AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Sub-section 1503.1 of Section 1500 of MORT&H specification (4 revision)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Judges
Acts
  • Sub-section 1503.1 of Section 1500 of MORT&H specification (4 revision)
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The petitioner is a registered Super-Class Contractor who challenged an order dated 12 December 2017 issued by the Chief Engineer (DPI & Roads), Odisha, which blacklisted the petitioner from participating in or bidding for any Government of Odisha works and from transacting business with the Government (directly or indirectly). The factual nucleus is an accident during concreting of a rail over bridge (ROB) at Level Crossing No. 188 SPL-3E near Bhubaneswar where a ten-metre slab collapsed, resulting in one death and several injuries.

Following the accident, the Works Department constituted a Committee which submitted a report on 26 September 2017 attributing responsibility to the petitioner. On 10 October 2017 the Under Secretary, Works Department, wrote to the Chief Engineer stating that Government orders had been obtained for blacklisting the petitioner and requesting immediate action to process blacklisting pursuant to the OPWD Code. A show cause notice (SCN) was issued by the Chief Engineer on 18 October 2017. The petitioner replied on 1 November 2017 denying wrongdoing and describing departmental inspections and approvals prior to concreting; it asked the Department to withdraw the SCN.

Despite the reply, the Chief Engineer passed the impugned blacklisting order on 12 December 2017, blacklisting the petitioner with immediate effect and suspending its Super-Class registration. The petitioner filed the present writ petition challenging that order. The Court heard senior counsel for the petitioner and counsel for the opposite parties. By an order dated 26 November 2018 this Court permitted the petitioner to approach the Chief Engineer with a representation. The petitioner submitted a twelve-page representation on 11 December 2018. The Court observed that the direction to take a fresh decision within two months of the representation did not appear to have been complied with. The Court was also provided with a copy of a disciplinary enquiry report in respect of three departmental officers, which did not find them guilty of dereliction of duty.

Legal Issues Presented

  1. Whether the impugned blacklisting order dated 12 December 2017 was validly and lawfully made, having regard to the procedure followed and the content of the show cause notice (SCN) and the petitioner's reply.
  2. Whether the action of blacklisting was pre-determined — specifically, whether the Government direction of 10 October 2017 (requesting immediate action to blacklist) meant the later SCN was an empty formality.
  3. Whether the impugned order complied with principles of natural justice and Article 14 of the Constitution (i.e., whether the order was a reasoned, speaking order that dealt with the petitioner's replies).
  4. Whether an order imposing permanent blacklisting is legally tenable, and if not, what the permissible nature or duration of debarment/blacklisting should be.

Arguments of the Parties

Petitioner's Arguments

  • The blacklisting process was pre-determined: the Under Secretary's letter dated 10 October 2017 directed the Chief Engineer to blacklist the petitioner and this direction was not disclosed in the SCN; the SCN did not mention the Committee report which attributed responsibility to the petitioner.
  • The SCN was issued after the Government's direction and therefore issuing the SCN and accepting a reply was an empty formality; the impugned order did not refer to the SCN or the petitioner's reply nor did it deal with the petitioner's submissions.
  • Permanently blacklisting a contractor is impermissible as a matter of law; the petitioner relied on several precedents (including Kulja Industries, Vetindia, Erusian, Raghunath Thakur, and a decision of this Court in Gupta Sports v. State of Odisha) to show that permanence is legally untenable and that blacklisting must follow fair procedure and be proportionate.
  • In its rejoinder and representations the petitioner noted intervening facts: a design change and completion of remaining spans (fifteen spans and seventy-five approach spans) to the Department's satisfaction by 31 March 2018; and that it was not given a chance to put forth its defence to the Committee which inquired into the incident.

