE

    18. The Petitioner in the present petition has claimed the following capital cost in respect of the transmission assets for truing-up of tariff for 2014-19 period and has submitted Auditor's certificates of actual expenditure in support of the same for the purpose of truing up:

    (₹ in lakh) ACE for 2014-2019 Cost as on

    Expenditure

    FR RCE-I RCE-II 31.3.2019 up to COD/

    Apportioned Apportioned Apportioned (As per Auditor's Certificate) (as

    Assets 31.4.2014 (as claimed for true up) claimed approved approved approved (as claimed

    cost cost cost for true-

    for true-up) up)

    2014-15 2015-16 2016-17 2017-18 2018-19

    Asset-1 3015.76 2692.86 2734.02 2118.89 277.06 43.39 8.24 3.17 0.00 2450.75 Asset-2 1119.87 1073.94 1048.02 892.38 35.7 47.92 1.25 0.00 0.00 977.25 Asset-3 875.50 843.88 915.15 557.88 43.64 132.27 0.09 0.00 0.00 733.88 Asset-4 102220.99 115967.79 119828.33 113537.96 1571.34 1489.71 860.36 210.90 361.40 118031.67 Asset-5 2430.98 2850.65 3076.94 2266.61 0.00 37.75 305.97 85.09 54.89 2750.31 Asset-6 1333.64 1917.41 2065.05 1448.53 0.00 32.38 247.52 68.84 7.74 1805.01 Asset-7 1333.64 1923.49 2079.54 1560.05 0.00 25.17 191.55 53.28 3.81 1833.86 Asset-8 5352.49 7846.08 9947.34 6396.80 0.00 186.78 763.4 212.33 2.36 7561.67 Asset-9 5228.96 5252.39 4292.54 0.00 186.70 128.11 35.18 459.28 5101.81

    14496.41

    Asset-10 13749.77 14750.56 12448.85 0.00 639.91 430.84 530.65 459.28 14509.53 Asset-11 0.00 1452.05 1465.98 1308.94 0.00 0.00 0.00 46.69 73.09 1428.72 Asset-12 1169.00 2710.32 2910.32 2420.64 0.00 0.00 0.00 38.85 192.00 2651.49 Asset-13 1169.00 2710.32 2910.32 2444.45 0.00 0.00 0.00 35.47 168.63 2648.55 Asset-14 2297.93 0.00 232.46 120.35 75.28 25.97 2751.99

    10155.26 11767.82 13210.96

    Asset-15 7005.64 0.00 928.44 269.19 344.66 340.65 8888.58 Asset-16 2281.57 3252.78 3617.44 2565.61 0.00 293.86 210.06 160.04 65.46 3295.03 Asset-17 2395.22 3175.08 3421.57 2601.96 0.00 204.88 120.07 75.10 164.79 3166.80 Asset-18 641074.53 871003.91 887106.06 806800.85 0.00 14647.03 25776.83 15383.04 10367.10 872974.85

    Page 32 of 162

    Asset-19 194699.17 254374.87 259005.37 209794.48 0.00 0.00 14476.69 11385.44 895.06 236551.67
    TOTAL 985123.03 1304541.98 1335345.36 1182760.99 1927.74 19128.65 43910.52 28744.01 13641.50 1290113.42

    Cost Over-run

    19. The Petitioner has submitted that there is cost over-run in case of some of the transmission assets and it has already been settled vide order dated 11.3.2016 in Petition No. 391/TT/2014 for Asset-1; vide order dated 28.1.2016 in Petition No.131/TT/2015 for Asset-2; vide order dated 18.2.2016 in Petition No. 217/TT/2015 for Asset-3; vide order dated 14.7.2016 in Petition No. 65/TT/2015 for Asset-4; vide order dated 26.5.2016 in Petition No. 259/TT/2015 for Asset-5 to Asset-10; vide order dated 25.6.2019 in Petition No. 242/TT/2018 for Asset-11 to Asset-13 and vide order dated 17.12.2019 in Petition No. 363/TT/2018 for Asset- 14 to Asset-19. The Petitioner has submitted that there is no cost over-run in case of the transmission assets as on 31.3.2019 as per the RCE-II apportioned approved cost.

    20. We have considered the submissions of the Petitioner and perused the record. It is observed that the Commission has already taken into consideration the FR, RCE-I and RCE-II in the previous tariff orders and settled the issue of cost over-run based on the justification given by the Petitioner for variation between estimated completion cost and FR. The apportioned approved cost based on RCE-II for the trasnsmission assets is ₹1335345.36 lakh while the estimated completion cost as on 31.3.2019 as per the Auditor's certificate is ₹1290113.42 lakh. Therefore, the estimated completion cost of the transmission assets is within the RCE-II apportioned approved cost.

    Time Over-run

    21. The details of the SCOD, COD and the time over-run, if any, in respect of

    Page 33 of 162

    the transmission assets are as follows:

    Assets SCOD Actual COD Time over-run Time over-run condoned
    Asset-1 26.2.2013 1.7.2012 - -
    Asset-2 1.10.2012 - -
    Asset-3 1.3.2013 - -
    Asset-4 7.11.2014 21 months Not condoned
    Asset-5 27.8.2013 1.10.2015 25 months and 4 days Not condoned
    Asset-6 3.10.2015 25 months and 7 days Not condoned
    Asset-7 26.2.2016 29 months and 30 days Not condoned
    Asset-8 10.12.2015 27 months and 13 days Not condoned
    Asset-9 12.10.2015 25 months and 15 days Not condoned
    Asset-10 1.10.2015 25 months and 4 days Not condoned
    Asset-11 December, 2017 (As per RCE, asset was included in scope in RCE) 1.8.2017 - -
    Asset-12 26.2.2013 21.7.2017 52 months and 21 days Condoned
    Asset-13 11.12.2017 57 months and 11 days Condoned
    Asset-14 27.8.2013 28.10.2015 25 Months and 27 days Condoned
    Asset-15 27.10.2015 25 Months and 26 day Condoned
    Asset-16 1.10.2015 25 Months Condoned
    Asset-17 19.12.2015 27 Months and 18 days Condoned
    Asset-18 1.11.2015 26 Months Condoned
    Asset-19 2.9.2016 36 Months Condoned

    22. The time over-run in case of Asset-4 was discussed and settled vide order dated 14.7.2016 in Petition No. 65/TT/2015, Asset-5 to Asset-10 vide order dated 26.5.2016 in Petition No. 259/TT/2015, Asset-11 to Asset-13 vide order dated 25.6.2019 in Petition No. 242/TT/2018, Asset-14 to Asset-18 vide order dated 31.8.2017 in Petition No. 67/TT/2015 and Asset-19 vide order dated 15.12.2017 in Petition No. 184/TT/2016.

    Interest During Construction ('IDC') and Incidental Expenditure During Construction ('IEDC')

    23. The COD of Asset-1 to Asset-3 is during 2009-14 tariff period and the IDC has already been approved by the Commission in the previous orders. The Petitioner has claimed IDC for the remaining transmission assets i.e. Asset-4 to Asset-19 and has submitted the Auditor's Certificates with IDC statement showing

    Page 34 of 162

    the loan wise IDC discharged upto COD and IDC discharged after COD.

    24. We have considered the submissions of the Petitioner. The allowable IDC has been worked out considering the information submitted by the Petitioner in respect of the transmission assets (Asset-4 to Asset-19). Accordingly, based on the information furnished by the Petitioner, IDC considered for Asset-4 to Asset- 19 is as follows:

    (₹ in lakh)

    Particulars IDC claimed as per the Auditor's Certificate IDC as on COD as worked out IDC dis- allowed as on COD due to computation difference and time over-run Un- discharged portion of entitled IDC as on COD IDC allowed on cash basis as on COD
    a b c d=b-c e f=b-d-e
    Asset-4 19900.96 20550.19 0.00 1650.31 18250.65
    Asset-5 217.68 261.75 0.00 0.00 217.68
    Asset-6 143.22 186.76 0.00 0.00 143.22
    Asset-7 147.81 196.42 0.00 9.68 138.13
    Asset-8 674.93 735.22 0.00 128.04 546.89
    Asset-9 479.15 669.15 0.00 15.11 464.04
    Asset-10 1555.19 2082.40 0.00 323.43 1231.76
    Asset-11 49.98 49.79 0.19 29.72 20.06
    Asset-12 473.52 515.53 0.00 61.18 412.34
    Asset-13 473.44 513.40 0.00 101.08 372.36
    Asset-14 249.81 283.07 0.00 64.09 185.72
    Asset-15 948.20 1275.45 0.00 0.00 948.20
    Asset-16 303.71 531.15 0.00 0.00 303.71
    Asset-17 247.03 297.52 0.00 34.41 212.62
    Asset-18 93144.18 92928.89 215.29 6242.53 86686.36
    Asset-19 19609.40 19606.71 2.69 792.52 18814.19

    25. IEDC in case of Assets-1 to Asset-3 has already been approved by the Commission in previous orders. The Petitioner has claimed IEDC for the remaining transmission assets i.e. Asset-4 to Asset-19 in the present petition and has submitted Form-12A and Auditor's Certificate in support of its claim.

    26. APTEL in judgment dated 2.12.2019 in Appeal No. 95 of 2018 and Appeal No. 140 of 2018 observed that IEDC should be computed on actual basis after

    Page 35 of 162

    prudence check. Therefore, IEDC is allowed in accordance with the APTEL's judgement. The relevant protion of the said judgement is extracted as follows:

    "7.16 In light of the above, we are of the considered opinion that Central Commission has not considered the IEDC for the reference assets correctly in line with provisions of its own regulations which cannot be sustained in the eyes of law. In catena of judgments of Hon'ble Supreme Court and this Tribunal, it has been held that the Regulations framed by the Commissions are binding for all stakeholders including the Commission itself. The Regulations framed under the Act, in no way, mandate the Central Commission to restrict the IEDC to 5% of the original estimated hard cost.

    7.17 Accordingly, we hold that IEDC should be computed only on actual basis after due prudence check based on the data submitted by the Appellant in accordance with the Tariff Regulations"

    27. As per the APTEL's judgemnt, we have examined Form-12A along with the Auditor's Certificate submitted by the Petitioner in support of its claim. We have considered the submissions of the Petitioner. IEDC allowed for Assets-4 to Asset- 19 is as follows:

    (₹ in lakh)

    Assets IEDC claimed IEDC allowed
    Asset-4 4677.23 4677.23
    Asset-5 39.25 39.25
    Asset-6 26.81 26.81
    Asset-7 27.63 27.63
    Asset-8 113.23 113.23
    Asset-9 139.04 139.04
    Asset-10 572.71 572.71
    Asset-11 253.98 253.98
    Asset-12 87.14 87.14
    Asset-13 87.17 87.17
    Asset-14 71.94 71.94
    Asset-15 352.92 352.92
    Asset-16 101.24 101.24
    Asset-17 45.13 45.13
    Asset-18 27850.95 27850.95
    Asset-19 4694.54 4694.54
    Total 39140.91 39140.91

    Initial Spares

    28. The Petitioner has claimed the following Initial Spares in respect of the transmission assets and has prayed to revise the Initial Spares allowed earlier in

    Page 36 of 162

    light of the APTEL's judgment dated 14.9.2019 in Appeal No. 74 of 2017. Initial Spares claimed by the Petitioner in respect of the transmission assets are as follows:

    Sub-station Estimated Initial Spares worked Initial Spares Ceiling completion cost out

    Assets claimed (B) limit (in %)

    (A) (₹ in lakh) (₹ in lakh) (C) (₹ in lakh) D = [(A-B)*C /(100-C)]

    Asset-1 2488.59 65.33* 2.5 62.13 Asset-2 997.08 13.49 2.5 25.22 Asset-3 749.60 30.29** 2.5 18.44 Asset-4 9454.51 453.05 6.0 574.56 Asset-5 1907.48 0.00 4.0 79.48 Asset-6 1323.03 31.74 4.0 53.80 Asset-7 1323.03 31.74 4.0 53.80 Asset-8 6085.81 69.46 6.0 384.02 Asset-9 2360.85 134.37 6.0 142.12 Asset-10 2360.85 134.37 6.0 142.12 Asset-11 1124.76 40.01 6.0 69.24 Asset-12 1703.64 8.80 4.0 70.62 Asset-13 1704.43 8.80 4.0 70.65 Asset-14 1464.67 0.00 4.0 61.03 Asset-15 1464.67 0.00 4.0 61.03 Asset-16 1520.07 25.85 4.0 62.26 Asset-17 2461.66 24.30 4.0 101.56 Asset-18 178533.73 7362.84 4.0 7132.12 Asset-19 164152.37 6999.95 4.0 6548.02

    Total 383180.83 15434.39 15712.22

    * Original claim ₹65.33 lakh, disallowed ₹2.43 lakh vide order dated 11.3.2016 in Petition No.391/TT/2014.

    ** Original claim ₹30.29 lakh, disallowed ₹14.27 lakh vide order dated 18.2.2016 in Petition No. 217/TT/2015

    Transmission Line Estimated Initial Initial Spares worked out Ceiling

    completion Spares (₹ in lakh)

    Assets Limit (in %)

    cost (A) claimed (B)

    (C) D = [(A-B)*C /(100-C)] (₹ in lakh) (₹ in lakh)

    Asset-4 84970.41 575.37 1.0 852.48 Asset-9 1382.89 0.00 1.0 13.97 Asset-10 9339.52 0.00 1.0 94.34 Asset-14 5905.94 122.50 1.0 58.42 Asset-15 728.03 7.35 1.0 7.28 Asset-16 1093.97 47.27 1.0 10.57 Asset-18 549544.33 4760.17 1.0 5502.94

    Page 37 of 162

    Asset-19 25590.31 420.58 1.0 254.24
    Total 678555.40 5933.24 - 6794.23

    29. MPPMCL has submitted that some of the transmission assets were executed during 2009-14 tariff period while some of the transmission assets were executed during 2014-19 tariff period and that the norm for brown field and green field sub- stations is different and as such the Petitioner cannot claim the cost for the transmission project as a whole. The demand of the Petitioner is therefore not in consonance of the provisions of tariff regulations and is liable to be rejected. MPPMCL has also submitted that excess Initial Spares claimed in respect of Asset-1, Asset-3, Asset-18 and Asset-19 may be disallowed keeping in mind the interest of end consumers of the State.

    30. In response, the Petitioner has submitted that Initial Spares under sub-station (HVDC & AIS-Green/Brown Filed) and transmission line head for the transmission assets covered under the instant petition are within the specified limit for sub- station and transmission line for the transmission project as per Regulation 13 of the 2014 Tariff Regulations. The Petitioner has further submitted that the details of calculations of Initial Spares for overall project basis have been given and has prayed that Initial Spares may be allowed as claimed in terms of the judgment of APTEL dated 14.9.2019 in Appeal No. 74 of 2017.

    31. We have considered the submissions of the Petitioner and MPPMCL. As per the APTEL's judgment dated 14.9.2019 in Appeal No. 74 of 2017, Initial Spares are to be allowed as per the norms on overall project cost. In the present case, the entire transmission project has been completed during 2014-19 tariff period except for Asset-21. Overall project cost of the transmission assets can ideally be arrived

    Page 38 of 162

    at only when all the transmission assets are combined. Asset-21 i.e. 2x400 kV D/C Lower Subansiri-Biswanath Chariali line with 1x80 MVAR Bus Reactor and 4x63 MVAR Line Reactors along with associated bays has not yet been executed, therefore, the said judgment dated 14.9.2019 of the APTEL cannot be applied to the present case as of now. We, therefore, allow Initial Spares on the basis of individual cost of transmission assets in 2009-14 tariff period for Asset-1 to Assset- 3 and in 2014-19 tariff period for Asset-4 to Asset-19. We observe that Initial Spares with respect to Asset-20 has already been allowed for 2019-24 tariff period separately vide order dated 7.10.2022 in Petition No. 165/TT/2022, therefore, its cost shall also be clubbed with other transmission assets at the time of truing up of 2019-24 tariff period. Accordingly, Initial Spares allowed in respect of the transmission assets are as follows:

    (₹ in lakh) Initial Already Cost for Initial Spares Allowed Excess Ceiling allowed Spare Spares in Initial

    Assets (in %) worked in

    Calculation Claimed

    (C) out current spares previous

    (A) (B) D = [(A-B)*C petition disallowed petitions

    /(100-C)]

    Asset-1 2398.38 65.33 2.5 59.82 62.90 (3.08) 3.08 Asset-2 997.08 13.49 2.5 25.22 13.49 0.00 0.00 Asset-3 748.06 30.29 2.5 18.40 16.02 2.38 0.00 Asset-4 9585.63 453.05 6.0 852.93 - 453.05 0.00 Asset-5 1907.48 0.00 4.0 79.48 - - 0.00 Asset-6 1323.03 31.74 4.0 53.80 - 31.74 0.00 Asset-7 1323.03 31.74 4.0 53.80 - 31.74 0.00 Asset-8 6085.81 69.46 6.0 384.02 - 69.46 0.00 Asset-9 2383.46 134.37 6.0 143.12 - 134.37 0.00 Asset-10 2383.81 134.37 6.0 143.58 - 134.37 0.00 Asset-11 1124.76 40.01 6.0 69.24 - 40.01 0.00 Asset-12 1703.64 8.80 4.0 70.62 - 8.80 0.00 Asset-13 1704.43 8.80 4.0 70.65 - 8.80 0.00 Asset-14 1464.67 0.00 4.0 61.03 - - 0.00 Asset-15 1464.67 0.00 4.0 61.03 - - 0.00 Asset-16 1520.07 25.85 4.0 62.26 - 25.85 0.00 Asset-17 2461.66 24.30 4.0 101.56 - 24.30 0.00 Asset-18 178533.73 7362.84 4.0 7132.12 - 7132.12 230.72 Asset-19 164152.37 6999.95 4.0 6548.02 - 6548.02 451.93

    Page 39 of 162

    Transmission Line:

    (₹ in lakh)

    Cost for

    Initial Initial Spares Allowed Excess Initial Ceiling

    Spares worked out in Initial Assets Spares (in %)

    claimed D = [(A-B)*C /(100- current spares calculation (C)

    (B)

    (A) C)]

    petition disallowed

    Asset-4 84970.41 575.37 1.0 852.48 575.37 0.00 Asset-9 1382.89 0.00 1.0 13.97 0.00 0.00 Asset-10 9339.52 0.00 1.0 94.34 0.00 0.00 Asset-14 728.03 7.35 1.0 7.28 7.28 0.07 Asset-15 5905.94 122.50 1.0 58.42 58.42 64.08 Asset-16 1093.97 47.27 1.0 10.57 10.57 36.70 Asset-18 549544.33 4760.17 1.0 5502.94 4760.17 0.00 Asset-19 25590.31 420.58 1.0 254.24 254.24 166.34

    Capital Cost Allowed as on COD

    32. The capital cost of the transmission assets allowed as on COD is as follows:

    (₹ in lakh) Capital cost Capital cost Less: IDC as on COD due to as on COD Initial as on COD IEDC disallowed

    Assets as per Un- Spares IDC on COD (on cash Auditor's discharged adjusted disallowed basis)

    Certificate IDC

    Asset-1 2118.89 0.00 0.00 0.00 3.08 2115.81 Asset-2 892.38 0.00 0.00 0.00 0.00 892.38 Asset-3 557.88 0.00 0.00 0.00 *2.38 560.26 Asset-4 113537.96 0.00 1650.31 0.00 0.00 111887.65 Asset-5 2266.61 0.00 0.00 0.00 0.00 2266.61 Asset-6 1448.53 0.00 0.00 0.00 0.00 1448.53 Asset-7 1560.05 0.00 9.68 0.00 0.00 1550.37 Asset-8 6396.80 0.00 128.04 0.00 0.00 6268.76 Asset-9 4292.54 0.00 15.11 0.00 0.00 4277.43 Asset-10 12448.85 0.00 323.43 0.00 0.00 12125.42 Asset-11 1308.94 0.19 29.72 0.00 0.00 1279.03 Asset-12 2420.64 0.00 61.18 0.00 0.00 2359.46 Asset-13 2444.45 0.00 101.08 0.00 0.00 2343.37 Asset-14 2297.93 0.00 64.09 0.00 0.07 2233.77 Asset-15 7005.64 0.00 0.00 0.00 64.08 6941.56 Asset-16 2565.61 0.00 0.00 0.00 36.70 2528.91 Asset-17 2601.96 0.00 34.41 0.00 0.00 2567.55 Asset-18 806800.85 215.29 6242.53 0.00 230.72 800112.31 Asset-19 209794.48 2.69 792.52 0.00 618.27 208381.00 *2.38 lakh is added back as excess spares were deducted in previous order.

    Page 40 of 162

    Additional Capital Expenditure ("ACE")

    33. The Petitioner has claimed the following ACE in respect of the transmission assets and has submitted the Auditor's Certificates in support of the same:

    (₹ in lakh) ACE 2014-2019 Assets ( As per Auditor's certificate) 2014-15 2015-16 2016-17 2017-18 2018-19

    Asset-1 277.06 43.39 8.24 3.17 0.00 Asset-2 35.70 47.92 1.25 0.00 0.00 Asset-3 43.64 132.27 0.09 0.00 0.00 Asset-4 1571.34 1489.71 860.36 210.9 361.4 Asset-5 0.00 37.75 305.97 85.09 54.89 Asset-6 0.00 32.38 247.52 68.84 7.74 Asset-7 0.00 25.17 191.55 53.28 3.81 Asset-8 0.00 186.78 763.4 212.33 2.36 Asset-9 0.00 186.70 128.11 35.18 459.28 Asset-10 0.00 639.91 430.84 530.65 459.28 Asset-11 0.00 0.00 0.00 46.69 73.09 Asset-12 0.00 0.00 0.00 38.85 192.00 Asset-13 0.00 0.00 0.00 35.47 168.63 Asset-14 0.00 232.46 120.35 75.28 25.97 Asset-15 0.00 928.44 269.19 344.66 340.65 Asset-16 0.00 293.86 210.06 160.04 65.46 Asset-17 0.00 204.88 120.07 75.10 164.79 Asset-18 0.00 14647.03 25776.83 15383.04 10367.10 Asset-19 0.00 0.00 14476.69 11385.44 895.06 Total 1927.74 19128.65 43910.52 28744.01 13641.50

    34. The transmission assets have been executed during 2009-14 and 2014-19 tariff periods and accordingly, their cut-off dates with relevant clause under Regulation 14 of the 2014 Tariff Regulations for ACE are as follows:

    Cut-off ACE Regulation during 2014-2019 Assets COD

    date 2014-15 2015-16 2016-17 2017-18 2018-19

    Asset-1 1.7.2012 31.3.2015 14(1)(i) 14(3)(v) 14(3)(v) 14(3)(v) 0.00 Asset-2 1.10.2012 31.3.2015 14(1)(i) 14(3)(v) 14(3)(v) 0.00 0.00 Asset-3 1.3.2013 31.3.2016 14(1)(i) 14(1)(i) 14(3)(v) 0.00 0.00 Asset-4 7.11.2014 31.3.2017 14(1)(i) 14(1)(i) 14(1)(i) 14(2)(iv) 14(2)(iv) 14(1)(i) & 14(1)(i) & 14(1)(i) &

    Asset-5 1.10.2015 31.3.2018 0.00 14(2)(iv)

    14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) &

    Asset-6 3.10.2015 31.3.2018 0.00 14(2)(iv)

    14(1)(ii) 14(1)(ii) 14(1)(ii)

    Page 41 of 162

    Cut-off ACE Regulation during 2014-2019 Assets COD

    date 2014-15 2015-16 2016-17 2017-18 2018-19

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-7 26.2.2016 31.3.2019 0.00 14(1)(i) 14(1)(ii) 14(1)(ii) 14(1)(ii) 14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-8 10.12.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-9 12.10.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-10 1.10.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) &

    Asset-11 1.8.2017 31.3.2020 0.00 0.00 0.00 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) &

    Asset-12 21.7.2017 31.3.2020 0.00 0.00 0.00 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) &

    Asset-13 11.12.2017 31.3.2020 0.00 0.00 0.00 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-14 28.10.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-15 27.10.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-16 1.10.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-17 19.12.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-18 1.11.2015 31.3.2018 0.00 14(2)(iv) 14(1)(ii) 14(1)(ii) 14(1)(ii)

    14(1)(i) & 14(1)(i) & 14(1)(i) & Asset-19 2.9.2016 31.3.2019 0.00 0.00 14(1)(ii) 14(1)(ii) 14(1)(ii)

    35. The Petitioner vide affidavit dated 8.3.2021 has submitted that ACE claimed for Asset-1 to Asset-19 is within the original scope of work. However, ACE during the year 2018-19, 2019-20 and 2020-21 for Asset-4 and Asset-18 is on account of construction of pile foundation due to the change in river course of Pagladia and Maansiri river and the same has been approved in 17thTCC meeting of NERPC held on 4.10.2016. The Petitioner has further submitted that ACE approved by the Commission in earlier order for 2014-19 tariff period was based on projected expenditure as contracts were not closed and liabilities were not finalized. The Petitioner has submitted that in the present petition, ACE is claimed on the basis of actual payments made to the contractors after receipt of final invoices and incorporating the amendments. The Petitioner has provided liability flow statement indicating contractor-wise details of liabilities and balance work for 2014-19 tariff

    Page 42 of 162

    period for the transmission assets.

    36. We have considered the submissions of the Petitioner. Regulation 14 of the 2014 Tariff Regulations provides as follows:

    "(1) The capital expenditure in respect of the new project or an existing project incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

    (i) Undischarged liabilities recognized to be payable at a future date;

    (ii) Works deferred for execution;" ………

    "(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court of law; and"

    "(2) The capital expenditure incurred or projected to be incurred in respect of the new project on the following counts within the original scope of work after the cut-off date may be admitted by the Commission, subject to prudence check:

    ………

    (iv) Any liability for works executed prior to the cut-off date, after prudence check of the details of such undischarged liability, total estimated cost of package, reasons for such withholding of payment and release of such payments etc."

    "(3) The capital expenditure, in respect of existing generating station or the transmission system including communication system, incurred or projected to be incurred on the following counts after the cut-off date, may be admitted by the Commission, subject to prudence check:

    …….

    (v) Any liability for works executed prior to the cut-off date, after prudence check of the details of such undischarged liability, total estimated cost of package, reasons for such withholding of payment and release of such payments etc.;"

    37. The details of COD and the cut-off date of the transmission assets is indicated in the above table. The Petitioner has submitted that ACE is incurred for work executed within the 'cut-off' date on account of balance and retention payment under Regulation 14(1)(i) and Regulation 14(1)(ii) of the 2014 Tariff Regulations and beyond the 'cut-off' date under Regulation 14(3)(v) of the 2014 Tariff Regulations in respect of the transmission assets and has submitted the Auditor's Certificate in support of the same. The Petitioner vide affidavit dated 8.3.2021 has

    Page 43 of 162

    submitted that ACE claimed for the transmission assets is within the original scope of work. However, ACE during the years 2018-19, 2019-20 and 2020-21 for Asset- 4 (400 kV Balipara-Bongaigaon D/C line) and Asset-18 (± 800 kV Biswanath Chariali-Agra HVDC line) is on account of construction of pile foundation due to change in river course of Pagladia and Maansiri rivers and the same has been approved in the 17thTCC meeting and 17thNERPC meeting held on 4.10.2016.

    38. The Petitioner has submitted that ACE incurred is inclusive of undischarged IDC. The details of underlying reasons for ACE have been given in Form-7. ACE approved by the Commission during 2014-19 tariff period was based on the projections as at that time contracts were not closed and liabilities were not frozen. However, in the present petition ACE is claimed as per actual payments made to the contractors after receipt of the final invoices and after incorporating the contract amendments.

