Structured Summary of the National Green Tribunal Order

Factual and Procedural Background

Applicant: Saurabh Tiwari. Respondents: Union of India & Ors. (Original Application No. 128/2021). The application complains of pollution of the Varuna and Assi rivers in Varanasi arising from discharge of untreated sewage and from unauthorized constructions. The application notes that Varuna and Assi are tributaries of the Ganga and that cleaning the Ganga requires prevention of pollution of these tributaries. The opinion records water quality measurements and media reports: fecal coliform bacteria count at the Varuna–Ganga confluence is recorded as 71 million per 100 ml, at the Assi–Ganga confluence as 52 million per 100 ml, and at Assi Ghat as 140,000 per 100 ml; the permissible limit cited in the report is 500 per 100 ml. Reference is made to a water quality report prepared by Sankat Mochan Foundation, Varanasi.

Procedural history included an earlier order dated 17.06.2021 (referenced in this opinion). Considering the seriousness of the issue and in light of a Supreme Court judgment and prior orders of this Tribunal, the Tribunal had constituted an independent Monitoring Committee comprising CPCB, State PCB, NMCG and the District Magistrate, Varanasi to ascertain factual status and take remedial action. An action taken report was filed on 18.08.2021 by the U.P. State PCB on behalf of the joint Committee. The hearing was completed and order reserved on 16.11.2021; the order was uploaded on the website on 23.11.2021. The Coram comprises: Hon'ble Mr. Justice Adarsh Kumar Goel (Chairperson), Hon'ble Mr. Justice Sudhir Agarwal (Judicial Member) and Hon'ble Dr. Nagin Nanda (Expert Member).

Legal Issues Presented

The opinion addresses a procedural matter and does not frame distinct legal issues.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Paryavaran Suraksha case (Supreme Court) — cited as (2017) 5 SCC 326 Cited as an authoritative judgment considered relevant to the seriousness of the river pollution issue. The Tribunal, taking the judgment into account, proceeded (vide order dated 17.06.2021) to constitute an independent Monitoring Committee to ascertain factual status and take remedial action.
Paryavaran Suraksha Samiti & Anr. v. Union of India & Ors. (O.A. No. 593/2017) Cited as an earlier order of this Tribunal relevant to river pollution and remedial oversight. Referenced along with other Tribunal orders as part of the basis for constituting the Monitoring Committee and directing action and reporting by NMCG in related proceedings.
M.C. Mehta v. Union of India & Ors. (O.A. No. 200/2014) Cited as the OA relating to rejuvenation of River Ganga and as a procedural context for seeking action taken reports by NMCG. The Tribunal directed NMCG to file an action taken report in OA No. 200/2014 inter alia covering status on water quality of Assi and Varuna, sewage diversion and treatment, and demarcation of flood plain zones.

Court's Reasoning and Analysis

The Tribunal's analysis proceeded from recorded factual findings to procedural and implementation directions:

  1. Factual foundation: the application and accompanying reports (including monitoring data and media reports) establish serious pollution of the Varuna and Assi rivers (with cited fecal coliform counts and water quality concerns).
  2. Prior steps: in view of the seriousness and relevant precedents/orders, the Tribunal had earlier constituted an independent Monitoring Committee (CPCB, State PCB, NMCG and District Magistrate, Varanasi) to determine factual status and propose remedial measures. An action taken report was subsequently filed by the UP State PCB for the joint Committee providing minutes of meetings, surveys and a comprehensive action plan for restoration and rejuvenation.
  3. Content of the joint Committee's report: the action plan (reproduced in the opinion) contains detailed, itemised remedial measures across multiple thematic areas — river desilting, constructed wetland systems (CWS), development of floodplain biodiversity parks, sewage management (including STP works and sewerage masterplan implications), sludge management, industrial pollution control (including textile charter implementation), solid waste management, and encroachment removal. The report also proposes Supervisory and Execution Committees, implementation timelines and designated implementing agencies.
  4. Need for ground execution and coordination: the Tribunal observed that, because the issues and remedial steps have been identified and exhaustive recommendations made by the joint Committee, what remains is execution at ground level, which requires coordination among Local Bodies, District Administration and State Government.
  5. Institutional and monitoring measures: the Tribunal accepted the report's suggested Supervisory and Execution Committees and specified operational modalities — the Execution Committee to meet at least monthly under the District Magistrate; the Supervisory Committee to meet quarterly under the Commissioner, Varanasi Division; appointment or assignment of full-time environmental coordinators to the District Magistrate and Commissioner; public posting of minutes on official websites; a request to the Tribunal's Oversight Committee (headed by Justice S.V.S. Rathore) to periodically interact with the Execution and Supervisory Committees if necessary.
  6. Monitoring and dissemination: the Tribunal directed NMCG and CPCB to monitor implementation progress in accordance with the Namami Gange project, and directed CPCB to place the action plan on its website and circulate it to River Rejuvenation Committees of all States/UTs through respective State PCBs/PCCs.
  7. Funding: the Tribunal noted that funding issues should be worked out by NMCG and the Chief Secretary, UP; where Namami Gange funds are inadequate, the State of UP is to provide the required funds.
  8. Conclusion: on the basis of the above factual findings and the joint Committee's recommendations, the Tribunal disposed of the application while issuing directions for implementation, monitoring, inter-departmental coordination and dissemination.

Holding and Implications

HOLDING: The application is DISPOSED OF.

Direct consequences and orders

  • The Supervisory and Execution Committees as suggested in the joint Committee's report are to take further action and implement the action plan on the ground.
  • The Execution Committee shall meet at least once a month under the Chairmanship of the District Magistrate, Varanasi; the Supervisory Committee shall meet quarterly under the Chairmanship of the Commissioner, Varanasi Division.
  • District Magistrate and Commissioner, Varanasi Division, are to have full-time environmental coordinators (either existing incumbents or specially engaged persons) attached to them for this purpose.
  • Minutes of meetings of both the District Magistrate and the Commissioner should be placed on their respective websites to enable public information and participation.
  • The Tribunal requested oversight by the Oversight Committee headed by Justice S.V.S. Rathore to periodically interact with the Execution and Supervisory Committees if necessary.
  • NMCG and CPCB are directed to monitor progress of implementation of the action plan in accordance with the Namami Gange project.
  • The action plan is to be placed on the CPCB website and circulated by CPCB to River Rejuvenation Committees of all States/UTs through respective State PCBs/PCCs.
  • Funding issues: NMCG and the Chief Secretary, UP are to work out funding; where Namami Gange funds are inadequate, the State of UP is responsible to provide the necessary funds.
  • Administrative compliance: copies of the order are to be forwarded to CPCB, NMCG, Chief Secretary UP, Additional Chief Secretary (Irrigation Department, UP), State PCB, District Magistrate and Commissioner, Varanasi Division, and to Justice S.V.S. Rathore for oversight; the Additional Chief Secretary, Irrigation Department, UP, is also directed to provide copies to other concerned departments.

Broader implications

The order does not announce a new legal precedent; rather, it records factual findings and directs execution, inter-agency coordination, monitoring and funding measures to implement a detailed remedial action plan for restoration and rejuvenation of the Varuna and Assi rivers. The practical implications are procedural and administrative: institution of supervisory/execution structures, timelines for implementation of the multi-faceted action plan, public disclosure of meeting minutes, and centralized monitoring by NMCG/CPCB in line with Namami Gange.


Administrative details from the order: Hearing completed and order reserved on 16.11.2021; order uploaded on website on 23.11.2021. Bench: Hon'ble Mr. Justice Adarsh Kumar Goel (Chairperson), Hon'ble Mr. Justice Sudhir Agarwal (Judicial Member) and Hon'ble Dr. Nagin Nanda (Expert Member). Order dated November 23, 2021.