Opposite Parties' (Respondent) Arguments

  • The counter affidavit did not dispute the basic chronology but characterized the petitioner's assertion that departmental officers had inspected and approved scaffolding, centering and shuttering as "an intelligent plea to shirk responsibility".
  • The respondents relied on clauses of MORT&H specifications (Clause 115.3 of 5th revision and Sub-section 1503.1 of Section 1500 of 4th revision) to contend that the contractor alone bears responsibility for adequacy and safety of the methods adopted notwithstanding any approval by the Engineer; i.e., responsibility for safety remains with the contractor even where there is approval.
  • The counter affidavit did not dispute that the action was triggered by the Committee's report or that the SCN was issued pursuant to the Works Department's direction; it also did not dispute that the SCN made no reference to the Under Secretary's letter or the Committee report.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kulja Industries Limited v. Chief General Manager, Western Telecom Project, Bharat Sanchar Nigam Limited (2014) 14 SCC 731 The principle that debarment or debarment-like measures (blacklisting) are recognised discipline measures but such debarment is not to be permanent; the period of debarment should depend on the nature of the offence. The Court relied on this authority to hold that making blacklisting permanent in the impugned order was legally untenable.
Vetindia Pharmaceuticals Limited v. State of Uttar Pradesh (Civil Appeal No. 3647 of 2020; judgment dated 6 Nov 2020) The observation that blacklisting operates prejudicially beyond the present and can amount to a "civil death"; the duration and consequences of blacklisting are matters that may turn on proper consideration of SCN and reply and on proportionality. The Court cited this decision to reinforce that blacklisting can permanently prejudice a commercial entity and that proper SCN/reply consideration could affect the duration and consequences of blacklisting.
Erusian Equipment & Chemicals Ltd. v. State of West Bengal (1975) 1 SCC 70 Blacklisting involves civil consequences, casts a slur, creates a barrier in transactions with Government, and requires that affected persons be given an opportunity to represent their case before being put on a blacklist. The Court invoked this principle to stress the necessity of fair play and an opportunity to be heard before imposing blacklisting, finding the procedure followed in this case deficient.
Raghunath Thakur v. State of Bihar (1989) 1 SCC 229 It is an implied principle of rule of law that any order having civil consequences should be passed only after following principles of natural justice; parties should have a right to be heard. The Court applied this authority to conclude that the impugned order was a non-speaking order that failed to show that the petitioner's right to be heard had been properly respected.
Daffodills Pharmaceuticals Ltd. v. State of U.P. (2019) 17 Scale 758 Commentary in earlier jurisprudence that blacklisting for a period beyond three years up to five years may be disproportionate. The Court referenced this decision (through Vetindia) when addressing proportionality and duration of blacklisting, supporting the view that lengthy or permanent debarment may be disproportionate.
Gupta Sports v. State of Odisha (W.P.(Civil) No. 20554 of 2017, High Court judgment) This local decision was cited by the petitioner among other authorities to support the submission that permanent blacklisting is not permissible and that procedure must be followed. The Court noted the petitioner's reliance on this judgment; the opinion does not record separate doctrinal reliance beyond noting that the petitioner invoked it in argument.

Court's Reasoning and Analysis

The Court's analysis proceeded on a sequential and evidence-based approach grounded in procedural fairness and the cited jurisprudence:

  1. Sequence of governmental action: The Court observed that the Under Secretary's letter dated 10 October 2017 indicated that the Government had already "obtained orders for blacklisting" the petitioner and requested immediate action by the Chief Engineer. This pre-dated the SCN (issued on 18 October 2017), which suggested that the decision to blacklist had effectively been taken before the SCN was issued.
  2. Meaning of the SCN and reply: Given the chronology, the Court accepted the petitioner's contention that the SCN and the opportunity to reply were effectively an empty formality because the decision had already been made. The Court noted that the SCN did not disclose the Under Secretary's letter or the Committee report that had led to that letter, and the impugned order also did not mention issuance of the SCN or the petitioner's detailed reply of 1 November 2017.
  3. Continuation of work: The Court found it significant that despite the SCN containing serious allegations, the petitioner was asked to continue and complete the balance work (on a revised design), which it did to the Department's satisfaction by 31 March 2018. This fact undermined the asserted immediacy and necessity of blacklisting and suggested that the Department treated the petitioner operationally as acceptable for some period after the SCN.
  4. Failure to apply mind and non-speaking order: The Court concluded that the Engineer-in-Chief who passed the impugned order did not adequately apply his mind to the petitioner's defence. The impugned order did not discuss or reject the petitioner's contentions in any reasoned manner; it was characterized as arbitrary, unreasonable and violative of Article 14. In particular, the order failed to (a) set out reasons in clear terms, (b) state that it was passed after consideration of the contractor's reply, and (c) explain why the contractor's plea was found unacceptable.
  5. Legal position on permanence and proportionality: Applying the Supreme Court authorities (Kulja, Vetindia, Daffodills) and established principles on natural justice (Erusian, Raghunath Thakur), the Court found that making blacklisting permanent was legally untenable and that the duration and consequences of debarment must be proportionate and result from a fair process that considers replies.
  6. Conclusion from combined analysis: For these combined procedural and substantive defects — pre-determination, empty formal SCN, non-speaking impugned order, and impermissible permanency — the Court found the impugned blacklisting order unsustainable in law.