    39. We have considered the submissions of the Petitioner and perused Form-7. The asset wise ACE allowed/ disallowed in case of the transmission assets and the reasons are as follows:

    Asset Justification Reason for admissibility/non admissibility
    Asset-1 The Petitioner has claimed an amount of ₹277.06 lakh, ₹43.48 lakh, ₹8.24 lakh and ₹3.17 lakh for FY 2014-15, FY 2015-16, FY 2016-17 and FY 2017-18, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability for 2014-15 is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations and discharge liability for 2015-16,2016- 17 and 2017-18 is allowed under Regulation 14(3)(v) of the 2014 Tariff Regulations.
    Asset-2 The Petitioner has claimed an amount of ₹35.70 lakh, ₹47.92 lakh and ₹1.25 lakh, for FY 2014- 15, FY 2015-16 and FY 2016-17, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability for 2014-15 is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations and discharge liability for 2015-16, 2016- 17 is allowed under Regulation

    Page 44 of 162

    Asset Justification Reason for admissibility/non admissibility
    14(3)(v) of the 2014 Tariff Regulations.
    Asset-3 The Petitioner has claimed an amount of ₹43.64 lakh, ₹132.27 lakh and ₹0.09 lakh, for FY 2014- 15, FY 2015-16 and FY 2016-17, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability for 2014-15 and 2015-16 is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations and discharge liability for 2016-17 is allowed under Regulation 14(3)(v) of the 2014 Tariff Regulations.
    Asset-5 The Petitioner has claimed an amount of ₹15.35 lakh, ₹118.84 lakh, ₹78.96 lakh and ₹54.89 lakh for FY 2015-16,FY 2016-17,FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹22.40 lakh, ₹187.13 lakh and ₹6.13 lakh for un executed work towards Sub- station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-6 The Petitioner has claimed an amount of ₹31.01 lakh, ₹79.84 lakh, ₹59.71 lakh and ₹7.73 lakh for FY 2015-16,FY 2016-17,FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹1.37 lakh, ₹167.68 lakh and ₹9.13 lakh for un executed work towards Sub- station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-7 The Petitioner has claimed an amount of ₹0.90 lakh, ₹164.55 lakh, ₹30.49 lakh and ₹3.81 lakh for FY 2015-16, FY 2016-17,FY 2017-18 and FY 2018-19, respectively towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹24.27 lakh, ₹27.00 lakh, ₹22.79 lakh for un executed work towards Sub-station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-8 The Petitioner has claimed an amount of ₹6.97 lakh, ₹157.46 lakh, ₹65.41 lakh and ₹2.36 lakh for FY 2015-16,FY 2016-17,FY ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.

    Page 45 of 162

    Asset Justification Reason for admissibility/non admissibility
    2017-18 and FY 2018-19 towards discharge liabilities.
    The Petitioner has claimed an amount of ₹179.81 lakh, ₹605.94 lakh and ₹146.92 lakh for un executed work towards Sub- station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-9 The Petitioner has claimed an amount of ₹170.81 lakh, ₹114.65 lakh, ₹25.52 lakh and ₹459.27 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.
    The Petitioner has claimed an amount of ₹15.89 lakh, ₹13.47 lakh and ₹9.66 lakh for un executed work towards Sub- station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-10 The Petitioner has claimed an amount of ₹624.02 lakh, ₹417.38 lakh, ₹520.99 lakh and ₹459.27 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.
    The Petitioner has claimed an amount of ₹15.89 lakh, ₹13.46 lakh and ₹9.66 lakh for un executed work towards Sub- station and civil works ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-11 The Petitioner has claimed an amount of ₹70.41 lakh, ₹77.49 FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    Asset-12 The Petitioner has claimed an amount of ₹0.97 lakh and ₹51.44 lakh, for FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.
    The Petitioner has claimed an amount of ₹37.88 lakh and ₹140.56 lakh for FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-13 The Petitioner has claimed an amount of ₹0.56 lakh and ₹52.00 lakh for FY 2017-18 and FY 2018- ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.

    Page 46 of 162

    Asset Justification Reason for admissibility/non admissibility
    19, respectively, towards discharge liabilities.
    The Petitioner has claimed an amount of ₹34.91 lakh and ₹116.63 lakh for FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-14 The Petitioner has claimed an amount of ₹63.78 lakh, ₹77.69 lakh, ₹59.82 lakh and ₹26.97 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations.
    The Petitioner has claimed an amount of ₹168.68 lakh, ₹42.66 lakh and ₹15.46 lakh for FY 2015- 16, FY 2016-17 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-15 The Petitioner has claimed an amount of ₹759.76 lakh, ₹226.53 lakh, ₹329.20 lakh and ₹340.65 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹168.68 lakh, ₹42.66 lakh and ₹15.46 lakh for FY 2015- 16, FY 2016-17 and FY 2017-18, respectively, towards balance Sub-station works, PLCC,Civil works and line comepensation paid. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-16 The Petitioner has claimed an amount of ₹207.08 lakh, ₹97.99 lakh, ₹98.70 lakh and ₹65.46 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹86.78 lakh, ₹112.07 lakh and ₹61.34 lakh for FY 2015- 16, FY 2016-17 and FY 2017-18, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-17 The Petitioner has claimed an amount of ₹44.74 lakh, ₹115.14 ACE claimed by the Petitioner towards discharge liability is allowed

    Page 47 of 162

    Asset Justification Reason for admissibility/non admissibility
    lakh, ₹61.50 lakh and ₹164.79 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹160.14 lakh, ₹4.93 lakh and ₹13.60 lakh for FY 2015- 16, FY 2016-17 and FY 2017-18, respectively, towards balance Sub-station works and Civil works. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.
    Asset-19 The Petitioner has claimed an amount of ₹5684.81 lakh, ₹9114.36 lakh and ₹895.06 lakh for FY 2015-16, FY 2016-17, FY 2017-18 and FY 2018-19, respectively, towards discharge liabilities. ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations.
    The Petitioner has claimed an amount of ₹8791.88 lakh and ₹2271.08 lakh, FY 2016-17 and FY 2017-18, respectively, towards for un executed work towards Sub-station and civil works and compensation towards transmission line ACE claimed by the Petitioner towards discharge liability is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.

    40. As regards Asset-4, the Petitioner has claimed the an amount of ₹1571.34 lakh, ₹1489.71 lakh, ₹860.36 lakh, ₹210.90 lakh and ₹250.93 lakh towards discharge liabilities for 2014-15 to 2018-19 and ₹110.47 lakh towards additional works in 2018-19.

    41. In case of Asset-18, the Petitioner has claimed an amount of ₹11455.74 lakh, ₹20143.45 lakh, ₹13972.45 lakh and ₹10118.75 lakh towards discharge liabilities and an amount of ₹3191.30 lakh, ₹5633.38 lakh, ₹1449.91 lakh and ₹248.35 lakh towards additional work for 2015-16, 2016-17, 2017-18 and 2018-19.

    42. As regards Asset-4 and Asset-18, the Petitioner has submitted that ACE claimed in 2018-19, 2019-20 and 2020-21 is due to construction of pile foundation

    Page 48 of 162

    due to the change of the river course. The Petitioner has submitted that the proposal was discussed and approved in the 125thOCCM and 17thTCC and 17th NERPC meetings.

    43. We have gone through the submissions of the Petitioner. The proposal of shifting of vulnerable location 118 (DB+0) of  800 kV HVDC biswanath chariali- agra transmission line and loc.495 (DC+0) of 400 kV D/C Balipara-Bongaigaon (quad) transmission line on pile on account of unpredicted change in river course is appoved by TCC and RPC in its 17thTCC & 17thNER Power Committee Meetings held at Imphal and 125thof Operation Coordination Sub-Committee meeting of NERPC. Taking into consideration of the approval of TCC, RPC and OCCM, the ACE calimed by the Petitioner for an amount of ₹110.47 lakh towards Asset-4 and ₹248.35 lakh towards Asset-18 has been allowed for tower pile foundation works.

    44. ACE claimed by the Petitioner for Asset-4 for 2014-15, 2015-16 and 2016-17 for an amount of ₹1571.34 lakh, ₹1489.71 lakh and ₹860.36 lakh, respectively, is towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 tariff Regulations and ACE of ₹210.90 lakh and ₹250.93 lakh towards un discharge liability is allowed under Regulation 14(2)(iv) of the 2014 Tariff Regulations.

    45. ACE claimed by the Petitioner for Asset-18 for 2015-16, 2016-17 and 2017- 18 for an amount of ₹11455.74 lakh, ₹20143.45 lakh and ₹13972.45 lakh is towards is towards discharge liability is allowed under Regulation 14(1)(i) of the 2014 Tariff Regulations and ACE of ₹10118.75 lakh for 2018-19 is allowed towards deferred works is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.

    Page 49 of 162

    ACE for 2015-16, 2016-17, 2017-18 for an amount of ₹3191.30 lakh, ₹5633.38 lakh and ₹1449.91 lakh is allowed towards deferred works is allowed under Regulation 14(1)(ii) of the 2014 Tariff Regulations.

    46. As discussed above, ACE allowed for 2014-19 tariff period is as follows:

    (₹ in lakh) ACE allowed Total ACE allowed for

    Assets

    2014-15 2015-16 2016-17 2017-18 2018-19 2014-19 for true up

    Asset-1 277.06 43.39 8.24 3.17 0.00 331.86

    Asset-2 35.70 47.92 1.25 0.00 0.00 84.87

    Asset-3 43.64 132.27 0.09 0.00 0.00 176.00

    Asset-4 3215.98 1495.38 860.36 210.90 361.40 6144.02

    Asset-5 0.00 37.75 305.97 85.09 54.89 483.70

    Asset-6 0.00 32.38 247.52 68.84 7.74 356.48

    Asset-7 0.00 32.46 193.94 53.28 3.81 283.49

    Asset-8 0.00 279.25 798.97 212.33 2.36 1292.91

    Asset-9 0.00 201.80 128.12 35.18 459.26 824.36

    Asset-10 0.00 720.86 673.32 530.65 459.26 2384.09

    Asset-11 0.00 0.00 0.00 70.41 79.09 149.5

    Asset-12 0.00 0.00 0.00 99.25 192.77 292.02

    Asset-13 0.00 0.00 0.00 131.38 173.80 305.18

    Asset-14 0.00 295.86 121.03 75.28 25.95 518.12

    Asset-15 0.00 928.44 269.19 344.66 340.64 1882.93

    Asset-16 0.00 293.86 210.06 160.04 65.45 729.41

    Asset-17 0.00 239.29 120.07 75.10 164.80 599.26

    Asset-18 0.00 19314.05 27352.35 15383.04 **9060.56 62049.44

    Asset-19 0.00 0.00 15205.98 11448.67 **782.26 26654.65 Total 3572.38 24094.96 46496.46 28987.27 2391.22 105542.29

    ** ACE for 319 days only and capital cost is as on 13.02.2018.

    Treatment of PSDF Grants Availed

    47. The Petitioner has submitted that in line with the direction of the Commission vide its order in Petition No. 67/TT/2015, the Petitioner has taken up the matter for PSDF funding for the transmission project with the Ministry of Power (MoP).

    48. The Petiitoner has submitted that Petitioner has been pursuing with MoP for the disbursement of ₹288900 lakh in quarterly performance review of the Petitioner for 2nd, 3rdand 4thquarters of 2017-18 and requested Secretary (Power) to

    Page 50 of 162

    intervene to enable release of PSDF funding. However, in quarterly performance review meeting of the Petitioner for 1stquarter of 2018-19 taken by Secretary (Power) on 11.9.2018, Secretary (Power) has advised that "in view of non- availability of PSDF funds POWERGRID should approach CERC for appropriate orders for tariff".

    49. The Petitioner has submitted that subsequently, MoP vide letter dated 21.1.2019 has conveyed approval of raising EBRs for the scheme of 'Power System Development Fund (PSDF)' during 2018-19 for ₹288900 lakh (Total ₹348753 lakh including the other projects) for meeting loan liabilities (including ₹288900 lakh for the transmission assets for which PSDF grant is applied).

    50. The Petitioner has further submitted that out of total EBRs amounting to ₹348753 lakh, EBR's of ₹288900 lakh for aforesaid projects has been raised and received on 14.2.2019. Accordingly, EBR amount in lieu of PSDF grant has been deployed in the HVDC assets i.e. Asset-I and Asset-VI covered under Petition No. 363/TT/2018 decreasing the domestic loan to the extent applicable.

    51. The Petitioner has received a grant of ₹288900 lakh and the grant has been utilized against domestic debt portion of the transmission assets as approved vide letter ref. no: No. 10/1/2014-OM dated: 10.3.2017 (Point-4(vii)). Accordingly, tariff has been calculated and revised for HVDC asset (Asset-I and Asset-VI) in Petition No. 363/TT/2018.

    52. The Petitioner has further submitted that domestic loan opening as on 1.4.2018 and actual repayment of the loan during the year upto 13.2.2019 and loan deployed for ACE upto 13.2.2019 has been considered for arriving at the closing

    Page 51 of 162

    balance on 13.2.2019/ opening balance on 14.2.2019 for grant adjustment from the capital cost of the Asset-18 (HVDC Pole-I) and Asset-19 (HVDC Pole-II).

    53. We have considered the submissions of the Petitioner. Regulation 9(6) of the 2014 Tariff Regulations provides as follows:

    "The following shall be excluded or removed from the capital cost of the existing and new project:

    (a) xxx

    (b) xxx

    (c) xxx

    (d) xxx Provided that any grant received from the Central or State Government or any statutory body or authority for the execution of the project which does not carry any liability of repayment shall be excluded from the Capital Cost for the purpose of computation of interest on loan, return on equity and depreciation;

    Further, Regulation 19 of the 2014 Tariff Regulations provides as follows.

    "19. Debt-Equity Ratio: (1) For a project declared under commercial operation on or after 1.4.2014, the debt-equity ratio would be considered as 70:30 as on COD. If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30%shall be treated as normative loan: Provided that:

    i. xxx

    ii. xxx

    iii. any grant obtained for the execution of the project shall not be considered as a part of capital structure for the purpose of debt : equity ratio.

    xxxxx"

    54. As stated in Government of India's approval, the Petitioner has received ₹288900 lakh in lieu of PSDF grant and it has been adjusted with Asset-18 and Asset-19 by decreasing the domestic loan deployed for the said assets.

    55. COD of Asset-18 is 1.11.2015 and that of Asset-19 is 2.9.2016 whereas EBR of ₹288900 lakh has been received on 14.2.2019. Petitioner has utilised the grant in these two assets, i.e. ₹270045.33 lakh in Asset-18 and ₹18854.67 lakh in Asset-

    19. Accordingly, while working out the tariff, AFC has been calculated in two parts for both of these transmission assets- first from COD to 13.2.2019 and the other being from 14.2.2019 to 31.3.2019.

    Page 52 of 162

    56. Application of grant is in line with the terms and conditions specified by the Ministry of Finance (MoF) as well as MoP. As the grant has been received post- COD and for decreasing the domestic debt portion of the transmission project, the same has been reduced from the loan portfolio corresponding to high interest bearing domestic loans. This may be seen as similar to re-financing with zero interest loan.

    57. Accordingly, the details of ACE in case of Asset-18 and Asset-19 during 14.2.2019 to 31.3.2019 is as follows:

    (₹ in lakh)

    Assets ACE during 14.2.2019 to 31.3.2019
    Asset-18 1306.54
    Asset-19 112.80
    Total 1419.34

    Summary of Capital Cost From COD to 31.3.2019

    58. Based on the above, summary of capital cost considered for tariff in respect of the transmission assets from COD/ 1.4.2014 to 31.3.2019 is as follows:

    (₹ in lakh) Assets Capital cost ACE allowed for true-up in 2014-19 Admitted allowed as on capital cost

    COD/ 2014-15 2015-16 2016-17 2017-18 2018-19 as on 31.3.19 31.3.2014 (as allowed

    for true-up)

    *Asset-1 2115.81 277.06 43.39 8.24 3.17 0.00 2447.67 *Asset-2 892.38 35.70 47.92 1.25 0.00 0.00 977.25 *Asset-3 560.26 43.64 132.27 0.09 0.00 0.00 736.26 Asset-4 111887.65 3215.98 1495.38 860.36 210.90 361.40 118031.67 Asset-5 2266.61 0.00 37.75 305.97 85.09 54.89 2750.31 Asset-6 1448.53 0.00 32.38 247.52 68.84 7.74 1805.01 Asset-7 1550.37 0.00 32.46 193.94 53.28 3.81 1833.86 Asset-8 6268.76 0.00 279.25 798.97 212.33 2.36 7561.67 Asset-9 4277.43 0.00 201.80 128.12 35.18 459.26 5101.79 Asset-10 12125.42 0.00 720.86 673.32 530.65 459.26 14509.51 Asset-11 1279.03 0.00 0.00 0.00 70.41 79.09 1428.53 Asset-12 2359.46 0.00 0.00 0.00 99.25 192.77 2651.48

    Page 53 of 162

    Asset-13 2343.37 0.00 0.00 0.00 131.38 173.80 2648.55
    Asset-14 2233.77 0.00 295.86 121.03 75.28 25.95 2751.89
    Asset-15 6941.56 0.00 928.44 269.19 344.66 340.64 8824.49
    Asset-16 2528.91 0.00 293.86 210.06 160.04 65.45 3258.32
    Asset-17 2567.55 0.00 239.29 120.07 75.10 164.80 3166.81
    Asset-18 800112.31 0.00 19314.05 27352.35 15383.04 **9060.56 871222.31
    Asset-19 208381.00 0.00 0.00 15205.98 11448.67 **782.26 235817.91

    *As on 1.4.2014 for Asset-1,Asset-2 & Asset-3 and as on COD for Assets-4 to Asset-19.

    ** ACE for 319 days only and capital cost is as on 13.02.2018.

    59. Details of capital cost for Asset-18 and Asset-19 after adjustment of grants is as follows:

    (₹ in lakh)

    Assets Capital cost as on 13.2.2018 Grants used Capital cost as on 14.2.2018 ACE for 46 days Admitted cost as on 31.3.2019
    Asset-18 871222.31 268996.95 602225.36 1306.54 603531.90
    Asset-19 235817.91 19903.05 215914.86 112.80 216027.66

    Debt-Equity Ratio

    60. The details of debt-equity ratio in respect of the transmission assets as on COD and 31.3.2019 are as follows:

    Asset-1 Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1481.07 70.00 1713.37 70.00 Equity 634.74 30.00 734.30 30.00

    Total 2115.81 100.00 2447.67 100.00 Asset-2

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 624.67 70.00 684.08 70.00 Equity 267.71 30.00 293.18 30.00

    Total 892.38 100.00 977.25 100.00 Asset-3

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 392.19 70.00 515.39 70.00 Equity 168.08 30.00 220.88 30.00

    Total 560.26 100.00 736.26 100.00

    Page 54 of 162

    Asset-4 Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 89510.12 80.00 94132.78 79.75 Equity 22377.53 20.00 23898.89 20.25

    Total 111887.65 100.00 118031.67 100.00 Asset-5

    Capital cost Capital cost

    Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1813.29 80.00 2151.88 78.24 Equity 453.32 20.00 598.43 21.76

    Total 2266.61 100.00 2750.31 100.00 Asset-6

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1158.83 80.00 1408.36 78.03 Equity 289.71 20.00 396.65 21.97

    Total 1448.54 100.00 1805.01 100.00 Asset-7

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1240.30 80.00 1442.00 78.63 Equity 310.07 20.00 391.86 21.37

    Total 1550.37 100.00 1833.86 100.00 Asset-8

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 5015.01 80.00 5932.01 78.45 Equity 1253.75 20.00 1629.66 21.55

    Total 6268.76 100.00 7561.67 100.00 Asset-9

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 3421.94 80.00 4000.51 78.41 Equity 855.49 20.00 1101.28 21.59

    Total 4277.43 100.00 5101.79 100.00

    Page 55 of 162

    Asset-10 Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 9700.34 80.00 11377.31 78.41 Equity 2425.08 20.00 3132.20 21.59

    Total 12125.42 100.00 14509.51 100.00 Asset-11

    Capital cost Capital cost

    Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1023.22 80.00 1130.69 79.15 Equity 255.80 20.00 297.84 20.85

    Total 1279.02 100.00 1428.53 100.00 Asset-12

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1887.57 80.00 2098.11 79.13 Equity 471.89 20.00 553.37 20.87

    Total 2359.46 100.00 2651.48 100.00 Asset-13

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1874.70 80.00 2098.44 79.23 Equity 468.67 20.00 550.11 20.77

    Total 2343.37 100.00 2648.55 100.00 Asset-14

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 1787.02 80.00 2198.97 79.91 Equity 446.75 20.00 552.92 20.09

    Total 2233.77 100.00 2751.89 100.00 Asset-15

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 5553.25 80.00 7025.60 79.61 Equity 1388.31 20.00 1798.89 20.39

    Total 6941.56 100.00 8824.49 100.00

    Page 56 of 162

    Asset-16 Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 2023.11 80.00 2600.10 79.80 Equity 505.78 20.00 658.21 20.20

    Total 2528.89 100.00 3258.30 100.00 Asset-17

    Capital cost Capital cost Particulars (as on COD) (in %) (as on 31.3.2019) (in %) (₹ in lakh) (₹ in lakh)

    Debt 2054.05 80.00 2516.98 79.48 Equity 513.51 20.00 649.84 20.52

    Total 2567.56 100.00 3166.82 100.00 Asset-18

    Capital cost

    Capital cost

    (as on

    Particulars (as on COD) (in %) (in %)

    13.02.2019)

    (₹ in lakh) (₹ in lakh)

    Debt 640089.85 80.00 696127.96 79.90 Equity 160022.46 20.00 175094.35 20.10

    Total 800112.31 100.00 871222.31 100.00 Asset-19

    Capital cost

    Capital cost

    (as on

    Particulars (as on COD) (in %) (in %)

    13.02.2019)

    (₹ in lakh) (₹ in lakh)

    Debt 166704.80 80.00 188643.90 80.00 Equity 41676.20 20.00 47174.00 20.00

    Total 208381.00 100.00 235817.90 100.00 Debt Equity Ratio after adjusting grants for Asset-18 and Asset-19 Asset-18

    Capital cost

    Capital cost

    (as on

    Particulars (in %) (as on 31.3.2019) (in %)

    14.2.2019)

    (₹ in lakh) (₹ in lakh)

    Debt 427131.01 70.93 428045.59 70.92 Equity 175094.35 29.07 175486.31 29.08

    Total 602225.36 100.00 603531.90 100.00 Asset-19

    Capital cost

    Capital cost

    (as on

    Particulars (in %) (as on 31.3.2019) (in %)

    14.2.2019)

    (₹ in lakh) (₹ in lakh)

    Debt 168740.85 78.15 168819.82 78.15

    Page 57 of 162

    Equity 47174.00 21.85 47207.84 21.85
    Total 215914.85 100.00 216027.66 100.00

    Depreciation

    61. Depreciation has been allowed as per the methodology provided in Regulation 27 of the 2014 Tariff Regulations. Depreciation has been allowed considering capital expenditure as on 1.4.2014 and approved ACE during 2014- 19 tariff period. The Gross Block during 2014-19 tariff period has been depreciated at Weighted Average Rate of Depreciation (WAROD). WAROD at Annexure-I has been worked out after taking into account the depreciation rates of assets as specified in the 2014 Tariff Regulations and trued-up depreciation allowed in respect of the transmission assets for 2014-19 tariff period is as follows:

    (₹ in lakh) Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Opening Gross Block 2115.81 2392.87 2436.26 2444.50 2447.67

    B ACE 277.06 43.39 8.24 3.17 0.00

    C Closing Gross Block (A+B) 2392.87 2436.26 2444.50 2447.67 2447.67 D Average Gross Block (A+C)/2 2254.34 2414.57 2440.38 2446.09 2447.67 Weighted average rate of Depreciation 5.1998 5.1922 5.1922 5.1924 5.1925

    E

    (WAROD) (in %) Balance useful life at the beginning of the 24 23 22 21 20

    F

    year (Year) Lapsed life at the beginning of the year 1 2 3 4 5

    G

    (Year) H Aggregated Depreciable Value (D*90%) 2028.91 2173.11 2196.34 2201.48 2202.90

    Combined Depreciation during the year 117.22 125.37 126.71 127.01 127.10

    I

    (D*E)

    Cumulative Depreciation at the end of the 301.62 426.99 553.70 680.71 807.81

    J

    year Remaining Aggregated Depreciable 1727.29 1746.12 1642.64 1520.76 1395.10

    K

    Value

    (₹ in lakh) Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Opening Gross Block 892.38 928.08 976.00 977.25 977.25

    B ACE 35.70 47.92 1.25 0.00 0.00

    C Closing Gross Block (A+B) 928.08 976.00 977.25 977.25 977.25 D Average Gross Block (A+C)/2 910.23 952.04 976.63 977.25 977.25

    Page 58 of 162

    Asset-2
    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    E Weighted average rate of Depreciation (WAROD) (in %) 5.2800 5.2800 5.2800 5.2800 5.2800
    F Balance useful life at the beginning of the year (Year) 24 23 22 21 20
    G Lapsed life at the beginning of the year (Year) 1 2 3 4 5
    H Aggregated Depreciable Value (D*90%) 819.21 856.84 878.96 879.53 879.53

    (₹ in lakh) Asset-4

    2014-15 Particulars (Pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    A Opening Gross Block 111887.65 115103.63 116599.01 117459.37 117670.27

    B ACE 3215.98 1495.38 860.36 210.90 361.40

    C Closing Gross Block (A+B) 115103.63 116599.01 117459.37 117670.27 118031.67 D Average Gross Block (A+C)/2 113495.64 115851.32 117029.19 117564.82 117850.97 Weighted average rate of 5.2803 5.2803 5.2791 5.2779 5.2779

    E

    Depreciation (WAROD) (in %) Balance useful life at the 34 34 33 32 31

    F

    beginning of the year (Year) Lapsed life at the beginning of 0 0 1 2 3

    G

    the year (Year)

    Page 59 of 162

    Asset-4 2014-15 Particulars (Pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    Aggregated Depreciable Value 102146.07 104266.19 105326.27 105808.34 106065.87

    H

    (D*90%)

    Combined Depreciation during 2380.72 6117.25 6178.09 6205.00 6220.09

    I

    the year (D*E)

    Cumulative Depreciation at the 2380.72 8497.97 14676.06 20881.06 27101.15

    J

    end of the year Remaining Aggregated 99765.35 95768.21 90650.21 84927.28 78964.72

    K

    Depreciable Value

    (₹ in lakh) Asset-5

    2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Opening Gross Block 2266.61 2304.36 2610.33 2695.42

    B ACE 37.75 305.97 85.09 54.89

    C Closing Gross Block (A+B) 2304.36 2610.33 2695.42 2750.31 D Average Gross Block (A+C)/2 2285.49 2457.35 2652.88 2722.87 Weighted average rate of Depreciation 4.7391 4.7266 4.7143 4.7103

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0 1 2

    F

    year (Year) Lapsed life at the beginning of the year 25 25 24 23

    G

    (Year) H Aggregated Depreciable Value (D*90%) 2006.70 2161.37 2337.35 2400.34

    Combined Depreciation during the year 54.16 116.15 125.06 128.26

    I

    (D*E)

    Cumulative Depreciation at the end of the 54.16 170.30 295.37 423.62

    J

    year Remaining Aggregated Depreciable 1952.54 1991.07 2041.98 1976.72

    K

    Value

    (₹ in lakh) Asset-6

    2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 181 days)

    A Opening Gross Block 1448.54 1480.92 1728.44 1797.28

    B ACE 32.38 247.52 68.84 7.73

    C Closing Gross Block (A+B) 1480.92 1728.44 1797.28 1805.01 D Average Gross Block (A+C)/2 1464.73 1604.68 1762.86 1801.15 Weighted average rate of Depreciation 4.7179 4.7203 4.7226 4.7230

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0 1 2

    F

    year (Year) Lapsed life at the beginning of the year 25 25 24 23

    G

    (Year)

    Page 60 of 162

    Asset-6
    Particulars 2015-16 (Pro-rata for 181 days) 2016-17 2017-18 2018-19
    H Aggregated Depreciable Value (D*90%) 1268.02 1393.97 1536.34 1570.79

    (₹ in lakh) Asset-8

    2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 113 days)

    A Opening Gross Block 6268.76 6548.01 7346.98 7559.31

    B ACE 279.25 798.97 212.33 2.36

    C Closing Gross Block (A+B) 6548.01 7346.98 7559.31 7561.67 D Average Gross Block (A+C)/2 6408.39 6947.50 7453.15 7560.49 Weighted average rate of Depreciation 5.0487 5.0448 5.0413 5.0405