    SAURABH TIWARI v. UNION OF INDIA

    Item No. 02 (Court No. 1)

    BEFORE THE NATIONAL GREEN TRIBUNAL

    (By Video Conferencing) Original Application No. 128/2021 (With report dated 18.08.2021) Saurabh Tiwari Applicant Versus

    Union of India & Ors. Respondent(s) Date of completion of hearing and reserving of order: 16.11.2021 Date of uploading of order on the website: 23.11.2021

    CORAM: HON'BLE MR. JUSTICE ADARSH KUMAR GOEL, CHAIRPERSON HON'BLE MR. JUSTICE SUDHIR AGARWAL, JUDICIAL MEMBER HON'BLE DR. NAGIN NANDA, EXPERT MEMBER

    ORDER

    1. Grievance in this application is against pollution of rivers Varuna and Assi in Varanasi by discharge of untreated sewage and unauthorized constructions. Case set out in the application is that the above rivers are tributaries of river Ganga and cleaning of river Ganga cannot be imagined without first ensuring prevention of pollution of the said rivers. The pollution of the said rivers is subject matter of various media reports. Water quality of river Ganga at Varanasi is in bad condition. Fecal coliform bacteria count at Varun-Ganga confluence is 71 million per 100ML of water (Ganga Jal) and fecal coliform count at Assi River and Ganga confluence is 52 Million per 100ML of water and on Assi Ghat fecal coliform is 1 lakh 40 thousand per 100ML of Ganga Jal. Permissible limit of fecal coliform bacteria should not exceed 500 per 100ML of water. Reference has been made to a report on water quality prepared by Sankat Mochan

    1

    Foundation in Varanasi. It is further stated that there is concrete construction inside Ganga water channel at Lalita Ghat.

    2. Vide order dated 17.06.2021, considering the seriousness of the issue and in the light of judgment of the Hon'ble Supreme Court in Paryavaran Suraksha case1

    and orders of this Tribunal in O.A. No. 593/2017, Paryavaran Suraksha Samiti & Anr. v. Union of India & Ors., O.A. No. 673/2018, In Re: News item published in "The Hindu" authored by Shri Jacob Koshy, titled "More river stretches are now critically polluted:

    CPCB" and O.A. No. 200/2014, M.C. Mehta v. UOI & Ors. (relating to river Ganga), the Tribunal constituted an independent Monitoring Committee comprising of Central Pollution Control Board (CPCB), State PCB, National Mission for Clean Ganga (NMCG) and District Magistrate, Varanasi to ascertain the factual status and take remedial action. NMCG was directed to file an action taken report in OA No. 200/2014, relating to rejuvenation of River Ganga, inter alia covering status on water quality of Assi and Varuna, action taken on diversion and treatment of sewage, water quality of upstream and downstream of confluence of Assi and Varuna to River Ganga, demarcation of Flood Plain Zones of Assi, Varuna and Ganga (in the said area), in accordance with the River Ganga (Rejuvenation, Protection and Management) Authorities Order, 2016.

    3. Accordingly, an action taken report has been filed on 18.08.2021 by the U.P. State PCB on behalf of the joint Committee. The report mentions the minutes of meeting held on 30.06.2021 at CPCB attended by Dr. A. K. Vidyarthi, Additional Director & DH, WQM-II representing CPCB, Sh. Kalika Singh, RO, UPPCB, Varanasi representing State PCB, Sh. Rajat Gupta, SWM Specialist representing National Mission for Clean Ganga

    2

    (NMCG) and Sh. Gulab Chand, ADM representing District Magistrate, Varanasi. In the said meeting action plan for river Varuna, prepared in pursuance of orders of this Tribunal in OA No. 673/2018, was discussed and revised. Issues of prevention of river water pollution, river ecosystem study and groundwater recharge, sewage and surface runoff management and encroachment were identified and addressing of gaps was planned. Thereafter, water quality was monitored and river restoration plan updated. Survey of all the concerned drains, tributaries was also undertaken. The revised action plan covering Restoration and rejuvenation of Varuna River and Restoration and rejuvenation of Assi River has been proposed which includes steps like de-silting, remediation of waste, development of floodplain, bio-diversity parks, sewage management, sludge management, industrial pollution management, solid waste management, removal of encroachments and monitoring mechanism.

    4. The action plan proposed is reproduced below:

    "Chapter 4. Action Plan Action Plan, Work Plan, Timelines and Implementing Agencies for restoration and rejuvenation of Varuna and Assi Rivers, Varanasi

    Riverscape restoration and rejuvenation of Varuna and Assi A. Restoration and rejuvenation of Varuna River Action Plan 1: Restoration of catchment wetlands located at the origin and downstream from the origin before joining Basuhi river (in this stretch the river is not polluted and does not have water in dry season).

    Table 4.1 Action Plan for Restoration and rejuvenation of Varuna River

    S. No Work Plan Timeline Implementing Agency

    3

    1. Desilting of wetlands upto the bed level and developing embankments with inlets from the catchment Location: i) Mailhan, Phulpur, Prayagr aj (25.599 571N, 82.1073 91E) 10 - 12 months UP Irrigation and Water Resource Department under the guidance of CEMDE
    2. Development of Biotic Communities (at both the above locations and other sites including embankments. CEMDE, University of Delhi

    Action Plan 2: Restoration of Basuhi and Morwa tributaries. Both the tributaries have clean water. However, two drains meet Morwa having small quantity of discharge which get diluted and carry clean water from their catchments and irrigation canal water to Varuna.

    Table 4.2 Action Plan for Restoration of Basuhi and Morwa tributaries

    S. No Work Plan Timeline Implementing Agency
    i. Desilting of channels if it is not done during last 10 year Location: I. Upardaha Taal/Wetland in Handia of Prayagraj district II. Kaitihawa, Tara (a small Pond) nearby Jigna Taal area in Handia, District Prayagraj (U.P) (25.38836 and 82.29644) 6 months Irrigation and Water Resource Department
    ii. Vegetation development along the embankments and restoration riparian zone 2 years CEMDE

    Action Plan 3: Remediation of waste water that is discharged into Morwa (from two drains) and three major drains Dhoraira drain, Durga drain, Basti/ Naya Bazar drain that discharge sewage and industrial waste water into Varuna.

    Table 4.3 Remediation of waste water that is discharged into Morwa

    S. No Work Plan Timeline Implementing Agency

    4

    i. Remediation of waste water using Constructed Wetland System. A schematic Constructed Wetland System (CWS) is attached. These CWS are set up at the confluence of the drain with the tributary/river and extend upto 100 m in the upstream from the confluence point. The length of CWS and number of units depends on the flow of water, the BoD, CoD, TSS and DO levels of water and width of the drain. Locations: i) Dhoraira drain on Varuna at Bhadohi (25.417900N, 82.567600E) ii) Basti/ Naya Bazar drain on Varuna at Bhadohi (25.415251N, 82.576675E) iii)Durga drain on Varuna at Danyalpur, Varanasi (25.320033N, 82.955642E) iv) Burbuspur drain on Morwa at Rampura, Bhadohi (25.409475 N, 82.556622 E) v) Chauri Drain on Morwa at Kom, Bhadohi (25.369723N, 82.606431E) 1-2 years Designed by CEMDE and Implemented by Irrigation and water Resource Department under guidance of CEMDE, water quality will be monitored by UPPCB
    i. Desilting of drains upto bed level and strengthening of bunds with desilted material if not done during the last 5 year 1 year Irrigation and Water Resource Department
    ii. Vegetation development on embankments of restored drain CEMDE

    Action Plan 4: Development of Floodplain Biodiversity Park at Adikeshwar Ghat where Varuna joins Ganga not only to enhance the water quality in Ganga in the stretch but also further enhance the quality of water of Varuna before discharged into Ganga by passing through treatment wetlands. The Biodiversity also help in restoring of riparian ecosystems and in stream community and also provide aesthetic and recreation value to Ganga.

    Table 4.4 Development of Floodplain Biodiversity Park

    S. No Work Plan Timeline Implementing Agency
    i. Plan, Design and Development of Biodiversity Park. A schematic layout of a typical floodplains Biodiversity Park is attached. 5 years CEMDE Irrigation and Water Resource Department (supporting structure) UPPCB (monitoring water quality)

    Action Plan 5: Desilting of river Varuna in stretches where heavy sedimentation has taken place.