Holding and Implications

IMPUGNED ORDER SET ASIDE

Holding: The Court set aside the Chief Engineer's order dated 12 December 2017 blacklisting the petitioner and allowed the writ petition.

Implications:

  • Direct effect on the parties: The impugned blacklisting order is declared unsustainable and has been set aside; the petition is allowed. The opinion does not expressly record any further measures such as reinstatement of registration or other administrative consequences beyond setting aside the blacklisting order.
  • Broader legal consequences: The Court grounded its decision on established principles requiring that blacklisting orders be preceded by a fair, reasoned process — a proper show cause notice that discloses material facts, due consideration of the reply, and issuance of a speaking order explaining reasons and proportionality. The opinion reiterates existing Supreme Court authorities that blacklisting should not be permanent and must be proportionate; the Court does not purport to lay down any new legal principle beyond applying these authorities to the facts of this case.

This summary is prepared strictly from the text of the provided opinion and does not add, infer or expand upon facts or reasoning beyond what appears in the opinion.

    Panda Infraproject Limited v. State Of Odisha And Others Opposite Parties.

    1. The challenge in the present petition by the Petitioner, who is admittedly a Super-Class Contractor is to an order dated 12 December, 2017 passed by the Chief Engineer (DPI & Roads), Odisha banning the Petitioner “from participating or bidding for any work to be undertaken by Government of Odisha” and also banning it from “transacting business with Government of Odisha either directly in the name of propriety bidder or indirectly under different name or title”.

    2. The background to the present petition is that the Petitioner, who is a contractor involved in the construction of rail over bridge (ROB) along with bridge over ROB at-L.C. No-188-SPL-3E at-RD-433/23.25 km. of Howrah-Chennai Railway Line at RD-1/200 km from N.H.-203 (Bomikhal Square) connected to RD-1/30 km. to Janapath Via-Maharshi College, Saheed Nagar. It is stated that there was an accident where ten meters slab collapsed during the concreting of the said ROB at Level Crossing No. 188 SPL-3E, Bhubaneswar resulting the death of one person and injuries to some others.

    3. As a result of this incident, a Committee was formed by the Works Department, Government of Odisha to enquire into and submit a detailed report. That report was submitted on 26 September, 2017. The said inquiry report is stated to have placed the responsibility for incident on the Petitioner.

    4. By letter dated 10 October 2017 the Under Secretary to Government of Odisha, Works Department addressed the communication to the Chief Engineer (DPI & Roads) stating that on the basis of the aforementioned report submitted by the Committee on 22 September, 2017 the “Government orders have been obtained for blacklisting M/s. Panda Infra Projects (India) Pvt. Ltd., Bhubaneswar, the contractor for intentional violation of important conditions of contract, leading to injuries and loss of life. You are therefore requested to take immediate necessary action may be processed for blacklisting the contractor M/s. Panda Infra Projects (India) Pvt. Ltd., Bhubaneswar, following the procedure as per OPWD Code.”

    5. As a result of the above direction, a show cause notice (SCN) was issued by the Chief Engineer to the Petitioner on 18 October, 2017 asking the Petitioner to show cause why it should not be blacklisted.

    6. On 1 November, 2017, the Petitioner submitted a detailed reply to the SCN notice inter alia pointing out that the contract was a P1 contract, wherein items of work executed, their quantity and rates are specified in the contract itself. The work had to be executed by the contractor “as per detail Design, Drawing and Specifications determined, approved and provided by the Department and also as per the direction of Engineer-in-Charge of the site.” It was further stated that before casting of the Span from P19 to P20 the arrangement of the Petitioner for “shuttering and centering, staging, safety arrangements were inspected by the Departmental Engineers and the reinforcement were measured” and after which the Petitioner was allowed to “lay concrete which were also executed in presence of the Departmental Engineers”. It was also stated that “all our material permanent as well as temporary” had satisfied the requisite specifications that have been accepted by the Engineer-in-Charge and they were permitted to go ahead to the concreting under the direct supervision of Departmental Engineers “after they were satisfied all our arrangements.” The Department was accordingly asked to withdraw the SCN.

    7. Thereafter the impugned order was passed on 12 December, 2017, blacklisting the Petitioner “with immediate effect” as per codal provisions for “intentional violation of the condition of contract leading to injuries and loss of life.” The registration of the Petitioner as a Super Class Contractor also stood suspended.

    8. This Court has heard the submission of Mr. Milan Kanungo, learned Senior Counsel for the Petitioner and Mr. D.K. Mohanty, learned Additional Government Advocate.