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0 1 2

    F

    year (Year) Lapsed life at the beginning of the year 25

    G

    (Year) 25 24 23 H Aggregated Depreciable Value (D*90%) 5767.55 6252.75 6707.83 6804.44

    Page 61 of 162

    Asset-8 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 113 days)

    Combined Depreciation during the year 99.89 350.49 375.73 381.09

    I

    (D*E)

    Cumulative Depreciation at the end of the 99.89 450.38 826.11 1207.20

    J

    year Remaining Aggregated Depreciable 5667.66 5802.37 5881.72 5597.24

    K

    Value

    (₹ in lakh) Asset-9

    2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 172 days)

    A Opening Gross Block 4277.43 4479.23 4607.35 4642.53

    B ACE 201.80 128.12 35.18 459.26

    C Closing Gross Block (A+B) 4479.23 4607.35 4642.53 5101.79 D Average Gross Block (A+C)/2 4378.33 4543.29 4624.94 4872.16 Weighted average rate of Depreciation 4.9915 4.9907 4.9866 4.9667

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0 1 2

    F

    year (Year) Lapsed life at the beginning of the year 29

    G

    (Year) 29 28 27 H Aggregated Depreciable Value (D*90%) 3890.26 4038.72 4112.21 4334.71

    Combined Depreciation during the year 102.70 226.74 230.63 241.99

    I

    (D*E)

    Cumulative Depreciation at the end of the 102.70 329.45 560.08 802.06

    J

    year Remaining Aggregated Depreciable 3787.56 3709.28 3552.13 3532.64

    K

    Value

    (₹ in lakh) Asset-10 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Opening Gross Block 12125.42 12846.28 13519.60 14050.25

    B ACE 720.86 673.32 530.65 459.26

    C Closing Gross Block (A+B) 12846.28 13519.60 14050.25 14509.51 D Average Gross Block (A+C)/2 12485.85 13182.94 13784.93 14279.88 Weighted average rate of Depreciation 5.1801 5.1807 5.1813 5.1728

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0 1 2

    F

    year (Year) Lapsed life at the beginning of the year 33

    G

    (Year) 33 32 31 H Aggregated Depreciable Value (D*90%) 11187.03 11814.41 12356.19 12801.65

    Combined Depreciation during the year 323.39 682.97 714.23 738.67

    I

    (D*E)

    Page 62 of 162

    Asset-10 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    Cumulative Depreciation at the end of the 323.39 1006.36 1720.59 2459.26

    J

    I Combined Depreciation during the year (D*E) 81.67 124.59
    J Cumulative Depreciation at the end of the year 81.67 206.25

    Page 63 of 162

    Asset-12 2017-18 Particulars (Pro-rata for 2018-19 254 days)

    Remaining Aggregated Depreciable 2086.51 2093.33

    K

    Value

    (₹ in lakh) Asset-13 2017-18 Particulars (Pro-rata for 2018-19 111 days)

    A Opening Gross Block 2343.37 2474.75

    B ACE 131.38 173.80

    C Closing Gross Block (A+B) 2474.75 2648.55 D Average Gross Block (A+C)/2 2409.06 2561.65 Weighted average rate of Depreciation 4.8751 4.8778

    E

    (WAROD) (in %) Balance useful life at the beginning of the 0 0

    F

    year (Year) Lapsed life at the beginning of the year 25 25

    G

    (Year) H Aggregated Depreciable Value (D*90%) 2168.15 2305.49

    Combined Depreciation during the year 35.72 124.95

    I Combined Depreciation during the year (D*E) 49.46 126.78 131.83 134.43
    J Cumulative Depreciation at the end of the year 49.46 176.24 308.07 442.50
    K Remaining Aggregated Depreciable Value 1993.60 2054.42 2010.93 1922.06

    Page 64 of 162

    (₹ in lakh)

    Asset-15
    Particulars 2015-16 (Pro-rata for 157 days) 2016-17 2017-18 2018-19
    A Opening Gross Block 6941.56 7870.00 8139.19 8483.85
    B ACE 928.44 269.19 344.66 340.64
    C Closing Gross Block (A+B) 7870.00 8139.19 8483.85 8824.49
    D Average Gross Block (A+C)/2 7405.78 8004.59 8311.52 8654.17
    E Weighted average rate of Depreciation (WAROD) (in %) 5.1481 5.1553 5.1583 5.1623
    F Balance useful life at the beginning of the year (Year) 0 0 1 2
    G Lapsed life at the beginning of the year (Year) 33 33 32 31
    H Aggregated Depreciable Value (D*90%) 6564.73 7103.67 7379.90 7688.28

    Combined Depreciation during the year 163.55 412.66 428.73 446.75

    I Combined Depreciation during the year (D*E) 65.54 144.14 153.69 159.55
    J Cumulative Depreciation at the end of the year 65.54 209.68 363.37 522.92
    K Remaining Aggregated Depreciable Value 2242.24 2324.86 2337.71 2279.63

    Page 65 of 162

    (₹ in lakh)

    Asset-17
    Particulars 2015-16 (Pro-rata for 104 days) 2016-17 2017-18 2018-19
    A Opening Gross Block 2567.56 2806.85 2926.92 3002.02
    B ACE 239.29 120.07 75.10 164.80
    C Closing Gross Block (A+B) 2806.85 2926.92 3002.02 3166.82
    D Average Gross Block (A+C)/2 2687.21 2866.89 2964.47 3084.42
    E Weighted average rate of Depreciation (WAROD) (in %) 4.9198 4.9208 4.9209 4.9211
    F Balance useful life at the beginning of the year (Year) 0 0 1 2
    G Lapsed life at the beginning of the year (Year) 25 25 24 23
    H Aggregated Depreciable Value (D*90%) 2368.25 2529.96 2617.79 2725.74

    Combined Depreciation during the year 37.57 141.07 145.88 151.79

    I Combined Depreciation during the year (D*E) 17567.29 43478.88 44548.04 39474.62
    J Cumulative Depreciation at the end of the year 17567.29 61046.17 105594.22 145068.84
    K Remaining Aggregated Depreciable Value 709581.22 687102.21 661785.09 633310.09

    Page 66 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2016-17 (Pro-rata for 211 days) 2017-18 2018-19
    A Opening Gross Block 208381.00 223586.98 235035.65
    B ACE 15205.98 11448.67 782.26
    C Closing Gross Block (A+B) 223586.98 235035.65 235817.90
    D Average Gross Block (A+C)/2 215983.99 229311.31 235426.77
    E Weighted average rate of Depreciation (WAROD) (in %) 5.0781 5.0702 5.0652
    F Balance useful life at the beginning of the year (Year) 0 0 1
    G Lapsed life at the beginning of the year (Year) 26 26 25
    H Aggregated Depreciable Value (D*90%) 192159.36 204153.95 209657.87

    I Combined Depreciation during the year (D*E) 6340.30 11626.47 10422.06
    J Cumulative Depreciation at the end of the year 6340.30 17966.77 28388.83
    K Remaining Aggregated Depreciable Value 185819.06 186187.17 181269.03

    After adjustment of grants

    Particulars 2018-19 (Pro-rata for 46 days) 2018-19 (Pro-rata for 46 days)
    Asset-18 Asset-19
    Opening Gross Block 602225.36 215914.85
    ACE 1306.54 112.80
    Closing Gross Block (A+B) 603531.90 216027.66
    Average Gross Block (A+C)/2 602878.63 215971.25
    Weighted average rate of Depreciation (WAROD) (in %) 5.2108% 5.0642%
    Balance useful life at the beginning of the year (Year) 2 1
    Lapsed life at the beginning of the year (Year) 31 25
    Aggregated Depreciable Value (D*90%) 540946.87 192335.79

    Combined Depreciation during the year (D*E) 3959.13 1378.38
    Cumulative Depreciation at the end of the year 149027.97 29767.22
    Remaining Aggregated Depreciable Value 391918.90 162568.58

    Interest on Loan ("IoL")

    62. The Petitioner has prayed for floating rate of IoL for 2014-19 period. The

    Page 67 of 162

    Petitioner has claimed the weighted average rate of interest based on its actual loan portfolio and actual rate of interest on loan. Bihar Discoms has submitted that the 2014 Tariff Regulations do not permit change in interest rate due to floating rate of interest.

    63. In response, the Petitioner has submitted that in the tariff calculation for 2014- 19 period, IoL has been calculated on the basis of actual rate of interest of various loans deployed for each year. The change in interest rate due to floating rate of interest applicable, if any, for the transmission project needs to be claimed/ adjusted over the tariff period of 5 years directly from/ with the beneficiaries. The Petitioner has further submitted that the floating interest rate mentioned in the cash IDC statement for bank loans varies on daily/monthly/quarterly basis and the IDC calculation has been done by multiplying the particular loan interest rate with applicable number of days (i.e. for the number of days upto which the particular rate is applicable) till COD.

    64. We have considered the submissions of the Petitioner and Bihar Discoms. IoL is calculated based on actual interest rate, in accordance with Regulation 26 of the 2014 Tariff Regulations. The details of IoL allowed in respect of the transmission assets are as follows:

    (₹ in lakh)

    Asset-1
    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    A Gross Normative Loan 1481.07 1675.01 1705.38 1711.15 1713.37
    B Cumulative Repayments upto Previous Year 184.40 301.62 426.99 553.70 680.71
    C Net Loan-Opening (A-B) 1296.67 1373.39 1278.39 1157.45 1032.66
    D Addition due to ACE 193.94 30.37 5.77 2.22 0.00
    E Repayment during the year 117.22 125.37 126.71 127.01 127.10
    F Net Loan-Closing (C+D-E) 1373.39 1278.39 1157.45 1032.66 905.56
    G Average Loan (C+F)/2 1335.03 1325.89 1217.92 1095.05 969.11

    Page 68 of 162

    Asset-1 Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    H Weighted Average Rate of Interest on 8.9920 8.9743 8.9647 8.9321 8.8740 Loan (in %)

    I Interest on Loan (G*H) 120.05 118.99 109.18 97.81 86.00 (₹ in lakh)

    Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Gross Normative Loan 624.67 649.66 683.20 684.08 684.08 B Cumulative Repayments upto Previous 59.99 108.05 158.32 209.88 261.48 Year

    C Net Loan-Opening (A-B) 564.68 541.61 524.88 474.19 422.59 D Addition due to ACE 24.99 33.54 0.88 0.00 0.00

    E Repayment during the year 48.06 50.27 51.57 51.60 51.60 F Net Loan-Closing (C+D-E) 541.61 524.88 474.19 422.59 370.99 G Average Loan (C+F)/2 553.14 533.24 499.54 448.39 396.79 H Weighted Average Rate of Interest on 8.9250 8.9186 8.9024 8.8928 8.8912 Loan (in %)

    I Interest on Loan (G*H) 49.37 47.56 44.47 39.87 35.28 (₹ in lakh)

    Asset-3

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Gross Normative Loan 392.19 422.73 515.32 515.39 515.39 B Cumulative Repayments upto Previous 30.59 61.32 96.70 135.57 174.45 Year

    C Net Loan-Opening (A-B) 361.60 361.41 418.62 379.81 340.94 D Addition due to ACE 30.55 92.59 0.06 0.00 0.00 E Repayment during the year 30.73 35.38 38.87 38.87 38.87 F Net Loan-Closing (C+D-E) 361.41 418.62 379.81 340.94 302.06 G Average Loan (C+F)/2 361.50 390.01 399.22 360.37 321.50 H Weighted Average Rate of Interest on 9.1486 9.1537 9.0639 8.0550 8.7130 Loan (in %)

    I Interest on Loan (G*H) 33.07 35.70 36.18 29.03 28.01 (₹ in lakh)

    Asset-4

    2014-15

    Particulars (Pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    A Gross Normative Loan 89510.12 92082.90 93129.67 93731.92 93879.55 B Cumulative Repayments upto Previous 0.00 2380.72 8497.97 14676.06 20881.06 Year

    C Net Loan-Opening (A-B) 89510.12 89702.18 84631.70 79055.86 72998.49 D Addition due to ACE 2572.78 1046.77 602.25 147.88 252.98 E Repayment during the year 2380.72 6117.25 6178.09 6205.00 6220.09 F Net Loan-Closing (C+D-E) 89702.18 84631.70 79055.86 72998.49 67031.38 G Average Loan (C+F)/2 89606.15 87166.94 81843.78 76027.18 70014.93 H Weighted Average Rate of Interest on 9.5223 9.3673 9.2181 8.9368 8.8374 Loan (in %)

    Page 69 of 162

    Asset-4 2014-15 Particulars (Pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    I Interest on Loan (G*H) 3389.65 8165.19 7544.44 6794.41 6187.50 (₹ in lakh)

    Asset-5

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Gross Normative Loan 1813.29 1839.71 2053.89 2113.46 B Cumulative Repayments upto Previous 0.00 54.16 170.30 295.37 Year

    C Net Loan-Opening (A-B) 1813.29 1785.56 1883.59 1818.09 D Addition due to ACE 26.43 214.18 59.56 38.42 E Repayment during the year 54.16 116.15 125.06 128.26 F Net Loan-Closing (C+D-E) 1785.56 1883.59 1818.09 1728.25 G Average Loan (C+F)/2 1799.42 1834.57 1850.84 1773.17 H Weighted Average Rate of Interest on 9.2519 9.1518 8.9443 8.8865 Loan (in %)

    I Interest on Loan (G*H) 83.24 167.90 165.54 157.57 (₹ in lakh)

    Asset-6

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 181 days)

    A Gross Normative Loan 1158.83 1181.50 1354.76 1402.95 B Cumulative Repayments upto Previous 0.00 34.17 109.92 193.17 Year

    C Net Loan-Opening (A-B) 1158.83 1147.32 1244.84 1209.78 D Addition due to ACE 22.67 173.26 48.19 5.41 E Repayment during the year 34.17 75.75 83.25 85.07 F Net Loan-Closing (C+D-E) 1147.32 1244.84 1209.78 1130.12 G Average Loan (C+F)/2 1153.08 1196.08 1227.31 1169.95 H Weighted Average Rate of Interest on 9.2773 9.1448 8.8568 8.7698 Loan (in%)

    I Interest on Loan (G*H) 52.90 109.38 108.70 102.60 (₹ in lakh)

    Asset-7

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 35 days)

    A Gross Normative Loan 1240.30 1266.28 1402.04 1439.34 B Cumulative Repayments upto Previous 0.00 7.03 86.09 171.12 Year

    C Net Loan-Opening (A-B) 1240.30 1259.25 1315.95 1268.22 D Addition due to ACE 25.98 135.76 37.30 2.67

    Page 70 of 162

    Asset-7 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 35 days)

    E Repayment during the year 7.03 79.05 85.03 86.41 F Net Loan-Closing (C+D-E) 1259.25 1315.95 1268.22 1184.47 G Average Loan (C+F)/2 1249.77 1287.60 1292.08 1226.35 H Weighted Average Rate of Interest on Loan 9.1637 9.0859 8.9590 8.9246 (in %)

    I Interest on Loan (G*H) 10.95 116.99 115.76 109.45 (₹ in lakh)

    Asset-8

    2015-16

    (Pro-rata

    Particulars 2016-17 2017-18 2018-19 for 113

    days)

    A Gross Normative Loan 5015.01 5219.74 5781.73 5930.36 B Cumulative Repayments upto Previous 0.00 99.89 450.38 826.11 Year

    C Net Loan-Opening (A-B) 5015.01 5119.85 5331.36 5104.25 D Addition due to ACE 204.73 561.99 148.63 1.65 E Repayment during the year 99.89 350.49 375.73 381.09 F Net Loan-Closing (C+D-E) 5119.85 5331.36 5104.25 4724.82 G Average Loan (C+F)/2 5067.43 5225.60 5217.81 4914.53 H Weighted Average Rate of Interest on 9.2145 9.1278 8.9452 8.8852 Loan (in %)

    I Interest on Loan (G*H) 144.16 476.98 466.74 436.67 (₹ in lakh)

    Asset-9

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 172 days)

    A Gross Normative Loan 3421.94 3564.71 3654.40 3679.02 B Cumulative Repayments upto Previous 0.00 102.70 329.45 560.08 Year

    C Net Loan-Opening (A-B) 3421.94 3462.01 3324.95 3118.95 D Addition due to ACE 142.77 89.68 24.63 321.48 E Repayment during the year 102.70 226.74 230.63 241.99 F Net Loan-Closing (C+D-E) 3462.01 3324.95 3118.95 3198.44 G Average Loan (C+F)/2 3441.98 3393.48 3221.95 3158.70 H Weighted Average Rate of Interest on 9.1120 9.0195 8.7241 8.6185 Loan (in %)

    I Interest on Loan (G*H) 147.39 306.07 281.09 272.23 (₹ in lakh)

    Asset-10

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Gross Normative Loan 9700.34 10213.04 10684.37 11055.83

    Page 71 of 162

    Asset-10 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    B Cumulative Repayments upto Previous 0.00 323.39 1006.36 1720.59 Year

    C Net Loan-Opening (A-B) 9700.34 9889.65 9678.01 9335.24 D Addition due to ACE 512.70 471.33 371.46 321.48 E Repayment during the year 323.39 682.97 714.23 738.67 F Net Loan-Closing (C+D-E) 9889.65 9678.01 9335.24 8918.05 G Average Loan (C+F)/2 9794.99 9783.83 9506.62 9126.64 H Weighted Average Rate of Interest on 9.0794 8.9745 8.6573 8.5436 Loan (in %)

    I Interest on Loan (G*H) 444.66 878.05 823.02 779.74 (₹ in lakh)

    Asset-11

    2017-18

    Particulars (Pro-rata for 2018-19

    242 days)

    A Gross Normative Loan 1023.22 1074.88 B Cumulative Repayments upto Previous 0.00 46.20 Year

    C Net Loan-Opening (A-B) 1023.22 1028.68 D Addition due to ACE 51.66 55.81

    E Repayment during the year 46.20 73.34 F Net Loan-Closing (C+D-E) 1028.68 1011.15 G Average Loan (C+F)/2 1025.95 1019.92 H Weighted Average Rate of Interest on Loan 7.8101 7.8066 (in %)

    I Interest on Loan (G*H) 53.35 79.62 (₹ in lakh)

    Asset-12

    2017-18

    Particulars (Pro-rata for 2018-19 254 days)

    A Gross Normative Loan 1887.57 1963.08 B Cumulative Repayments upto Previous 0.00 81.67 Year

    C Net Loan-Opening (A-B) 1887.57 1881.41

    D 75.51 135.03

    Addition due to ACE E Repayment during the year 81.67 124.59 F Net Loan-Closing (C+D-E) 1881.41 1891.85 G Average Loan (C+F)/2 1884.49 1886.63 H Weighted Average Rate of Interest on 8.1795 8.1432 Loan (in %)

    I Interest on Loan (G*H) 107.27 153.63

    Page 72 of 162

    (₹ in lakh) Asset-13 2017-18 Particulars (Pro-rata for 2018-19 111 days)

    A Gross Normative Loan 1874.70 1976.26 B Cumulative Repayments upto Previous 0.00 35.72 Year

    C Net Loan-Opening (A-B) 1874.70 1940.54 D Addition due to ACE 101.56 122.18 E Repayment during the year 35.72 124.95 F Net Loan-Closing (C+D-E) 1940.54 1937.77 G Average Loan (C+F)/2 1907.62 1939.15 H Weighted Average Rate of Interest on 8.0785 8.0422 Loan (in %)

    I Interest on Loan (G*H) 46.87 155.95 (₹ in lakh)

    Asset-14

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 156 days)

    A Gross Normative Loan 1787.02 2023.76 2120.58 2180.80 B Cumulative Repayments upto Previous 0.00 49.46 176.24 308.07 Year

    C Net Loan-Opening (A-B) 1787.02 1974.30 1944.34 1872.73 D Addition due to ACE 236.74 96.82 60.22 18.17 E Repayment during the year 49.46 126.78 131.83 134.43 F Net Loan-Closing (C+D-E) 1974.30 1944.34 1872.73 1756.47 G Average Loan (C+F)/2 1880.66 1959.32 1908.54 1814.60 H Weighted Average Rate of Interest on 9.3923 9.2953 9.2033 9.1448 Loan (in %)

    I Interest on Loan (G*H) 75.29 182.12 175.65 165.94 (₹ in lakh)

    Asset-15

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 156 days)

    A Gross Normative Loan 5553.25 6296.07 6511.42 6787.15 B Cumulative Repayments upto Previous 0.00 163.55 576.21 1004.94 Year

    C Net Loan-Opening (A-B) 5553.25 6132.52 5935.21 5782.20 D Addition due to ACE 742.82 215.35 275.73 238.45 E Repayment during the year 163.55 412.66 428.73 446.75 F Net Loan-Closing (C+D-E) 6132.52 5935.21 5782.20 5573.90 G Average Loan (C+F)/2 5842.88 6033.86 5858.71 5678.05 H Weighted Average Rate of Interest on 9.1433 8.9622 8.4783 8.3198 Loan (in %)

    I Interest on Loan (G*H) 229.17 540.77 496.72 472.40

    Page 73 of 162

    (₹ in lakh) Asset-16 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Gross Normative Loan 2023.11 2258.20 2426.25 2554.28 B Cumulative Repayments upto Previous 0.00 65.54 209.68 363.37 Year

    C Net Loan-Opening (A-B) 2023.11 2192.67 2216.57 2190.91 D Addition due to ACE 235.09 168.05 128.03 45.82 E Repayment during the year 65.54 144.14 153.69 159.55 F Net Loan-Closing (C+D-E) 2192.67 2216.57 2190.91 2077.17 G Average Loan (C+F)/2 2107.89 2204.62 2203.74 2134.04 H Weighted Average Rate of Interest on 9.3631 9.1314 8.5665 8.3724 Loan (in %)

    I Interest on Loan (G*H) 98.68 201.31 188.78 178.67 (₹ in lakh)

    Asset-17

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 104 days)

    A Gross Normative Loan 2054.05 2245.48 2341.54 2401.62 B Cumulative Repayments upto Previous 0.00 37.57 178.64 324.52 Year

    C Net Loan-Opening (A-B) 2054.05 2207.91 2162.90 2077.10 D Addition due to ACE 191.43 96.06 60.08 115.36 E Repayment during the year 37.57 141.07 145.88 151.79 F Net Loan-Closing (C+D-E) 2207.91 2162.90 2077.10 2040.67 G Average Loan (C+F)/2 2130.98 2185.41 2120.00 2058.88 H Weighted Average Rate of Interest on 9.0356 8.9651 8.8345 8.7596 Loan (in %)

    I Interest on Loan (G*H) 54.71 195.92 187.29 180.35 (₹ in lakh)

    Asset-18

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 152 days)

    A Gross Normative Loan 640089.85 655596.20 677478.76 689785.57 B Cumulative Repayments upto Previous 0.00 17567.29 61046.17 105594.22 Year

    C Net Loan-Opening (A-B) 640089.85 638028.91 616432.58 584191.35 D Addition due to ACE 15506.36 21882.55 12306.81 6342.39 E Repayment during the year 17567.29 43478.88 44548.04 39474.62 F Net Loan-Closing (C+D-E) 638028.91 616432.58 584191.35 551059.12 G Average Loan (C+F)/2 639059.38 627230.75 600311.96 567625.23 H Weighted Average Rate of Interest on 5.1187 5.3565 5.4368 5.8382 Loan (in %)

    I Interest on Loan (G*H) 13585.12 33597.61 32637.76 28962.66

    Page 74 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2016-17 (Pro-rata for 211 days) 2017-18 2018-19
    A Gross Normative Loan 166704.80 178869.59 188017.35
    B Cumulative Repayments upto Previous Year 0.00 6340.30 17966.77
    C Net Loan-Opening (A-B) 166704.80 172529.28 170050.57
    D Addition due to ACE 12164.79 9147.76 626.56
    E Repayment during the year 6340.30 11626.47 10422.06
    F Net Loan-Closing (C+D-E) 172529.28 170050.57 160255.07
    G Average Loan (C+F)/2 169617.04 171289.93 165152.82
    H Weighted Average Rate of Interest on Loan (in %) 3.0040 3.3755 4.1570
    I Interest on Loan (G*H) 2945.50 5781.89 6000.17

    After adjustment of grants (₹ in lakh)

    Particulars 2018-19 (prorata 46 days) 2018-19 (prorata 46 days)
    Asset-18 Asset-19
    Gross Normative Loan 427131.01 168740.85
    Cumulative Repayments upto Previous Year 145068.84 28388.83
    Net Loan-Opening (A-B) 282062.17 140352.02
    Addition due to ACE 914.58 78.96
    Repayment during the year 3959.13 1378.38
    Net Loan-Closing (C+D-E) 279017.61 139052.60
    Average Loan (C+F)/2 280539.89 139702.31
    Weighted Average Rate of Interest on Loan (in %) 3.8438 3.944
    Interest on Loan (G*H) 1359.00 694.36

    Return on Equity ("RoE")

    65. The Petitioner has claimed RoE in respect of the transmission assets in terms of Regulation 24 and Regulation 25 of the 2014 Tariff Regulations. The Petitioner has submitted that they are liable to pay income tax at MAT rates and has claimed the following effective tax rates for 2014-19 tariff period:

    Year Claimed effective tax rate (in %) Grossed up RoE [(Base Rate)/(1-t)] (in %)
    2014-15 21.018 19.624
    2015-16 21.382 19.716
    2016-17 21.338 19.705

    Page 75 of 162

    Year Claimed effective tax rate (in %) Grossed up RoE [(Base Rate)/(1-t)] (in %)
    2017-18 21.337 19.704
    2018-19 21.549 19.758

    66. The Commission in order dated 27.4.2020 in Petition No. 274/TT/2019 has arrived at the effective tax rate based on the notified MAT rates and the same is as follows:

    Year Notified MAT rates (inclusive of surcharge & cess) Effective tax (in %)
    2014-15 20.961 20.961
    2015-16 21.342 21.342
    2016-17 21.342 21.342
    2017-18 21.342 21.342
    2018-19 21.549 21.549

    67. The same MAT rates as allowed vide order dated 27.4.2020 in Petition No. 274/TT/2019, are considered for the purpose of grossing up of rate of RoE for truing-up of the tariff of 2014-19 period in terms of the provisions of the 2014 Tariff Regulations and the same is as follows:

    Year Notified MAT rates (inclusive of surcharge & cess) (in %) Base rate of RoE (in %) Grossed up RoE [(Base Rate)/(1-t)] (in %)
    2014-15 20.961 15.50 19.610
    2015-16 21.342 15.50 19.705
    2016-17 21.342 15.50 19.705
    2017-18 21.342 15.50 19.705
    2018-19 21.549 15.50 19.758

    68. The Petitioner has claimed RoE for 2014-19 tariff period after grossing up the RoE @15.50% with Effective Tax rates (based on MAT rates) each year as per the above said Regulation. Accordingly, RoE allowed in respect of the transmission assets is as follows:

    Page 76 of 162

    (₹ in lakh) Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Opening Equity 634.74 717.86 730.88 733.35 734.30 B Addition due to Additional Capitalization 83.12 13.02 2.47 0.95 0.00 C Closing Equity (A+B) 717.86 730.88 733.35 734.30 734.30 D Average Equity (A+C)/2 676.30 724.37 732.11 733.83 734.30 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 20.961 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.610 19.705 19.705 19.705 19.758

    H Return on Equity (Pre-tax) (D*G) 132.62 142.74 144.26 144.60 145.08 (₹ in lakh)

    Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Opening Equity 267.71 278.42 292.80 293.18 293.18 B Addition due to Additional Capitalization 10.71 14.38 0.38 0.00 0.00 C Closing Equity (A+B) 278.42 292.80 293.18 293.18 293.18 D Average Equity (A+C)/2 273.07 285.61 292.99 293.18 293.18 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 20.961 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.610 19.705 19.705 19.705 19.758

    H Return on Equity (Pre-tax) (D*G) 53.55 56.28 57.73 57.77 57.93 (₹ in lakh)