    Table 4.5 Desilting of river Varuna

    5

    S. No Work Plan Timeline Implementing Agency
    i. Desilting of river and Strengthening of embankments using desilted material 2 years Irrigation and Water Resource Department
    ii. Vegetation Development on embankments 5 years CEMDE

    Action Plan 6: Monitoring of water quality at different sampling sites to assess the health of river ecosystems.

    Table 4.6 Monitoring of water quality

    S. No Work Plan Timeline Implementing Agency
    i. Monitoring of water quality as per CPCB norms for river water before, during and after restoration 5 years UPPCB

    B. Restoration and rejuvenation of Assi River Action Plan 1: Restoration of catchment wetlands at the point of origin and other wetland in the downstream to enhance the flow rates of water in the river.

    Table 4.7 Restoration and rejuvenation of Assi River

    S. No Work Plan Timeline Implementing Agency
    i. esilting of catchment wetlands and use of esilted material for making embankments ith inlets andwa wetland at Varanasi point of rigin (25.273258 N, 82.962083 E) nd other wetland located in the ownstream from the point of origin. 6 months Irrigation and Water Resource Department
    ii. Remediation of sewage water that enters into catchment wetland using CWS at the mouth of the inlets before the confluence point. The length of wetland depends upon the flow of sewage and depth of water. A schematic layout of a typical CWS is attached. 1 year CEMDE and Irrigation and Water Resource Department
    iii. Vegetation Development on the embankment and development of aquatic communities in the wetland. 2-3 years CEMDE

    Action Plan 2: Remediation of sewage + household industrial waste water using Constructed Wetlands at stretches in the river where width is maximum with one largest CWS at 100 m away from the confluence of river with Ganga.

    6

    Table 4.8 Remediation of sewage and household industrial waste water using Constructed Wetlands

    S. No Work Plan Timeline Implementing Agency
    i. Setting up of CWS at 4 locations where width of river is maximum. The length of CWS depends upon the volume of water, quality of water, width of river. The riparian zones will also be restored. 2 years CEMDE and Irrigation and Water Resource Department

    Action Plan 3: Desiltation of river, if not desilted during the last 5 years and use of desilted material for strengthening of embankments wherever possible.

    Table 4.9 Desiltation of river

    S. No Work Plan Timeline Implementing Agency
    i. Desilting of river up to the bed level and strengthening of embankment with desilted material 1 year Irrigation and Water Resource Department
    ii. Development of vegetation on embankment wherever possible and restoration of riparian zone. 2-3 years CEMDE

    Action Plan 4: Development of Floodplain Biodiversity Parks at the Assi Ghat, from the historical confluence of Assi with Ganga, to the point where diverted. About 25 years ago the Assi River was diverted towards Ravidas Park from Nagwa road and it passes through Nagwa Colony and known as Nagwa drain before confluence with River Ganga. The old route of River Assi which is about 700 meters (from the point of interception Udupi Shri Krishna Madhav Temple to Sant Ravidas Park) carries household sewage and discharge into Nagwa drain. This may help in restoring the original Ghat where Assi used to confluence with Ganga and also enhance the quality of Ganga water.

    Table 4.10 Development of Floodplain Biodiversity Parks

    S. No Work Plan Timeline Implementing Agency
    i. Plan, design and develop Biodiversity Park 5 years CEMDE, Irrigation and Water Resource Department

    Action Plan 5: Monitoring quality of water for sustaining the health of restored river ecosystem.

    Table 4.11 Monitoring of water Quality S. No Work Plan Timeline Implementing Agency

    7

    i. Monitoring of water quality as per 5 years UPPCB CPCB norms before and after

    restoration

    Figure 4.1 Schematic Diagram of Constructed Wetland Figure 4.2 Schematic Diagram of Biodiversity Park

    8

    Sewage Management A. Introduction

    Varanasi city is presently divided into four sewerage districts located within current municipal corporation limits. Under the present sewerage master plan the existing districts are re-aggregated into 4 Districts to correspond roughly with natural drainage catchments. These Districts are described as follows:

    District 1: District 1 is the Central City Sewerage District draining to

    80 MLD Dinapur STP via 6 no. sewerage pumping stations. This area includes the old city, about 1km in breadth and 5km along the Ganga river from Assi to Raj Ghat. Density in this area is very high.

    District 2: District 2 is further bifurcated in 3 zones name 2A,2B,2C & Future Sewerage Area 1 (FSA1). Zone 2A is the Sub-Central District on the cis-Varuna side west of the city centre and zone 2B is a slice of the trans-Varuna district along the Varuna river up to the ridge line defined by the Jaunpur road. Wastewater in these two zones will be collected at 140 MLD Chauka ghat MPS and finally treated in 140 MLD STP at Dinapur

    District 2 Zone 2C: Zone 2C is the trans-Varuna District north of the Jaunpur road. Wastewater in this area generally falls to the north and to the east. FSA1 is north of the trans-Varuna District just outside the current Municipal Corporation limit. Wastewater generated in this area tends to flow north and east towards 120 MLD STP Goithaha.

    District 3: District 3 is the BHU/Assi District south of the city including FSA 4. At present this area is mainly the Banares Hindu University campus which is fully sewered. Wastewater discharged in this area follows natural drains flowing into river Assi nala and Nakkhi nala. FSA4 is outside the current Municipal Corporation limit and surrounds the area occupied by BHU campus. Wastewater in this area drains to Assi river and Nakkhi nala which discharge to Ganga river upstream of the water supply intake and Ghats.currently 2 STP namely 50 MLD Ramana STP and 8 MLD Bhagwanpur STP are in service in district 3.

    District 4: District 4 include FSA-2 and FSA-3 area which is outside the current Municipal Corporation limit. FSA2 is west of the current Municipal Corporation limit, and bounded by North-eastern railway. FSA3 is west of FSA2 and bounded by the Northern railway line. Currently there is no sewage treatment facility available in district 4.

    9

    Figure 4.3 Schematic representation of sewerage district of Varanasi city

    Non-Sewerage Areas (NSA)

    Non-serviced areas are identified as follows:

    NWA1: NSA1 is within current Municipal Corporation limits to the east of the Trans-Varuna district. It includes the local community of Sarnath. Wastewater generated in this area drains naturally into Narokar nala which is now diverted to 120 MLD Goithaha via Intermediate Pumping Station.

    NSA2: NSA2 is within current Municipal Corporation limits to the extreme north west of the trans-Varuna District. Sewage generation will be diverted to 120 MLD GoithahaVaranasi

    B. Sewerage master plan- 2005 (JAPAN INTERNATIONAL COOPERATION AGENCY-JICA)

    JICA formulated sewerage masterplan in 2005. The plan for 2015 is explained in (Figure 1)

    10

    Figure 4.4: JICA Sewerage Plan for 2015

    As per JICA masterplan-2005 (figure 1) the projected population in Assi catchment area for the year 2015 is 78335 + 214570 = 292,905. The projected sewage generation was 14.5 + 39.7 = 54.2 MLD. To cater 54.2 MLD, 8.0 MLD is to be treated by 8.0 MLD existing Bhagwanpur STP and new proposed 37 MLD at Ramna.

    The plan for 2030 is explained in Figure 2

    Figure 4.5: JICA Sewerage Plan for 2030

    As per JICA masterplan-2005 (above) the projected population for the year 2030 is 182781 + 291188 = 476969. The projected sewage generation was 28.3 + 39.7 = 73.4 MLD. To cater 73.4 MLD, new 37 (2015) + 38 (2030) = 75 MLD was proposed.

    11

    However, in 2014 situation, JICA relooked into the sewerage masterplan and revised the capacity of 75 MLD to 59.8 MLD (50 MLD new Ramana STP + Existing 9.8 MLD Bhagwanpur).

    Action plan for Varuna catchment Trans Varuna Catchment

    It consists of sewage District 2 B and 2 C.A new STP of 120 MLD is constructed at Goitha and working efficiently. Around 40 MLD flow is treated. The STP capacity is sufficient for next 15 years. No new STP or upgradation of existing STP is proposed.