    9. Mr. Kanungo submits that the entire action leading to the blacklisting of the Petitioner was pre-determined. Admittedly the SCN itself was issued under the direction of the Under Secretary to the Government contained in the letter dated 10 October, 2017 to the Chief Engineer. He points out that there was no mention made of this letter in the SCN. Also the fact that the enquiry report dated 26 September, 2017 submitted by the Committee had placed the responsibility for the mishap on the Petitioner, which led to the impugned action, was not mentioned in the SCN. In other words, the real reasons that led to the issuing of the SCN were not mentioned therein.

    10. Secondly, it is pointed out by Mr. Kanungo that in the impugned order there was no reference to the fact that a SCN was issued to the Petitioner on 18 October, 2017 to which the Petitioner had replied on 1 November, 2017. The impugned order also did not deal with the any of the Petitioner's submission. It simply reiterated the allegation in the SCN that the Petitioner had intentionally violated the condition of the contract leading to injuries and loss of life.

    11. Lastly, it is submitted by Mr. Kanungo that there cannot be an order for permanent blacklisting and this is contrary to the law explained in several judgments including Kulja Industries Limited v. Chief General Manager, Western Telecom Project Bharat Sanchar Nigam Limited (2014) 14 SCC 731 and the recent judgment dated 6 November, 2020 of the Supreme Court of India in Civil Appeal No. 3647 of 2020 (Vetindia Pharmaceuticals Limited v. State of Uttar Pradesh). Mr. Kanungo also places reliance on the judgments in Erusian Equipment & Chemicals Ltd. v. State of West Bengal (1975) 1 SCC 70, Raghunath Thakur v. State of Bihar (1989) 1 SCC 229 and a judgment of this Court in W.P.(Civil) No. 20554 of 2017 (Gupta Sports v. State of Odisha).

    12. Mr. D.K. Mohanty, learned counsel appearing for the Opposite Parties is unable to dispute that the impugned order makes no reference to a SCN having been issued to the Petitioner to which the Petitioner replied on 1 November, 2020. The counter affidavit terms the Petitioner's contention that the scaffolding, centering and shuttering had been inspected and approved by the official of the Engineering Department as “an intelligent plea to shirk responsibility”.

    13. Reference is made in the counter affidavit to Clause 115.3 of the MORT&H specification for Road and Bridges (5 revision) under which the sole responsibility for adequacy and safety of the method adopted by the contractor shall rest on the contractor irrespective of any approval by the Engineer. Reference is also made to Sub-section 1503.1 of Section 1500 of MORT&H specification (4 revision) which inter alia states that “notwithstanding any approval or review of drawings and design by the Engineer, the contractor shall be entirely responsible for the adequacy and safety for framework”.

    14. What the counter affidavit is silent on is the fact that the entire action was triggered by the report submitted on 26 September, 2017 by the Committee. The counter affidavit is also unable to deny that it is only pursuant to the direction issued on 10 October, 2017 by the Works Department to the Chief Engineer (DPI & Roads), that the impugned SCN was issued. The counter affidavit also does not dispute the fact that in the SCN issued to the Petitioner no reference is made to the above letter dated 10 October, 2017 or the report dated 26 September, 2017 of the Committee.

    15. In the rejoinder affidavit the Petitioner points out how the design for Pb19 & Pb20 was changed and the Petitioner was allowed to complete all the balance fifteen spans from the period September, 2017 to March, 2018; that even after the SCN was issued to it, the Petitioner completed all seventy five spans of the approach roads both on the Saheed Nagar side and the Rasulgarh side by 31 March, 2018 i.e., within the time granted by the Department.

    16. At this stage, it requires to be noted that pursuant to an order passed by this Court on 26 November, 2018 permitting the Petitioner to approach the Chief Engineer with a representation, the Petitioner on 11 December, 2018 submitted a twelve page representation reiterating that it had not violated any terms and conditions of the contract. It is stated that even before the Committee, which enquired into the incident, the Petitioner was not given a chance to put forth its defence.

    17. Although this Court on 26 November, 2018 had directed that a fresh decision should be taken within two months of the making of the representation, that direction appears not to have been complied with.

    18. It must also be mentioned that the Court has been provided with a copy of the report of the Disciplinary enquiry of a three-member Committee which examined the conduct of three of the Department officers involved in the project. It does not appear to have held any of the three officials guilty of dereliction of duty.

