ORDER
1. Grievance in this application is against pollution of rivers Varuna and Assi in Varanasi by discharge of untreated sewage and unauthorized constructions. Case set out in the application is that the above rivers are tributaries of river Ganga and cleaning of river Ganga cannot be imagined without first ensuring prevention of pollution of the said rivers. The pollution of the said rivers is subject matter of various media reports. Water quality of river Ganga at Varanasi is in bad condition. Fecal coliform bacteria count at Varun-Ganga confluence is 71 million per 100ML of water (Ganga Jal) and fecal coliform count at Assi River and Ganga confluence is 52 Million per 100ML of water and on Assi Ghat fecal coliform is 1 lakh 40 thousand per 100ML of Ganga Jal. Permissible limit of fecal coliform bacteria should not exceed 500 per 100ML of water. Reference has been made to a report on water quality prepared by Sankat Mochan
1
Foundation in Varanasi. It is further stated that there is concrete construction inside Ganga water channel at Lalita Ghat.
2. Vide order dated 17.06.2021, considering the seriousness of the issue and in the light of judgment of the Hon'ble Supreme Court in Paryavaran Suraksha case1
and orders of this Tribunal in O.A. No. 593/2017, Paryavaran Suraksha Samiti & Anr. v. Union of India & Ors., O.A. No. 673/2018, In Re: News item published in "The Hindu" authored by Shri Jacob Koshy, titled "More river stretches are now critically polluted:
CPCB" and O.A. No. 200/2014, M.C. Mehta v. UOI & Ors. (relating to river Ganga), the Tribunal constituted an independent Monitoring Committee comprising of Central Pollution Control Board (CPCB), State PCB, National Mission for Clean Ganga (NMCG) and District Magistrate, Varanasi to ascertain the factual status and take remedial action. NMCG was directed to file an action taken report in OA No. 200/2014, relating to rejuvenation of River Ganga, inter alia covering status on water quality of Assi and Varuna, action taken on diversion and treatment of sewage, water quality of upstream and downstream of confluence of Assi and Varuna to River Ganga, demarcation of Flood Plain Zones of Assi, Varuna and Ganga (in the said area), in accordance with the River Ganga (Rejuvenation, Protection and Management) Authorities Order, 2016.
3. Accordingly, an action taken report has been filed on 18.08.2021 by the U.P. State PCB on behalf of the joint Committee. The report mentions the minutes of meeting held on 30.06.2021 at CPCB attended by Dr. A. K. Vidyarthi, Additional Director & DH, WQM-II representing CPCB, Sh. Kalika Singh, RO, UPPCB, Varanasi representing State PCB, Sh. Rajat Gupta, SWM Specialist representing National Mission for Clean Ganga
2
(NMCG) and Sh. Gulab Chand, ADM representing District Magistrate, Varanasi. In the said meeting action plan for river Varuna, prepared in pursuance of orders of this Tribunal in OA No. 673/2018, was discussed and revised. Issues of prevention of river water pollution, river ecosystem study and groundwater recharge, sewage and surface runoff management and encroachment were identified and addressing of gaps was planned. Thereafter, water quality was monitored and river restoration plan updated. Survey of all the concerned drains, tributaries was also undertaken. The revised action plan covering Restoration and rejuvenation of Varuna River and Restoration and rejuvenation of Assi River has been proposed which includes steps like de-silting, remediation of waste, development of floodplain, bio-diversity parks, sewage management, sludge management, industrial pollution management, solid waste management, removal of encroachments and monitoring mechanism.
4. The action plan proposed is reproduced below:
"Chapter 4. Action Plan Action Plan, Work Plan, Timelines and Implementing Agencies for restoration and rejuvenation of Varuna and Assi Rivers, Varanasi
Riverscape restoration and rejuvenation of Varuna and Assi A. Restoration and rejuvenation of Varuna River Action Plan 1: Restoration of catchment wetlands located at the origin and downstream from the origin before joining Basuhi river (in this stretch the river is not polluted and does not have water in dry season).
Table 4.1 Action Plan for Restoration and rejuvenation of Varuna River
S. No Work Plan Timeline Implementing Agency
3
| 1. |
Desilting of wetlands upto the bed level and developing embankments with inlets from the catchment Location: i) Mailhan, Phulpur, Prayagr aj (25.599 571N, 82.1073 91E) |
10 - 12 months |
UP Irrigation and Water Resource Department under the guidance of CEMDE |
| 2. |
Development of Biotic Communities (at both the above locations and other sites including embankments. |
|
CEMDE, University of Delhi |
Action Plan 2: Restoration of Basuhi and Morwa tributaries. Both the tributaries have clean water. However, two drains meet Morwa having small quantity of discharge which get diluted and carry clean water from their catchments and irrigation canal water to Varuna.
Table 4.2 Action Plan for Restoration of Basuhi and Morwa tributaries
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Desilting of channels if it is not done during last 10 year Location: I. Upardaha Taal/Wetland in Handia of Prayagraj district II. Kaitihawa, Tara (a small Pond) nearby Jigna Taal area in Handia, District Prayagraj (U.P) (25.38836 and 82.29644) |
6 months |
Irrigation and Water Resource Department |
| ii. |
Vegetation development along the embankments and restoration riparian zone |
2 years |
CEMDE |
Action Plan 3: Remediation of waste water that is discharged into Morwa (from two drains) and three major drains Dhoraira drain, Durga drain, Basti/ Naya Bazar drain that discharge sewage and industrial waste water into Varuna.
Table 4.3 Remediation of waste water that is discharged into Morwa
S. No Work Plan Timeline Implementing Agency
4
| i. |
Remediation of waste water using Constructed Wetland System. A schematic Constructed Wetland System (CWS) is attached. These CWS are set up at the confluence of the drain with the tributary/river and extend upto 100 m in the upstream from the confluence point. The length of CWS and number of units depends on the flow of water, the BoD, CoD, TSS and DO levels of water and width of the drain. Locations: i) Dhoraira drain on Varuna at Bhadohi (25.417900N, 82.567600E) ii) Basti/ Naya Bazar drain on Varuna at Bhadohi (25.415251N, 82.576675E) iii)Durga drain on Varuna at Danyalpur, Varanasi (25.320033N, 82.955642E) iv) Burbuspur drain on Morwa at Rampura, Bhadohi (25.409475 N, 82.556622 E) v) Chauri Drain on Morwa at Kom, Bhadohi (25.369723N, 82.606431E) |
1-2 years |
Designed by CEMDE and Implemented by Irrigation and water Resource Department under guidance of CEMDE, water quality will be monitored by UPPCB |
| i. |
Desilting of drains upto bed level and strengthening of bunds with desilted material if not done during the last 5 year |
1 year |
Irrigation and Water Resource Department |
| ii. |
Vegetation development on embankments of restored drain |
|
CEMDE |
Action Plan 4: Development of Floodplain Biodiversity Park at Adikeshwar Ghat where Varuna joins Ganga not only to enhance the water quality in Ganga in the stretch but also further enhance the quality of water of Varuna before discharged into Ganga by passing through treatment wetlands. The Biodiversity also help in restoring of riparian ecosystems and in stream community and also provide aesthetic and recreation value to Ganga.