    Cis Varuna Catchment

    It consists of District 2 A. The present sewage flow from district 2 A is

    80 MILD, which is being pumped from Chauka ghat pumping station and treated at Dinapur new 140 MILD STP.

    In addition, new 140 MILD STP shall also treat 40 MILD flow diverted from Shahi Nala.

    Recommendations

    140 MLD Dinapur need to be upgraded to meet discharge standard.

    A new STP is needed to cater the future population for District 2 A. Action plan to treat wastewater from Durga drain discharging to Varuna River should be prepared.

    Interceptor drain plan is under execution by UP Irrigation Department. All designs should be checked by expert authorities.

    Figure 4.9: Interceptor drain plan of Varuna River Existing condition in Assi catchment

    At present, as per CPCB measurement (12-15th July 2021), the flow in Assi River is around 92 MLD. In addition, STP at Bhagwanpur also

    12

    treat 8.0 MLD flow and discharges into River Ganga via Nakha drain. Hence total discharge in Assi catchment is 92 + 8 = 100 MLD. However, water supply in municipal area of Assi catchment isonly 26

    MLD.

    The pumping capacity at Nagwa Pumping Station to cater 50 MLD Ramana STP is only 50 MLD, 8 MLD is treated at Bhagwanpur STP and rest 92-50 = 42 MLD discharges directly into the River Ganga.

    Figure 4.12 Present sewerage Situation of Varanasi City

    This rapid increase in flow to Assi River is due to:

    1. Unprecedented residential/commercial growth is due to large no. of developmental projects during last 4-5 years owing to VIP constituency, which seems convincing.

    2. The growth within the city is limited due to constraint of land availability. Assi -BHU area and Trans Varuna area is vast open for development. Hence, increment significantly in migratory/floating population.

    3. Untreated wastewater from Sewerage District 2 & 4.

    4. Much higher water consumption than prescribed 135 lpcd because of unregulated water usage i.e., personnel source of water- submersible pumps etc, which has no control of water usage.

    Recommendations A. Short Term plan

    1. Presently actual discharge is mixed with rainfall. Actual dry weather flow can only be ascertained after rainy season. Detailed

    13

    assessment of excess discharge is required to be done and hence future forecasting is to be done accordingly.

    2. There should be 24-h proper flow measurement of Assi River by both Area velocity and V notch method after the monsoon season.

    3. Controlling wastewater from other sewerage districts.

    4. There should be check and control on non-revenue water (NRW). NRW is defined as loss of water through leakages and illegal usage.

    5. Based on the flow measurement, water supply and population projection, a new STP need to be proposed either at Ravinder Puri Culvert (on the bank of Assi River around 1km upstream of confluence) or at Ramana existing 50 MLD STP site wherever found feasible. The DPR for additional STP is to be prepared after flow assessment and population projection.

    B. Long Term Plan

    1. Wastewater generation is very high, hence proper 24 x 7 water supply with metering is needed to control wastewater generation and non-revenue water. A JICA project is underway to control non- revenue water

    2. Laying of complete sewerage system for the entire city.

    3. 9.8 MLD Bhagwanpur STP need to be decommissioned and new STP for higher capacity for future projections with new standards need to be constructed.

    4. Banaras Locomotive Works STP should be upgraded to meet discharge standard.

    Action plan for Ganga catchment

    The sewage from District 1 (Old Varanasi) is treated in old 80 Dinapur STP. It is pumped from Konia Pumping station.

    Recommendations

    Old Dinapur STP (80 MLD) need to be decommissioned and new STP for higher capacity for future projections (as well as Shahi Nala Flow) with new standards need to be constructed.

    Action plan for trans- Ganga

    One new 10 MLD STP is constructed and treating around 8.0 MLD flow.

    Recommendations

    It is recommended that due to recent infrastructural development, there shall be rapid increase in population in near future.It is assumed that 10 MLD full flow shall be reached within next 1-2 years. Hence, authorities should start planning for the next phase so that no untreated wastewater discharge from the trans Ganga in near future.

    14

    Table 4.12: Action Plan for sewage management in catchment of river Varuna, Assi and Ganga in Varanasi Sl Sewerage Estimated Pumping River Existing Key issues Proposed Action Implementing No District Sewage Station catchm Sewage Plan Agencies

    Generation ent Treatment Timeline for Action

    2030 Facility

    (MLD)

     District 1 covers the old part New STP of higher UttarPradesh Preparation of DPR - 3 Month of the city Varanasi capacity for future Jal Nigam & Approval of DPR - 3 Months including most of the projections with new National Award of Work - 6 Months markets and tourist standard to be Mission for Completion of Work - 2 years destinations constructed after Clean Ganga Total Time required - 36 months

     The district has very less decommissioning of scope of further escalation 80 MLD STP at in sewage generation in near Dinapur. future

     Approx.80 MLD sewage

    Generated inthis district

    currently reaches 80 MLD

    Dinapur STP for treatment

    Konia through Konia and Saraiya

    MPS, 80 MLD Pumping station via Old Cis

    1 District 1 93.7 Saraiya STP Trunk Sewer Varuna

    P.S. 3.7 DinapurThe rest of the sewage from MLD old trunk sewer is

    discharged into river Management of rest Ganga through of the sewage from closed conduit at Shahi old trunk sewer, Nala Outfall, Rajghat presently discharging Uttar Pradesh  Dinpaur 80 MLD STP has Work to be completed - 3 monthsat Shahi Nala outfall Jal Nigam completed the design life through pumping to

    and it was designed as per 140 MLD STP

    old discharge standards Dinapur.

    resulting in non-compliance

    of STP to norms prescribed

    by NGT

    15

     Chaukaghat pumping station is currently pumping only 70- 80 MLD to Dinapur 140 MLD STP.  The interception and Preparation of DPR for upgradation diversion of Shahi Nala - 3 months The 140 MLD STP outfall at Rajghat to requires upgradation Chaukaghat pumping Uttar Pradesh Jal Approval of Work - 3 months to meet the norms station through a new Nigam & National prescribed by

    rescue trunk sewer is Mission for Clean Award of Work for upgradation - 3 Hon'ble NGT proposed and work is Ganga months Completion of upgradation including nutrient underway - 6 months removal

     The Cis-interceptor line at

    Varuna bank will also Total time required - 12- 14 months

    intercept the untapped

    drains on the cis Varuna

    Chauka bank to Chauka Ghat

    225.3 Ghat MPS pumping station for (including (140 MLD), Cis 140 MLD

    2 District 2A pumping to Dinapur 140 NSA 1&2 & Phulwaria Varuna STP Dinapur MLD STP FSA-1 MPS (7.6  ASP technology based 140 MLD) Design of MLD Dinapur STP without interceptor plan tertiary filtration needs to be checked  No Biological nutrient by expert agency and removal (BNR) system Design finalization - 1 month tapping shall be  Under capacity utilization executed completely Irrigation  I&D of drains (mainly Shahi I&D work completion with final  I&D work of drains Department, Uttar Nala) is not completed tapping and pumping provisions - 2 falling into Varuna in Pradesh Jal Nigam  Damaged & non-functional months Cis-Varuna area & subject expert

    I&D structure shall (mainly Shahi Total time required- 3 months

    Nala) to be

    completed and

    tapped to STPs for

    treatment

    16

     Trans Varuna area contains zone 2B & 2C sewage

    districts which has its sewage reaching partially for treatment at Goithaha STP through 7.6 MLD

    Narokhar pumping station and rest quantity by gravity.  An interceptor line is under commissioning in trans Varuna river bank for interception of 7 drains in the area discharging into Varuna currently and other small minor outfalls from lanes  Design of interceptor

    District 2B Irrigation Department, Uttar Pradesh Jal Nigam & subject expert Design finalization – 1 month I&D work completion with final tapping and pumping provisions – 2 months Total time required- 3 months
    Design of interceptor plan needs to be checked by expert. Interception and diversion have to be completed at the earliest by the executing agencies

    been connected with checked by expert. Irrigation

    Narokhar I&D work completion with final

    Trans 120 MLD pumping station currently  Interception and Department, Uttar

    3 District 2B IPS (7.6 tapping and pumping provisions - 2 Varuna STP Goitaha and the interceptor system diversion have to be Pradesh Jal Nigam MLD) months

    is open to flow completed at the & subject expert

     This interceptor line will earliest by the Total time required- 3 months

    pump the sewage to 140 executing agencies MLD Dinapur STP for

    treatment through Chauka

    Ghat MPS as an interim

    measure

     The Goithaha STP is

    currently functioning at

    around 30-40 MLD

    treatment (Under capacity

    utilization)

     Currently the catchment

    area of Goithaha STP has

    less population density so

    the capacity utilization is

    less and it is targeted to

    achieve future utilization

    17

     I&D of the Trans Varuna area is not completed.  Damaged & non-functional I&D structure meant for intercepting the Trans Varuna bank drains.