    19. The Court finds that the manner in which the Opposite Parties have proceeded against the Petitioner, on the face of it bears out the principal ground of challenge viz., that the impugned action of blacklisting the Petitioner was pre-determined. A perusal of the letter dated 10 October, 2017 written by the Under Secretary in the Works Department to the Chief Engineer shows that the Government had already ordered blacklisting of the Petitioner and asked the Engineer-in-Chief to take immediate action “for blacklisting the contractor” even before a SCN was issued to the Petitioner.

    20. There is merit in the contention of Mr. Kanungo that the issuing of a SCN to the Petitioner thereafter and eliciting a reply thereto, was an empty formality which was not going to change the decision already taken to blacklist the Petitioner. This also explains why the SCN makes no reference to the letter dated 10 October, 2017 or to the report of the Committee, which led to issuance of that letter. It is also surprising that the impugned order makes no reference to the fact that an SCN was issued to the Petitioner or to the detailed reply thereto by the Petitioner.

    21. Indeed, there is no answer to the contention of the Petitioner that despite issuance of the SCN containing serious allegations of violations by the Petitioner of the terms and conditions of the contract, the Petitioner was asked to execute the balance work, on a revised design, which the Petitioner admittedly completed to the satisfaction of the Department by 31 March, 2018.

    22. This casts serious doubts on whether the Engineer-in-Chief, who passed the impugned order, applied his mind to the defence taken by the Petitioner in its reply denying violation of any of the terms and conditions of the contract. The impugned order does not discuss any of the defences of the Petitioner and why the Engineer-in-Chief did not find them to be acceptable. All of this renders the impugned order arbitrary, unreasonable and violative of Article 14 of the Constitution.

    23. In Erusian Equipment (supra), the Supreme Court observed as under:

    “15…….The blacklisting order involves civil consequences. It casts a slur. It creates a barrier between the persons blacklisted and the Government in the matter of transactions. The black lists are instruments of coercion.

    20. Blacklisting has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for purposes of gains. The fact that a disability is created by the order of blacklisting indicates that the relevant authority is to have an objective satisfaction. Fundamentals of fair play require that the person concerned should be given an opportunity to represent his case before he is put on the blacklist.”

    24. It was reiterated in Raghunath Thakur (supra),

    “4………(I)t is an implied principle of the rule of law that any order having civil consequences should be passed only after following the principles of natural justice. It has to be realized that blacklisting any person in respect of business ventures has civil consequence for the future business of the person concerned in any event. Even if the rules do not express so, it is an elementary principle of natural justice that parties affected by any order should have right of being heard and making representations against the order.”

    25. In the considered view of the Court, the impugned order of blacklisting the Petitioner does not satisfy the requirements of law and in particular the bare necessity that an order blacklisting a contractor has to spell out the reasons in clear and unmistakable terms; must state that it has been passed after eliciting a reply from the contractor; spell out the reasons why the plea of the contractor was found unacceptable. In that sense, the impugned order is an unreasoned, non-speaking one.

    26. The other serious problem with the impugned order is that it makes the blacklisting permanent, which is legally untenable as explained in Kulja Industries Limited (supra) by the Supreme Court as under:

    “24. Suffice it to say that ‘debarment’ is recognised and often used as an effective method for discriplining deviant suppliers/contractors who may have committed acts of omission and commission or frauds including misrepresentations, falsification of records and other breaches of the regulations under which such contracts were allotted. What is notable is that the ‘debarment’ is never permanent and the period of debarment would invariably depend upon the nature of the offence committed by the erring contractor.”

    27. The above legal position was reiterated in Vetindia Pharmaceuticals Limited (supra) as under:

    “An order of blacklisting operates to the prejudice of a commercial person not only in praesenti but also puts a taint which attaches for beyond any may well spell the death knell of the organization/instruction for all times to come described as a civil death. The repercussions on the appellant were clearly spelt out by it in the representations as also in the writ petition, including the consequences under the Rajasthan tender where it stood debarred expressly because of the present impugned order. The possibility always remains that if a proper show cause notice had been given and the reply furnished would have been considered in accordance with law, even if the respondents decided to blacklist the appellant, entirely different considerations may have prevailed in tier minds especially with regard to the duration.”

    28. A reference in the above decision was also made to an earlier decision in Daffodills Pharmaceuticals Ltd. v. State of U.P., (2019) 17 Scale 758 wherein an order of blacklisting a contractor for a period beyond three years up to a maximum of five years was considered disproportionate.

    29. For the aforementioned reasons, this Court finds the impugned order blacklisting the Petitioner to be unsustainable in law and it is hereby set aside.

    30. This petition is allowed in the above terms.