    Asset-3

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    A Opening Equity 168.08 181.17 220.85 220.88 220.88 B Addition due to Additional Capitalization 13.09 39.68 0.03 0.00 0.00 C Closing Equity (A+B) 181.17 220.85 220.88 220.88 220.88 D Average Equity (A+C)/2 174.63 201.01 220.87 220.88 220.88 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 20.961 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.610 19.705 19.705 19.705 19.758

    H Return on Equity (Pre-tax) (D*G) 34.24 39.61 43.52 43.52 43.64 (₹ in lakh)

    Asset-4

    2014-15

    Particulars (Pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    A Opening Equity 22377.53 23020.73 23469.34 23727.45 23790.72 B Addition due to Additional Capitalization 643.20 448.61 258.11 63.02 108.42 C Closing Equity (A+B) 23020.73 23469.34 23727.45 23790.47 23899.14 D Average Equity (A+C)/2 22699.13 23245.03 23598.39 23758.96 23844.93 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 20.961 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.610 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 1768.32 4580.67 4650.30 4681.94 4711.28

    Page 77 of 162

    (₹ in lakh) Asset-5

    2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Opening Equity 453.32 464.65 556.44 581.97 B Addition due to Additional Capitalization 11.33 91.79 25.53 16.47 C Closing Equity (A+B) 464.65 556.44 581.97 598.43 D Average Equity (A+C)/2 458.98 510.54 569.20 590.20 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 45.22 100.61 112.17 116.61 (₹ in lakh)

    Asset-6

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 181 days)

    A Opening Equity 289.71 299.42 373.68 394.33 B Addition due to Additional Capitalization 9.71 74.26 20.65 2.32 C Closing Equity (A+B) 299.42 373.68 394.33 396.65 D Average Equity (A+C)/2 294.57 336.55 384.00 395.49 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 28.71 66.32 75.67 78.14 (₹ in lakh)

    Asset-7

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 35 days)

    A Opening Equity 310.07 316.55 374.73 390.71 B Addition due to Additional Capitalization 6.48 58.18 15.98 1.14 C Closing Equity (A+B) 316.55 374.73 390.71 391.86 D Average Equity (A+C)/2 313.31 345.64 382.72 391.28 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 5.90 68.11 75.42 77.31 (₹ in lakh)

    Asset-8

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 113 days)

    A Opening Equity 1253.75 1328.27 1565.25 1628.95 B Addition due to Additional Capitalization 74.52 236.98 63.70 0.71 C Closing Equity (A+B) 1328.27 1565.25 1628.95 1629.66 D Average Equity (A+C)/2 1291.01 1446.76 1597.10 1629.30

    Page 78 of 162

    Asset-8 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 113 days)

    E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 78.55 285.10 314.72 321.92 (₹ in lakh)

    Asset-9

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 172 days)

    A Opening Equity 855.49 914.52 952.95 963.51 B Addition due to Additional Capitalization 59.03 38.44 10.55 137.78 C Closing Equity (A+B) 914.52 952.95 963.51 1101.28 D Average Equity (A+C)/2 885.00 933.73 958.23 1032.40 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 81.96 184.00 188.83 203.98 (₹ in lakh)

    Asset-10

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Opening Equity 2425.08 2633.24 2835.23 2994.42 B Addition due to Additional Capitalization 208.16 201.99 159.19 137.78 C Closing Equity (A+B) 2633.24 2835.23 2994.42 3132.20 D Average Equity (A+C)/2 2529.16 2734.24 2914.83 3063.31 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 249.20 538.81 574.40 605.25 (₹ in lakh)

    Asset-11

    2017-18

    Particulars (Pro-rata for 2018-19

    242 days)

    A Opening Equity 255.80 274.55 B Addition due to Additional Capitalization 18.75 23.28 C Closing Equity (A+B) 274.55 297.84

    D Average Equity (A+C)/2 265.18 286.20 E Return on Equity (Base Rate) (in %) 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 34.79 56.55

    Page 79 of 162

    (₹ in lakh) Asset-12 2017-18 Particulars (Pro-rata for 2018-19 254 days)

    A Opening Equity 471.89 495.63 B Addition due to Additional Capitalization 23.74 57.74 C Closing Equity (A+B) 495.63 553.37

    D Average Equity (A+C)/2 483.76 524.50 E Return on Equity (Base Rate) (in %) 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 66.34 103.63 (₹ in lakh)

    Asset-13

    2017-18

    Particulars (Pro-rata for 2018-19 111 days)

    A Opening Equity 468.67 498.49 B Addition due to Additional Capitalization 29.82 51.62 C Closing Equity (A+B) 498.49 550.11

    D Average Equity (A+C)/2 483.58 524.30 E Return on Equity (Base Rate) (in %) 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 28.98 103.59 (₹ in lakh)

    Asset-14

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 156 days)

    A Opening Equity 446.75 505.87 530.08 545.14 B Addition due to Additional Capitalization 59.12 24.21 15.06 7.79 C Closing Equity (A+B) 505.87 530.08 545.14 552.92 D Average Equity (A+C)/2 476.31 517.98 537.61 549.03 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 40.01 102.07 105.94 108.48 (₹ in lakh)

    Asset-15

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 153 days)

    A Opening Equity 1388.31 1573.93 1627.77 1696.70 B Addition due to Additional Capitalization 185.62 53.84 68.93 102.19 C Closing Equity (A+B) 1573.93 1627.77 1696.70 1798.89 D Average Equity (A+C)/2 1481.12 1600.85 1662.24 1747.80

    Page 80 of 162

    Asset-15 2015-16 Particulars (Pro-rata for 2016-17 2017-18 2018-19 153 days)

    E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 125.20 315.46 327.56 345.33 (₹ in lakh)

    Asset-16

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 183 days)

    A Opening Equity 505.78 564.55 606.56 638.57 B Addition due to Additional Capitalization 58.77 42.01 32.01 19.64 C Closing Equity (A+B) 564.55 606.56 638.57 658.21 D Average Equity (A+C)/2 535.16 585.56 622.57 648.39 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 52.73 115.39 122.68 128.11 (₹ in lakh)

    Asset-17

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 104 days)

    A Opening Equity 513.51 561.37 585.38 600.40 B Addition due to Additional Capitalization 47.86 24.01 15.02 49.44 C Closing Equity (A+B) 561.37 585.38 600.40 649.84 D Average Equity (A+C)/2 537.44 573.38 592.89 625.12 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 30.09 112.99 116.84 123.51 (₹ in lakh)

    Asset-18

    2015-16

    Particulars (Pro-rata for 2016-17 2017-18 2018-19 152 days)

    A Opening Equity 160022.46 163830.16 169299.95 172376.18 B Addition due to Additional Capitalization 3807.69 5469.80 3076.23 2718.17 C Closing Equity (A+B) 163830.16 169299.95 172376.18 175094.35 D Average Equity (A+C)/2 161926.31 166565.05 170838.07 173735.27 E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 F Tax Rate applicable (in %) 21.342 21.342 21.342 21.549 G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.706 19.758

    H Return on Equity (Pre-tax) (D*G) 13251.91 32823.31 33665.35 30000.52

    Page 81 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2016-17 (Pro-rata for 211 days) 2017-18 2018-19
    A Opening Equity 41676.20 44717.39 47018.30
    B Addition due to Additional Capitalization 3041.19 2300.91 155.70
    C Closing Equity (A+B) 44717.39 47018.30 47174.00
    D Average Equity (A+C)/2 43196.80 45867.85 47096.15
    E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50
    F Tax Rate applicable (in %) 21.342 21.342 21.549
    G Rate of Return on Equity (Pre-tax) (in %) 19.706 19.706 19.758
    H Return on Equity (Pre-tax) (D*G) 4920.84 9038.72 8132.54

    After adjustment of grants (₹ in lakh)

    Particulars 2018-19 (Prorata 46 days) 2018-19 (Prorata 46 days)
    Asset-18 Asset-19
    Opening Equity 175094.35 47174.00
    Addition due to Additional Capitalization 391.96 33.84
    Closing Equity (A+B) 175486.31 47207.84
    Average Equity (A+C)/2 175290.33 47190.92
    Return on Equity (Base Rate) (in %) 15.50 15.50
    Tax Rate applicable (in %) 21.549 21.549
    Rate of Return on Equity (Pre-tax) (in %) 19.758 19.758
    Return on Equity (Pre-tax) (D*G) 4364.82 1175.08

    Operation & Maintenance Expenses ("O&M Expenses")

    69. Regulation 29(4)(a) of the 2014 Tariff Regulations specifies norms for O&M Expenses for the transmission system based on type of sub-station and transmission line and the same is as follows:

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    Norms as per Regulation
    Single Circuit (Single Conductor) (₹ lakh/km) 0.202 0.209 0.216 0.223 0.230
    Single Circuit (Twin & Triple Conductor) (₹ lakh/km) 0.404 0.418 0.432 0.446 0.461
    Single Circuit (Bundled Conductor with six or more sub-conductors) (₹ lakh/km) 0.707 0.731 0.755 0.780 0.806
    Double Circuit (Single Conductor) (km) 0.303 0.313 0.324 0.334 0.346
    Double Circuit (Twin & Triple Conductor) (₹ lakh/km) 0.707 0.731 0.755 0.780 0.806
    Double Circuit (Bundled Conductor with 1.062 1.097 1.133 1.171 1.210

    Page 82 of 162

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    four or more sub-conductors) (₹ lakh/km)
    Multi Circuit (Twin & Triple Conductor) (₹ lakh/km) 1.240 1.282 1.324 1.368 1.413
    400 kV GIS Bays (₹ lakh/bay) 51.54 53.25 55.02 56.84 58.73
    400 kV Bays (₹ lakh/bay) 60.30 62.30 64.37 66.51 68.71
    220 kV Bays (₹ lakh/bay) 42.21 43.61 45.06 46.55 48.10
    132 kV & below Bays (₹ lakh/bay) 30.15 31.15 32.18 33.25 34.36
    2000 MW, Talcher- Kolar HVDC bi-pole scheme (Rs. Lakh) 1173 1271 1378 1493 1617

    70. The Petitioner has computed normative O&M Expenses as per Regulation 29(4)(a) of the 2014 Tariff Regulations. O&M Expenses have been worked out as per transmission line and sub-station details verified from the previous orders of 2014-19 tariff period and the norms specified in the 2014 Tariff Regulations. Accordingly, the O&M Expenses allowed in respect of the transmission assets are as follows:

    Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    400 kV Bays (Number) 1 1 1 1 1
    220 kV Bays (Number ) 1 1 1 1 1
    Total O&M Expenses (₹ in lakh) 102.51 105.91 109.43 113.06 116.81
    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    400 kV Bays (Number) 1 1 1 1 1
    Total O&M Expenses (₹ in lakh) 60.30 62.30 64.37 66.51 68.71
    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    400 kV Bays (Number) 1 1 1 1 1
    Total O&M Expenses (₹ in lakh) 60.30 62.30 64.37 66.51 68.71
    Particulars 2014-15* 2015-16 2016-17 2017-18 2018-19
    Double Circuit (Bundled Conductor with four or more sub-conductors) (km) 309.00 309.00 309.00 309.00 309.00

    Page 83 of 162

    Particulars 2014-15* 2015-16 2016-17 2017-18 2018-19
    400 kV Bays (Number) 6 6 6 6 6
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 130.36 338.97 350.10 361.84 373.89
    Sub-total O&M Expenses for Sub- station (B) (₹ in lakh) 143.73 373.80 386.22 399.06 412.26
    Total O&M Expenses (A+B) (₹ in lakh) 274.09 712.77 736.32 760.90 786.15

    *Pro-rata has been considered from 7.11.2014 to 31.3.2015=145 days

    Asset-5

    Particulars 2014-15 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Number) - 1 1 1 1
    132 kV & below Bays (Number) - 1 1 1 1
    Total O&M Expenses (₹ in lakh) - 46.73 96.55 99.76 103.07

    *Pro-rata has been considered from 1.10.2015 to 31.3.2016= 183 days

    Asset-6

    Particulars 2014-15 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Number) - 1 1 1 1
    Total O&M Expenses (₹ in lakh) - 30.81 64.37 66.51 68.71

    *Pro-rata has been considered from 3.10.2015 to 31.3.2016=181 days

    Asset-7

    Particulars 2014-15 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Number) - 1 1 1 1
    Total O&M Expenses (₹ in lakh) - 5.96 64.37 66.51 68.71

    *Pro-rata has been considered from 26.2.2016 to 31.3.2016=35 days

    Asset-8

    Particulars 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Number) 1 1 1 1
    220 kV Bays (Number) 3 3 3 3
    Total O&M Expenses (₹ in lakh) 59.63 199.55 206.16 213.01

    *Pro-rata has been considered from 10.12.2015 to 31.3.2016=113 days

    Asset-9

    Particulars 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Number) 2 2 2 2
    Total O&M Expenses (₹ in lakh) 58.56 128.74 133.02 137.42

    *Pro-rata has been considered from 12.10.2015 to 31.3.2016=172 days

    Page 84 of 162

    Asset-10

    Particulars 2015-16* 2016-17 2017-18 2018-19
    Multi Circuit (four or more sub-Conductor) (km) 0.86 0.86 0.86 0.86
    Double Circuit (Twin & Triple Conductor) (km) 56.44 56.44 56.44 56.44
    400 kV Bays (Number) 2 2 2 2
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 21.46 44.32 45.79 47.32
    Sub-total O&M Expenses for Sub-station (B) (₹ in lakh) 62.30 128.74 133.02 137.42
    Total O&M Expenses (A+B) (₹ in lakh) 83.76 173.06 178.81 184.74

    *Pro-rata has been considered from 110.2015 to 31.3.2016=183 days

    Asset-12

    Particulars 2015-16 2016-17 2017-18* 2018-19
    400 kV Bays (Number) - - 1 1
    Total O&M Expenses (₹ in lakh) - - 46.28 68.71

    *Pro-rata has been considered from 21.7.2017 to 31.3.2018=254 days

    Asset-13

    Particulars 2017-18* 2018-19
    400 kV Bays (Number) 1 1
    Total O&M Expenses (₹ in lakh) 20.23 68.71

    *Pro-rata has been considered from 11.12.2017 to 31.3.2018=111 days

    Asset-14

    Particulars 2015-16* 2016-17 2017-18 2018-19
    Double Circuit (Twin & Triple Conductor) (km) 24.772 24.772 24.772 24.772
    400 kV Bays (Numbers) 4 4 4 4
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 7.72 18.70 19.32 19.97
    Sub-total O&M Expenses for Sub- station (B) (₹ in lakh) 106.22 257.48 266.04 274.84
    Total O&M Expenses (A+B) (₹ in lakh) 113.93 276.18 285.36 294.81

    *Pro-rata has been considered from 28.10.2015 to 31.3.2016=156 day

    Asset-15

    Particulars 2015-16* 2016-17 2017-18 2018-19
    Multi Circuit (Twin & Triple Conductor) (km) 1.158 1.158 1.158 1.158
    Double Circuit (Twin & Triple Conductor) (km) 24.772 24.772 24.772 24.772
    400 kV Bays (Number) 2 2 2 2
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 8.40 20.24 20.91 21.60
    Sub-total O&M Expenses for Sub- 53.45 128.74 133.02 137.42

    Page 85 of 162

    Particulars 2015-16* 2016-17 2017-18 2018-19
    station (B) (₹ in lakh)
    Total O&M Expenses (A+B) (₹ in lakh) 61.85 148.98 153.93 159.02

    *Pro-rata has been considered from 27.10.2015 to 31.3.2016=157 day

    Asset-16

    Particulars 2015-16* 2016-17 2017-18 2018-19
    Double Circuit (single Conductor) (km) 12.931 12.931 12.931 12.931
    132 kV & below Bays (Number) 4 4 4 4
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 2.02 4.19 4.32 4.47
    Sub-total O&M Expenses for Sub- station (B) (₹ in lakh) 62.30 128.72 133.00 137.44
    Total O&M Expenses (A+B) (₹ in lakh) 64.32 132.91 137.32 141.91

    *Pro-rata has been considered from 1.10.2015 to 31.3.2016=183 days

    Asset-17

    Particulars 2015-16* 2016-17 2017-18 2018-19
    400 kV Bays (Numbers) 1 1 1 1
    132 kV & below Bays (Number) 1 1 1 1
    Total O&M Expenses (₹ in lakh) 26.55 96.55 99.76 103.07

    Sub-total O&M Expenses for Sub-station

    (B) (₹ in lakh) 395.89 1033.50 1119.75 1212.75 Total O&M Expenses (A+B) (₹ in lakh) 928.24 2357.44 2487.53 2626.12

    2295.16

    *Pro-rata has been considered from 1.11.2015 to 31.3.2016=152 days

    ** Pro-rata has been considered from 1.4.2018 to 13.2.2019=319 days

    Asset-19 Particulars 2016-17* 2017-18 **2018-19

    Single Circuit (Single Conductor) (km) 113.454 113.454 113.454 One Pole of 1500 MW of Bi-Pole HVDC station 1 1 1

    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 14.17 25.30 26.09

    Sub-total O&M Expenses for Sub-station (B) (₹ in lakh) 597.45 1119.75 1212.75 Total O&M Expenses (A+B) (₹ in lakh) 611.61 1145.05 1238.84

    1082.71

    *Pro-rata has been considered from 2.9.2016 to 31.3.2017=211 days

    ** Pro-rata has been considered from 1.4.2018 to 13.2.2019=319 days

    Page 86 of 162

    After adjusting grants Asset-18

    Particulars 2018-19
    HVDC Hexa lapwing line (km) 1753.56
    One Pole of 1500 MW of Bi-Pole HVDC station 1
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 1413.37
    Sub-total O&M Expenses for Sub-station (B) (₹ in lakh) 1212.75
    Total O&M Expenses (A+B) (₹ in lakh) 2626.12
    Pro-rata 330.96

    *Pro-rata has been considered from 14.2.2019 to 31.3.2019=46 days

    Asset-19

    Particulars 2018-19
    Single Circuit (Single Conductor) (km) 113.454
    One Pole of 1500 MW of Bi-Pole HVDC station 1
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 26.09
    Sub-total O&M Expenses for Sub-station (B) (₹ in lakh) 1212.75
    Total O&M Expenses (A+B) (₹ in lakh) 1238.84
    Pro-rata 156.13

    *Pro-rata has been considered from 14.2.2019 to 31.3.2019=46 days

    Interest on Working Capital ('IWC')

    71. The Petitioner has claim claimed IWC as per Regulation 28(1)(c) of the 2014 Tariff Regulations. The trued-up IWC allowed in respect of the transmission assets are as follows:

    (₹ in lakh)

    Asset-1
    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    A Working Capital for O&M Expenses (O&M Expenses for one month) 8.54 8.83 9.12 9.42 9.73
    B Working Capital for Maintenance Spares (15% of O&M Expenses) 15.38 15.89 16.41 16.96 17.52
    C Working Capital for Receivables (equivalent to two months of Annual Fixed Charges/Annual Transmission Charges) 81.10 84.63 84.06 82.87 81.61
    D Total Working Capital (A+B+C) 105.02 109.34 109.60 109.25 108.87
    E Rate of Interest (in %) 13.50 13.50 13.50 13.50 13.50
    F Interest of Working Capital (D*E) 14.18 14.76 14.80 14.75 14.70

    Page 87 of 162

    (₹ in lakh) Asset-2

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Working Capital for O&M 5.03 5.19 5.36 5.54 5.73 A Expenses

    (O&M Expenses for one month)

    Working Capital for Maintenance 9.05 9.35 9.66 9.98 10.31 B Spares

    (15% of O&M Expenses)

    Working Capital for Receivables 36.35 37.23 37.54 37.14 36.77 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 50.42 51.77 52.56 52.66 52.81 E Rate of Interest (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of Working Capital 6.81 6.99 7.10 7.11 7.13

    F

    (D*E) (₹ in lakh) Asset-3

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Working Capital for O&M 5.03 5.19 5.36 5.54 5.73 A Expenses

    (O&M Expenses for one month)

    Working Capital for Maintenance 9.05 9.35 9.66 9.98 10.31 B Spares

    (15% of O&M Expenses)

    Working Capital for Receivables 27.32 29.83 31.54 30.70 30.93 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 41.39 44.37 46.56 46.22 46.96 E Rate of Interest (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of Working Capital 5.59 5.99 6.29 6.24 6.34

    F

    (D*E) (₹ in lakh) Asset-4

    2014-15 Particulars (pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    Working Capital for O&M 57.50 59.40 61.36 63.41 65.51 A Expenses (O&M Expenses for

    one month)

    Working Capital for 103.49 106.92 110.45 114.14 117.92 B Maintenance Spares (15% of

    O&M Expenses)

    Working Capital for Receivables 3356.93 3341.57 3262.12 3148.55 3057.08 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    Page 88 of 162

    Asset-4 2014-15 Particulars (pro-rata for 2015-16 2016-17 2017-18 2018-19 145 days)

    Total Working Capital 3517.92 3507.89 3433.93 3326.09 3240.52

    D

    (A+B+C)

    E Rate of Interest (in %) 13.50 13.50 13.50 13.50 13.50

    Interest of Working Capital 188.67 473.56 463.58 449.02 437.47

    F

    (D*E) (₹ in lakh) Asset-5

    2015-16 Particulars (pro-rata for 2016-17 2017-18 2018-19 183 days)

    Working Capital for O&M 7.79 8.05 8.31 8.59 A Expenses (O&M Expenses for

    one month)

    Working Capital for Maintenance 14.02 14.48 14.96 15.46

    B

    Spares (15% of O&M Expenses) Working Capital for Receivables 78.71 82.56 86.22 86.74 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 100.52 105.09 109.50 110.79 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    Interest of Working Capital

    F

    (D*E) 6.79 14.19 14.78 14.96 (₹ in lakh)

    Asset-6

    2015-16

    Particulars (pro-rata for 2016-17 2017-18 2018-19 181 days)

    Working Capital for O&M 5.19 5.36 5.54 5.73 A Expenses

    (O&M Expenses for one month)

    Working Capital for 9.35 9.66 9.98 10.31 B Maintenance Spares

    (15% of O&M Expenses)

    Working Capital for Receivables 50.88 54.19 57.33 57.41 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    Total Working Capital 65.41 69.21 72.85 73.44

    D

    (A+B+C)

    E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    Interest of Working Capital

    F 4.37 9.34 9.83 9.91

    (D*E)

    Page 89 of 162

    (₹ in lakh) Asset-7

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata for

    35 days)

    A Working Capital for O&M Expenses 5.19 5.36 5.54 5.73 (O&M Expenses for one month)

    B Working Capital for Maintenance 9.35 9.66 9.98 10.31 Spares

    (15% of O&M Expenses)

    C Working Capital for Receivables 53.56 56.36 58.79 58.66 (equivalent to two months of Annual

    Fixed Charges/Annual Transmission

    Charges)

    D Total Working Capital (A+B+C) 68.10 71.38 74.31 74.69 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital (D*E) 0.88 9.64 10.03 10.08 (₹ in lakh)

    Asset-8

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata for

    113 days)

    A Working Capital for O&M Expenses 16.09 16.63 17.18 17.75 (O&M Expenses for one month)

    B Working Capital for Maintenance Spares 28.97 29.93 30.92 31.95 (15% of O&M Expenses)

    C Working Capital for Receivables 212.12 224.79 233.56 231.78 (equivalent to two months of Annual

    Fixed Charges/Annual Transmission

    Charges)

    D Total Working Capital (A+B+C) 257.19 271.35 281.67 281.48 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital (D*E) 10.72 36.63 38.03 38.00 (₹ in lakh)

    Asset-9

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata for

    172 days)

    A Working Capital for O&M 10.38 10.73 11.09 11.45 Expenses (O&M Expenses for

    one month)

    B Working Capital for 18.69 19.31 19.95 20.61 Maintenance Spares

    (15% of O&M Expenses)

    C Working Capital for Receivables 142.39 144.86 142.84 146.62 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital 171.46 174.90 173.88 178.69

    (A+B+C)

    Page 90 of 162

    E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital 10.88 23.61 23.47 24.12 (D*E)

    (₹ in lakh)

    Asset-10

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata for

    183 days)

    A Working Capital for O&M 13.96 14.42 14.90 15.40 Expenses (O&M Expenses for

    one month)

    B Working Capital for Maintenance 25.13 25.96 26.82 27.71 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 376.35 388.46 391.49 394.58 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C) 415.44 428.84 433.21 437.69 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital 28.04 57.89 58.48 59.09 (D*E)

    (₹ in lakh)

    Asset-11

    Particulars 2017-18 2018-19

    (pro-rata for

    242 days)

    A Working Capital for O&M 0.00 0.00 Expenses (O&M Expenses for one month)

    B Working Capital for Maintenance 0.00 0.00 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 34.35 35.67 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C) 34.35 35.67 E Rate of Interest (in %) 12.60 12.60

    F Interest of Working Capital 2.88 4.49 (D*E)

    (₹ in lakh)

    Asset-12

    2017-18

    Particulars (pro-rata for 2018-19 254 days)

    Working Capital for O&M 5.54 5.73 A Expenses (O&M Expenses for one month)

    Page 91 of 162

    Asset-12 2017-18 Particulars (pro-rata for 2018-19 254 days)

    Working Capital for Maintenance 9.98 10.31

    B

    Spares (15% of O&M Expenses) Working Capital for Receivables 74.10 77.05 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 89.62 93.08 E Rate of Interest (in %) 12.60 12.60

    Interest of Working Capital 7.86 11.73

    F

    (D*E) (₹ in lakh) Asset-13 Particulars 2017-18 2018-19 (pro-rata for

    111 days)

    A Working Capital for O&M 5.54 5.73 Expenses (O&M Expenses for one month)

    B Working Capital for Maintenance 9.98 10.31 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 74.11 77.50 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C)

    89.63 93.53

    E Rate of Interest (in %) 12.60 12.60

    F Interest of Working Capital (D*E) 3.43 11.78

    (₹ in lakh)

    Asset-14

    2015-16

    (pro-rata

    Particulars 2016-17 2017-18 2018-19 for 156

    days)

    Working Capital for O&M 22.27 23.02 23.78 24.57 A Expenses (O&M Expenses for

    one month)

    Working Capital for Maintenance 40.09 41.43 42.80 44.22

    B

    Spares (15% of O&M Expenses) Working Capital for Receivables 112.92 118.65 120.68 121.56 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 175.29 183.09 187.26 190.35 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    Page 92 of 162

    Asset-14 2015-16 (pro-rata Particulars 2016-17 2017-18 2018-19 for 156

    days)

    Interest of Working Capital

    F

    (D*E) 10.09 24.72 25.28 25.70 (₹ in lakh)

    Asset-15

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata

    for 157

    days)

    A Working Capital for O&M 12.02 12.42 12.83 13.25 Expenses (O&M Expenses for

    one month)

    B Working Capital for Maintenance 21.63 22.35 23.09 23.85 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 231.22 242.55 240.71 243.57 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C) 264.86 277.31 276.63 280.67 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital 15.34 37.44 37.35 37.89 (D*E)

    (₹ in lakh)

    Asset-16

    2015-16

    (pro-rata

    Particulars 2016-17 2017-18 2018-19

    for 183

    days)

    Working Capital for O&M 10.72 11.08 11.44 11.83 A Expenses (O&M Expenses for

    one month)

    Working Capital for Maintenance 19.30 19.94 20.60 21.29

    B

    Spares (15% of O&M Expenses) Working Capital for Receivables 96.61 101.95 103.46 104.47 (equivalent to two months of

    C

    Annual Fixed Charges/Annual Transmission Charges)

    D Total Working Capital (A+B+C) 126.62 132.96 135.50 137.58 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    Interest of Working Capital 8.55 17.95 18.29 18.57

    F

    (D*E)

    Page 93 of 162

    (₹ in lakh) Asset-17 Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata

    for 104

    days)

    A Working Capital for O&M 7.79 8.05 8.31 8.59 Expenses (O&M Expenses for

    one month)

    B Working Capital for Maintenance 14.02 14.48 14.96 15.46 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 89.86 93.70 94.27 95.82 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C) 111.66 116.23 117.55 119.87 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital 4.28 15.69 15.87 16.18 (D*E)

    (₹ in lakh)