Table 4.4 Development of Floodplain Biodiversity Park
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Plan, Design and Development of Biodiversity Park. A schematic layout of a typical floodplains Biodiversity Park is attached. |
5 years |
CEMDE Irrigation and Water Resource Department (supporting structure) UPPCB (monitoring water quality) |
Action Plan 5: Desilting of river Varuna in stretches where heavy sedimentation has taken place.
Table 4.5 Desilting of river Varuna
5
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Desilting of river and Strengthening of embankments using desilted material |
2 years |
Irrigation and Water Resource Department |
| ii. |
Vegetation Development on embankments |
5 years |
CEMDE |
Action Plan 6: Monitoring of water quality at different sampling sites to assess the health of river ecosystems.
Table 4.6 Monitoring of water quality
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Monitoring of water quality as per CPCB norms for river water before, during and after restoration |
5 years |
UPPCB |
B. Restoration and rejuvenation of Assi River Action Plan 1: Restoration of catchment wetlands at the point of origin and other wetland in the downstream to enhance the flow rates of water in the river.
Table 4.7 Restoration and rejuvenation of Assi River
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
esilting of catchment wetlands and use of esilted material for making embankments ith inlets andwa wetland at Varanasi point of rigin (25.273258 N, 82.962083 E) nd other wetland located in the ownstream from the point of origin. |
6 months |
Irrigation and Water Resource Department |
| ii. |
Remediation of sewage water that enters into catchment wetland using CWS at the mouth of the inlets before the confluence point. The length of wetland depends upon the flow of sewage and depth of water. A schematic layout of a typical CWS is attached. |
1 year |
CEMDE and Irrigation and Water Resource Department |
| iii. |
Vegetation Development on the embankment and development of aquatic communities in the wetland. |
2-3 years |
CEMDE |
Action Plan 2: Remediation of sewage + household industrial waste water using Constructed Wetlands at stretches in the river where width is maximum with one largest CWS at 100 m away from the confluence of river with Ganga.
6
Table 4.8 Remediation of sewage and household industrial waste water using Constructed Wetlands
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Setting up of CWS at 4 locations where width of river is maximum. The length of CWS depends upon the volume of water, quality of water, width of river. The riparian zones will also be restored. |
2 years |
CEMDE and Irrigation and Water Resource Department |
Action Plan 3: Desiltation of river, if not desilted during the last 5 years and use of desilted material for strengthening of embankments wherever possible.
Table 4.9 Desiltation of river
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Desilting of river up to the bed level and strengthening of embankment with desilted material |
1 year |
Irrigation and Water Resource Department |
| ii. |
Development of vegetation on embankment wherever possible and restoration of riparian zone. |
2-3 years |
CEMDE |
Action Plan 4: Development of Floodplain Biodiversity Parks at the Assi Ghat, from the historical confluence of Assi with Ganga, to the point where diverted. About 25 years ago the Assi River was diverted towards Ravidas Park from Nagwa road and it passes through Nagwa Colony and known as Nagwa drain before confluence with River Ganga. The old route of River Assi which is about 700 meters (from the point of interception Udupi Shri Krishna Madhav Temple to Sant Ravidas Park) carries household sewage and discharge into Nagwa drain. This may help in restoring the original Ghat where Assi used to confluence with Ganga and also enhance the quality of Ganga water.
Table 4.10 Development of Floodplain Biodiversity Parks
| S. No |
Work Plan |
Timeline |
Implementing Agency |
| i. |
Plan, design and develop Biodiversity Park |
5 years |
CEMDE, Irrigation and Water Resource Department |
Action Plan 5: Monitoring quality of water for sustaining the health of restored river ecosystem.
Table 4.11 Monitoring of water Quality S. No Work Plan Timeline Implementing Agency
7
i. Monitoring of water quality as per 5 years UPPCB CPCB norms before and after
restoration
Figure 4.1 Schematic Diagram of Constructed Wetland Figure 4.2 Schematic Diagram of Biodiversity Park
8
Sewage Management A. Introduction
Varanasi city is presently divided into four sewerage districts located within current municipal corporation limits. Under the present sewerage master plan the existing districts are re-aggregated into 4 Districts to correspond roughly with natural drainage catchments. These Districts are described as follows:
District 1: District 1 is the Central City Sewerage District draining to
80 MLD Dinapur STP via 6 no. sewerage pumping stations. This area includes the old city, about 1km in breadth and 5km along the Ganga river from Assi to Raj Ghat. Density in this area is very high.
District 2: District 2 is further bifurcated in 3 zones name 2A,2B,2C & Future Sewerage Area 1 (FSA1). Zone 2A is the Sub-Central District on the cis-Varuna side west of the city centre and zone 2B is a slice of the trans-Varuna district along the Varuna river up to the ridge line defined by the Jaunpur road. Wastewater in these two zones will be collected at 140 MLD Chauka ghat MPS and finally treated in 140 MLD STP at Dinapur
District 2 Zone 2C: Zone 2C is the trans-Varuna District north of the Jaunpur road. Wastewater in this area generally falls to the north and to the east. FSA1 is north of the trans-Varuna District just outside the current Municipal Corporation limit. Wastewater generated in this area tends to flow north and east towards 120 MLD STP Goithaha.
District 3: District 3 is the BHU/Assi District south of the city including FSA 4. At present this area is mainly the Banares Hindu University campus which is fully sewered. Wastewater discharged in this area follows natural drains flowing into river Assi nala and Nakkhi nala. FSA4 is outside the current Municipal Corporation limit and surrounds the area occupied by BHU campus. Wastewater in this area drains to Assi river and Nakkhi nala which discharge to Ganga river upstream of the water supply intake and Ghats.currently 2 STP namely 50 MLD Ramana STP and 8 MLD Bhagwanpur STP are in service in district 3.
District 4: District 4 include FSA-2 and FSA-3 area which is outside the current Municipal Corporation limit. FSA2 is west of the current Municipal Corporation limit, and bounded by North-eastern railway. FSA3 is west of FSA2 and bounded by the Northern railway line. Currently there is no sewage treatment facility available in district 4.
9
Figure 4.3 Schematic representation of sewerage district of Varanasi city
Non-Sewerage Areas (NSA)
Non-serviced areas are identified as follows:
NWA1: NSA1 is within current Municipal Corporation limits to the east of the Trans-Varuna district. It includes the local community of Sarnath. Wastewater generated in this area drains naturally into Narokar nala which is now diverted to 120 MLD Goithaha via Intermediate Pumping Station.