    District 2C Uttar Pradesh Jal Nigam, Varanasi Municipal Corporation, Irrigation Department and Urban Development Department Preparation of DPR – 6 months Approval of Work – 6 months Award of work – 6 months Execution of work – 2 years Total time required- 36-42 months
    new comprehensive ewage management lan for trans Varuna eeds to be developed hich can cater all the rains of trans Varuna rea in Varanasi.

    sewage management Municipal Approval of Work - 6 months

    plan for trans Varuna Corporation,

    4 District 2C needs to be developed Irrigation Award of work - 6 months which can cater all the Department and

    drains of trans Varuna Urban Execution of work - 2 years area in Varanasi. Development Total time required- 36-42

    Department months

    18

     Estimated much higher water

    consumption/discharge than prescribed Varanasi Municipal  Detailed

     Unregulated water uses and Corporation, Urban assessment of flow of freshwater from Development excess discharge in Kanchanpur talab and Department and dry weather other water bodies in the Uttar Pradesh Jal  Control on NRW

    low-lying areas joining river Nigam

    Assi shall be identified and

    fresh water channels shall

    be separated from the

    sewerage line/drain

    50 MLD  Estimated approximately

    STP

    Nagwa 50% Non -revenue water  A new STP of Ramana, 8

    5 District 3 73.5 MPS (50 Assi River (NRW) is consumed of total adequate capacity Uttar Pradesh Jal Preparation of DPR - 3 Month

    MLD STP

    MLD) freshwater usags to treat the excess Nigam & National Approval of DPR - 3 Months Bhagwanp  Excess wastewater around approx. 50 MLD Mission for Clean Award of Work - 6 Months ur 40- 45 MLD goes directly to flow from the Assi Ganga Execution of work - 2 years Ganga River from the river outfall.

    bypass point of Nagwa 50

    MLD pumping station

     Bhagwanpur STP treats the  New STP at

    sewage from Banaras Hindu Preparation of DPR - 3Months Bhagwanpur of University campus and Approval of DPR - 3 Months requisite capacity to treated sewage discharged Uttar Pradesh Jal be constructed as

    through the Nakha drain Nigam & National Award of Work - 6 Months per new norms & which also carries Mission for Clean Completion of Work - 2 years flow data to cater untreated sewage from the Ganga the needs of BHU

    Bhagwanpur local area and Total Time required - 32- 34  and nearby nearby areas of district 3. months municipal areas.

    19

     The Bhagwanpur STP is designed to treat 9.8 MLD sewage (8 + 1.8) but currently only 8 MLD plant is operated and 1.8 MLD unit is nonoperational  The Bhagwanpur STP treats around 10 MLD sewage working overcapacity  The Bhagwanpur STP has completed its designed life  Restoration of origin  Large areas in adjoining & stretches of river district 4 and district 4 has Irrigation Assi (with land recently been added in Department, availability) through Municipal area and has no Varanasi Municipal constructed sewage management Corporation, Urban wetlands. Within 6 months system existing which Development  Separation of contributes to excess flow Department and freshwater from district 2 & 4 reaching Uttar Pradesh Jal channels/storm river Assi. Nigam water drains and

    sewerage system

     Most part of the Sewerage CEMDE Delhi Preparation of feasibility reports & In-situ treatment at district 4 has recently been University, DPR - 02 Months

    Durga Drain through

    included in the Varanasi Irrigation

    Constructed Wetland

    Municpal Area and Department, Approval of Work - 3 Months

    as interim measure.

    estimation and planning for Varanasi Municipal Award of work and implementation the newly added areas is Corporation. - 3 Months

    underway Total Time required - 8- 12

    Cis Not  Currently no dedicated

    months

    6 District 4 45.1 None Varuna available treatment facility available  No sewerage networks

     'Untreated sewage directly

    discharges in R. Varuna.

     The Durga (Lohta) drain is

    the major drain Uttar Pradesh Jal Preparation of DPR - 01 Month New STP of requisite discharging to River Nigam & National Approval of DPR - 3 Months capacity to be Varuna from the district Mission for Clean constructed as per Ganga. Award of Work - 6 Months

    20

     Actual discharge status is new norms & flow Completion of Work - 2 years unknown data. Total Time required - 32- 34

     Lohta STP (50 MLD) is months

    proposed by 2030 (JICA Detailed assessment Irrigation report) of excess discharge in Department, Uttar Within 2 months dry weather Pradesh Jal Nigam,

    Urban

    Development

    department

    21

     The BLW campus has a STP of 12 MLD installed inside campus to treat the sewage generated in the campus.  The BLW campus lies in the Assi river catchment.  At least one drain originates from the campus and two Preparation of DPR - 01 Month drains passes near the BLW Approval of DPR - 3 Months Award campus and ultimately of Work - 6 Months Completion of discharges into river Assi Work - 2 years Total Time required  DLW-1 originates from the - 32- 34 months campus and carries treated BLW STP has

    sewage and storm water outlived its designed from the BLW campus life BLW Engineering

    Banaras  DLW-2 originates from the Department, UP Locomoti 50 Staff Cis

    7 12 MLD Manduwadih area and flows

    BLW STP shall be

    Jal Nigam, National

    ve Work colonies Varuna near the BLW campus upgraded/new STP to Mission for Clean (BLW)  DLW-1 and DLW-2 be installed to meet Ganga

    ultimately meets river Assi norms prescribed by

    near Sunderpur Chauraha NGT including for

    DLW-3 originates from the coliform count

    Kanchanpur taal area and

    carries pond water and

    waste water from nearby

    low-lying areas

     DLW 3 meets river Assi near

    the DLW campus trans of

    DLW-Chunar Road.

     Around 2-3 MLD

    wastewater from this drain

    is treated at BLW STP for

    sometime

    22

     The 12 MLD STP at DLW Reason for weak operates at around 4 MLD organic load only and the inlet raw characteristics of BLW Engineering sewage shows weak sewage sewage at inlet of BLW Department, UP characteristics with low STP shall be explored Jal Nigam, Uttar Within 1-2 Month organic load  Water audit of water Pradesh Pollution

     STP has no disinfection usage and discharge Control Board system to control Coliform from BLW campus

    count in treated sewage may be done

    Sources of sewage and BLW Engineering

    freshwater in the Department,

    BLW Engineering Department, Irirgation Department, Urban Development Department, UP Jal Nigam, Uttar Pradesh Pollution Control Board Identification of sources of waste and freshwater – 1 Months Preparation of action plan for separation of freshwater channels/storm water and waste water carrying drains– 6 Months
    ources of sewage and reshwater in the rains near the BLW ampus ultimately ischarging into Assi iver shall be dentified and eparated for reducing he flow in Assi river at nterception point

    and freshwater - 1 Months

    campus ultimately Department,

    discharging into Assi Urban

    river shall be Development Preparation of action plan for

    separation of freshwater

    identified and Department, UP

    channels/storm water and waste

    separated for reducing Jal Nigam, Uttar

    water carrying drains- 6 Months

    the flow in Assi river at Pradesh Pollution

    interception point Control Board

    Table 4.13: Road map for execution of proposed action Plan for restoration of Varuna & Assi river Sr. Sewerage Existing Proposed Project Activity

    No. District Sewage Action/remedial

    /region Treatment measure Work Plan Time line Implementation Agency

    Facility

    80 MLD Decommissioning Condition assessment & 1 Month UP Jal Nigam/ Other STP of existing STP feasibility report (CAFR) government organization and construction Approval of CAFR 1 month NMCG

    23

    1. District 1 Dinapur of new STP of Submission of DPR 2 Months UP Jal Nigam/ Other higher capacity government organization

    for future Administrative approval & 2 months NMCG

    projections with estimated sanctioned

    new standard Tendering & award of project 2 months NMCG

    Basic Engineering Package (BEP) 3 months UP Jal Nigam/ Other submission government

    organization /EPC

    Design & Engineering 2 months cIIoTn/MtraNcItTo/rDeemed

    approval university

    Construction & 2 years UP Jal Nigam/ EPC

    Commissioning contractor/others

    2. District 140 MLD STP Upgradation of STP Submission of DPR 2 Months UP Jal Nigam/ Other 2A as per new NGT government organization

    Dinapur norms.