    Asset-18

    Particulars 2015-16 2016-17 2017-18 2018-19 (pro-rata

    for 152

    days)

    A Working Capital for O&M 186.26 196.45 207.29 218.84 Expenses (O&M Expenses for

    one month)

    B Working Capital for Maintenance 335.27 353.62 373.13 393.92 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 18623.43 19152.86 19337.94 19666.06 (equivalent to two months of

    Annual Fixed Charges/Annual

    Transmission Charges)

    D Total Working Capital (A+B+C) 19144.96 19702.93 19918.37 20278.82 E Rate of Interest (in %) 13.50 13.50 13.50 13.50

    F Interest of Working Capital 1073.37 2659.90 2688.98 2392.62 (D*E)

    (₹ in lakh)

    Asset-19

    Particulars 2016-17 2017-18 2018-19

    (pro-rata for

    211 days)

    A Working Capital for O&M 88.17 95.42 103.24 Expenses (O&M Expenses for

    one month)

    B Working Capital for Maintenance 158.70 171.76 185.83 Spares (15% of O&M Expenses)

    C Working Capital for Receivables 4370.75 4704.76 5001.95 (equivalent to two months of

    Page 94 of 162

    Annual Fixed Charges/Annual Transmission Charges)
    D Total Working Capital (A+B+C) 4617.62 4971.93 5291.01
    E Rate of Interest (in %) 12.80 12.80 12.80
    F Interest of Working Capital (D*E) 341.68 636.41 591.90

    After adjusting grants (₹ in lakh)

    Particulars 2018-19 (pro-rata for 46 days) 2018-19 (pro-rata for 46 days)
    Asset-18 Asset-19
    A Working Capital for O&M Expenses (O&M Expenses for one month) 218.84 103.24
    B Working Capital for Maintenance Spares (15% of O&M Expenses) 393.92 185.83
    C Working Capital for Receivables (equivalent to two months of Annual Fixed Charges/Annual Transmission Charges) 13530.62 4601.03
    D Total Working Capital (A+B+C) 14143.38 4890.09
    E Rate of Interest (in %) 12.20 12.20
    F Interest of Working Capital (D*E) 217.46 75.19

    Approved Annual Fixed Charges for 2014-19 Tariff Period

    72. The trued-up Annual Fixed Charges (AFC) allowed in respect of the transmission assets for 2014-19 tariff period are as follows:

    (₹ in lakh) Asset-1

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 117.22 125.37 126.71 127.01 127.10 Interest on Loan 120.05 118.99 109.18 97.81 86.00 Return on Equity 132.62 142.74 144.26 144.60 145.08 O&M Expenses 102.51 105.91 109.43 113.06 116.81 Interest on Working Capital 14.18 14.76 14.80 14.75 14.70

    Total 486.58 507.77 504.38 497.23 489.69 (₹ in lakh)

    Asset-2

    Particulars

    2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 48.06 50.27 51.57 51.60 51.60 Interest on Loan 49.37 47.56 44.47 39.87 35.28 Return on Equity 53.55 56.28 57.73 57.77 57.93 O&M Expenses 60.30 62.30 64.37 66.51 68.71

    Page 95 of 162

    Asset-2 Particulars 2014-15 2015-16 2016-17 2017-18 2018-19

    Interest on Working Capital 6.81 6.99 7.10 7.11 7.13

    Total 218.09 223.40 225.24 222.86 220.65 (₹ in lakh)

    Asset-3

    Particulars

    2014-15 2015-16 2016-17 2017-18 2018-19

    Depreciation 30.73 35.38 38.87 38.87 38.87 Interest on Loan 33.07 35.70 36.18 29.03 28.01 Return on Equity 34.24 39.61 43.52 43.52 43.64 O&M Expenses 60.30 62.30 64.37 66.51 68.71 Interest on Working Capital 5.59 5.99 6.29 6.24 6.34

    Total 163.93 178.98 189.23 184.17 185.57 (₹ in lakh)

    Asset-4

    2014-15 2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    145 days)

    Depreciation 2380.72 6117.25 6178.09 6205.00 6220.09 Interest on Loan 3389.65 8165.19 7544.44 6794.40 6187.50 Return on Equity 1768.32 4580.67 4650.30 4681.96 4711.28 O&M Expenses 274.09 712.77 736.32 760.90 786.15 Interest on Working Capital 188.67 473.56 463.58 449.02 437.47

    Total 8001.45 20049.44 19572.73 18891.28 18342.49 (₹ in lakh)

    Asset-5

    2015-16 2016-17 2017-18 2018-19

    Particulars

    (pro-rata for

    183 days)

    Depreciation 54.16 116.15 125.06 128.26 Interest on Loan 83.24 167.90 165.54 157.57 Return on Equity 45.22 100.61 112.17 116.61 O&M Expenses 46.73 96.55 99.76 103.07 Interest on Working Capital 6.79 14.19 14.78 14.96

    Total 236.14 495.40 517.31 520.47 (₹ in lakh)

    Asset-6

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    181 days)

    Depreciation 34.17 75.75 83.25 85.07 Interest on Loan 52.90 109.38 108.70 102.60 Return on Equity 28.71 66.32 75.67 78.14 O&M Expenses 30.81 64.37 66.51 68.71 Interest on Working Capital 4.37 9.34 9.83 9.91

    Total 150.96 325.16 343.96 344.43

    Page 96 of 162

    (₹ in lakh) Asset-7

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    35 days)

    Depreciation 7.03 79.05 85.03 86.41 Interest on Loan 10.95 116.99 115.76 109.45 Return on Equity 5.90 68.11 75.42 77.31 O&M Expenses 5.96 64.37 66.51 68.71 Interest on Working Capital 0.88 9.64 10.03 10.08

    Total 30.72 338.16 352.75 351.96 (₹ in lakh)

    Asset-8

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    113 days)

    Depreciation 99.89 350.49 375.73 381.09 Interest on Loan 144.16 476.98 466.74 436.67 Return on Equity 78.55 285.10 314.72 321.92 O&M Expenses 59.63 199.55 206.16 213.01 Interest on Working Capital 10.72 36.63 38.03 38.00

    Total 392.95 1348.75 1401.38 1390.69 (₹ in lakh)

    Asset-9

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    172 days)

    Depreciation 102.70 226.74 230.63 241.99 Interest on Loan 147.39 306.07 281.09 272.23 Return on Equity 81.96 184.00 188.83 203.98 O&M Expenses 58.56 128.74 133.02 137.42 Interest on Working Capital 10.88 23.61 23.47 24.12

    Total 401.49 869.16 857.04 879.74 (₹ in lakh)

    Particulars Asset-10

    2015-16 2016-17 2017-18 2018-19 (pro-rata for

    183 days)

    Depreciation 323.39 682.97 714.23 738.67 Interest on Loan 444.66 878.05 823.02 779.74 Return on Equity 249.20 538.81 574.40 605.25 O&M Expenses 83.76 173.06 178.81 184.74 Interest on Working Capital 28.04 57.89 58.48 59.09

    Total 1129.05 2330.78 2348.94 2367.49

    Page 97 of 162

    (₹ in lakh) Asset-11 2017-18 2018-19 Particulars (pro-rata for 242 days)

    Depreciation 46.20 73.34 Interest on Loan 53.35 79.62 Return on Equity 34.79 56.55 O&M Expenses 0.00 0.00 Interest on Working Capital 2.88 4.49

    Total 137.22 214.00 (₹ in lakh)

    Asset-12

    2017-18 2018-19 Particulars (pro-rata for 254 days)

    Depreciation 81.67 124.59 Interest on Loan 107.27 153.63 Return on Equity 66.34 103.64 O&M Expenses 46.28 68.71 Interest on Working Capital 7.86 11.73

    Total 309.42 462.30 (₹ in lakh)

    Asset-13

    2017-18 2018-19 Particulars (pro-rata for 111 days)

    Depreciation 35.72 124.95 Interest on Loan 46.87 155.95 Return on Equity 28.98 103.59 O&M Expenses 20.23 68.71 Interest on Working Capital 3.43 11.78

    Total 135.23 464.98 (₹ in lakh)

    Asset-14

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    156 days)

    Depreciation 49.46 126.78 131.83 134.43 Interest on Loan 75.29 182.12 175.64 165.94 Return on Equity 40.01 102.08 105.95 108.49 O&M Expenses 113.93 276.18 285.36 294.81 Interest on Working Capital 10.09 24.72 25.28 25.70

    Total 288.78 711.88 724.06 729.37

    Page 98 of 162

    (₹ in lakh) Asset-15 2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    157 days)

    Depreciation 163.55 412.66 428.73 446.75 Interest on Loan 229.17 540.77 496.72 472.40 Return on Equity 125.20 315.46 327.56 345.33 O&M Expenses 61.85 148.98 153.93 159.02 Interest on Working Capital 15.34 37.44 37.35 37.89

    Total 595.11 1455.31 1444.29 1461.39 (₹ in lakh)

    Asset-16

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    183 days)

    Depreciation 65.54 144.14 153.69 159.55 Interest on Loan 98.68 201.31 188.78 178.67 Return on Equity 52.73 115.39 122.68 128.11 O&M Expenses 64.32 132.91 137.32 141.91 Interest on Working Capital 8.55 17.95 18.29 18.57

    Total 289.82 611.70 620.76 626.81 (₹ in lakh)

    Asset-17

    2015-16 2016-17 2017-18 2018-19 Particulars (pro-rata

    for 104

    days)

    37.57 141.07 145.88 151.79

    Depreciation

    Interest on Loan 54.71 195.92 187.29 180.35 Return on Equity 30.09 112.99 116.84 123.51 O&M Expenses 26.55 96.55 99.76 103.07 Interest on Working Capital 4.28 15.69 15.87 16.18

    Total 153.20 562.22 565.64 574.90 (₹ in lakh)

    Asset-18

    2015-16 2016-17 2017-18 2018-19 Particulars

    (pro-rata for

    152 days)

    Depreciation 17567.29 43478.88 44548.04 39474.62 Interest on Loan 13585.12 33597.61 32637.76 28962.66 Return on Equity 13251.91 32823.31 33665.35 30000.52 O&M Expenses 928.24 2357.44 2487.53 2295.16 Interest on Working Capital 1073.37 2659.90 2688.98 2392.62

    Total 46405.93 114917.14 116027.67 103125.58

    Page 99 of 162

    (₹ in lakh)

    Particulars Asset-19
    2016-17 (pro-rata for 211 days) 2017-18 2018-19
    Depreciation 6340.30 11626.47 10422.06
    Interest on Loan 2945.50 5781.89 6000.17
    Return on Equity 4920.84 9038.72 8132.54
    O&M Expenses 611.61 1145.05 1082.71
    Interest on Working Capital 341.68 636.41 591.90
    Total 15159.93 28228.54 26229.38

    After adjusting grants (₹ in lakh)

    2018-19 2018-19

    Particulars
    2018-19 (pro-rata for 46 days) 2018-19 (pro-rata for 46 days)
    Asset-18 Asset-19
    Depreciation 3959.13 1378.38
    Interest on Loan 1359.00 694.36
    Return on Equity 4364.82 1175.08
    O&M Expenses 330.96 156.13
    Interest on Working Capital 217.46 75.19
    Total 10231.37 3479.14

    Determination of Annual Fixed Charges for 2019-24 Tariff Period

    73. The Petitioner has combined tariff forms for AC assets i.e. Asset-1 to Asset- 17 and has claimed their combined tariff for 2019-24 period as a Combined Asset while separate tariff has been claimed for HVDC assets i.e. Asset-18 and Asset- 19 for 2019-24 tariff period.

    74. The Petitioner has claimed the following transmission charges in respect of the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period:

    (₹ in lakh)

    Combined Asset (Asset-1 to Asset-17)
    Particulars 2019-20 2020-21 201-22 2022-23 2023-24
    Depreciation 9445.60 9499.85 9514.32 9514.32 9514.32
    Interest on Loan 8947.64 8186.20 7371.81 6539.83 5706.04
    Return on Equity 7094.32 7168.74 7184.18 7184.18 7184.18
    Interest on Working Capital 466.29 461.01 452.19 442.77 432.34
    1909.23 1976.09 2044.96 2116.79 2189.41

    Page 100 of 162

    Combined Asset (Asset-1 to Asset-17) Particulars 2019-20 2020-21 201-22 2022-23 2023-24 Total 27863.08 27291.89 26567.46 25797.89 25026.29 (₹ in lakh)

    Asset-18

    Particulars 2019-20 2020-21 201-22 2022-23 2023-24

    Depreciation 31706.00 31807.93 31865.60 31866.29 31866.29 Interest on Loan 9820.23 8888.12 7827.30 6685.51 5524.56 Return on Equity 33130.12 33349.88 33411.43 33412.16 33412.16 Interest on Working Capital 1278.15 1279.13 1270.63 1259.35 1244.79 O&M Expenses 3599.71 3725.37 3856.04 3991.72 4131.15

    Total 79534.21 79050.43 78231.00 77215.03 76178.95 (₹ in lakh)

    Asset-19

    Particulars 2019-20 2020-21 201-22 2022-23 2023-24

    Depreciation 11094.43 11216.42 11219.72 11219.72 11219.72 Interest on Loan 5256.22 5086.14 4749.80 4297.52 3845.59 Return on Equity 9028.73 9171.09 9174.61 9174.61 9174.61 Interest on Working Capital 438.75 443.30 440.41 435.72 430.06 O&M Expenses 1310.09 1356.00 1403.63 1452.65 1503.79

    Total 27128.22 27272.95 26988.17 26580.22 26173.77

    75. The Petitioner has claimed the following IWC in respect of the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period:

    (₹ in lakh) Combined Asset (Asset-1 to Asset-17) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    O&M Expenses 159.10 164.67 170.41 176.40 182.45 Maintenance Spares 286.38 296.41 306.84 317.52 328.41 Receivables 3424.18 3364.75 3275.44 3180.56 3077.00

    Total 3869.66 3825.83 3752.69 3674.48 3587.86

    Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05

    Interest on Working

    399.41 405.12 409.47 408.76 400.48

    Capital (₹ in lakh) Asset-18 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    O&M Expenses 299.98 310.45 321.34 332.64 344.26 Maintenance Spares 539.96 558.81 578.41 598.76 619.67 Receivables 9767.15 9745.94 9644.92 9519.66 9366.26

    Total 10607.09 10615.20 10544.67 10451.06 10330.19

    Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05

    Interest on Working

    1278.15 1279.13 1270.63 1259.35 1244.79

    Capital

    Page 101 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    O&M Expenses 109.17 113.00 116.97 121.05 125.32
    Maintenance Spares 196.51 203.40 210.54 217.90 225.57
    Receivables 3335.44 3362.42 3327.31 3277.01 3218.09
    Total 3,641.12 3,678.82 3,654.82 3,615.96 3,568.98
    Rate of Interest (in %) 12.05 12.05 12.05 12.05 12.05
    Interest on Working Capital 438.75 443.30 440.41 435.72 430.06

    Effective Date of Commercial Operation ("E-COD")

    76. The Petitioner has claimed E-COD of the Combined Asset (Asset-1 to Asset-

    17) as 9.3.2015. Based on the trued-up admitted capital cost and actual COD of all the assets, E-COD has been worked out as follows:

    Computed of E-COD Admitted capital No. of days cost as on Weight of the Assets Actual COD from last Weighted days 31.3.2019 cost (in %)

    COD

    (₹ in lakh)

    Asset-1 1.7.2012 2447.67 1.36 1989 26.97 Asset-2 1.10.2012 977.25 0.54 1897 10.27 Asset-3 1.3.2013 736.26 0.41 1746 7.12 Asset-4 7.11.2014 118031.67 65.40 1130 738.99 Asset-5 1.10.2015 2750.31 1.52 802 12.22 Asset-6 3.10.2015 1805.01 1.00 800 8.00 Asset-7 26.2.2016 1833.86 1.02 654 6.65 Asset-8 10.12.2015 7561.67 4.19 732 30.67 Asset-9 12.10.2015 5101.79 2.83 791 22.36 Asset-10 1.10.2015 14509.51 8.04 802 64.47 Asset-11 1.8.2017 1428.53 0.79 132 1.04 Asset-12 21.7.2017 2651.48 1.47 143 2.10 Asset-13 11.12.2017 2648.55 1.47 0 0.00 Asset-14 28.10.2015 2751.89 1.52 775 11.82 Asset-15 27.10.2015 8824.49 4.89 776 37.94 Asset-16 1.10.2015 3258.30 1.81 802 14.48 Asset-17 19.12.2015 3166.82 1.75 723 12.69

    Total 180485.06 100.00 1007.79 E-COD (Latest COD - Total Weighted Days) 9.3.2015

    77. E-COD of AC system is used to determine the lapsed life of the project as a

    Page 102 of 162

    whole which works out as four (4) years as on 1.4.2019 (i.e. the number of completed years as on 1.4.2019 from E-COD).

    Weighted Average Life ("WAL")

    78. The life as defined in Regulation 33 of the 2019 Tariff Regulations has been considered for determination of WAL. The Combined Asset (Asset-1 to Asset-17) may have multiple elements such as land, building, transmission line, sub-station and PLCC and each element may have different span of life. Therefore, the concept of WAL has been used as the useful life of the project as a whole.

    79. WAL has been determined based on the admitted capital cost of individual elements as on 31.3.2019, irrespective of life as stipulated in the 2019 Tariff Regulations. The element-wise life as defined in the 2014 Tariff Regulations prevailing at the time of actual COD of individual assets has been ignored for this purpose. The life as defined in the 2019 Tariff Regulations has been considered for determination of WAL. Accordingly, WAL of the Combined Asset (Asset-1 to Asset-17) has been worked out as 32 years and the same is as follows:

    Admitted capital cost (Excluding land) as on 31.3.2019)
    Particulars Combined asset cost (₹ in lakh) (1) Life in years (2) Weighted cost (3)=(1) x (2) (₹ in lakh) (3) Weighted average life of asset (in Years) (4)=(3)/(1)
    Building 6623.27 25 165581.68
    Transmission Line 128025.91 35 4480906.73
    Sub-station Equipment 44446.19 25 1111154.70
    PLCC 719.89 15 10798.39
    Land (Lease hold) 0.00 25 0.00
    IT Equipment 0.00 6.67 0.00
    Total 179815.25 5768441.49 32.08 years, rounded off to 32 years

    Page 103 of 162

    80. WAL as on 1.4.2019 as determined above is applicable prospectively (i.e. for 2019-24 tariff period no retrospective adjustment of depreciation in previous tariff period is required to be done. As discussed, E-COD of the Combined Asset is 9.3.2015 and the lapsed life of the project as a whole, works out as four years as on 1.4.2019 (i.e. the number of completed years as on 1.4.2019 from E- COD). Accordingly, WAL has been used to determine the remaining useful life as on 31.3.2019 to be 28 years.

    Capital Cost

    81. Regulation 19 of the 2019 Tariff Regulations provides as follows:

    "19 Capital Cost: (1) The Capital cost of the generating station or the transmission system, as the case may be, as determined by the Commission after prudence check in accordance with these regulations shall form the basis for determination of tariff for existing and new projects.

    (2) The Capital Cost of a new project shall include the following:

    (a) The expenditure incurred or projected to be incurred up to the date of commercial operation of the project;

    (b) Interest during construction and financing charges, on the loans (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the funds deployed;

    (c) Any gain or loss on account of foreign exchange risk variation pertaining to the loan amount availed during the construction period;

    (d) Interest during construction and incidental expenditure during construction as computed in accordance with these regulations;

    (e) Capitalised Initial Spares subject to the ceiling rates in accordance with these regulations;

    (f) Expenditure on account of additional capitalization and de-capitalisation determined in accordance with these regulations;

    (g) Adjustment of revenue due to sale of infirm power in excess of fuel cost prior to the date of commercial operation as specified under Regulation 7 of these regulations;

    (h) Adjustment of revenue earned by the transmission licensee by using the Asset-before the date of commercial operation;

    (i) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;

    (j) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal upto the receiving end of the generating station but does not include the transportation cost and any other appurtenant cost paid to the railway;

    Page 104 of 162

    (k) Capital expenditure on account of biomass handling equipment and facilities, for co-firing;

    (l) Capital expenditure on account of emission control system necessary to meet the revised emission standards and sewage treatment plant;

    (m) Expenditure on account of fulfilment of any conditions for obtaining environment clearance for the project;

    (n) Expenditure on account of change in law and force majeure events; and

    (o) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries.

    (3) The Capital cost of an existing project shall include the following:

    (a) Capital cost admitted by the Commission prior to 1.4.2019 duly trued up by excluding liability, if any, as on 1.4.2019;

    (b) Additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with these regulations;

    (c) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;

    (d) Capital expenditure on account of ash disposal and utilization including handling and transportation facility;

    (e) Capital expenditure incurred towards railway infrastructure and its augmentation for transportation of coal up to the receiving end of generating station but does not include the transportation cost and any other appurtenant cost paid to the railway; and

    (f) Capital cost incurred or projected to be incurred by a thermal generating station, on account of implementation of the norms under Perform, Achieve and Trade (PAT) scheme of Government of India shall be considered by the Commission subject to sharing of benefits accrued under the PAT scheme with the beneficiaries."

    (4) The capital cost in case of existing or new hydro generating station shall also include:

    (a) cost of approved rehabilitation and resettlement (R&R) plan of the project in conformity with National R&R Policy and R&R package as approved; and

    (b) cost of the developer's 10% contribution towards Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) and Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY) project in the affected area.

    (5) The following shall be excluded from the capital cost of the existing and new projects:

    (a) The Asset-forming part of the project, but not in use, as declared in the tariff petition;

    (b) De-capitalised Asset-after the date of commercial operation on account of replacement or removal on account of obsolescence or shifting from one project to another project:

    Provided that in case replacement of transmission Asset-is recommended by Regional Power Committee, such Asset-shall be decapitalised only after its redeployment;

    Page 105 of 162

    Provided further that unless shifting of an Asset-from one project to another is of permanent nature, there shall be no de-capitalization of the concerned asset.

    (c) In case of hydro generating stations, any expenditure incurred or committed to be incurred by a project developer for getting the project site allotted by the State Government by following a transparent process;

    (d) Proportionate cost of land of the existing project which is being used for generating power from generating station based on renewable energy; and

    (e) Any grant received from the Central or State Government or any statutory body or authority for the execution of the project which does not carry any liability of repayment."

    82. The trued-up capital cost as on 31.3.2019 for Asset-1 to Asset-17 has been considered as capital cost as on 31.3.2019 for Combined Asset (Asset-1 to Asset-

    17). The capital cost has been dealt in line with Regulation 19(3) of the 2019 Tariff Regulations. The element-wise capital cost (i.e. land, building, transmission line, sub-station and PLCC) as admitted by the Commission as on 31.3.2019 for the transmission assets are clubbed together and the capital cost has been considered as capital cost for the Combined Asset (Asset-1 to Asset-17) as on 31.3.2019. Further, with regard to Asset-18 and Asset-19 (being HVDC assets), the Petitioner has claimed the tariff separately as per requirement of Sharing Regulations.

    83. Accordingly, the trued-up capital cost of ₹180485.06 lakh, ₹603531.90 lakh and ₹216027.66 lakh for the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19, respectively, is considered as admitted capital cost as on 31.3.2019 for working out tariff for the 2019-24 tariff period. The Petitioner has claimed ACE for 2019-24 tariff period and estimated capital cost as on 31.3.2024 as follows:

    (₹ in lakh)

    Assets FR Apportioned approved cost RCE-II Apportioned approved cost Expenditure up to 1.4.2019 (as claimed ) ACE c l a i med 2019-24 Estimated comple- tion cost as on 31.3.2024 (as claimed)
    Combined Asset 154966.52 191684.43 180586.90 2634.93 183221.83

    Page 106 of 162

    (Asset-1 to 17)
    Asset-18 641074.53 887106.06 872974.85 7755.42 880730.27
    Asset-19 194699.17 259005.37 236551.67 5052.94 241604.61
    Total 990740.22 1337795.86 1290113.42 15443.29 1305556.71

    84. We have considered the submissions of the Petitioner. The cost of Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 is within RCE-II. The capital cost allowed as on 1.4.2019 for the Combined Asset (Asset-1 to 17), Asset-18 and Asset-19 is as follows:

    (₹ in lakh)

    Assets Expenditure u p to 1.4.2019
    Combined Asset (Asset-1 to 17) 180485.06
    Asset-18 603531.90
    Asset-19 216027.66

    Additional Capital Expenditure ("ACE")

    85. Regulation 24 and Regulation 25 of the 2019 Tariff Regulations provides as follows:

    "24. Additional Capitalization within the original scope and up to the cut-off date:

    (1) The Additional Capital Expenditure in respect of a new project or an existing project incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

    (a) Undischarged liabilities recognized to be payable at a future date;

    (b) Works deferred for execution;

    (c) Procurement of initial capital spares within the original scope of work, in accordance with the provisions of Regulation 23 of these regulations;

    (d) Liabilities to meet award of arbitration or for compliance of the directions or order of any statutory authority or order or decree of any court of law;

    (e) Change in law or compliance of any existing law; and

    (f) Force Majeure events:

    Provided that in case of any replacement of the assets, the additional capitalization shall be worked out after adjusting the gross fixed assets and cumulative depreciation of the assets replaced on account of de-capitalization.

    (2) The generating company or the transmission licensee, as the case may be shall submit the details of works asset wise/work wise included in the original scope of work along with estimates of expenditure, liabilities recognized to be payable at a

    Page 107 of 162

    future date and the works deferred for execution."

    25. Additional Capitalisation within the original scope and after the cut-off date:

    (1) The ACE incurred or projected to be incurred in respect of an existing project or a new project on the following counts within the original scope of work and after thecutoff date may be admitted by the Commission, subject to prudence check:

    a) Liabilities to meet award of arbitration or for compliance of the directions or order of any statutory authority, or order or decree of any court of law;

    b) Change in law or compliance of any existing law;

    c) Deferred works relating to ash pond or ash handling system in the original scope of work;

    d) Liability for works executed prior to the cut-off date;

    e) Force Majeure events;

    f) Liability for works admitted by the Commission after the cut-off date to the extent of discharge of such liabilities by actual payments; and

    g) Raising of ash dyke as a part of ash disposal system."

    (2) In case of replacement of assets deployed under the original scope of the existing project after cut-off date, the additional capitalization may be admitted by the Commission, after making necessary adjustments in the gross fixed assets and the cumulative depreciation, subject to prudence check on the following grounds:

    (a) The useful life of the assets is not commensurate with the useful life of the project and such assets have been fully depreciated in accordance with the provisions of these regulations;

    (b) The replacement of the asset or equipment is necessary on account of change in law or Force Majeure conditions;

    (c) The replacement of such asset or equipment is necessary on account of obsolescence of technology; and

    (d) The replacement of such asset or equipment has otherwise been allowed by the Commission."

    86. The Petitioner has claimed projected ACE in respect of the transmission assets and has submitted the Auditor's Certificate in support of the same. The Petitioner has submitted that claimed ACE is incurred on account of undischarged liability towards final payment/ withheld payment due to contractual exigencies for works executed within the cut-off date and the same is covered under Regulation 24(1)(a) and Regulation 24(1)(b) of the 2019 Tariff Regulations.