NSA2: NSA2 is within current Municipal Corporation limits to the extreme north west of the trans-Varuna District. Sewage generation will be diverted to 120 MLD GoithahaVaranasi
B. Sewerage master plan- 2005 (JAPAN INTERNATIONAL COOPERATION AGENCY-JICA)
JICA formulated sewerage masterplan in 2005. The plan for 2015 is explained in (Figure 1)
10
Figure 4.4: JICA Sewerage Plan for 2015
As per JICA masterplan-2005 (figure 1) the projected population in Assi catchment area for the year 2015 is 78335 + 214570 = 292,905. The projected sewage generation was 14.5 + 39.7 = 54.2 MLD. To cater 54.2 MLD, 8.0 MLD is to be treated by 8.0 MLD existing Bhagwanpur STP and new proposed 37 MLD at Ramna.
The plan for 2030 is explained in Figure 2
Figure 4.5: JICA Sewerage Plan for 2030
As per JICA masterplan-2005 (above) the projected population for the year 2030 is 182781 + 291188 = 476969. The projected sewage generation was 28.3 + 39.7 = 73.4 MLD. To cater 73.4 MLD, new 37 (2015) + 38 (2030) = 75 MLD was proposed.
11
However, in 2014 situation, JICA relooked into the sewerage masterplan and revised the capacity of 75 MLD to 59.8 MLD (50 MLD new Ramana STP + Existing 9.8 MLD Bhagwanpur).
Action plan for Varuna catchment Trans Varuna Catchment
It consists of sewage District 2 B and 2 C.A new STP of 120 MLD is constructed at Goitha and working efficiently. Around 40 MLD flow is treated. The STP capacity is sufficient for next 15 years. No new STP or upgradation of existing STP is proposed.
Cis Varuna Catchment
It consists of District 2 A. The present sewage flow from district 2 A is
80 MILD, which is being pumped from Chauka ghat pumping station and treated at Dinapur new 140 MILD STP.
In addition, new 140 MILD STP shall also treat 40 MILD flow diverted from Shahi Nala.
Recommendations
140 MLD Dinapur need to be upgraded to meet discharge standard.
A new STP is needed to cater the future population for District 2 A. Action plan to treat wastewater from Durga drain discharging to Varuna River should be prepared.
Interceptor drain plan is under execution by UP Irrigation Department. All designs should be checked by expert authorities.
Figure 4.9: Interceptor drain plan of Varuna River Existing condition in Assi catchment
At present, as per CPCB measurement (12-15th July 2021), the flow in Assi River is around 92 MLD. In addition, STP at Bhagwanpur also
12
treat 8.0 MLD flow and discharges into River Ganga via Nakha drain. Hence total discharge in Assi catchment is 92 + 8 = 100 MLD. However, water supply in municipal area of Assi catchment isonly 26
MLD.
The pumping capacity at Nagwa Pumping Station to cater 50 MLD Ramana STP is only 50 MLD, 8 MLD is treated at Bhagwanpur STP and rest 92-50 = 42 MLD discharges directly into the River Ganga.
Figure 4.12 Present sewerage Situation of Varanasi City
This rapid increase in flow to Assi River is due to:
1. Unprecedented residential/commercial growth is due to large no. of developmental projects during last 4-5 years owing to VIP constituency, which seems convincing.
2. The growth within the city is limited due to constraint of land availability. Assi -BHU area and Trans Varuna area is vast open for development. Hence, increment significantly in migratory/floating population.
3. Untreated wastewater from Sewerage District 2 & 4.
4. Much higher water consumption than prescribed 135 lpcd because of unregulated water usage i.e., personnel source of water- submersible pumps etc, which has no control of water usage.
Recommendations A. Short Term plan
1. Presently actual discharge is mixed with rainfall. Actual dry weather flow can only be ascertained after rainy season. Detailed
13
assessment of excess discharge is required to be done and hence future forecasting is to be done accordingly.
2. There should be 24-h proper flow measurement of Assi River by both Area velocity and V notch method after the monsoon season.
3. Controlling wastewater from other sewerage districts.
4. There should be check and control on non-revenue water (NRW). NRW is defined as loss of water through leakages and illegal usage.
5. Based on the flow measurement, water supply and population projection, a new STP need to be proposed either at Ravinder Puri Culvert (on the bank of Assi River around 1km upstream of confluence) or at Ramana existing 50 MLD STP site wherever found feasible. The DPR for additional STP is to be prepared after flow assessment and population projection.
B. Long Term Plan
1. Wastewater generation is very high, hence proper 24 x 7 water supply with metering is needed to control wastewater generation and non-revenue water. A JICA project is underway to control non- revenue water
2. Laying of complete sewerage system for the entire city.
3. 9.8 MLD Bhagwanpur STP need to be decommissioned and new STP for higher capacity for future projections with new standards need to be constructed.
4. Banaras Locomotive Works STP should be upgraded to meet discharge standard.
Action plan for Ganga catchment
The sewage from District 1 (Old Varanasi) is treated in old 80 Dinapur STP. It is pumped from Konia Pumping station.
Recommendations
Old Dinapur STP (80 MLD) need to be decommissioned and new STP for higher capacity for future projections (as well as Shahi Nala Flow) with new standards need to be constructed.
Action plan for trans- Ganga
One new 10 MLD STP is constructed and treating around 8.0 MLD flow.
Recommendations
It is recommended that due to recent infrastructural development, there shall be rapid increase in population in near future. It is assumed that 10 MLD full flow shall be reached within next 1-2 years. Hence, authorities should start planning for the next phase so that no untreated wastewater discharge from the trans Ganga in near future.
14
Table 4.12: Action Plan for sewage management in catchment of river Varuna, Assi and Ganga in Varanasi Sl Sewerage Estimated Pumping River Existing Key issues Proposed Action Implementing No District Sewage Station catchm Sewage Plan Agencies
Generation ent Treatment Timeline for Action
2030 Facility
(MLD)
District 1 covers the old part New STP of higher UttarPradesh Preparation of DPR - 3 Month of the city Varanasi capacity for future Jal Nigam & Approval of DPR - 3 Months including most of the projections with new National Award of Work - 6 Months markets and tourist standard to be Mission for Completion of Work - 2 years destinations constructed after Clean Ganga Total Time required - 36 months
The district has very less decommissioning of scope of further escalation 80 MLD STP at in sewage generation in near Dinapur. future
Approx.80 MLD sewage
Generated inthis district
currently reaches 80 MLD
Dinapur STP for treatment
Konia through Konia and Saraiya
MPS, 80 MLD Pumping station via Old Cis
1 District 1 93.7 Saraiya STP Trunk Sewer Varuna
P.S. 3.7 DinapurThe rest of the sewage from MLD old trunk sewer is
discharged into river Management of rest Ganga through of the sewage from closed conduit at Shahi old trunk sewer, Nala Outfall, Rajghat presently discharging Uttar Pradesh Dinpaur 80 MLD STP has Work to be completed - 3 monthsat Shahi Nala outfall Jal Nigam completed the design life through pumping to
and it was designed as per 140 MLD STP
old discharge standards Dinapur.