    Approval & Tendering 3 months NMCG
    Design assessment of interceptor plan 2 months IIT/MNIT/Deemed university
    Approval, Tendering and project award 3-4 month NMCG

    24

    needs to be Construction & 3-4 month UP Irrigation checked by expert commissioning

    I&D work of Tapping and diversion of Sahi 1-2 months dPreopjaercttm ise unnt/dEePrC e cxoencutrtaioctno bry Shahi Nala nala to 140 MLD STP UP Jal Nigam

    I&D work of drains I&D work of drains up to 1-2 months Project is under execution by in cis Varuna 140 MLD MPS Chaukaghat UP irrigation department

    region

    3. District 120 MLD I&D work of I&D work of drains up to 1-2 months Project is under execution by STP drains in trans 140 MLD MPS Chaukaghat UP irrigation department 2B Varuna region as an interim measure

    4. District Goitaha Development of Condition assessment & 1 Month UP Jal Nigam/ Other new feasibility report (CAFR) government organization

    2C comprehensive Approval of CAFR 1 month NMCG

    sewage Submission of DPR 2 Months UP Jal Nigam/ Other

    government organization

    management plan Administrative approval & 2 months NMCG

    for trans Varuna estimated sanctioned

    Tendering & award of project 2 months NMCG

    BEP submission 3 months UP Jal Nigam/ Other

    government

    organization /EPC

    Design & Engineering 2 months IcIoTn/MtraNcItTo/rDeemed

    approval university

    Construction & 1-2 years UP Jal Nigam/ EPC

    Commissioning contractor/others

    50 MLD Assessment of Detailed assessment of excess 3-4 months UP Jal Nigam STP excess discharge of Assi River in dry

    discharge of weather &

    Assi River

    Control on NRW

    25

    5. District 3 Ramana, Design, Condition assessment & 1 Month UP Jal Nigam/ Other construction and feasibility report (CAFR) government organization

    8 MLD STP commissioning of Bhagwanpur new tapping Approval of CAFR 1 month NMCG

    Submission of DPR 2 Months UP Jal Nigam/ Other government organization
    Administrative approval & estimated sanctioned 2 months NMCG
    Tendering & award of project 2 months NMCG
    BEP submission 3 months UP Jal Nigam/ Other government organization /EPC contractor
    Design & Engineering approval 2 months IIT/MNIT/Deemed university
    Construction & Commissioning 1-2 years UP Jal Nigam/ EPC contractor/others
    Restoration of Origin & stretches through constructed wetlands Submission of design details & drawing of CWS 1 month CEMDE
    Submission of DPR for desilting, civil work etc. 2 months Irrigation and water resources department/
    Approval, Tendering and project award 3-4 month NOMthCeGr government
    Desilting and civil construction 3-4 months Irrigation and water resources department/
    Vegetation development & commissioning 1-2 years COEtMheDrE government
    Condition assessment & feasibility report (CAFR) 1 Month UP Jal Nigam/ Other government organization

    Bhagwanpur And Approval of CAFR 1 month NMCG

    Design, Submission of DPR 2 Months UP Jal Nigam/ Other

    Construction and government organization

    26

    commission of Administrative approval & 2 months NMCG new STP as per estimated sanctioned

    Tendering & award of project 2 months NMCG
    BEP submission 3 months UP Jal Nigam/ Other government organization /EPC contractor
    Design & Engineering approval 2 months IIT/MNIT/Deemed university
    Construction & Commissioning 1-2 years UP Jal Nigam/ EPC contractor/others
    1 month In-situ development of Constructed Wetland System in Durga Drain as interim measure Submission of design details & drawing of CWS CEMDE
    Submission of DPR for desilting, civil work etc. 2 months Irrigation and water resources department/ Other government organization
    Approval, Tendering and project award 3-4 month NMCG
    Desilting and civil construction 3-4 months Irrigation and water resources department/ Other government
    Vegetation development & commissioning 1-2 years oCrgEaMnDizEation
    Condition assessment & feasibility report (CAFR) 1 Month UP Jal Nigam/ Other government organization

    new STP of Approval of CAFR 1 month NMCG

    27

    District 4 available requisite capacity Submission of DPR 2 Months UP Jal Nigam/ Other

    6. as per new norms government organization & flow data

    Administrative approval & 2 months NMCG estimated sanctioned

    Tendering & award of project 2 months NMCG BEP submission 3 months UP Jal Nigam/ Other government organization

    /EPC contractor

    Design & Engineering 2 months IIT/MNIT/Deemed approval university

    Construction & 1-2 years UP Jal Nigam/ EPC Commissioning contractor/others

    7. Varuna Not Restoration of Submission of design details 1 month CEMDE origin catchment & drawing

    available origin of R. Submission of DPR for 2 months Irrigation and water Varuna desilting, channeling etc.

    resources department/

    Approval, Tendering and 3-4 month NOMthCeGr government project award

    Desilting, channeling and 10-12 months Irrigation and water other construction work

    resources department/

    Biotic community 1-2 years COEtMheDrE government

    Not Desilting of R dSeuvbemloispsmioenn otf & d erseisgtno draettiaoinls 1 month CEMDE Varuna & In-situ & drawing of CWS

    development of Submission of DPR for 2 months Irrigation and water Constructed desilting, civil work etc. resources department

    Wetland System Approval, Tendering and 3-4 month NMCG

    in Dhoraira, Naya project award

    Desilting and civil 3-4 months Irrigation and water

    construction resources department

    28

    8. Along R. available Bazar, Bubuspur Vegetation development & 1-2 years CEMDE Varuna and Chauri drains commissioning

    9. Varuna confluence Not available Development of flood plain Biodiversity Park Demarcation of flood plain of R. Vruna at confluence 3-4 months Irrigation and water resources department
    Submission of DPR for planning, design & development of Biodiversity park 3-4 months CEMDE
    Approval, Tendering and project award 3-4 month NMCG
    Development of Biodiversity park 4-5 years CEMDE

    29

    Performance assessment of STPs and requirement for upgradation /augmentation

    The estimated sewage generation of Varanasi (including Ramnagar) is approximately 330 MLD (201718) (as per data received from UPPCB). Total 7 STPs (5 commissioned and 2 under trial) with total capacity of 421.8 MLD (361 MLD for commissioned STPs and 60 MLD for under trial STPs) have been installed for the treatment of the generated sewage. Utilized capacity of the commissioned and operational STPs is approximately 210 MLD.

    Characteristics of raw sewage received at inlet of STPs located in Varanasi have BOD ranging from 10.5 mg/l to 52.4 mg/l, COD ranging from 45.7 mg/l to 193 mg/l indicating weak sewage as compared to typical municipal wastewater (BOD: 200-250 mg/l, COD: 350-500 mg/l); is received at inlet of the STPs. The weak sewage strength could be due to dilution of the sewage from septic tanks and addition of grey water from households etc. As per inspections conducted in last 2 years, the treated sewage from STPs is found non- complying with respect to the discharge norms. As per inspection dated 23.06.2021, reduction in BOD was found in range 38% to and 85%. Similarly, reduction in the COD was found in range 39% to 81%. STPs meet the prescribed norm for Total Nitrogen (10 mg/l) only when raw sewage with low Total Nitrogen (around 10 mg/l) is received. This necessitates upgradation and augmentation of these STPs. The measure suggested for the upgradation and augmentation of STPs are mentioned in the table below.