    87. Asset-wise ACE claimed by the Petitioner is as follows:

    Page 108 of 162

    (₹ in lakh)

    Asset details Projected ACE for 2019-24 Total ACE claimed during 2019-24 tariff period
    2019-20 2020-21 2021-22 2022-23
    Asset-1 37.84 0.00 0.00 0.00 37.84
    Asset-2 19.83 0.00 0.00 0.00 19.83
    Asset-3 15.72 0.00 0.00 0.00 15.72
    Asset-4 1040.51 290.16 0.00 0.00 1330.67
    Asset-5 96.41 0.00 0.00 0.00 96.41
    Asset-6 112.80 0.00 0.00 0.00 112.80
    Asset-7 89.35 0.00 0.00 0.00 89.35
    Asset-8 282.51 0.00 0.00 0.00 282.51
    Asset-9 57.32 0.00 0.00 0.00 57.32
    Asset-10 57.32 58.62 0.00 0.00 115.94
    Asset-11 0.00 0.00 0.00 0.00 0.00
    Asset-12 33.99 0.00 0.00 0.00 33.99
    Asset-13 37.68 0.00 0.00 0.00 37.68
    Asset-14 45.62 80.51 0.00 0.00 126.13
    Asset-15 45.62 101.20 0.00 0.00 146.82
    Asset-16 73.12 17.46 0.00 0.00 90.58
    Asset-17 41.34 0.00 0.00 0.00 41.34
    Asset-18 5570.85 2158.57 26.00 0.00 7755.42
    Asset-19 4927.92 125.02 0.00 0.00 5052.94
    Total 12585.75 2831.54 26.00 0.00 15443.29

    88. The Petitioner has submitted the details of cut-off date of the transmission assets and with regulation under which the ACE is claimed and the same is as follows:

    Cut-off ACE Regulation during 2019-2024 Assets COD

    date 2019-20 2020-21 2021-22 2022-23 2023-24

    Asset-1 1.7.2012 31.3.2015 25(1)(f) - - - - Asset-2 1.10.2012 31.3.2015 25(1)(f) - - - - Asset-3 1.3.2013 31.3.2016 25(1)(f) - - - - Asset-4 7.11.2014 31.3.2017 25(2)(b) 25(2)(b) - - - Asset-5 1.10.2015 31.3.2018 25(1)(f) - - - - Asset-6 3.10.2015 31.3.2018 25(1)(f) - - - - Asset-7 26.2.2016 31.3.2019 25(1)(f) - - - - Asset-8 10.12.2015 31.3.2018 25(1)(f) - - - - Asset-9 12.10.2015 31.3.2018 25(1)(f) - - - - Asset-10 1.10.2015 31.3.2018 25(1)(f) 25(1)(f) - - - Asset-11 1.8.2017 31.3.2020 - - - - - 24(1)(a) - - -

    Asset-12 21.7.2017 31.3.2020 & -

    24(1)(b)

    24(1)(a) - - -

    Asset-13 11.12.2017 31.3.2020 & -

    24(1)(b)

    Page 109 of 162

    Cut-off ACE Regulation during 2019-2024 Assets COD

    date 2019-20 2020-21 2021-22 2022-23 2023-24

    Asset-14 28.10.2015 31.3.2018 25(1)(f) 25(1)(f) - - - Asset-15 27.10.2015 31.3.2018 25(1)(f) 25(1)(f) - - - Asset-16 1.10.2015 31.3.2018 25(1)(f) 25(1)(f) - - - Asset-17 19.12.2015 31.3.2018 25(1)(f) 25(1)(f) - - - Asset-18 1.11.2015 31.3.2018 25(1)(f) 25(1)(f) 25(1)(f) - - Asset-19 2.9.2016 31.3.2019 25(1)(f) 25(1)(f) - - -

    89. The Petitioner vide affidavit dated 8.3.2021 has submitted that ACE claimed for Asset-1 to Asset-19 is within the original scope of work. However, ACE claimed during the year 2019-20 and 2020-21 for Asset-4 and Asset-18 is on account of construction of pile foundation due to change in river course of Pagladia and Maansiri river and the same has been approved in 17thTCC meeting of NERPC held on 4.10.2016. Further, the Petitioner has submitted that de-capitalization of Asset-4 and Asset-18 during 2019-20 is on account of shifting of existing tower on new pile foundation and dismantling of tower parts, conductors and insulators.

    90. The Petitioner has submitted that ACE claimed by it for 2019-24 tariff period is based on projected expenditure and the actual capital expenditure to be incurred during 2019-24 and will be finalized after the closing of contract which may be higher or lower than the estimated ACE submitted. The payments to be made during 2019-24 period after submission of invoice and after reconciliation in accordance with the provisions of the contract. The Petitioner has provided the liability flow statement indicating contractor-wise details of liabilities and balance work for 2019-24 tariff period for the transmission assets. The Petitioner has clarified that no 'previously recognized liabilities' is to be discharged beyond 2019- 24 tariff period.

    Page 110 of 162

    91. The Petitioner vide affidavit dated 8.3.2021 has submitted that ACE claimed for Asset-1 to Asset-19 is within the original scope of work. However, ACE incurred during the year 2019-20 and 2020-21 for Asset-4 (400 kV Balipara-Bongaigaon D/C line) and Asset-18 (± 800 kV Biswanath Chariali-Agra HVDC line) is on account of construction of pile foundation due to the change in the course of Pagladia and Maansiri river and the same has been approved in 17th TCC meeting and 17th NERPC meeting held on 4.10.2016. The ACE towards pile foundation in case of Asset-4 and Asset-18 has been claimed under Regulation 25(2)(b) of the 2019 Tariff Regulations. The Petitioner has also submitted that ACE incurred is inclusive of undischarged IDC.

    92. We have considered the submissions of the Petitioner. The ACE in case of Asset-1 to Asset-19 incurred for the work executed within the 'cut-off' date is allowed under Regulation 24(1)(a) and Regulation 24(1)(b) of the 2019 Tariff Regulations and the ACE in case of Asset-12 and Asset-13 beyond the 'cut-off' date is allowed under Regulation 25(1)(d) and Regulation 25(1)(f) of the 2019 Tariff Regulations. The ACE towards pile foundation in case of Asset-4 and Asset-18, Balipara-Bongaigaon line and Biswanath Chariali-Agra HVDC line, has become necessary due to change in river course and proximity of the river to the tower foundation and the same was also discussed and approved in the 125thOCCM, 17thTCC and 17thNERPC meetings. The same is allowed under Regulation 25(2)(b) of the 2019 Tariff Regulations.

    93. Asset-wise ACE allowed in respect of the transmission assets is as follows:

    Page 111 of 162

    (₹ in lakh)

    Asset ACE allowed/ dis-allowed
    Asset-1 The Petitioner has claimed an amount of ₹37.84 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-2 The Petitioner has claimed an amount of ₹19.83 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-3 The Petitioner has claimed an amount of ₹15.72 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-4 Out of the total ACE of ₹1330.67 lakh, an amount of ₹1199.62 is towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations. The Petitioner has claimed an amount of ₹131.05 lakh towards pile foundation works and the same has been allowed under Regulation 25(2)(b) of the 2019 Tariff Regulations.
    Asset-5 The Petitioner has claimed an amount of ₹96.41 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-6 The Petitioner has claimed an amount of ₹112.80 lakh towards outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-7 The Petitioner has claimed an amount of ₹89.35 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-8 The Petitioner has claimed an amount of ₹282.51 lakh towards outstanding liability towards works executed prior to cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-9 The Petitioner has claimed an amount of ₹57.32 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-10 The Petitioner has claimed an amount of ₹57.32 lakh and ₹58.62 lakh for outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.

    Page 112 of 162

    Asset-12 The Petitioner has claimed an amount of ₹13.60 lakh towards undischarged liabilities and an amount of ₹20.39 lakh for works deferred for execution upto the cut-off date and the same has been allowed under Regulation 24(1)(a) and Regulation 24(1)(b) of the 2019 Tariff Regulations.
    Asset-13 The Petitioner has claimed an amount of ₹13.59 lakh towards undischarged liabilities and an amount of ₹24.09 lakh for works deferred for execution upto the cut-off date and the same has been allowed under Regulation 24(1)(a) and Regulation 24(1)(b) of the 2019 Tariff Regulations.
    Asset-14 The Petitioner has claimed an amount of ₹45.62 lakh and ₹80.51 lakh towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-15 The Petitioner has claimed an amount of ₹45.62 lakh and ₹101.2 lakh for outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-16 The Petitioner has claimed an amount of ₹73.12 lakh and ₹17.46 lakh for outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-17 The Petitioner has claimed an amount of ₹41.34 lakh for outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019- 20 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.
    Asset-18 Out of the total ACE of ₹7755.42 lakh, an amount of ₹7716.86 lakh is towards outstanding liability for works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations. The Petitioner has claimed an amount of ₹38.56 lakh towards pile foundation works and the same has been allowed under Regulation 25(2)(b) of the 2019 Tariff Regulations.
    Asset-19 The Petitioner has claimed an amount of ₹4927.92 lakh and ₹125.02 lakh towards outstanding liability towards works executed prior to the cut-off date and to be discharged in 2019-20 and 2020-21 and the same has been allowed under Regulation 25(1)(d) of the 2019 Tariff Regulations.

    De-capitalisation:

    94. The Petitioner has carried out de-capitalisation in respect of Asset-4 and Asset-18 in 2019-20. The Petitioner has provided Form-10B for Asset-4 and Asset- 18 and submitted that de-capitalization of Asset-4 and Asset-18 is projected during 2019-20 on account of shifting of existing tower on new pile foundation and

    Page 113 of 162

    dismantling of tower parts, conductors and insulators. The assets are in use and shifted on new pile foundation tower by availing minimum shut-down of the said lines. The details of shut-down taken for shifting of the transmission lines from existing tower foundations to new pile foundations is as follows:

    (i) Asset-4: Shut-down availed from 24.4.2019 to 1.6.2019 for shifting on new pile foundation and line charged on 1.6.2019.

    (ii) Asset-18: Shut-down availed from 5.1.2020 to 11.1.2020 for shifting on new pile foundation and line charged on 11.1.2020.

    95. The details submitted by the Petitioner in Form-10B in respect of Asset-4 and Asset-18 are as follows:

    Assets Category Date/ Year of decapital- ization Details of asset decapital- ised Date/ Year of capital- ization of asset/ equipment being decapital- ised Original capital cost admitted for tariff for the asset being decapital- ised Debt- Equity ratio considered for tariff on the capital cost Cummul- ative depre- ciation corress- ponding to decapital- ised asset upto the date of decapital- isation Cummul- ative re- payment of loan corress- ponding to decapital- ised asset upto the date of decapital- isation Details of petition in which tariff of the asset being decapital- ised was approved by Commi- ssion
    (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
    Asset-4 Trans- mission Line 1.6.2019 (2019-20) Conductors & Insulators 7.11.2014 (2014-15) 19.64 80:20 4.56 4.56 Order dated 14.7.2016 in P. No. 65/TT/2015
    Asset- 18 Trans- mission Line 11.1.2020 (2019-20) Towers, Conductors & Insulators 1.11.2015 (2015-16) 213.47(*) 80:20 38.02 38.02 Order dated 17.12.2019 in P. No. 363/TT/2019

    Original Details of depre- payment Date/ Year capital petition in ciation of loan

    of capital- cost Debt- which tariff corress- corress-

    Date/ Details of ization of admitted Equity ratio of the asset ponding ponding

    Year of asset asset/ for tariff considered being Assets Category to to

    decapital- decapital- equipment for the for tariff on decapital- decapital- decapital-

    ization ised being asset the capital ised was ised asset ised asset

    decapital- being cost approved

    upto the upto the

    ised decapital- by Commi-

    date of date of

    ised ssion

    decapital- decapital-

    isation isation

    (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

    Trans- Order dated 1.6.2019 Conductors 7.11.2014 14.7.2016 in Asset-4 mission 19.64 80:20 4.56 4.56 (2019-20) & Insulators (2014-15) P. No. Line 65/TT/2015

    Trans- Towers, Order dated

    Asset- 11.1.2020 1.11.2015 17.12.2019 mission Conductors 213.47(*) 80:20 38.02 38.02 18 (2019-20) (2015-16) in P. No. Line & Insulators 363/TT/2019

    (*) The amount shown in Form-10A is ₹147.59 lakh which is after adjustment of grant amount

    96. The Petitioner has further submitted that cumulative depreciation has been adjusted by taking into account the depreciation recovered in tariff by the de- capitalized assets during its useful life and has requested to allow to recover the unrecovered depreciation in case of Asset-4 and Asset-18, separately, on account

    Page 114 of 162

    of de-capitalization. The details of depreciation recovered from de-capitalized asset is as follows:

    (₹ in lakh)

    Assets Gross block of de-capitalized asset (A) Year of de- capitalization Cumulative depreciation recovered (B) Unrecovered Depreciation (0.9*A-B)
    Asset-4 19.64 2019-20 4.56 13.12
    Asset-18 147.59* 2019-20 38.02 94.81

    *The gross block of de-capitalized asset in case of Asset-18 has been considered net of grant.

    97. We have considered the submission of the Petitioner. The Petitioner has prayed for allowing the unrecovered depreciation in case of the de-capitalised assets. It is observed that the assets are no more in use and they are to be removed from the capital cost and as they are not part of the capital cost and hence, depreciation cannot be allowed. It is observed that there is no specific provision for recovering unrecovered depreciation in the 2019 Tariff Regulations. Accordingly, we are not inclined to allow the un-recovered depreciation claimed by the Petitioner.

    98. The details of ACE allowed is subject to truing up is as follows:

    (₹ in lakh) ACE 2019-24 Total ACE for Assets 2019-24 (as 2019-20 2020-21 2021-22 2022-23 2023-24 allowed)

    Combined 2086.98 547.95 0.00 0.00 0.00 2634.93

    Asset (Asset-1 to Asset-17) Asset-18 5,636.72 2158.57 26.00 0.00 0.00 7821.29

    Asset-19 4927.92 125.02 0.00 0.00 0.00 5052.94

    99. Accordingly, capital cost considered for the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period is as follows:

    Page 115 of 162

    (₹ in lakh)

    Assets Capital cost as on 1.4.2019 2019-20 2020-21 2021-22 2022-23 2023-24 Capital cost as on 31.3.2024
    Combined Asset- (Asset-1 to Asset-17) 180485.06 2086.97 547.95 0.00 0.00 0.00 183119.98
    Asset-18 603531.90 5636.72 2158.57 26.00 0.00 0.00 611353.19
    Asset-19 216027.66 4927.92 125.02 0.00 0.00 0.00 221080.60

    Debt-Equity Ratio

    100. Regulations 18 of the 2019 Tariff Regulations provides as follows:

    "18. Debt-Equity Ratio: (1) For new projects, the debt-equity ratio of 70:30 as on date of commercial operation shall be considered. If the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan:

    Provided that:

    i. where equity actually deployed is less than 30% of the capital cost, actual equity shall be considered for determination of tariff:

    ii. the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment:

    iii. any grant obtained for the execution of the project shall not be considered as a part of capital structure for the purpose of debt:

    equity ratio.

    Explanation-The premium, if any, raised by the generating company or the transmission licensee, as the case may be, while issuing share capital and investment of internal resources created out of its free reserve, for the funding of the project, shall be reckoned as paid up capital for the purpose of computing return on equity, only if such premium amount and internal resources are actually utilised for meeting the capital expenditure of the generating station or the transmission system.

    (2) The generating company or the transmission licensee, as the case may be, shall submit the resolution of the Board of the company or approval of the competent authority in other cases regarding infusion of funds from internal resources in support of the utilization made or proposed to be made to meet the capital expenditure of the generating station or the transmission system including communication system, as the case may be.

    (3) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, debt:

    equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2019 shall be considered:

    Provided that in case of a generating station or a transmission system including communication system which has completed its useful life as on or after 1.4.2019, if

    Page 116 of 162

    the equity actually deployed as on 1.4.2019 is more than 30% of the capital cost, equity in excess of 30%shall not be taken into account for tariff computation; Provided further that in case of projects owned by Damodar Valley Corporation, the debt: equity ratio shall be governed as per sub-clause (ii) of clause (2) of Regulation 72 of these regulations.

    (4) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2019, but where debt: equity ratio has not been determined by the Commission for determination of tariff for the period ending 31.3.2019, the Commission shall approve the debt: equity ratio in accordance with clause (1) of this Regulation.

    (5) Any expenditure incurred or projected to be incurred on or after 1.4.2019 as may be admitted by the Commission as additional capital expenditure for determination of tariff, and renovation and modernisation expenditure for life extension shall be serviced in the manner specified in clause (1) of this Regulation."

    (6) Any expenditure incurred for the emission control system during the tariff period as may be admitted by the Commission as additional capital expenditure for determination of supplementary tariff, shall be serviced in the manner specified in clause (1) of this Regulation."

    101. The details of debt-equity ratio considered for the purpose of computation of tariff for 2019-24 tariff period in respect of Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 is as follows:

    Combined (Asset-1 to Asset-17) Capital cost as on 1.4.2019 (₹ in lakh) (in %) Total Capital cost as on 31.3.2024 (₹ in lakh) (in %)
    Debt 143026.48 79.25 144870.93 79.11
    Equity 37458.58 20.75 38249.05 20.89
    Total 180485.06 100.00 183119.98 100.00
    Asset-18
    Debt 428045.59 70.92 433520.48 70.91
    Equity 175486.31 29.08 177832.71 29.09
    Total 603531.90 100.00 611353.19 100.00
    Asset-19
    Debt 168819.82 78.15 172356.87 77.96
    Equity 47207.84 21.85 48723.72 22.04
    Total 216027.66 100.00 221080.60 100.00

    Depreciation

    102. Regulation 33 of the 2019 Tariff Regulations provide as follows:

    "33. Depreciation: (1) Depreciation shall be computed from the date of commercial operation of a generating station or unit thereof or a transmission system or element

    Page 117 of 162

    thereof including communication system. In case of the tariff of all the units of a generating station or all elements of a transmission system including communication system for which a single tariff needs to be determined, the depreciation shall be computed from the effective date of commercial operation of the generating station or the transmission system taking into consideration the depreciation of individual units:

    Provided that effective date of commercial operation shall be worked out by considering the actual date of commercial operation and installed capacity of all the units of the generating station or capital cost of all elements of the transmission system, for which single tariff needs to be determined.

    (2) The value base for the purpose of depreciation shall be the capital cost of the Asset-admitted by the Commission. In case of multiple units of a generating station or multiple elements of a transmission system, weighted average life for the generating station of the transmission system shall be applied. Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the Asset-for part of the year, depreciation shall be charged on pro rata basis."

    (3) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of theasset:

    Provided that the salvage value for IT equipment and software shall be considered as NIL and 100% value of the assets shall be considered depreciable; Provided further that in case of hydro generating stations, the salvage value shall be as provided in the agreement, if any, signed by the developers with the State Government for development of the generatingstation

    Provided also that the capital cost of the assets of the hydro generating station for the purpose of computation of depreciated value shall correspond to the percentage of sale of electricity under long-term power purchase agreement at regulated tariff:

    Provided also that any depreciation disallowed on account oflower availability of the generating station or unit or transmission system as the case may be, shall not be allowed to be recovered at a later stage during the useful life or the extended life.

    (4) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall beexcluded from the capital cost while computing depreciable value of theasset.

    (5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-I to these regulations for the Asset-of the generating station and transmission system:

    Provided that the remaining depreciable value as on 31st March of the year closing after a period of 12 years from the effective date of commercial operation of the station shall be spread over the balance useful life of the asset.

    Page 118 of 162

    (6) In case of the existing projects, the balance depreciable value as on 1.4.2019 shall be worked out by deducting the cumulative depreciation as admitted by the Commission up to 31.3.2019 from the gross depreciable value of the asset.

    (7) The generating company or the transmission licensee, as the case may be, shall submit the details of proposed capital expenditure five years before the completion of useful life of the project along with justification and proposed life extension. The Commission based on prudence check of such submissions shall approve the depreciation on capital expenditure.

    (8) In case of de-capitalization of asset in respect of generating station or unit thereof or transmission system or element thereof, the cumulative depreciation shall be adjusted by taking into account the depreciation recovered in tariff by the de- capitalizedasset during its useful services.

    (9) Where the emission control system is implemented within the original scope of the generating station and the date of commercial operation of the generating station or unit thereof and the date of operation of the emission control system are the same, depreciation of the generating station or unit thereof including the emission control system shall be computed in accordance with Clauses (1) to (8) of this Regulation.

    (10) Depreciation of the emission control system of an existing or a new generating station or unit thereof where the date of operation of the emission control system is subsequent to the date of commercial operation of the generating station or unit thereof, shall be computed annually from the date of operation of such emission control system based on straight line method, with salvage value of 10%, over a period of ─

    a) twenty five years, in case the generating station or unit thereof is in operation for fifteen years or less as on the date of operation of the emission control system; or

    b) balance useful life of the generating station or unit thereof plus fifteen years, in case the generating station or unit thereof is in operation for more than fifteen years as on the date of operation of the emission control system; or

    c) ten years or a period mutually agreed by the generating company and the beneficiaries, whichever is higher, in case the generating station or unit thereof has completed its useful life."

    103. We have considered the submissions of the Petitioner. The depreciation has been worked out considering the admitted capital expenditure as on 31.3.2019 and accumulated depreciation up to 31.3.2019. Depreciation allowed for Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 is as follows:

    Page 119 of 162

    (₹ in lakh) Combined Asset (Asset- 1 to Asset-17) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Opening Gross Block 180485.06 182572.03 183119.98 183119.98 183119.98 B Addition during the year 2019- 2086.97 547.95 0.00 0.00 0.00 24 due to projected ACE

    C Closing Gross Block (A+B) 182572.03 183119.98 183119.98 183119.98 183119.98 D Average Gross Block (A+C)/2 181528.55 182846.01 183119.98 183119.98 183119.98 E Weighted average rate of 5.19 5.19 5.19 5.19 5.19

    Depreciation (WAROD) (in %)

    F Lapsed useful life at the 4 5 6 7 8

    beginning of the year (Year)

    G Balance useful life at the 28 27 26 25 24

    beginningof the year (Year)

    H Depreciable value (D*90%) 162772.87 163958.58 164205.16 164205.16 164205.16

    I Combined Depreciation 9426.22 9493.60 9508.07 9508.07 9508.07

    during the year (D*E)

    J Cumulative Depreciation at the 46664.77 56158.37 65666.44 75174.50 84682.57 end of the year

    K Remaining Aggregate

    Depreciable Value at the end 116108.10 107800.21 98538.72 89030.65 79522.58 of the year

    (₹ in lakh) Asset-18 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Opening Gross Block 603531.90 609168.62 611327.19 611353.19 611353.19 B Addition during the year 2019- 5636.72 2158.57 26.00 0.00 0.00 24 due to projected ACE

    C Closing Gross Block (A+B) 609168.62 611327.19 611353.19 611353.19 611353.19 D Average Gross Block 606350.26 610247.90 611340.19 611353.19 611353.19 (A+C)/2

    E Weighted average rate of 5.2095 5.2085 5.2086 5.2086 5.2086 Depreciation (WAROD) (in

    %)

    F Lapsed useful life at the 3 4 5 6 7

    beginning of the year (Year)

    G Balance useful life at the 30 29 28 27 26

    beginningof the year (Year)

    H Depreciable value (D*90%) 544578.90 548086.78 549069.84 549081.54 549081.54

    I Combined Depreciation 31587.91 31784.54 31842.22 31842.90 31842.90 during the year (D*E)

    J Cumulative Depreciation at 180615.89 212400.43 244242.65 276085.55 307928.45 the end of the year

    K Remaining Aggregate 363963.02 335686.35 304827.19 272995.99 241153.09 Depreciable Value at the end

    of the year

    Page 120 of 162

    (₹ in lakh)

    Asset-19
    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    A Opening Gross Block 216027.66 220955.58 221080.60 221080.60 221080.60
    B Addition during the year 2019- 24 due to projected ACE 4927.92 125.02 0.00 0.00 0.00
    C Closing Gross Block (A+B) 220955.58 221080.60 221080.60 221080.60 221080.60
    D Average Gross Block (A+C)/2 218491.62 221018.09 221080.60 221080.60 221080.60
    E Weighted average rate of Depreciation (WAROD) (in %) 5.0628 5.0601 5.0602 5.0602 5.0602
    F Lapsed useful life at the beginning of the year (Year) 2 3 4 5 6
    G Balance useful life at the beginningof the year (Year) 24 23 22 21 20
    H Depreciable value (D*90%) 194590.62 196850.94 196907.20 196907.20 196907.20
    I Combined Depreciation during the year (D*E) 11061.75 11183.74 11187.04 11187.04 11187.04
    J Cumulative Depreciation at the end of the year 40828.97 52012.71 63199.76 74386.80 85573.85
    K Remaining Aggregate Depreciable Value at the end of the year 153761.65 144838.23 133707.44 122520.40 111333.35

    Interest on Loan ("IoL")

    104. Regulation 32 of the 2019 Tariff Regulations provides as follows:

    "32. Interest on loan capital: (1) The loans arrived at in the manner indicated in Regulation 18 of these regulations shall be considered as gross normative loan for calculation of interest on loan.

    (2) The normative loan outstanding as on 1.4.2019 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2019 from the gross normative loan.

    (3) The repayment for each of the year of the tariff period 2019-24 shall be deemed to be equal to the depreciation allowed for the corresponding year/period. In case of de-capitalization of asset, the repayment shall be adjusted by taking into account cumulative repayment on a pro rata basis and the adjustment should not exceed cumulative depreciation recovered upto the date of de-capitalisation of such asset.

    (4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be, the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the depreciation allowed for the year or part of the year.

    (5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio after providing appropriate accounting adjustment for interest capitalized:

    Page 121 of 162

    Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered;

    Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

    (5a) The rate of interest on loan for installation of emission control system shall be the weighted average rate of interest of actual loan portfolio of the emission control system or in the absence of actual loan portfolio, the weighted average rate of interest of the generating company as a whole shall be considered.

    (6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.

    (7) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing".

    105. The Petitioner has prayed for floating rate of IoL for 2019-24 tariff period. Bihar Discosms have submitted that the 2014 Tariff Regulations do not permit change in interest rate due to floating rate of interest.

    106. In response, the Petitioner has submitted that IoL has been calculated on the basis of actual rate of interest of various loans deployed for each year. The change in interest rate due to floating rate of interest applicable, if any, for the transmission project needs to be claimed/ adjusted over the tariff period of 5 years directly from/ with the beneficiaries. The Petitioner has further submitted that the floating interest rate mentioned in the cash IDC statement for bank loans varies on daily/monthly/quarterly basis and the IDC calculation has been done by multiplying the particular loan interest rate with applicable number of days (i.e. for the number of days upto which the particular rate is applicable) till COD.

    107. We have considered the submissions of the Petitioner and Bihar Discoms. The weighted average rate of IoL has been considered on the basis of rate

    Page 122 of 162

    prevailing as on 1.4.2019. Accordingly, the floating rate of interest, if any, shall be considered at the time of true up. IoL has been allowed in accordance with Regulation 32 of the 2019 Tariff Regulations. IoL allowed for the Combined Asset, (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period is follows:

    (₹ in lakh) Combined Asset (Asset-1 to Asset-17) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Gross Normative Loan 143026.49 144487.36 144870.93 144870.93 144870.93 Cumulative Repayments 37238.55 46664.77 56158.37 65666.44 75174.50

    B

    upto Previous Year C Net Loan-Opening (A-B) 105787.95 97822.59 88712.56 79204.49 69696.42 D Addition due to ACE 1460.87 383.57 0.00 0.00 0.00 E Repayment during the year 9426.22 9493.60 9508.07 9508.07 9508.07 F Net Loan-Closing (C+D-E) 97822.59 88712.56 79204.49 69696.42 60188.35 G Average Loan (C+F)/2 101805.27 93267.57 83958.52 74450.46 64942.39 Weighted Average Rate of 8.782 8.770 8.774 8.777 8.779

    H

    Interest on Loan (in %)

    I Interest on Loan (G*H) 8940.95 8179.94 7366.10 6534.67 5701.42 (₹ in lakh)

    Asset-18

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Gross Normative Loan 428045.59 431991.28 433502.28 433520.48 433520.48 Cumulative Repayments 149027.97 180615.89 212400.43 244242.65 276085.55

    B

    upto Previous Year C Net Loan-Opening (A-B) 279017.61 251375.40 221101.85 189277.83 157434.93 D Addition due to ACE 3945.70 1511.00 18.20 0.00 0.00 E Repayment during the year 31587.91 31784.54 31842.22 31842.90 31842.90 F Net Loan-Closing (C+D-E) 251375.40 221101.85 189277.83 157434.93 125592.03 G Average Loan (C+F)/2 265196.51 236238.62 205189.84 173356.38 141513.48 Weighted Average Rate of 3.6985 3.7573 3.8092 3.8505 3.8971

    H

    Interest on Loan (in %) I Interest on Loan (G*H) 9808.29 8876.19 7816.09 6675.09 5514.92

    (₹ in lakh) Asset-19 Particular 2019-20 2020-21 2021-22 2022-23 2023-24

    A Gross Normative Loan 168819.82 172269.36 172356.87 172356.87 172356.87 Cumulative Repayments 29767.22 40828.97 52012.71 63199.76 74386.80

    B

    upto Previous Year C Net Loan-Opening (A-B) 139052.60 131440.39 120344.16 109157.12 97970.07 D Addition due to ACE 3449.54 87.51 0.00 0.00 0.00

    E Repayment during the year 11061.75 11183.74 11187.04 11187.04 11187.04 F Net Loan-Closing (C+D-E) 131440.39 120344.16 109157.12 97970.07 86783.03 G Average Loan (C+F)/2 135246.49 125892.27 114750.64 103563.59 92376.55

    Page 123 of 162

    Weighted Average Rate of 3.8751 4.0285 4.1274 4.1378 4.1511

    H

    Interest on Loan (in %)

    I Interest on Loan (G*H) 5240.94 5071.57 4736.22 4285.25 3834.64 Return on Equity("RoE")

    108. Regulation 30 and Regulation 31 of the 2019 Tariff Regulations provide as follows:

    "30. Return on Equity: (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with Regulation 18 of these regulations.