resulting in non-compliance
of STP to norms prescribed
by NGT
15
Chaukaghat pumping station is currently pumping only 70- 80 MLD to Dinapur 140 MLD STP. The interception and Preparation of DPR for upgradation diversion of Shahi Nala - 3 months The 140 MLD STP outfall at Rajghat to requires upgradation Chaukaghat pumping Uttar Pradesh Jal Approval of Work - 3 months to meet the norms station through a new Nigam & National prescribed by
rescue trunk sewer is Mission for Clean Award of Work for upgradation - 3 Hon'ble NGT proposed and work is Ganga months Completion of upgradation including nutrient underway - 6 months removal
The Cis-interceptor line at
Varuna bank will also Total time required - 12- 14 months
intercept the untapped
drains on the cis Varuna
Chauka bank to Chauka Ghat
225.3 Ghat MPS pumping station for (including (140 MLD), Cis 140 MLD
2 District 2A pumping to Dinapur 140 NSA 1&2 & Phulwaria Varuna STP Dinapur MLD STP FSA-1 MPS (7.6 ASP technology based 140 MLD) Design of MLD Dinapur STP without interceptor plan tertiary filtration needs to be checked No Biological nutrient by expert agency and removal (BNR) system Design finalization - 1 month tapping shall be Under capacity utilization executed completely Irrigation I&D of drains (mainly Shahi I&D work completion with final I&D work of drains Department, Uttar Nala) is not completed tapping and pumping provisions - 2 falling into Varuna in Pradesh Jal Nigam Damaged & non-functional months Cis-Varuna area & subject expert
I&D structure shall (mainly Shahi Total time required- 3 months
Nala) to be
completed and
tapped to STPs for
treatment
16
Trans Varuna area contains zone 2B & 2C sewage
districts which has its sewage reaching partially for treatment at Goithaha STP through 7.6 MLD
Narokhar pumping station and rest quantity by gravity. An interceptor line is under commissioning in trans Varuna river bank for interception of 7 drains in the area discharging into Varuna currently and other small minor outfalls from lanes Design of interceptor
| District 2B |
Irrigation Department, Uttar Pradesh Jal Nigam & subject expert |
Design finalization – 1 month I&D work completion with final tapping and pumping provisions – 2 months Total time required- 3 months |
| Design of interceptor plan needs to be checked by expert. Interception and diversion have to be completed at the earliest by the executing agencies |
been connected with checked by expert. Irrigation
Narokhar I&D work completion with final
Trans 120 MLD pumping station currently Interception and Department, Uttar
3 District 2B IPS (7.6 tapping and pumping provisions - 2 Varuna STP Goitaha and the interceptor system diversion have to be Pradesh Jal Nigam MLD) months
is open to flow completed at the & subject expert
This interceptor line will earliest by the Total time required- 3 months
pump the sewage to 140 executing agencies MLD Dinapur STP for
treatment through Chauka
Ghat MPS as an interim
measure
The Goithaha STP is
currently functioning at
around 30-40 MLD
treatment (Under capacity
utilization)
Currently the catchment
area of Goithaha STP has
less population density so
the capacity utilization is
less and it is targeted to
achieve future utilization
17
I&D of the Trans Varuna area is not completed. Damaged & non-functional I&D structure meant for intercepting the Trans Varuna bank drains.
| District 2C |
Uttar Pradesh Jal Nigam, Varanasi Municipal Corporation, Irrigation Department and Urban Development Department |
Preparation of DPR – 6 months Approval of Work – 6 months Award of work – 6 months Execution of work – 2 years Total time required- 36-42 months |
| new comprehensive ewage management lan for trans Varuna eeds to be developed hich can cater all the rains of trans Varuna rea in Varanasi. |
sewage management Municipal Approval of Work - 6 months
plan for trans Varuna Corporation,
4 District 2C needs to be developed Irrigation Award of work - 6 months which can cater all the Department and
drains of trans Varuna Urban Execution of work - 2 years area in Varanasi. Development Total time required- 36-42
Department months
18
Estimated much higher water
consumption/discharge than prescribed Varanasi Municipal Detailed
Unregulated water uses and Corporation, Urban assessment of flow of freshwater from Development excess discharge in Kanchanpur talab and Department and dry weather other water bodies in the Uttar Pradesh Jal Control on NRW
low-lying areas joining river Nigam
Assi shall be identified and
fresh water channels shall
be separated from the
sewerage line/drain
50 MLD Estimated approximately
STP
Nagwa 50% Non -revenue water A new STP of Ramana, 8
5 District 3 73.5 MPS (50 Assi River (NRW) is consumed of total adequate capacity Uttar Pradesh Jal Preparation of DPR - 3 Month
MLD STP
MLD) freshwater usags to treat the excess Nigam & National Approval of DPR - 3 Months Bhagwanp Excess wastewater around approx. 50 MLD Mission for Clean Award of Work - 6 Months ur 40- 45 MLD goes directly to flow from the Assi Ganga Execution of work - 2 years Ganga River from the river outfall.
bypass point of Nagwa 50
MLD pumping station
Bhagwanpur STP treats the New STP at
sewage from Banaras Hindu Preparation of DPR - 3Months Bhagwanpur of University campus and Approval of DPR - 3 Months requisite capacity to treated sewage discharged Uttar Pradesh Jal be constructed as
through the Nakha drain Nigam & National Award of Work - 6 Months per new norms & which also carries Mission for Clean Completion of Work - 2 years flow data to cater untreated sewage from the Ganga the needs of BHU
Bhagwanpur local area and Total Time required - 32- 34 and nearby nearby areas of district 3. months municipal areas.
19
The Bhagwanpur STP is designed to treat 9.8 MLD sewage (8 + 1.8) but currently only 8 MLD plant is operated and 1.8 MLD unit is nonoperational The Bhagwanpur STP treats around 10 MLD sewage working overcapacity The Bhagwanpur STP has completed its designed life Restoration of origin Large areas in adjoining & stretches of river district 4 and district 4 has Irrigation Assi (with land recently been added in Department, availability) through Municipal area and has no Varanasi Municipal constructed sewage management Corporation, Urban wetlands. Within 6 months system existing which Development Separation of contributes to excess flow Department and freshwater from district 2 & 4 reaching Uttar Pradesh Jal channels/storm river Assi. Nigam water drains and
sewerage system
Most part of the Sewerage CEMDE Delhi Preparation of feasibility reports & In-situ treatment at district 4 has recently been University, DPR - 02 Months
Durga Drain through
included in the Varanasi Irrigation
Constructed Wetland
Municpal Area and Department, Approval of Work - 3 Months
as interim measure.
estimation and planning for Varanasi Municipal Award of work and implementation the newly added areas is Corporation. - 3 Months
underway Total Time required - 8- 12
Cis Not Currently no dedicated
months
6 District 4 45.1 None Varuna available treatment facility available No sewerage networks
'Untreated sewage directly
discharges in R. Varuna.