    Discharge norm for Fecal coliform (230MPN/100ml) is not achieved in all STPs. Hence to achieve the norms there is requirement of upgradation/optimization of the existing disinfection system or installation of new disinfection system (if no disinfection system is present). The inflow at STP at Bhagwanpur is ranging from 8-14 MLD which is above the designed capacity (9.8 MLD). This STP needs capacity enhancement after detailed study for capacity requirement. STPs at Dinapur and Goithaha are underutilized. The reason for less inflow into STPs should be studied and areas without sewerage network should be provided with sewerage network and connected to respective STP.

    Online continuous Effluent System (OCEMS) is installed at 12 MLD STP, BLW only. OCEMS should be installed at remaining 6 (4 operational and 2 under trial) STPs and connected to CPCB/ SPCB server at the earliest for on-line monitoring of the STPs.

    30

    Table 4.14: Performance assessment of STPs of Varanasi and requirement for their upgradation and augmentation.

    Sr. No STPs Technol ogy & Process used Designated Capacity (MLD) Maximum Utilised Capacity (inspection date) Inlet characteristics (mg/l) Discharge to river Operational/ Non- operational/ Non- functional Compliance with respect to discharge standards (2021) Suggested upgradation and Augmentation
    1 Dinapur (Old) STP TF followed by ASP 80 70 (23.06.2021) BOD – 46.4, COD – 160, TSS – 169 TN – 7.02 (23.06.2021) Ganga through open channel Operational Mostly found non-complying for FC 1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be ensured in the existing ASP 2. Optimization of existing disinfection system 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas
    2 Dinapur (New) STP ASP 140 125 (23.02.2021) BOD-52.4 COD-161 TSS- 138 Varuna river through pipeline Operational Mostly found non-complying for TN and FC 1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be

    31

    TN-16.5 (23.06.2021) ensured in the existing ASP 2. Optimization of existing disinfection system. 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas
    3 Bhagwanpur BHU STP ASP 9.8 14 (23.06.2021) BOD-24.9 COD-92.2 TSS- 1242 TN- 8.83 (23.06.2021) River Ganga through Nakkhi Nala Operational Mostly found non-complying for TN and FC 1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be ensured in the existing ASP. 2. Optimization of existing disinfection system. 3. Installation of OCEMS 4. Capacity Enhancement
    4 Goithaha STP SBR 120 55 (23.06.2021) BOD-56.3, COD-193 TSS- 491 River Ganga via Sharda Canal Operational Mostly found non-complying for FC 1. Installation of Anoxic treatment of adequate capacity before existing ASP. Return activated sludge flow (about 75% of inflow) may be

    32

    TN- 6.49 (23.06.2021) ensured in the existing ASP. 2. Optimization of existing disinfection system 3. Installation of OCEMS 4. Provision for sewerage network in uncovered areas
    5 BLW (formerly DLW) STP ASP 12 5 (23.02.2021) BOD-10.5, COD-45.7, TSS- 19.1 TN- 6.13 (23.06.2021) Reused (may reach Ganga through Assi river) Operational Mostly found Non-Complying for FC 1. Disinfection system of adequate capacity

    (23.06.2021)

    2. Optimization of existing disinfection system

    3. Installation of OCEMS

    4. Provision for sewerage network in uncovered areas

    5 BLW ASP 12 5 BOD-10.5, Reused Operational Mostly found 1. Disinfection system of (formerly (may Non-Complying adequate capacity

    DLW) STP (23.02.2021) COD-45.7, reach for FC

    Ganga

    TSS- 19.1

    through

    TN- 6.13 Assi river)

    (23.06.2021)

    Note: Compliance status as per Hon'ble NGT order dated 30.04.2019. (pH: 5.5- 9.0; BOD: 10 mg/l; TSS: 20 mg/L; COD: 50 mg/L; Total Nitrogen (TN):

    10 mg/L; Total Phosphorus (for discharge into ponds and lakes): 01 mg/L; Faecal Coliform: Desirable limit 100 MPN/100 ml, Permissible limit 230 MPN/100ml)

    33

    Sludge Management Plan

    Treatment and disposal of sewage sludge are major factors in the design and operation of all wastewater treatment plants. Two basic goals of treating sludge before final disposal are to reduce its volume and to stabilize the organic materials. Stabilized sludge does not have an offensive odour and can be handled without causing a nuisance or health hazard. Sludge management is an issue of great concern due to its potential threat to human health and the environment with necessitated explicit regulations to organize their production and use. Currently adopted sludge management plan practices as provided by UP Jal Nigam for management of generated sludge is tabled below;

    Table 4.15: Sludge management plan for generated STPs sludge Sr Name of Capacity Approximate Disposal of Remarks No. STP (MLD) Generation sludge

    of Sludge

    (Tonnes/Yr.)

    1 Dinapur 80 8250 Being used as Since, removal ingredient of of Nitrogen

    2 Dinapur 140 6500 Fertilizer by local and farmers/manufact Phosphorous

    ures is not part of

    3 Bhagwan 9.8 275 Being used in the design pur Horticulture. process, hence the sludge has

    nutritional

    value and is

    being used as

    an ingredient of

    fertilizer.

    4 Goithaha 120 4350 Being used in Process land fill at design of

    various STPs contains

    locations. provision for

    5 Ramana 50 5200 Proposed to be removal of used in land fill at Nitrogen and STP site itself. Phosphorous, hence

    6 Ramnagar 10 740 Proposed to be generated used in land fill at sludge doesn't STP site itself. have

    nutrients.

    Industrial Pollution Control Industrial Pollution Management

    During recent survey, 118 water polluting industries located in Varanasi and Bhadohi having potential to discharge into river Ganga and its tributary Varuna were inventoried which comprised Textile/Yarn (54 units), Sari Printing (33 units), Metal surface treatment (23 units), slaughter houses & meat processing (03 units), food & beverage (03 units) and Heavy engineering & Loco (02). Out of 118, 87 units are from textile/yarn and Sari printing sector.

    34

    Action Plan for prevention of pollution from Textile Cluster

    Central Pollution Control Board (CPCB) has formulated the 'Charter for Water Recycling and Pollution Prevention in Textile industries" in consultation with experts from the departments of Chemical Engineering & Technology, IIT (BHU), Textile Engineering Department, IIT Delhi, Polymer and Fiber Technology, IIT Delhi, Fibre and Textile Processing, ICT, Mumbai, UP Textile Technology Institute, Kanpur and Textile industries (Annexure-V).

    Charter is based on participatory approach and one of the important objectives of charter is to setup a bench mark for water consumption & optimize the use of water & chemicals in processing. Charter is formulated, with a view to envisage upgradation of the status of textile industries in sustainable manner in terms of process technology upgradation, adoption of best practices, improved environmental performance, substantial reduction in the fresh water consumption and waste water generation, improvement in effluent treatment including tertiary treatment and optimize water recycling. Compliance with the prescribed standards is mandatory. There will be no compromise with regard to the industry not meeting the prescribed standards.

    Charter prepared for textile industries was launched in the workshop with the textile units at Kanpur on 05.04.2019. For implementation of Textile Charter to all River Ganga Main Stem GPIs, UPPCB issued direction under section 33A of Water (Prevention and control of Pollution), 1974 on 08.05.2019.

    Charter was discussed with textile mills and experts at a workshop organized by Carpet Export Promotion Council at Bhadohi on 6th August, 2018. A workshop was also organized by UPPCB on implementation of "Charter for water recycling and pollution prevention in Textile industry" was held on 15th Oct, 2019 at Bhadohi.

    As per data available with CPCB, during 2020, there were 31 textile sector GPIs in Bhadohi cluster and out of 31, 22 Textile units have prepared their individual action plan which were reviewed and the suggestions has been communicated to individual unit in the month of March-April, 2020 for implementation of recommendations as per charter.