    (2) Return on equity shall be computed at the base rate of 15.50% for thermal generating station, transmission system including communication system and run- of-river hydro generating station, and at the base rate of 16.50% for the storage type hydro generating stations including pumped storage hydro generating stations and run-of-river generating station with pondage:

    Provided that return on equity in respect of Additional Capitalization after cut-off date beyond the original scope excluding Additional Capitalization on account of emission control system, shall be computed at the weighted average rate of interest on actual loan portfolio of the generating station or the transmission system or in the absence of actual loan portfolio of the generating station or the transmission system, the weighted average rate of interest of the generating company or the transmission licensee, as the case may be, as a whole shall be considered, subject to celling of 14%; Provided further that:

    i. In case of a new project, the rate of return on equity shall be reduced by 1.00% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO) or Free Governor Mode Operation (FGMO), data telemetry, communication system up to load dispatch centre or protection system based on the report submitted by the respective RLDC;

    ii.in case of existing generating station, as and when any of the requirements under (i) above of this Regulation are found lacking based on the report submitted by the concerned RLDC, rate of return on equity shall be reduced by 1.00% for the period for which the deficiency continues;

    iii. in case of a thermal generating station, with effect from 1.4.2020:

    a) rate of return on equity shall be reduced by 0.25% in case of failure to achieve the ramp rate of 1% per minute;

    b) an additional rate of return on equity of 0.25% shall be allowed for every incremental ramp rate of 1% per minute achieved over and above the ramp rate of 1% per minute, subject to ceiling of additional rate of return on equity of 1.00%:

    Page 124 of 162

    Provided that the detailed guidelines in this regard shall be issued by National Load Dispatch Centre by 30.6.2019.

    (3) The return on equity in respect of additional capitalization on account of emission control system shall be computed at the base rate of one year marginal cost of lending rate (MCLR) of the State Bank of India as on 1st April of the year in which the date of operation (ODe) occurs plus 350 basis point, subject to ceiling of 14%;

    31. Tax on Return on Equity:(1) The base rate of return on equity as allowed by the Commission under Regulation 30 of these regulations shall be grossed up with the effective tax rate of the respective financial year. For this purpose, the effective tax rate shall be considered on the basis of actual tax paid in respect of the financial year in line with the provisions of the relevant Finance Acts by the concerned generating company or the transmission licensee, as the case may be. The actual tax paid on income from other businesses including deferred tax liability (i.e. income from business other than business of generation or transmission, as the case may be) shall be excluded for the calculation of effective tax rate.

    (2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below:

    Rate of pre-tax return on equity = Base rate / (1-t)

    Where "t" is the effective tax rate in accordance with clause (1) of this Regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non- transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), "t" shall be considered as MAT rate including surcharge and cess.

    Illustration-

    (i) In case of a generating company or a transmission licensee paying Minimum Alternate Tax (MAT) @ 21.55% including surcharge and cess:

    Rate of return on equity = 15.50/(1-0.2155) = 19.758%

    (ii) In case of a generating company or a transmission licensee paying normal corporate tax including surcharge and cess:

    (a) Estimated Gross Income from generation or transmission business for FY 2019-20 is Rs 1,000 crore;

    (b) Estimated Advance Tax for the year on above is Rs 240 crore;

    (c) Effective Tax Rate for the year 2019-20 = Rs 240 Crore/Rs 1000 Crore = 24%;

    (d) Rate of return on equity = 15.50/ (1-0.24) = 20.395%.

    (3) The generating company or the transmission licensee, as the case may be, shall true up the grossed up rate of return on equity at the end of every financial year based on actual tax paid together with any additional tax demand including interest thereon,

    Page 125 of 162

    duly adjusted for any refund of tax including interest received from the income tax authorities pertaining to the tariff period 2019-24 on actual gross income of any financial year. However, penalty, if any, arising on account of delay in deposit or short deposit of tax amount shall not be claimed by the generating company or the transmission licensee, as the case may be. Any under-recovery or over-recovery of grossed up rate on return on equity after truing up, shall be recovered or refunded to beneficiaries or the long term customers, as the case may be, on year to year basis."

    109. RoE allowed under Regulation 30 of the 2019 Tariff Regulations in respect of Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 is as follows:

    (₹ in lakh) Combined Asset (Asset-1 to Asset-17) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Opening Equity 37458.58 38084.67 38249.05 38249.05 38249.05 B Addition due to ACE 626.09 164.39 0.00 0.00 0.00 C Closing Equity (A+B) 38084.67 38249.05 38249.05 38249.05 38249.05 D Average Equity (A+C)/2 37771.62 38166.86 38249.05 38249.05 38249.05 Return on Equity (Base Rate) 15.50 15.50 15.50 15.50 15.50

    E

    (in %) F Tax Rate applicable (in %) 17.472 17.472 17.472 17.472 17.472 Rate of Return on Equity (Pre- 18.782 18.782 18.782 18.782 18.782

    G

    tax)

    Return on Equity (Pre-tax) 7094.27 7168.50 7183.94 7183.94 7183.94

    H

    (D*G) (₹ in lakh) Asset-18 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Opening Equity 175486.31 177177.34 177824.91 177832.71 177832.71 B Addition due to ACE 1691.02 647.57 7.80 0.00 0.00 C Closing Equity (A+B) 177177.34 177824.91 177832.71 177832.71 177832.71 D Average Equity (A+C)/2 176331.82 177501.12 177828.81 177832.71 177832.71 Return on Equity (Base 15.50 15.50 15.50 15.50 15.50

    E

    Rate) (in %) Tax Rate applicable (in 17.472 17.472 17.472 17.472 17.472

    F

    %) Rate of Return on Equity 18.782 18.782 18.782 18.782 18.782

    G

    (Pre-tax)

    Return on Equity (Pre- 33118.64 33338.26 33399.81 33400.54 33400.54

    H

    tax) (D*G) (₹ in lakh) Asset-19 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    A Opening Equity 47207.84 48686.22 48723.72 48723.72 48723.72 B Addition due to ACE 1478.38 37.51 0.00 0.00 0.00 C Closing Equity (A+B) 48686.22 48723.72 48723.72 48723.72 48723.72

    Page 126 of 162

    D Average Equity (A+C)/2 47947.03 48704.97 48723.72 48723.72 48723.72

    E Return on Equity (Base Rate) (in %) 15.50 15.50 15.50 15.50 15.50
    F Tax Rate applicable (in %) 17.472 17.472 17.472 17.472 17.472
    G Rate of Return on Equity (Pre- tax) 18.782 18.782 18.782 18.782 18.782
    H Return on Equity (Pre-tax) (D*G) 9005.41 9147.77 9151.29 9151.29 9151.29

    Operation & Maintenance Expenses ("O&M Expenses")

    110. The Petitioner has claimed the following O&M Expeses for the 2019-24 tariff period:

    (₹ in lakh) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Asset-1 to Asset-17

    Transmission line 502.94 520.50 538.75 557.74 577.16 Sub-station 1391.16 1440.46 1491.08 1543.92 1597.12

    PLCC 15.13 15.13 15.13 15.13 15.13

    Total O&M for Asset-1 to Asset-17 1909.23 1440.46 1491.08 1543.92 1597.12 Asset-18

    Transmission line 2318.21 2398.87 2483.04 2570.72 2660.15 Sub-station 1281.50 1326.50 1373.00 1421.00 1471.00 Total O&M for Asset-18

    Asset-19

    Transmission line 28.59 29.50 30.63 31.65 32.79 Sub-station 1281.50 1326.50 1373.00 1421.00 1471.00

    Total O&M for Asset-19 1310.09 1356.00 1403.63 1452.65 1503.79

    111. Regulation 35(3)(a) and Regulation 35(4) of the 2019 Tariff Regulations specify the norms for O&M Expenses which are as follows:

    "35 (3) Transmission system: (a) The following normative operation and maintenance expenses shall be admissible for the combined transmission system:

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24 Norms for sub-station Bays (₹ lakh per bay)

    765 kV 45.01 46.60 48.23 49.93 51.68 400 kV 32.15 33.28 34.45 35.66 36.91 220 kV 22.51 23.30 24.12 24.96 25.84 132 kV and below 16.08 16.64 17.23 17.83 18.46

    Norms for Transformers (₹ lakh per MVA)

    765 kV 0.491 0.508 0.526 0.545 0.564

    Page 127 of 162

    400 kV 0.358 0.371 0.384 0.398 0.411 220 kV 0.245 0.254 0.263 0.272 0.282 132 kV and below 0.245 0.254 0.263 0.272 0.282

    Norms for AC and HVDC lines (₹ lakh per km)

    Single Circuit (Bundled Conductor with six or more sub-conductors) 0.881 0.912 0.944 0.977 1.011 Single Circuit (Bundled conductor

    with four sub-conductors) 0.755 0.781 0.809 0.837 0.867 Single Circuit (Twin &

    Triple Conductor) 0.503 0.521 0.539 0.558 0.578 Single Circuit (Single Conductor) 0.252 0.260 0.270 0.279 0.289 Double Circuit (Bundled

    conductor with four or more 1.322 1.368 1.416 1.466 1.517 sub-conductors)

    Double Circuit (Twin &

    0.881 0.912 0.944 0.977 1.011

    Triple Conductor)

    Double Circuit (Single Conductor) 0.377 0.391 0.404 0.419 0.433 Multi Circuit (Bundled Conductor

    with four or more sub-conductor) 2.319 2.401 2.485 2.572 2.662 Multi Circuit (Twin &

    Triple Conductor) 1.544 1.598 1.654 1.713 1.773

    Norms for HVDC stations HVDC Back-to-Back stations (Rs Lakh per 500 MW) (Except 834 864 894 925 958 Gazuwaka BTB)

    Gazuwaka HVDC Back-to-Back

    station (₹ Lakh per 500 MW) 1,666 1,725 1,785 1,848 1,913 500 kV Rihand-Dadri HVDC

    bipole scheme (Rs Lakh) 2,252 2,331 2,413 2,498 2,586

    (1500 MW)

    ±500 kV Talcher- Kolar HVDC bipole scheme (Rs Lakh) (2000 2,468 2,555 2,645 2,738 2,834

    MW)

    ±500 kV Bhiwadi-Balia HVDC bipole scheme (Rs Lakh) (2500 1,696 1,756 1,817 1,881 1,947

    MW)

    ±800 kV, Bishwanath-Agra HVDC bipole scheme (Rs 2,563 2,653 2,746 2,842 2,942 Lakh) (3000 MW)

    Provided that the O&M expenses for the GIS bays shall be allowed as worked out by multiplying 0.70 of the O&M expenses of the normative O&M expenses for bays;

    Provided further that:

    i. the operation and maintenance expenses for new HVDC bi-pole schemes commissioned after 1.4.2019 for a particular year shall be allowed pro-rata

    Page 128 of 162

    on the basis of normative rate of operation and maintenance expenses of similar HVDC bi-pole scheme for the corresponding year of the tariff period;

    ii. the O&M expenses norms for HVDC bi-pole line shall be considered as Double Circuit quad AC line;

    iii. the O&M expenses of ±500 kV Mundra-Mohindergarh HVDC bipole scheme (2000 MW)shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±500 kV Talchar-Kolar HVDC bi-pole scheme (2000 MW);

    iv. the O&M expenses of ±800 kV Champa-Kurukshetra HVDC bi-pole scheme (3000 MW) shall be on the basis of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme;

    v. the O&M expenses of ±800 kV, Alipurduar-Agra HVDC bi-pole scheme (3000 MW)shall be allowed as worked out by multiplying 0.80 of the normative O&M expenses for ±800 kV, Bishwanath-Agra HVDC bi-pole scheme; and

    vi. the O&M expenses of Static Synchronous Compensator and Static Var Compensator shall be worked at 1.5% of original project cost as on commercial operation which shall be escalated at the rate of 3.51% to work out the O&M expenses during the tariff period. The O&M expenses of Static Synchronous Compensator and Static Var Compensator, if required, may be reviewed after three years.

    (b) The total allowable operation and maintenance expenses for the transmission system shall be calculated by multiplying the number of sub-station bays, transformer capacity of the transformer (in MVA) and km of line length with the applicable norms for the operation and maintenance expenses per bay, per MVA and per km respectively.

    (c) The Security Expenses and Capital Spares for transmission system shall be allowed separately after prudence check:

    Provided that the transmission licensee shall submit the assessment of the security requirement and estimated security expenses, the details of year-wise actual capital spares consumed at the time of truing up with appropriate justification.

    (4) Communication system: The operation and maintenance expenses for the communication system shall be worked out at 2.0% of the original project cost related to such communication system. The transmission licensee shall submit the actual operation and maintenance expenses for truing up."

    112. The Petitioner has claimed O&M Expenses as per Regulation 35(3)(a) of the 2019 Tariff Regulations. It is further observed that the Petitioner has claimed O&M Expenses separately for Asset-1 to Asset-17 towards PLCC under Regulation 35(4) of the 2019 Tariff Regulations @2% of its original project cost in the instant

    Page 129 of 162

    petition and the Petitioner has made similar claim in other petitions as well. Though PLCC is a communication system, it has been considered as part of the sub-station in the 2014 Tariff Regulations and 2019 Tariff Regulations and the norms for sub- station have been specified accordingly. Accordingly, the Commission vide order dated 24.1.2021 in Petition No. 126/TT/2020 has already concluded that no separate O&M Expenses can be allowed for PLCC under Regulation 35(4) of the 2019 Tariff Regulations even though PLCC is a communication system. Therefore, the Petitioner's claim for separate O&M Expenses for PLCC @2% is not allowed Asset-1 to Asset-17. The Petitioner has not claimed any O&M towards PLCC for Asset-18&Asset-19. Asset-1 to Asset-17 (AC assets) have been combined for 2019-24 tariff period. Accordingly, combined O&M Expenses have been worked out for Asset-1 to Asset-17. Further, O&M Expenses for Asset-18 and Asset-19, both being HVDC assets, have been calculated separately.

    113. Accordingly, O&M Expenses allowed in respect of Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 is as follows:

    Combined Asset (Asset-1 to Asset-17)

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    Double Circuit (bundle conductor with four sub-conductors) (km) 309.00 309.00 309.00 309.00 309.00
    Double Circuit (Twin & Triple Conductor) (km) 81.212 81.212 81.212 81.212 81.212
    Multi Circuit (Bundled Conductor with four or more sub-conductor) (km) 0.86 0.86 0.86 0.86 0.86
    Single Circuit (Twin & Triple Conductor) (km) 24.772 24.772 24.772 24.772 24.772
    Multi Circuit (Twin & Triple Conductor)(km) 1.158 1.158 1.158 1.158 1.158
    Double Circuit (Single Conductor) (km) 12.931 12.931 12.931 12.931 12.931
    400 kV Bays (Numbers) 26 26 26 26 26
    220 kV Bays (Numbers) 4 24 24 24 24
    132 kV & below Bays (Numbers) 6 12 12 12 12
    400 kV ICT (MVA)* 1030 1030 1030 1030 1030
    Sub-total O&M Expenses for transmission line (A) 501.16 518.65 536.84 555.77 575.12

    Page 130 of 162

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    Double Circuit (bundle conductor with four sub-conductors) (km) 309.00 309.00 309.00 309.00 309.00
    (₹ in lakh)
    Sub-total O&M Expenses for sub-station (B) (₹ in lakh) 1391.16 1440.45 1491.08 1543.92 1597.11
    Total O&M Expenses (A+B) (₹ in lakh) 1892.32 1959.10 2027.92 2099.69 2172.23

    *Total 4 numbers ICTs (2x200 MVA+2x315 MVA)=1030 MVA

    Asset-18

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    HVDC Transmission line (km) 1753.56 1753.56 1753.56 1753.56 1753.56
    One Pole (1500 MW) of ±800 kV, Bishwanath Chariali-Agra HVDC bi-pole scheme 1 1 1 1 1
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 2318.21 2398.87 2483.04 2570.72 2660.15
    Sub-total O&M Expenses for Sub- station (B) (₹ in lakh) 1281.50 1326.50 1373.00 1421.00 1471.00
    Total O&M Expenses (A+B) (₹ in lakh) 3599.71 3725.37 3856.04 3991.72 4131.15
    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    Single Circuit (Single Conductor) (km) 113.454 113.454 113.454 113.454 113.454
    One Pole (1500 MW) of ±800 kV, Bishwanath Chariali-Agra HVDC bipole scheme 1 1 1 1 1
    Sub-total O&M Expenses for transmission line (A) (₹ in lakh) 28.59 29.50 30.63 31.65 32.79
    Sub-total O&M Expenses for Sub- station (B) (₹ in lakh) 1281.50 1326.50 1373.00 1421.00 1471.00
    Total O&M Expenses (A+B) (₹ in lakh) 1310.09 1356.00 1403.63 1452.65 1503.79

    Interest on Working Capital ("IWC")

    114. Regulation 34(1)(c), Regulation 34(3) and Regulation 34(4) and Regulation 3(7) of the 2019 Tariff Regulations provide as follows:

    "34. Interest on Working Capital: (1) The working capital shall cover:

    (c) For Hydro Generating Station (including Pumped Storage Hydro Generating Station) and Transmission System:

    (i) Receivables equivalent to 45 days of annual fixed cost;

    Page 131 of 162

    (ii) Maintenance spares @ 15% of operation and maintenance expenses including security expenses; and

    (iii) Operation and maintenance expenses, including security expenses for one month."

    (3) Rate of interest on working capital shall be on normative basis and shall be considered as the bank rate as on 1.4.2019 or as on 1st April of the year during the tariff period 2019-24 in which the generating station or a unit thereof or the transmission system including communication system or element thereof, as the case may be, is declared under commercial operation, whichever is later:

    Provided that in case of truing-up, the rate of interest on working capital shall be considered at bank rate as on 1st April of each of the financial year during the tariff period 2019-24.

    (4) Interest on working capital shall be payable on normative basis notwithstanding that the generating company or the transmission licensee has not taken loan for working capital from any outside agency."

    "3. Definition - In these regulations, unless the context otherwise requires:-

    (7) 'Bank Rate' means the one year marginal cost of lending rate (MCLR) of the State Bank of India issued from time to time plus 350 basis points;"

    115. The components of the working capital and interest allowed thereon with respect to the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 are as follows:

    (₹ in lakh)

    Combined Asset (Asset-1 to Asset-17)
    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    A Working Capital for O&M Expenses (O&M expenses for one month) 157.69 163.26 168.99 174.97 181.02
    B Working Capital for Maintenance Spares (15% of O&M expenses) 283.85 293.87 304.19 314.95 325.83
    C Working Capital for Receivables (Equivalent to 45 days of annual fixed cost / annual transmission charges) 3420.38 3357.15 3264.47 3169.80 3066.50
    D Total of Working Capital 3861.92 3814.28 3737.65 3659.73 3573.35
    E Rate of Interest for Working Capital (in %) 12.05 11.25 10.5 10.5 10.5
    F Interest of working capital 465.36 429.11 392.45 384.27 375.20

    Page 132 of 162

    (₹ in lakh) Asset-18 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    Working Capital for O&M 299.98 310.45 321.34 332.64 344.26 A Expenses

    (O&M expenses for one month)

    Working Capital for Maintenance 539.96 558.81 578.41 598.76 619.67

    B

    Spares (15% of O&M expenses) Working Capital for Receivables 9761.31 9729.46 9618.73 9493.75 9340.76 (Equivalent to 45 days of annual

    C

    fixed cost / annual transmission charges)

    D Total of Working Capital 10,601.24 10,598.71 10,518.47 10,425.16 10,304.69 Rate of Interest for Working

    E 12.05 11.25 11.25 11.25 11.25

    Capital (in %)

    F Interest of working capital 1277.45 1192.36 1104.44 1094.64 1081.99 (₹ in lakh)

    Asset-19

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    Working Capital for O&M 109.17 113.00 116.97 121.05 125.32 A Expenses

    (O&M expenses for one month)

    Working Capital for Maintenance 196.51 203.40 210.54 217.90 225.57

    B

    Spares (15% of O&M expenses) Working Capital for Receivables 3326.54 3349.92 3311.54 3261.49 3202.86 (Equivalent to 45 days of annual

    C

    fixed cost / annual transmission charges)

    D Total of Working Capital 3632.23 3666.32 3639.06 3600.44 3553.74 Rate of Interest for Working

    E 12.05 11.25 11.25 11.25 11.25

    Capital (in %)

    F Interest of working capital 437.68 412.46 382.10 378.05 373.14 Annual Fixed Charges for 2019-24 Tariff Period

    116. The transmission charges allowed in respect of Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period are as follows:

    (₹ in lakh)

    Combined Asset (Asset-1 to Asset-17)
    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    Depreciation 9426.22 9493.60 9508.07 9508.07 9508.07
    Interest on Loan 8940.95 8179.94 7366.10 6534.67 5701.42
    Return on Equity 7094.27 7168.50 7183.94 7183.94 7183.94
    O&M Expenses 1892.32 1959.10 2027.92 2099.69 2172.23

    Page 133 of 162

    Combined Asset (Asset-1 to Asset-17) Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    Interest on Working 465.36 429.11 392.45 384.27 375.20 Capital

    Total 27819.12 27230.25 26478.48 25710.63 24940.86 (₹ in lakh)

    Asset-18

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    Depreciation 31587.91 31784.54 31842.22 31842.90 31842.90 Interest on Loan 9808.29 8876.19 7816.09 6675.09 5514.92 Return on Equity 33118.64 33338.26 33399.81 33400.54 33400.54 O&M Expenses 3599.71 3725.37 3856.04 3991.72 4131.15 Interest on Working 1277.47 1192.38 1104.46 1094.66 1082.01 Capital

    Total 79392.01 78916.72 78018.59 77004.89 75971.51

    (₹ in lakh) Asset-19 Particulars 2019-20 2020-21 2021-22 2022-23 2023-24

    Depreciation 11061.75 11183.74 11187.04 11187.04 11187.04 Interest on Loan 5240.94 5071.57 4736.22 4285.25 3834.64 Return on Equity 9005.41 9147.77 9151.29 9151.29 9151.29 O&M Expenses 1310.09 1356.00 1403.63 1452.65 1503.79 Interest on Working 437.68 412.46 382.10 378.05 373.14 Capital

    Total 27055.87 27171.54 26860.28 26454.28 26049.90 Filing Fee and Publication Expenses

    117. The Petitioner has sought reimbursement of fees paid by it for filing the petition and publication expenses in terms of Regulation 70(1) of the 2019 Tariff Regulations.

    118. Bihar Discoms has submitted that grant of filing fee and expenses incurred is strictly the discretion of the Commission and the same is to be exercised as per the facts and circumstances of each case and need not be necessarily allowed in all cases and certainly the present case is the one wherein the said prayer should not be granted. In response, the Petitioner has submitted that the Commission vide order dated 28.3.2016 in Petition No. 137/TT/2015 has rejected similar contention

    Page 134 of 162

    on the same issue and allowed recovery of petition filing fee and publication of notices from the beneficiaries on pro-rata basis as provided in the regulation and prayed that the same may be allowed.

    119. We have considered the submissions of the Petitioner and Bihar Discoms. The Petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with Regulation 70(1) of the 2019 Tariff Regulations.

    Licence Fee and RLDC Fees and Charges

    120. The Petitioner shall be entitled for reimbursement of licence fee in accordance with Regulation 70(4) of the 2019 Tariff Regulations for the 2019-24 tariff period. The Petitioner shall also be entitled for recovery of RLDC fee and charges in accordance with Regulations 70(3) of the 2019 Tariff Regulations for the 2019-24 tariff period.

    Goods and Services Tax

    121. The Petitioner has submitted that, if GST is levied at any rate and at any point of time in future on charges of transmission of electricity, the same has to be borne and additionally paid by the Respondent(s) to the Petitioner and the same will be charged and billed separately by the Petitioner. Further additional taxes, if any, are to be paid by the Petitioner on account of demand from Government/Statutory authorities, the same may be allowed to be recovered from the beneficiaries. MPPMCL and Bihar Discoms have submitted that the demand of the Petitioner is pre-mature and need not be considered at this juncture.

    Page 135 of 162

    122. We have considered the submissions of the Petitioner, MPPMCL and Bihar Discoms. GST is not levied on transmission service at present. Therefore, we are of the view that the Petitioner's prayer is premature.

    Security Expenses

    123. The Petitioner has submitted that security expenses in respect of the transmission assets are not claimed in the instant petition and it would file a separate petition for claiming the overall security expenses and the consequential

    IWC.

    124. We have considered the submissions of the Petitioner. The Petitioner has claimed consolidated security expenses on projected basis for 2019-24 tariff period on the basis of actual security expenses incurred in 2018-19 in Petition No. 260/MP/2020. The Commission vide order dated 3.8.2021 in Petition No. 260/MP/2020 approved security expenses from 1.4.2019 to 31.3.2024. Therefore, security expenses will be shared in terms of the order dated 3.8.2021 in Petition No. 260/MP/2020. Accordingly, the Petitioner's prayer in the instant petition for allowing it to file a separate petition for claiming the overall security expenses and consequential IWC has become infructuous.

    Capital Spares

    125. The Petitioner has sought reimbursement of capital spares at the end of tariff period. The Petitioner's claim, if any, shall be dealt with in accordance with the provisions of the 2019 Tariff Regulations.

    Sharing of Transmission Charges

    126. The Petitioner has submitted that the transmission charges for the

    Page 136 of 162

    transmission assets for 2014-19 and 2019-24 tariff periods with respect to Asset- 1 to Asset-17 will be shared by the beneficiaries and long term transmission customers under the applicable Sharing Regulations, as provided under Regulation 43 of the 2014 Tariff Regulations and Regulation 57 of the Tariff Regulations 2019 respectively. The Petitioner has further submitted that the transmission tariff for Asset-18 and Asset-19 will be shared from the DICs of all regions as per the provisions of the 2010 Sharing Regulations or as amended from time to time.

    127. We have considered the submissions of the Petitioner. The transmission charges approved for the transmission assets 1 to 17 covered in the instant order for 2014-19 tariff period and 2019-24 tariff period shall be governed by the applicable Sharing Regulations as provided under Regulation 43 of the 2014 Tariff Regulations and 57 of the 2019 Tariff Regulations respectively.

    128. The transmission charges in respect of Asset-18 and Asset-19 shall be shared by the DICs of all regions as per the provisions of the 2010 Sharing Regulations upto 31.10.2020 and from 1.11.2020, 100% of the Yearly Transmission Charges (YTC) shall be part of National Component as provided under Regulation 5(3)(b) of the 2020 Sharing Regulations.