The Durga (Lohta) drain is
the major drain Uttar Pradesh Jal Preparation of DPR - 01 Month New STP of requisite discharging to River Nigam & National Approval of DPR - 3 Months capacity to be Varuna from the district Mission for Clean constructed as per Ganga. Award of Work - 6 Months
20
Actual discharge status is new norms & flow Completion of Work - 2 years unknown data. Total Time required - 32- 34
Lohta STP (50 MLD) is months
proposed by 2030 (JICA Detailed assessment Irrigation report) of excess discharge in Department, Uttar Within 2 months dry weather Pradesh Jal Nigam,
Urban
Development
department
21
The BLW campus has a STP of 12 MLD installed inside campus to treat the sewage generated in the campus. The BLW campus lies in the Assi river catchment. At least one drain originates from the campus and two Preparation of DPR - 01 Month drains passes near the BLW Approval of DPR - 3 Months Award campus and ultimately of Work - 6 Months Completion of discharges into river Assi Work - 2 years Total Time required DLW-1 originates from the - 32- 34 months campus and carries treated BLW STP has
sewage and storm water outlived its designed from the BLW campus life BLW Engineering
Banaras DLW-2 originates from the Department, UP Locomoti 50 Staff Cis
7 12 MLD Manduwadih area and flows
BLW STP shall be
Jal Nigam, National
ve Work colonies Varuna near the BLW campus upgraded/new STP to Mission for Clean (BLW) DLW-1 and DLW-2 be installed to meet Ganga
ultimately meets river Assi norms prescribed by
near Sunderpur Chauraha NGT including for
DLW-3 originates from the coliform count
Kanchanpur taal area and
carries pond water and
waste water from nearby
low-lying areas
DLW 3 meets river Assi near
the DLW campus trans of
DLW-Chunar Road.
Around 2-3 MLD
wastewater from this drain
is treated at BLW STP for
sometime
22
The 12 MLD STP at DLW Reason for weak operates at around 4 MLD organic load only and the inlet raw characteristics of BLW Engineering sewage shows weak sewage sewage at inlet of BLW Department, UP characteristics with low STP shall be explored Jal Nigam, Uttar Within 1-2 Month organic load Water audit of water Pradesh Pollution
STP has no disinfection usage and discharge Control Board system to control Coliform from BLW campus
count in treated sewage may be done
Sources of sewage and BLW Engineering
freshwater in the Department,
| BLW Engineering Department, Irirgation Department, Urban Development Department, UP Jal Nigam, Uttar Pradesh Pollution Control Board |
Identification of sources of waste and freshwater – 1 Months Preparation of action plan for separation of freshwater channels/storm water and waste water carrying drains– 6 Months |
| ources of sewage and reshwater in the rains near the BLW ampus ultimately ischarging into Assi iver shall be dentified and eparated for reducing he flow in Assi river at nterception point |
and freshwater - 1 Months
campus ultimately Department,
discharging into Assi Urban
river shall be Development Preparation of action plan for
separation of freshwater
identified and Department, UP
channels/storm water and waste
separated for reducing Jal Nigam, Uttar
water carrying drains- 6 Months
the flow in Assi river at Pradesh Pollution
interception point Control Board
Table 4.13: Road map for execution of proposed action Plan for restoration of Varuna & Assi river Sr. Sewerage Existing Proposed Project Activity
No. District Sewage Action/remedial
/region Treatment measure Work Plan Time line Implementation Agency
Facility
80 MLD Decommissioning Condition assessment & 1 Month UP Jal Nigam/ Other STP of existing STP feasibility report (CAFR) government organization and construction Approval of CAFR 1 month NMCG
23
1. District 1 Dinapur of new STP of Submission of DPR 2 Months UP Jal Nigam/ Other higher capacity government organization
for future Administrative approval & 2 months NMCG
projections with estimated sanctioned
new standard Tendering & award of project 2 months NMCG
Basic Engineering Package (BEP) 3 months UP Jal Nigam/ Other submission government
organization /EPC
Design & Engineering 2 months cIIoTn/MtraNcItTo/rDeemed
approval university
Construction & 2 years UP Jal Nigam/ EPC
Commissioning contractor/others
2. District 140 MLD STP Upgradation of STP Submission of DPR 2 Months UP Jal Nigam/ Other 2A as per new NGT government organization
Dinapur norms.
| Approval & Tendering |
3 months |
NMCG |
| Design assessment of interceptor plan |
2 months |
IIT/MNIT/Deemed university |
| Approval, Tendering and project award |
3-4 month |
NMCG |
24
needs to be Construction & 3-4 month UP Irrigation checked by expert commissioning
I&D work of Tapping and diversion of Sahi 1-2 months dPreopjaercttm ise unnt/dEePrC e cxoencutrtaioctno bry Shahi Nala nala to 140 MLD STP UP Jal Nigam
I&D work of drains I&D work of drains up to 1-2 months Project is under execution by in cis Varuna 140 MLD MPS Chaukaghat UP irrigation department
region
3. District 120 MLD I&D work of I&D work of drains up to 1-2 months Project is under execution by STP drains in trans 140 MLD MPS Chaukaghat UP irrigation department 2B Varuna region as an interim measure
4. District Goitaha Development of Condition assessment & 1 Month UP Jal Nigam/ Other new feasibility report (CAFR) government organization
2C comprehensive Approval of CAFR 1 month NMCG
sewage Submission of DPR 2 Months UP Jal Nigam/ Other
government organization
management plan Administrative approval & 2 months NMCG
for trans Varuna estimated sanctioned
Tendering & award of project 2 months NMCG
BEP submission 3 months UP Jal Nigam/ Other
government
organization /EPC
Design & Engineering 2 months IcIoTn/MtraNcItTo/rDeemed
approval university
Construction & 1-2 years UP Jal Nigam/ EPC
Commissioning contractor/others
50 MLD Assessment of Detailed assessment of excess 3-4 months UP Jal Nigam STP excess discharge of Assi River in dry
discharge of weather &
Assi River
Control on NRW
25
5. District 3 Ramana, Design, Condition assessment & 1 Month UP Jal Nigam/ Other construction and feasibility report (CAFR) government organization
8 MLD STP commissioning of Bhagwanpur new tapping Approval of CAFR 1 month NMCG
| Submission of DPR |
2 Months |
UP Jal Nigam/ Other government organization |
| Administrative approval & estimated sanctioned |
2 months |
NMCG |
| Tendering & award of project |
2 months |
NMCG |
| BEP submission |
3 months |
UP Jal Nigam/ Other government organization /EPC contractor |
| Design & Engineering approval |
2 months |
IIT/MNIT/Deemed university |
|
Construction & Commissioning |
1-2 years |
UP Jal Nigam/ EPC contractor/others |
| Restoration of Origin & stretches through constructed wetlands |
Submission of design details & drawing of CWS |
1 month |
CEMDE |
| Submission of DPR for desilting, civil work etc. |
2 months |
Irrigation and water resources department/ |
| Approval, Tendering and project award |
3-4 month |
NOMthCeGr government |
| Desilting and civil construction |
3-4 months |
Irrigation and water resources department/ |
| Vegetation development & commissioning |
1-2 years |
COEtMheDrE government |
| Condition assessment & feasibility report (CAFR) |
1 Month |
UP Jal Nigam/ Other government organization |
Bhagwanpur And Approval of CAFR 1 month NMCG
Design, Submission of DPR 2 Months UP Jal Nigam/ Other
Construction and government organization
26
commission of Administrative approval & 2 months NMCG new STP as per estimated sanctioned
| Tendering & award of project |
2 months |
NMCG |
| BEP submission |
3 months |
UP Jal Nigam/ Other government organization /EPC contractor |
| Design & Engineering approval |
2 months |
IIT/MNIT/Deemed university |
| Construction & Commissioning |
1-2 years |
UP Jal Nigam/ EPC contractor/others |
| 1 month |
In-situ development of Constructed Wetland System in Durga Drain as interim measure |
Submission of design details & drawing of CWS |
CEMDE |
| Submission of DPR for desilting, civil work etc. |
2 months |
Irrigation and water resources department/ Other government organization |
| Approval, Tendering and project award |
3-4 month |
NMCG |
| Desilting and civil construction |
3-4 months |
Irrigation and water resources department/ Other government |
| Vegetation development & commissioning |
1-2 years |
oCrgEaMnDizEation |
| Condition assessment & feasibility report (CAFR) |
1 Month |
UP Jal Nigam/ Other government organization |
new STP of Approval of CAFR 1 month NMCG
27
District 4 available requisite capacity Submission of DPR 2 Months UP Jal Nigam/ Other
6. as per new norms government organization & flow data
Administrative approval & 2 months NMCG estimated sanctioned
Tendering & award of project 2 months NMCG BEP submission 3 months UP Jal Nigam/ Other government organization
/EPC contractor
Design & Engineering 2 months IIT/MNIT/Deemed approval university
Construction & 1-2 years UP Jal Nigam/ EPC Commissioning contractor/others
7. Varuna Not Restoration of Submission of design details 1 month CEMDE origin catchment & drawing
available origin of R. Submission of DPR for 2 months Irrigation and water Varuna desilting, channeling etc.