    However, during recent survey 54 yarn/textile and 33 sari printing units have been inventoried in Bhadohi, Jaunpur and Varanasi region in catchment of river Ganga and Varuna. Therefore, it is suggested that charter should be implemented in textile industrial cluster located in catchment of river Ganga and its tributaries in Uttar Pradesh in effective manner which will results in reduction in the fresh water consumption and waste water generation, optimize water recycling and overall improved environmental performance of industrial unit in sustainable manner. A monitoring committee may also be constituted to monitor the implementation status of charter in textile sector in a prescribed time frame.

    Solid waste management

    35

    Proper Solid waste treatment system based on Indore or Goa model need to be prepared along with Waste to Energy system. The un-segregated solid waste dumped in open plots or ponds/low lying areas within 500 meter of river Varuna in Varanasi contribute air and ground water pollution. The estimated quantity of legacy waste in this dumping site is approximately 30000 MT. Management of legacy waste having adequate capacities for collecting, transporting and disposing of the municipal solid waste produced on a day-to-day basis as well as legacy waste trapped in the dumpsites is proposed to be done.

    Illegal disposal of Construction and demolition waste in floodplain zone of river Varuna and Assi shall be prohibited.

    Solid waste management plan of Varanasi City

    Varanasi city has an estimated population of 15, 31,458 in 2020 based on projections for population taking 2011 population as base. Owing to its rich tourism potential, the estimated daily flow of tourists and pilgrims to the city is 25,000. The total area within Varanasi Nagar Nigam (VNN) is 82.1 km square for 90 wards and 86 more Villages have been merged with VNN area of 195 Sq km. The average waste generation of Varanasi is 0.400 kg per capita per day. The city at present generates 600 MT (Approx.) of waste per day at the rate of

    0.400 Kg per capita per day and decadal population growth of 2.67 per Year (as per trend of rate of population growth in last 10 year:

    2001-2011)

    Table 4.16: Population Projection and waste generation for Varanasi City

    Year House Hold Population Waste generation MT/Day (approx) @

    400 gm per capita

    per day

    2011 191278 11,98,491 479.39
    2021 (for 90 Wards) 248300 15,31,458 612.58
    2021 (For 86 Newly merged villages-20 wards) 151759 4,76,779 190.71
    2035 (for 110 Wards) 512012 29,64,678 1185.87
    2050 (for 110 wards) 655375 40,93,136 1637.25

    The Government of India published the Solid Waste Management

    Rules, 2016, the Rules are now applicable beyond Municipal areas

    and extend to urban agglomerations, census towns, notified

    industrial townships, etc.

    Administrative setup for MSW Management in Varanasi

    36

    The area falling under Varanasi Municipal Corporation is currently divided into 5 zones and 14 Subzone and 90 wards for administrative purposes and 86 newly merged villages. The details are annexed as Annexure VII.

    Table 4.17: Manpower Engaged in Varanasi Nagar Nigam (VNN) for MSW Management
    Designation No
    Municipal Commissioner 1
    Additional Municipal Commissioner 1
    Municipal Health officer 1
    Executive Engineer’s. (Transport & Processing-SWM) 2
    Zonal Officers 5
    Zonal Health officers 1
    Sanitary & Food Inspector 14
    Account Clerk 01
    Account Officer 02
    Safai Supervisors 93 (VNN-38 and Varanasi Waste Solution-40)
    Safai Mitra’s and drivers 5784 (VNN Safai Mitra’s = 4171, VWSPL Safai Mitra-850, VNN drivers = 331, VWSPL Drivers- 195, Rag Pickers = 237)

    Currently there are no 100% door to door collections in 90 wards

    of Varanasi. Most of the households, shops, and establishments

    throw their waste just outside their premises, on streets, in drains,

    in open spaces, in water bodies, and in other inappropriate places.

    These litters swept away by street sweeping and lifted by means

    of handcart or rickshaw trolley by Sweepers and waste collectors

    of VNN, this led to unsanitary condition across the city.

    Varanasi Nagar Nigam outsourced M/s Varanasi Waste solution

    Pvt. Ltd. For door to door collection in 90 wards, mechanized road

    Sweeping approx.. 22.1 km. daily basis (Sant. Athulananda to

    BHU) and toilet cleaning work of Varanasi.

    Apart from door to door collection three Ngo's named Anthill

    Services Pvt. Ltd; career consulting pvt. Ltd, Jan Vikas Kalyan

    Samiti; Engage for IEC activities for sanitation awareness in their

    respective wards.

    The length of roads, streets, lanes, bye-lens in the city is

    approximately 1200 km in the total and approx. length of drains

    2400 km area within Varanasi Nagar Nigam of 82.1 km square.

    Street sweeping starts between 8:00 AM and continues up to 2:00

    PM.

    The detailed action plan for MSW management in Varanasi city is enclosed as Annexure-VII

    37

    Encroachment

    Removal of encroachment from lower floodplain zone of river Varuna and Assi. Demarcation and notification of floodplain zone by introducing pillars to further prevent encroachment in River Varuna and Assi.

    Monitoring Committee a. Supervisory Committee - It may supervise the implementation of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist of representative from District Magistrate, Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, NMCG, UPPCB and CPCB under the chairmanship of Commissioner of Varanasi division, meeting to be held on quarterly basis.

    b. Execution Committee - The committee may responsible for execution of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, SMCG and SPCB under the chairmanship of District Magistrate of concerned district, meeting to be held on monthly basis."

    5. The report shows that there are serious issues adversely affecting rivers Varuna and Assi calling for remedial action in the form of desilting, remediation of waste water, development of constructed wetland systems and bio-diversity parks, apart from management of sewage, industrial pollution and solid waste which requires concerted and continuing steps and monitoring.

    6. Since the issues and remedial steps have been identified by the joint Committee and exhaustive recommendations for remedial action made, there is need for execution of the action plan at the ground level in the light of above report. This requires coordination among the concerned departments including the Local Bodies, District Administration and State Government.

    7. Accordingly, the Supervisory and Execution Committees suggested in the report may take further action. In terms of suggestions of the

    38

    Committee, problem of chocking at the origin point of said rivers may be remedied by taking restoration measures. The execution Committee may meet atleast once in a month under the Chairmanship of District Magistrate, Varanasi and the Supervisory Committee may meet on quarterly basis under the Chairmanship of Commissioner, Varanasi Division, as suggested. The District Magistrate as well as Commissioner, Varanasi Division may have full time environmental coordinators attached to them directly for this purpose either out of the existing incumbents or by specially engaging a suitable person for the task. It will be appropriate that minutes of the meeting of the District Magistrate as well as Commissioner, Varanasi are placed on their respective websites, which may enable public information and participation. Having regard to the significance of the issue and need for prompt action for keeping the important rivers pollution free, the timelines need to be shortened which aspect may be considered by the Execution and the Supervisory Committees. We request the Oversight Committee constituted by this Tribunal headed by Justice S.V.S. Rathore, former Judge of the Allahabad High Court to oversee the steps taken in the matter, if necessary, by periodically interacting with the Execution and Supervisory Committees.

    8. We further direct the NMCG and CPCB to monitor progress of implementation of action plan in accordance with the Namami Gange project.

    9. The action plan may be placed on the website of CPCB and also circulated by CPCB to the River Rejuvenation Committees of all the States/UTs through respective State PCBs/PCCs, for appropriate consideration of their respective action plans to the extent found necessary.

    39

    10. The issue of funding of the projects proposed may be worked by the NMCG and the Chief Secretary, UP and wherever Namami Gange funds are found inadequate, it will be the responsibility of the State of UP to provide the same.

    The application is disposed of.

    A copy of this order be forwarded to CPCB, NMCG, Chief Secretary, UP, Additional Chief Secretary, Irrigation Department, UP, State PCB and District Magistrate and Commissioner, Varanasi Division by e-mail for compliance.

    A copy of this order be also provided to all other concerned departments by the Additional Chief Secretary, Irrigation Department, UP. A copy of this order be also forwarded to Justice S.V.S. Rathore, former Judge of the Allahabad High Court by e-mail. Adarsh Kumar Goel, CP

    Sudhir Agarwal, JM

    Dr. Nagin Nanda, EM

    November 23, 2021

    Original Application No. 128/2021

    DV

    40