    129. To summarise:

    (a) The trued-up AFC approved in respect of the transmission assets for 2014-19 tariff period are as follows:

    (₹ in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19
    Asset-1 486.58 507.77 504.38 497.23 489.69

    Page 137 of 162

    Asset-2 218.09 223.40 225.24 222.86 220.65
    Asset-3 163.93 178.98 189.23 184.17 185.57
    Asset-4 8001.45 20049.44 19572.73 18891.28 18342.49
    Asset-5 0.00 236.14 495.40 517.31 520.47
    Asset-6 0.00 150.96 325.16 343.96 344.43
    Asset-7 0.00 30.72 338.16 352.75 351.96
    Asset-8 0.00 392.95 1348.75 1401.38 1390.69
    Asset-9 0.00 401.49 869.16 857.04 879.74
    Asset-10 0.00 1129.05 2330.78 2348.94 2367.49
    Asset-11 0.00 0.00 0.00 137.22 214.00
    Asset-12 0.00 0.00 0.00 309.42 462.30
    Asset-13 0.00 0.00 0.00 135.23 464.98
    Asset-14 0.00 288.78 711.88 724.06 729.37
    Asset-15 0.00 595.11 1455.31 1444.29 1461.39
    Asset-16 0.00 289.82 611.70 620.76 626.81
    Asset-17 0.00 153.20 562.22 565.64 574.90
    Asset-18 0.00 46405.93 114917.14 116027.67 103125.58
    Asset-19 0.00 0.00 15159.93 28228.54 26229.38

    After adjustment of grants (₹ in lakh)

    Particulars 2018-2019
    Asset-18 10231.37
    Asset-19 3479.14

    (b) AFC allowed in respect of the Combined Asset (Asset-1 to Asset-17), Asset-18 and Asset-19 for 2019-24 tariff period in this order are as follows:

    (₹ in lakh)

    Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
    Combined Assets (Asset-1 to Asset-17) 27819.12 27230.25 26478.48 25710.63 24940.86
    Asset-18 79392.01 78916.72 78018.59 77004.89 75971.51
    Asset-19 27055.87 27171.54 26860.28 26454.28 26049.90

    130. Annexure-I and Annexure-II given hereinafter form part of the order.

    131. This order disposes of Petition No. 681/TT/2020 in terms of the above discussions and findings.

    sd/- sd/- sd/- (P. K. Singh) (Arun Goyal) (I. S. Jha) Member Member Member

    Page 138 of 162

    CERC Website S. No. 324/2023

    138

    Annexure-I Asset-1

    Aggregate d admitted cost as on 31.3.2014 Projected ACE Admitted cost as 31.3.2019 Rate of Depreciation as per Regulation (in %) Depreciation as per Regulation
    Capital expenditure s as on 31.03.2014 2014- 15 2015- 16 2016- 17 2017-18 2018- 19 Total 2014-15 2015-16 2016-17 2017-18 2018-19
    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
    Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00
    Building & Other Civil Works 78.35 29.70 2.35 0.00 0.00 0.00 32.05 110.40 3.34 3.11 3.65 3.69 3.69 3.69
    Transmission Line 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 0.00
    Sub-Station Equipments 2037.46 247.36 41.04 8.24 3.17 0.00 299.81 2337.27 5.28 114.11 121.72 123.02 123.32 123.41
    PLCC 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00 0.00
    Total 2115.81 277.06 43.39 8.24 3.17 0.00 331.86 2447.67 117.22 125.37 126.71 127.01 127.10
    Weighted average rate of depreciation (in %) 5.1998 5.1922 5.1922 5.1924 5.1925
    Average gross block 2254.34 2414.57 2440.38 2446.09 2447.67

    Page 139 of 162

    Asset-2 Previous Tariff Aggregated Projected ACE Admitted Rate of Depreciation as per Regulation Reference admitted cost as Depreciation

    cost as on 31.3.2019 as per

    31.3.2014 Regulation

    (in %)

    Capital 2014-15 2015-16 2016-17 2017-18 2018-19 Total 2014-15 2015-16 2016-17 2017-18 2018-19 Expenditures as

    on 31.3.2014

    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00 Building & Other 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00 Civil Works

    Transmission Line 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 0.00 Sub-Station 892.38 35.70 47.92 1.25 0.00 0.00 84.87 977.25 5.28 48.06 50.27 51.57 51.60 51.60 Equipments

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00 0.00

    Total 892.38 35.70 47.92 1.25 0.00 0.00 84.87 977.25 48.06 50.27 51.57 51.60 51.60 Weighted average 5.2800 5.2800 5.2800 5.2800 5.2800

    rate of depreciation (in %) Average Gross 910.23 952.04 976.625 977.25 977.25

    Block

    Page 140 of 162

    Asset-3

    Previous Tariff Reference Aggregate d admitted cost as on 31.03.2014 Projected ACE Admitted cost as 31.3.2019 Rate of Depreciatio n as per Regulation (in %) Depreciation as per Regulation
    Capital Expenditure s as on 31.3.2014 2014- 15 2015-16 2016- 17 2017- 18 2018- 19 Total 2014-15 2015-16 2016-17 2017-18 2018-19
    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
    Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00
    Building & Other Civil Works 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00
    Transmission Line 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 0.00
    Sub-Station Equipments 560.26 43.64 132.27 0.09 0.00 0.00 176.00 736.26 5.28 30.73 35.38 38.87 38.87 38.87
    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00 0.00
    Total 560.26 43.64 132.27 0.09 0.00 0.00 176.00 736.26 30.73 35.38 38.87 38.87 38.87
    Weighted average rate of depreciation (in %) 5.2800 5.2800 5.2800 5.2800 5.2800
    Average gross block 582.08 4 670.03 9 736.21 9 736.26 4 736.26 4

    Page 141 of 162

    Asset-4 Capital Admissib Rate of expenditur

    le capital Estimated Projected ACE Depreciati

    Depreciation as per Regulation cost as completion

    es as on on as per

    on COD cost as

    COD / Regulation for tariff 2014- 2015- 2016- 2017- 2018- Total 31.3.2019 1.4.2014 (in %) 2014-15 2015-16 2016-17 2017-18 2018-19 purpose 15 16 17 18 19

    Freehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00 Land

    Building & 63.60 0.93 0.00 139.98 1.81 0.00 142.72 206.33 3.34 2.14 2.16 4.49 6.86 6.89 Other Civil

    Works

    Transmissio

    102480.30 2273.21 1495.38 0.00 0.00 123.45 3892.04 106372.3 5.28 5470.97 5570.46 5609.94 5609.94 5613.20

    n Line 5

    Sub-Station 9199.98 937.93 0.00 719.07 209.09 237.95 2104.04 11304.02 5.28 510.52 535.28 554.27 578.77 590.57 Equipments

    PLCC 143.76 3.90 0.00 1.31 0.00 0.00 5.21 148.97 6.33 9.22 9.35 9.39 9.43 9.43

    Total 111887.65 3215.98 1495.38 860.36 210.90 361.40 6144.02 118031.67 5992.86 6117.25 6178.09 6205.00 6220.09 Weighted average 5.2803 5.2803 5.2791 5.2779 5.2779

    rate of depreciation (in %)

    Average gross block 113495.6 115851.3 117029.1 117564.82 117850.97

    4 2 9

    Page 142 of 162

    Asset-5 Capital Admissible capital cost Rate of Depreciation as expenditures Projected ACE Estimated completion Depreciation as per Regulation as on COD per Regulation

    as on COD / cost as 31.3.2019 for tariff (in %)

    1.4.2014 purpose 2015-16 2016-17 2017-18 2018-19 Total 2015-16 2016-17 2017-18 2018-19

    Freehold 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 478.30 14.01 113.57 31.58 20.37 179.53 657.83 3.34 16.21 18.34 20.76 21.63 Other Civil

    Works

    Transmission 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 Line

    Sub-Station 1732.49 23.74 192.40 53.51 34.52 304.17 2036.66 5.28 92.10 97.81 104.30 106.62 Equipments

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00

    Total 2266.61 37.75 305.97 85.09 54.89 483.70 2750.31 108.31 116.15 125.06 128.26 weighted average rate of depreciation (in %) 4.7391 4.7266 4.7143 4.7103

    Average gross block 2285.49 2457.35 2652.88 2722.87

    Page 143 of 162

    Asset-6 Admissible Rate of capital Estimated Capital expenditures cost as on Projected ACE Depreciation

    completion Depreciation as per Regulation as per

    as on COD / 1.4.2014 COD for cost as Regulation tariff 31.3.2019

    2015-16 2016-17 2017-18 2018-19 Total (in %) purpose 2015-16 2016-17 2017-18 2018-19

    Freehold Land 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Building & Other Civil 268.04 8.92 68.18 18.96 2.13 98.19 366.23 3.34 9.10 10.39 11.84 12.20 Works

    Transmission Line 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 Sub-Station Equipments 1124.68 23.46 179.34 49.88 5.60 258.28 1382.96 5.28 60.00 65.36 71.41 72.87

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00

    Total 1448.54 32.38 247.52 68.84 7.73 356.47 1805.01 69.10 75.75 83.25 85.07 Weighted average rate 4.7179 4.7203 4.7226 4.7230

    of depreciation (in %) average Gross block 1464.73 1604.68 1762.86 1801.15

    Page 144 of 162

    Asset-7 Capital Admissib expenditur

    le capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    01.04.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 317.44 5.28 44.46 12.22 0.96 62.91 380.35 3.34 10.69 11.52 12.47 12.69 Other Civil

    Works

    Transmissio 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 n Line

    Sub-Station 1177.12 27.18 149.4 41.06 2.85 220.57 1397.69 5.28 62.87 67.53 72.56 73.72 Equipments 8

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00

    Total 1550.37 32.46 193.94 53.28 3.81 283.49 1833.86 73.56 79.05 85.03 86.41 Weighted Average rate of depreciation 4.6955 4.7062 4.7150 4.7168

    (in %) Average gross block 1566.60 1679.80 1803.41 1831.96

    Page 145 of 162

    Asset-8 Capital Admissibl expenditur

    e capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 807.81 43.20 132.45 35.56 0.40 211.61 1019.42 3.34 27.70 30.64 33.44 34.04 Other Civil

    Works

    Transmissio 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 n Line

    Sub-Station 5344.13 227.96 639.83 169.53 1.88 1039.20 6383.33 5.28 288.19 311.10 332.46 336.99 Equipments

    PLCC 116.82 8.09 26.68 7.24 0.08 42.10 158.92 6.33 7.65 8.75 9.83 10.06

    Total 6268.76 279.25 798.97 212.33 2.36 1292.91 7561.67 323.54 350.49 375.73 381.09 Weighted average rate of depreciation 5.0487 5.0448 5.0413 5.0405

    (in %) Average Gross block 6408.39 6947.50 7453.15 7560.49

    Page 146 of 162

    Asset-9 Capital Admissib expenditur

    le capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 535.95 18.74 35.59 9.90 169.01 233.24 769.19 3.34 18.21 19.12 19.88 22.87 Other Civil

    Works

    Transmissio 1631.45 23.25 0.40 0.00 0.00 23.65 1655.10 5.28 86.75 87.38 87.39 87.39 n Line

    Sub-Station 1969.73 158.51 90.01 24.69 283.06 556.27 2526.00 5.28 108.19 114.75 117.78 125.90 Equipments

    PLCC 84.48 1.30 2.12 0.59 7.19 11.20 95.68 6.33 5.39 5.50 5.58 5.83

    Total 4277.43 201.80 128.12 35.18 459.26 824.36 5101.79 218.54 226.74 230.63 241.99 Weighted average rate of depreciation 4.9915 4.9907 4.9866 4.9667

    (in %) Average gross block 4378.33 4543.29 4624.94 4872.16

    Page 147 of 162

    Asset-10 Capital Admissib expenditur

    le capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 523.83 20.33 46.11 9.90 169.01 245.36 769.19 3.34 17.84 18.95 19.88 22.87 Other Civil

    Works

    Transmissi 9555.30 537.18 492.62 495.47 0.00 1525.27 11080.57 5.28 518.70 545.89 571.97 585.05 on Line

    Sub-Station 1911.94 161.81 130.89 24.69 283.06 600.45 2512.39 5.28 105.22 112.95 117.06 125.18 Equipments

    PLCC 78.54 1.53 3.70 0.59 7.19 13.00 91.54 6.33 5.02 5.18 5.32 5.57

    Total 12125.42 720.86 673.32 530.65 459.26 2384.09 14509.51 646.78 682.97 714.23 738.67 Weighted average rate of depreciation 5.1801 5.1807 5.1813 5.1728

    (in %) Average gross block 12485.85 13182.94 13784.93 14279.88

    Page 148 of 162

    Asset-11 Admissible Rate of capital cost Estimated Depreciation as per Capital expenditures as on COD / Projected ACE Depreciation as as on COD completion cost Regulation

    1.4.2014 per Regulation for tariff as 31.3.2019 (in %)

    purpose 2017-18 2018-19 Total 2017-18 2018-19

    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 Building & Other Civil Works 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 Transmission Line 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 Sub-Station Equipments 1279.02 70.41 79.09 149.50 1428.53 5.28 69.39 73.34

    PLCC 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00

    Total 1279.02 70.41 79.09 149.50 1428.53 69.39 73.34 Weighted average rate of 5.2800 5.2800

    depreciation (in %) Average gross block 1314.23 1388.98

    Page 149 of 162

    Asset-12 Admissible Rate of capital cost Estimated Depreciation as per Capital expenditures as on COD / Projected ACE Depreciation as as on COD completion cost Regulation

    1.4.2014 per Regulation for tariff as 31.3.2019 (in %)

    purpose 2017-18 2018-19 Total 2017-18 2018-19

    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 Building & Other Civil Works 497.85 18.92 30.69 49.62 547.47 3.34 16.94 17.77 Transmission Line 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 Sub-Station Equipments 1861.61 80.33 162.08 242.40 2104.01 5.28 100.41 106.81

    PLCC 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00

    Total 2359.46 99.25 192.77 292.02 2651.48 117.36 124.59 Weighted average rate of 4.8715 4.8760

    depreciation (in %) Average gross block 2409.09 2555.10

    Page 150 of 162

    Asset-13 Admissible Rate of Estimated Depreciation as per Capital expenditures as on COD / capital cost as Projected ACE Depreciation as completion cost Regulation

    1.4.2014 on COD for tariff per Regulation as 31.3.2019 purpose (in %)

    2017-18 2018-19 Total 2017-18 2018-19

    Freehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 Building & Other Civil Works 489.63 26.22 30.45 56.67 546.30 3.34 16.79 17.74 Transmission Line 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 Sub-Station Equipments 1853.74 105.16 143.35 248.51 2102.25 5.28 100.65 107.21

    PLCC 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00

    Total 2343.37 131.38 173.80 305.18 2648.55 117.45 124.95 Weighted average rate of 4.8751 4.8778

    depreciation (in %) Average gross block 2409.06 2561.65

    Page 151 of 162

    Asset-14 Capital Admissibl expenditure

    e capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    s as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 111.63 0.00 0.00 0.00 0.00 0.00 111.63 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 228.04 24.88 11.30 7.02 2.44 45.65 273.69 3.34 8.03 8.64 8.94 9.10 Other Civil

    Works

    Transmissio 738.58 59.85 0.24 0.00 0.00 60.09 798.67 5.28 40.58 42.16 42.17 42.17 n Line

    Sub-Station 1079.85 200.70 104.42 65.10 22.72 392.93 1472.78 5.28 62.31 70.37 74.84 77.16 Equipments

    PLCC 75.66 10.43 5.07 3.16 0.79 19.46 95.12 6.33 5.12 5.61 5.87 6.00

    Total 2233.77 295.86 121.03 75.28 25.95 518.12 2751.89 116.04 126.78 131.83 134.43 Weighted average rate of depreciation 4.8723 4.8947 4.9038 4.9081

    (in %) average gross block 2381.70 2590.15 2688.30 2738.91

    Page 152 of 162

    Asset-15 Capital Admissib expenditur

    le capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 111.63 0.00 0.00 0.00 0.00 0.00 111.63 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 234.93 18.07 11.23 7.02 2.44 38.76 273.69 3.34 8.15 8.64 8.94 9.10 Other Civil

    Works

    Transmissio 5404.59 733.76 148.84 269.38 314.68 1466.66 6871.25 5.28 304.73 328.03 339.08 354.49 n Line

    Sub-Station 1112.46 168.43 104.07 65.10 22.73 360.33 1472.79 5.28 63.18 70.38 74.84 77.16 Equipments

    PLCC 77.95 8.18 5.05 3.16 0.79 17.18 95.13 6.33 5.19 5.61 5.87 6.00

    Total 6941.56 928.44 269.19 344.66 340.64 1882.93 8824.49 381.26 412.66 428.73 446.75 Weighted average rate of depreciation 5.1481 5.1553 5.1583 5.1623

    (in %) average gross block 7405.78 8004.59 8311.52 8654.17

    Page 153 of 162

    Asset-16 Capital Admissibl Expenditure

    e capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    s as on completion cost as as per Regulation

    on COD

    COD 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 111.63 0.00 0.00 0.00 0.00 0.00 111.63 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 229.82 11.56 17.13 10.72 0.22 39.63 269.45 3.34 7.87 8.35 8.81 9.00 Other Civil

    Works

    Transmissio 952.78 155.38 29.60 47.16 63.05 295.19 1247.97 5.28 54.41 59.29 61.32 64.23 n Line

    Sub-Station 1212.19 123.40 158.12 98.90 2.11 382.53 1594.72 5.28 67.26 74.69 81.48 84.15 Equipments

    PLCC 22.47 3.52 5.21 3.26 0.07 12.06 34.53 6.33 1.53 1.81 2.08 2.18

    Total 2528.89 293.86 210.06 160.04 65.45 729.41 3258.30 131.07 144.14 153.69 159.55 Weighted average rate of depreciation 4.8984 4.9233 4.9373 4.9465

    (in %) Average gross block 2675.82 2927.78 3112.83 3225.58

    Page 154 of 162

    Asset-17 Capital Admissibl expenditur

    e capital Projected ACE Estimated Rate of Depreciation Depreciation as per Regulation cost as

    es as on completion cost as as per Regulation

    on COD

    COD / 31.3.2019 (in %) for tariff

    1.4.2014 2015- 2016- 2017- 2018- Total 2015-16 2016-17 2017-18 2018-19 purpose 16 17 18 19

    Freehold 55.82 0.00 0.00 0.00 0.00 0.00 55.82 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 326.10 41.89 21.93 13.72 30.09 107.63 433.73 3.34 11.59 12.66 13.25 13.98 Other Civil

    Works

    Transmissio 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 0.00 0.00 0.00 0.00 n Line

    Sub-Station 2185.64 197.40 98.14 61.38 134.71 491.63 2677.27 5.28 120.61 128.42 132.63 137.80 Equipments

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00

    Total 2567.56 239.29 120.07 75.10 164.80 599.26 3166.82 132.20 141.07 145.88 151.79 Weighted average rate of depreciation 4.9198 4.9208 4.9209 4.9211

    (in %) Average gross block 2687.21 2866.89 2964.47 3084.42

    Page 155 of 162

    Asset-18 Admissi Capital ble expenditur capital Projected ACE Rate of

    Estimated Depreciation as per Regulation Depreciation as

    es as on cost as completion cost as per Regulation

    COD / on COD on 13.2.2019 for tariff 2015- 2016- 2017- 2018-19 Total (in %) 2015-16 2016-17 2017-18 2018-19

    1.4.2014

    purpose 16 17 18 1.4.2018-

    13.2.2019

    0.8739726

    03

    Freehold 1826.55 0.00 0.00 0.00 0.00 0.00 1826.55 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 Land

    Building & 17832.1 1365. 4128. 1959. 768.88 8222.89 26055.03 3.34 618.40 710.16 811.83 857.40 Other Civil 4 89 48 64

    Works

    Transmissi

    608440.28 14230.92 12844.02 7143.15 5462.19 39680.28 648120.56 5.28 32501.34 33216.12 33743.78 34076.56

    on Line

    Sub-

    172013.35 3717.24 10379.84 6280.25 2829.50 23206.83 195220.17 5.28 9180.44 9552.60 9992.43 10232.93

    Station

    Equipment

    s

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00

    Total 800112.31 19314.05 27352.35 15383.04 9060.56 71110.00 871222.31 42300.19 43478.88 44548.04 45166.89 Weighted average rate of 5.2237 5.2189 5.2135 5.2114

    depreciation (in %) Average gross block 809769.34 833102.53 854470.23 866692.03

    Page 156 of 162

    Asset-18 after grants Capital Expenditures as Admissible Projected ACE Estimated Rate of 2018-19 on COD / 1.11.2015 capital cost completion cost depreciation (14.2.2019- as on COD 2016-17 2017-18 2018-19 as on 31.3.2019 as per 31.3.2019) for tariff Regulation

    purpose

    Pro-rata period 0.126027397

    Freehold Land 1826.55 563.96 1262.59 0.00 1262.59 0.00% 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 3.34% 0.00 Building & Other Civil 26055.03 8044.70 18010.33 110.87 18121.20 3.34% 603.40 Works

    Transmission Line 648120.56 200112.48 448008.08 787.65 448795.73 5.28% 23675.62 Sub-Station Equipments 195220.17 60275.81 134944.36 408.01 135352.38 5.28% 7135.83 PLCC 0.00 0.00 0.00 0.00 0.00 6.33% 0.00

    Total 871222.31 268996.95 602225.36 1306.54 603531.90 31414.85 Weighted Average rate of 5.2108

    depreciation (in %) Average gross block 602878.63

    Page 157 of 162

    Asset-19 Admissible Capital capital Rate of expenditures cost as on Projected ACE Estimated

    Depreciation as per Depreciation as per Regulation completion cost as

    as on COD / COD for Regulation 13.2.2019 1.4.2014 tariff (in %)

    purpose 2016-17 2017-18 2018-19 Total 2016-17 2017-18 2018-19

    0.8740

    Freehold Land 2473.59 0.00 0.00 0.00 0.00 2473.59 0.00 0.00 0.00 0.00 Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 Land

    Building & 14676.53 2144.84 2497.32 22.54 4664.70 19341.23 3.34 526.01 603.54 645.62 Other Civil

    Works

    Transmission 21097.16 5430.64 528.14 685.99 6644.77 27741.93 5.28 1257.30 1414.61 1446.66 Line

    Sub-Station 170133.72 7630.50 8423.21 73.73 16127.44 186261.16 5.28 9184.51 9608.32 9832.64 Equipments

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00

    Total 208381.00 15205.98 11448.67 782.26 27436.91 235817.90 10967.82 11626.47 11924.93 Weighted average rate of depreciation 5.0781 5.0702 5.0652

    (in %) Average gross block 215983.99 229311.31 235426.77

    Page 158 of 162

    Asset-19 after grants Admitted Capital ACE for Admitted cost Rate of Cost as cost as on 46 days as 31.3.2019 Depreciation Capital expenditures as on COD /

    on 14.2.2019 during18- as per

    1.11.2015

    13.2.2019 19 Regulation 2018-19 (from 01.04.2014-13.02.2019) (in %)

    Prorata period 0.126027397

    Freehold Land 2473.59 2264.82 0.00 2264.82 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 3.34 0.00 Building & Other Civil Works 19341.23 17708.83 3.25 17712.08 3.34 591.47 Transmission Line 27741.93 25400.51 98.92 25499.43 5.28 1341.15 Sub-Station Equipments 186261.16 170540.70 10.63 170551.33 5.28 9004.55

    PLCC 0.00 0.00 0.00 0.00 6.33 0.00

    Total 235817.90 215914.85 112.80 216027.66 10937.17 Weighted average rate of 5.0642

    depreciation (in %) Average gross block 215971.25

    Page 159 of 162

    Annexure-II Asset-1-Asset-17 (2019-24)

    Projected ACE Admitted cost as 31.3.2024 Rate of Depreciation as per Regulation (in %) Depreciation as per Regulation
    Capital Expenditure Combined admitted capital cost as on 1.4.2014 2019- 20 2019- 2020 2020- 21 2021- 22 2022- 23 2023- 24 Total 2019-20 2020-21 2021-22 2022-23 2023-24
    Freehold Land 669.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 669.81 0.00 0.00 0.00 0.00 0.00 0.00
    Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00
    Building & Other Civil 6623.27 244.94 244.94 0.00 0.00 0.00 0.00 244.94 6868.21 3.34 225.31 229.40 229.40 229.40 229.40
    Transmissi on Line 128025.91 839.71 -19.64 820.07 547.95 0.00 0.00 0.00 1368.02 129393.93 5.28 6781.42 6817.53 6832.00 6832.00 6832.00
    Sub-Station Equipments 44446.19 985.57 985.57 0.00 0.00 0.00 0.00 985.57 45431.76 5.28 2372.78 2398.80 2398.80 2398.80 2398.80
    PLCC 719.89 36.39 36.39 0.00 0.00 0.00 0.00 36.39 756.28 6.33 46.72 47.87 47.87 47.87 47.87
    Total 180485.06 2106.61 2086.97 547.95 0.00 0.00 0.00 2634.92 183119.98 9426.22 9493.60 9508.07 9508.07 9508.07
    Weighted average rate of depreciation (in %) 5.1927 5.1921 5.1923 5.1923 5.1923
    Average gross block 181528.55 182846.01 183119.98 183119.98 183119.98

    Page 160 of 162

    Asset-18 (2019-24) Rate of

    Capital Admissible Projected ACE Estimated depreciation Depreciation as per Regulation expenditures capital cost completion

    as per

    as on COD/ as on cost as

    1.4.2019 31.3.2019 2021- 2022- 2023-

    Regulation 33

    2019-20 2020-21 Total 31.3.2024 2019-20 2020-21 2021-22 2022-23 2023-24 22 23 24 (in %)

    Freehold Land 1262.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1262.59 0.00 0.00 0.00 0.00 0.00 0.00 Leasehold Land 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00 Building & Other 18121.20 944.79 944.79 0.00 0.00 0.00 0.00 944.79 19065.99 3.34 621.03 636.80 636.80 636.80 636.80 Civil Works

    Transmission 448795.73 1362.63 - 1215.04 2158.57 26.00 3399.61 452195.34 5.28 23728.49 23817.56 23875.23 23875.91 23875.91 Line 147.59

    Sub-Station 3476.89 3476.89 0.00 0.00 0.00 0.00 3476.89 138829.27 5.28 7238.40 7330.19 7330.19 7330.19 7,330.19 Equipments 1,35,352.38

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00 0.00

    IT assets 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00

    - Total 603531.90 5784.31 147.59 5636.72 2158.57 26.00 - - 7821.29 611353.19 31587.91 31784.54 31842.22 31842.90 31,842.90

    - Weighted average rate of 5.2095 5.2085 5.2086 5.2086 5.2086

    depreciation (in %) Average gross block 606350.26 610247.90 611340.19 611353.19 611353.19

    Page 161 of 162

    Asset-19 (2019-24) Capital Admissible capital Projected ACE Estimated Rate of Depreciation as per Regulation expenditure cost as on completion depreciation as

    s as on 31.3.2019 cost as per Regulation 33

    COD/ 2019-20 2020-21 2021- 2022- 2023- Total 31.3.2024 (in %) 2019-20 2020-21 2021-22 2022-23 2023-24

    1.4.2019 22 23 24

    Freehold 2264.82 30.00 0.00 0.00 0.00 0.00 30.00 2294.82 0.00 0.00 0.00 0.00 0.00 0.00 Land

    Leasehold 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.34 0.00 0.00 0.00 0.00 0.00 Land

    Building & 17712.08 1094.36 0.00 0.00 0.00 0.00 1094.36 18806.44 3.34 609.86 628.13 628.13 628.13 628.13 Other Civil

    Works

    Transmission 25499.43 126.38 125.02 0.00 0.00 0.00 251.40 25750.83 5.28 1349.71 1356.34 1359.64 1359.64 1359.64 Line

    Sub-Station 3 6 7 7 .18 0.00 0.00 0.00 0.00 3677.18 174228.51 5.28 9199.27 9,199.27 9,199.27 Equipments 1,70,551.33 9,102.19 9,199.27

    PLCC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 0.00 0.00 0.00 0.00 0.00

    IT assets 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.00 0.00 0.00 0.00 0.00 0.00

    Total - - 5052.94 2,21,080.60 11,061.75 11,183.74 11187.04 11,187.04 11,187.04 2,16,027.66 4,927.92 125.02 -

    - Weighted average rate of 5.0628 5.0601 5.0602 5.0602 5.0602

    depreciation (in %)

    average gross block 218491.62 221018.09 221080.60 221080.60 221080.60

    Page 162 of 162