resources department/
Approval, Tendering and 3-4 month NOMthCeGr government project award
Desilting, channeling and 10-12 months Irrigation and water other construction work
resources department/
Biotic community 1-2 years COEtMheDrE government
Not Desilting of R dSeuvbemloispsmioenn otf & d erseisgtno draettiaoinls 1 month CEMDE Varuna & In-situ & drawing of CWS
development of Submission of DPR for 2 months Irrigation and water Constructed desilting, civil work etc. resources department
Wetland System Approval, Tendering and 3-4 month NMCG
in Dhoraira, Naya project award
Desilting and civil 3-4 months Irrigation and water
construction resources department
28
8. Along R. available Bazar, Bubuspur Vegetation development & 1-2 years CEMDE Varuna and Chauri drains commissioning
| 9. |
Varuna confluence |
Not available |
Development of flood plain Biodiversity Park |
Demarcation of flood plain of R. Vruna at confluence |
3-4 months |
Irrigation and water resources department |
| Submission of DPR for planning, design & development of Biodiversity park |
3-4 months |
CEMDE |
| Approval, Tendering and project award |
3-4 month |
NMCG |
| Development of Biodiversity park |
4-5 years |
CEMDE |
29
Performance assessment of STPs and requirement for upgradation /augmentation
The estimated sewage generation of Varanasi (including Ramnagar) is approximately 330 MLD (201718) (as per data received from UPPCB). Total 7 STPs (5 commissioned and 2 under trial) with total capacity of 421.8 MLD (361 MLD for commissioned STPs and 60 MLD for under trial STPs) have been installed for the treatment of the generated sewage. Utilized capacity of the commissioned and operational STPs is approximately 210 MLD.
Characteristics of raw sewage received at inlet of STPs located in Varanasi have BOD ranging from 10.5 mg/l to 52.4 mg/l, COD ranging from 45.7 mg/l to 193 mg/l indicating weak sewage as compared to typical municipal wastewater (BOD: 200-250 mg/l, COD: 350-500 mg/l); is received at inlet of the STPs. The weak sewage strength could be due to dilution of the sewage from septic tanks and addition of grey water from households etc. As per inspections conducted in last 2 years, the treated sewage from STPs is found non- complying with respect to the discharge norms. As per inspection dated 23.06.2021, reduction in BOD was found in range 38% to and 85%. Similarly, reduction in the COD was found in range 39% to 81%. STPs meet the prescribed norm for Total Nitrogen (10 mg/l) only when raw sewage with low Total Nitrogen (around 10 mg/l) is received. This necessitates upgradation and augmentation of these STPs. The measure suggested for the upgradation and augmentation of STPs are mentioned in the table below.
Discharge norm for Fecal coliform (230MPN/100ml) is not achieved in all STPs. Hence to achieve the norms there is requirement of upgradation/optimization of the existing disinfection system or installation of new disinfection system (if no disinfection system is present). The inflow at STP at Bhagwanpur is ranging from 8-14 MLD which is above the designed capacity (9.8 MLD). This STP needs capacity enhancement after detailed study for capacity requirement. STPs at Dinapur and Goithaha are underutilized. The reason for less inflow into STPs should be studied and areas without sewerage network should be provided with sewerage network and connected to respective STP.
Online continuous Effluent System (OCEMS) is installed at 12 MLD STP, BLW only. OCEMS should be installed at remaining 6 (4 operational and 2 under trial) STPs and connected to CPCB/ SPCB server at the earliest for on-line monitoring of the STPs.
30
Table 4.14: Performance assessment of STPs of Varanasi and requirement for their upgradation and augmentation.
| Sr. No |
STPs |
Technol ogy & Process used |
Designated Capacity (MLD) |
Maximum Utilised Capacity (inspection date) |
Inlet characteristics (mg/l) |
Discharge to river |
Operational/ Non- operational/ Non- functional |
Compliance with respect to discharge standards (2021) |
Suggested upgradation and Augmentation |
| 1 |
Dinapur (Old) STP |
TF followed by ASP |
80 |
70 (23.06.2021) |
BOD – 46.4, COD – 160, TSS – 169 TN – 7.02 (23.06.2021) |
Ganga through open channel |
Operational |
Mostly found non-complying for FC |
1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be ensured in the existing ASP 2. Optimization of existing disinfection system 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas |
| 2 |
Dinapur (New) STP |
ASP |
140 |
125 (23.02.2021) |
BOD-52.4 COD-161 TSS- 138 |
Varuna river through pipeline |
Operational |
Mostly found non-complying for TN and FC |
1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be |
31
|
|
|
|
|
TN-16.5 (23.06.2021) |
|
|
|
ensured in the existing ASP 2. Optimization of existing disinfection system. 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas |
| 3 |
Bhagwanpur BHU STP |
ASP |
9.8 |
14 (23.06.2021) |
BOD-24.9 COD-92.2 TSS- 1242 TN- 8.83 (23.06.2021) |
River Ganga through Nakkhi Nala |
Operational |
Mostly found non-complying for TN and FC |
1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be ensured in the existing ASP. 2. Optimization of existing disinfection system. 3. Installation of OCEMS 4. Capacity Enhancement |
| 4 |
Goithaha STP |
SBR |
120 |
55 (23.06.2021) |
BOD-56.3, COD-193 TSS- 491 |
River Ganga via Sharda Canal |
Operational |
Mostly found non-complying for FC |
1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be |
32
|
|
|
|
|
TN- 6.49 (23.06.2021) |
|
|
|
ensured in the existing ASP. 2. Optimization of existing disinfection system 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas |
| 5 |
BLW (formerly DLW) STP |
ASP |
12 |
5 (23.02.2021) |
BOD-10.5, COD-45.7, TSS- 19.1 TN- 6.13 (23.06.2021) |
Reused (may reach Ganga through Assi river) |
Operational |
Mostly found Non-Complying for FC |
1. Disinfection system of adequate capacity |
(23.06.2021)
2. Optimization of existing disinfection system
3. Installation of OCEMS
4. Provision for sewerage network in uncovered areas
5 BLW ASP 12 5 BOD-10.5, Reused Operational Mostly found 1. Disinfection system of (formerly (may Non-Complying adequate capacity
DLW) STP (23.02.2021) COD-45.7, reach for FC
Ganga
TSS- 19.1
through
TN- 6.13 Assi river)
(23.06.2021)
Note: Compliance status as per Hon'ble NGT order dated 30.04.2019. (pH: 5.5- 9.0; BOD: 10 mg/l; TSS: 20 mg/L; COD: 50 mg/L; Total Nitrogen (TN):
10 mg/L; Total Phosphorus (for discharge into ponds and lakes): 01 mg/L; Faecal Coliform: Desirable limit 100 MPN/100 ml, Permissible limit 230 MPN/100ml)
33
Sludge Management Plan
Treatment and disposal of sewage sludge are major factors in the design and operation of all wastewater treatment plants. Two basic goals of treating sludge before final disposal are to reduce its volume and to stabilize the organic materials. Stabilized sludge does not have an offensive odour and can be handled without causing a nuisance or health hazard. Sludge management is an issue of great concern due to its potential threat to human health and the environment with necessitated explicit regulations to organize their production and use. Currently adopted sludge management plan practices as provided by UP Jal Nigam for management of generated sludge is tabled below;
Table 4.15: Sludge management plan for generated STPs sludge Sr Name of Capacity Approximate Disposal of Remarks No. STP (MLD) Generation sludge
of Sludge
(Tonnes/Yr.)
1 Dinapur 80 8250 Being used as Since, removal ingredient of of Nitrogen
2 Dinapur 140 6500 Fertilizer by local and farmers/manufact Phosphorous
ures is not part of
3 Bhagwan 9.8 275 Being used in the design pur Horticulture. process, hence the sludge has
nutritional
value and is
being used as
an ingredient of
fertilizer.
4 Goithaha 120 4350 Being used in Process land fill at design of
various STPs contains
locations. provision for
5 Ramana 50 5200 Proposed to be removal of used in land fill at Nitrogen and STP site itself. Phosphorous, hence
6 Ramnagar 10 740 Proposed to be generated used in land fill at sludge doesn't STP site itself. have
nutrients.
Industrial Pollution Control Industrial Pollution Management
During recent survey, 118 water polluting industries located in Varanasi and Bhadohi having potential to discharge into river Ganga and its tributary Varuna were inventoried which comprised Textile/Yarn (54 units), Sari Printing (33 units), Metal surface treatment (23 units), slaughter houses & meat processing (03 units), food & beverage (03 units) and Heavy engineering & Loco (02). Out of 118, 87 units are from textile/yarn and Sari printing sector.
34
Action Plan for prevention of pollution from Textile Cluster
Central Pollution Control Board (CPCB) has formulated the 'Charter for Water Recycling and Pollution Prevention in Textile industries" in consultation with experts from the departments of Chemical Engineering & Technology, IIT (BHU), Textile Engineering Department, IIT Delhi, Polymer and Fiber Technology, IIT Delhi, Fibre and Textile Processing, ICT, Mumbai, UP Textile Technology Institute, Kanpur and Textile industries (Annexure-V).
Charter is based on participatory approach and one of the important objectives of charter is to setup a bench mark for water consumption & optimize the use of water & chemicals in processing. Charter is formulated, with a view to envisage upgradation of the status of textile industries in sustainable manner in terms of process technology upgradation, adoption of best practices, improved environmental performance, substantial reduction in the fresh water consumption and waste water generation, improvement in effluent treatment including tertiary treatment and optimize water recycling. Compliance with the prescribed standards is mandatory. There will be no compromise with regard to the industry not meeting the prescribed standards.
Charter prepared for textile industries was launched in the workshop with the textile units at Kanpur on 05.04.2019. For implementation of Textile Charter to all River Ganga Main Stem GPIs, UPPCB issued direction under section 33A of Water (Prevention and control of Pollution), 1974 on 08.05.2019.
Charter was discussed with textile mills and experts at a workshop organized by Carpet Export Promotion Council at Bhadohi on 6th August, 2018. A workshop was also organized by UPPCB on implementation of "Charter for water recycling and pollution prevention in Textile industry" was held on 15th Oct, 2019 at Bhadohi.
As per data available with CPCB, during 2020, there were 31 textile sector GPIs in Bhadohi cluster and out of 31, 22 Textile units have prepared their individual action plan which were reviewed and the suggestions has been communicated to individual unit in the month of March-April, 2020 for implementation of recommendations as per charter.
However, during recent survey 54 yarn/textile and 33 sari printing units have been inventoried in Bhadohi, Jaunpur and Varanasi region in catchment of river Ganga and Varuna. Therefore, it is suggested that charter should be implemented in textile industrial cluster located in catchment of river Ganga and its tributaries in Uttar Pradesh in effective manner which will results in reduction in the fresh water consumption and waste water generation, optimize water recycling and overall improved environmental performance of industrial unit in sustainable manner. A monitoring committee may also be constituted to monitor the implementation status of charter in textile sector in a prescribed time frame.
Solid waste management
35
Proper Solid waste treatment system based on Indore or Goa model need to be prepared along with Waste to Energy system. The un-segregated solid waste dumped in open plots or ponds/low lying areas within 500 meter of river Varuna in Varanasi contribute air and ground water pollution. The estimated quantity of legacy waste in this dumping site is approximately 30000 MT. Management of legacy waste having adequate capacities for collecting, transporting and disposing of the municipal solid waste produced on a day-to-day basis as well as legacy waste trapped in the dumpsites is proposed to be done.
Illegal disposal of Construction and demolition waste in floodplain zone of river Varuna and Assi shall be prohibited.
Solid waste management plan of Varanasi City
Varanasi city has an estimated population of 15, 31,458 in 2020 based on projections for population taking 2011 population as base. Owing to its rich tourism potential, the estimated daily flow of tourists and pilgrims to the city is 25,000. The total area within Varanasi Nagar Nigam (VNN) is 82.1 km square for 90 wards and 86 more Villages have been merged with VNN area of 195 Sq km. The average waste generation of Varanasi is 0.400 kg per capita per day. The city at present generates 600 MT (Approx.) of waste per day at the rate of
0.400 Kg per capita per day and decadal population growth of 2.67 per Year (as per trend of rate of population growth in last 10 year:
2001-2011)
Table 4.16: Population Projection and waste generation for Varanasi City
Year House Hold Population Waste generation MT/Day (approx) @
400 gm per capita
per day
| 2011 |
191278 |
11,98,491 |
479.39 |
| 2021 (for 90 Wards) |
248300 |
15,31,458 |
612.58 |
| 2021 (For 86 Newly merged villages-20 wards) |
151759 |
4,76,779 |
190.71 |
| 2035 (for 110 Wards) |
512012 |
29,64,678 |
1185.87 |
| 2050 (for 110 wards) |
655375 |
40,93,136 |
1637.25 |
The Government of India published the Solid Waste Management
Rules, 2016, the Rules are now applicable beyond Municipal areas
and extend to urban agglomerations, census towns, notified
industrial townships, etc.
Administrative setup for MSW Management in Varanasi
36
The area falling under Varanasi Municipal Corporation is currently divided into 5 zones and 14 Subzone and 90 wards for administrative purposes and 86 newly merged villages. The details are annexed as Annexure VII.
| Table 4.17: Manpower Engaged in Varanasi Nagar Nigam (VNN) for MSW Management |
| Designation |
No |
| Municipal Commissioner |
1 |
| Additional Municipal Commissioner |
1 |
| Municipal Health officer |
1 |
| Executive Engineer’s. (Transport & Processing-SWM) |
2 |
| Zonal Officers |
5 |
| Zonal Health officers |
1 |
| Sanitary & Food Inspector |
14 |
| Account Clerk |
01 |
| Account Officer |
02 |
| Safai Supervisors |
93 (VNN-38 and Varanasi Waste Solution-40) |
| Safai Mitra’s and drivers |
5784 (VNN Safai Mitra’s = 4171, VWSPL Safai Mitra-850, VNN drivers = 331, VWSPL Drivers- 195, Rag Pickers = 237) |
Currently there are no 100% door to door collections in 90 wards
of Varanasi. Most of the households, shops, and establishments
throw their waste just outside their premises, on streets, in drains,
in open spaces, in water bodies, and in other inappropriate places.
These litters swept away by street sweeping and lifted by means
of handcart or rickshaw trolley by Sweepers and waste collectors
of VNN, this led to unsanitary condition across the city.
Varanasi Nagar Nigam outsourced M/s Varanasi Waste solution
Pvt. Ltd. For door to door collection in 90 wards, mechanized road
Sweeping approx.. 22.1 km. daily basis (Sant. Athulananda to
BHU) and toilet cleaning work of Varanasi.
Apart from door to door collection three Ngo's named Anthill
Services Pvt. Ltd; career consulting pvt. Ltd, Jan Vikas Kalyan
Samiti; Engage for IEC activities for sanitation awareness in their
respective wards.
The length of roads, streets, lanes, bye-lens in the city is
approximately 1200 km in the total and approx. length of drains
2400 km area within Varanasi Nagar Nigam of 82.1 km square.
Street sweeping starts between 8:00 AM and continues up to 2:00
PM.
The detailed action plan for MSW management in Varanasi city is enclosed as Annexure-VII
37
Encroachment
Removal of encroachment from lower floodplain zone of river Varuna and Assi. Demarcation and notification of floodplain zone by introducing pillars to further prevent encroachment in River Varuna and Assi.
Monitoring Committee a. Supervisory Committee - It may supervise the implementation of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist of representative from District Magistrate, Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, NMCG, UPPCB and CPCB under the chairmanship of Commissioner of Varanasi division, meeting to be held on quarterly basis.
b. Execution Committee - The committee may responsible for execution of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, SMCG and SPCB under the chairmanship of District Magistrate of concerned district, meeting to be held on monthly basis."
5. The report shows that there are serious issues adversely affecting rivers Varuna and Assi calling for remedial action in the form of desilting, remediation of waste water, development of constructed wetland systems and bio-diversity parks, apart from management of sewage, industrial pollution and solid waste which requires concerted and continuing steps and monitoring.
6. Since the issues and remedial steps have been identified by the joint Committee and exhaustive recommendations for remedial action made, there is need for execution of the action plan at the ground level in the light of above report. This requires coordination among the concerned departments including the Local Bodies, District Administration and State Government.
7. Accordingly, the Supervisory and Execution Committees suggested in the report may take further action. In terms of suggestions of the
38
Committee, problem of chocking at the origin point of said rivers may be remedied by taking restoration measures. The execution Committee may meet atleast once in a month under the Chairmanship of District Magistrate, Varanasi and the Supervisory Committee may meet on quarterly basis under the Chairmanship of Commissioner, Varanasi Division, as suggested. The District Magistrate as well as Commissioner, Varanasi Division may have full time environmental coordinators attached to them directly for this purpose either out of the existing incumbents or by specially engaging a suitable person for the task. It will be appropriate that minutes of the meeting of the District Magistrate as well as Commissioner, Varanasi are placed on their respective websites, which may enable public information and participation. Having regard to the significance of the issue and need for prompt action for keeping the important rivers pollution free, the timelines need to be shortened which aspect may be considered by the Execution and the Supervisory Committees. We request the Oversight Committee constituted by this Tribunal headed by Justice S.V.S. Rathore, former Judge of the Allahabad High Court to oversee the steps taken in the matter, if necessary, by periodically interacting with the Execution and Supervisory Committees.
8. We further direct the NMCG and CPCB to monitor progress of implementation of action plan in accordance with the Namami Gange project.
9. The action plan may be placed on the website of CPCB and also circulated by CPCB to the River Rejuvenation Committees of all the States/UTs through respective State PCBs/PCCs, for appropriate consideration of their respective action plans to the extent found necessary.
39
10. The issue of funding of the projects proposed may be worked by the NMCG and the Chief Secretary, UP and wherever Namami Gange funds are found inadequate, it will be the responsibility of the State of UP to provide the same.
The application is disposed of.
A copy of this order be forwarded to CPCB, NMCG, Chief Secretary, UP, Additional Chief Secretary, Irrigation Department, UP, State PCB and District Magistrate and Commissioner, Varanasi Division by e-mail for compliance.
A copy of this order be also provided to all other concerned departments by the Additional Chief Secretary, Irrigation Department, UP. A copy of this order be also forwarded to Justice S.V.S. Rathore, former Judge of the Allahabad High Court by e-mail. Adarsh Kumar Goel, CP
Sudhir Agarwal, JM
Dr. Nagin Nanda, EM
November 23, 2021
Original Application No. 128/2021
DV
40