Structured Summary of the Opinion (Prakash Shrivastava, J.)

Factual and Procedural Background

The petitioner was awarded a large railway contract (composite electrical work) with a Letter of Acceptance dated 14.07.2016 and a contract value of Rs. 60,42,06,825.25, to be completed within 30 months. The petitioner executed nine performance guarantees. Progress on site suffered after a joint surprise check by CBI and Railway Vigilance; the petitioner was asked to recast foundations and agreed to do so. Ultimately, respondent issued notices citing lack of progress, threatened action under clause 62 for termination, granted short further time, issued a fresh tender for remaining work and terminated the petitioner’s contract on 17.07.2017 with steps to encash bank guarantees.

The petitioner applied under Section 9 of the Arbitration and Conciliation Act, 1996 to restrain encashment of the bank guarantees; the Commercial Court stayed encashment by order dated 04.07.2017. Arbitration proceedings then commenced. By order dated 21.08.2019 the Commercial Court restrained encashment for a limited period and permitted the petitioner to file a Section 17 application before the Arbitral Tribunal; the Section 9 proceedings were terminated. The petitioner filed a Section 17 application before the Arbitrator seeking restraint on encashment of nine bank guarantees; the Arbitrator rejected this application by order dated 08.10.2019. The petitioner challenged that order under Section 37(2) before the Commercial Judge, whose impugned order dated 29.02.2020 dismissed the appeal. The petitioner then filed this miscellaneous petition under Article 227 challenging the Commercial Judge's order.

Legal Issues Presented

  1. Whether the respondent (beneficiary) is entitled to encash the bank guarantees during the pendency of arbitration proceedings, given the terms of the guarantees and the contract.
  2. Whether there is any ground for supervisory interference under Article 227 of the Constitution with the orders of the Arbitral Tribunal and the Commercial Court rejecting the petitioner's application under Section 17 and dismissing the Section 37(2) appeal respectively.
  3. As a contextual matter: the legality, validity and correctness of termination of the contract — however, that issue was noted to be pending before the Arbitrator (and was not finally decided in this opinion).

Arguments of the Parties

Petitioner's Arguments

  • Delay in execution was not attributable to the petitioner; termination on short notice (7 days and 48 hours) was arbitrary.
  • The bank guarantees could not be encashed because, under the contract, the amount could be recovered only after a liability was determined as per contractual provisions.
  • The bank guarantees were conditional bank guarantees and could be encashed only after assessment of loss/damage and only to the extent found due.
  • An interim injunction had been operating since 2017 and continuation would cause no prejudice to the respondent; encashment would force amendment of claims and delay proceedings.
  • Relied upon multiple Supreme Court authorities (listed in the record) in support of these contentions.

Respondent's Arguments

  • The petitioner's foundation work was defective; the petitioner was asked to recast foundations and failed to complete work in time, justifying rescission/termination of the contract.
  • The bank guarantees are unconditional; contractual conditions between the parties do not affect the bank-guarantee contract, which is separate from the underlying contract.
  • Relied on several Supreme Court authorities and a judgment of this Court to support the proposition that unconditional bank guarantees must be honoured on demand and that the scope for interference under Article 227 is limited.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Hindustan Construction Co. Ltd. v. State of Bihar The opinion records this case as cited by the petitioner; no specific rule from this case is described in the opinion. Referenced as a reliance by the petitioner; the court did not rely on it in its analysis of bank guarantees in this opinion.
Union of India v. Raman Iron Foundry Referenced by the petitioner; the opinion indicates this case concerned entitlement to recover amounts from pending bills in respect of another contract. Distinguished by the court as not being a case about bank guarantee encashment; therefore not applied to support the petitioner's position on BG encashment.
KM. Kamaluddin Ansari & Co. v. Union of India Referenced by the petitioner; described as a case about injunction against a purchaser withholding payments under other contracts, not about BG encashment. Distinguished by the court as not relating to encashment of bank guarantee; not applied to deny encashment here.
State of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli Referenced by the petitioner; involved government's right under contract to recover damages as arrears of land revenue (as per the opinion). Distinguished by the court as factually different and not determinative of BG encashment issue here.
Gangotri Enterprises Ltd. v. Union of India Referenced by the petitioner; involved encashment of bank guarantee furnished in an unrelated contract between same parties (as per the opinion). Distinguished on facts: the court noted that the situation in Gangotri was not analogous to the present case.
State of Gujarat v. Amber Builders Referenced by the petitioner; concerned jurisdiction of a statutory tribunal to grant interim injunction (as per the opinion). Distinguished by the court as involving different issues (statutory tribunal jurisdiction), not the present BG encashment issue.
BSES Ltd. v. Fenner India Ltd. (2006) 2 SCC 728 Used by the respondent and by the court as authority for the general rule that unconditional bank guarantees must be honoured on demand. Applied by the court as part of settled law supporting the proposition that unconditional/ on-demand BGs are to be paid notwithstanding disputes between contractor and beneficiary, subject to narrow exceptions.
Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. (2007) 8 SCC 110 Used to support the rule concerning on-demand/ unconditional bank guarantees and the limited scope for injunction against encashment. Applied by the court as part of the line of authority that enforces on-demand BGs and recognizes limited exceptions (fraud/special equities).
Vinitec Electronics Pvt. Ltd. v. HCL Infosystems Ltd. (2008) 1 SCC 544 Cited by the court as authority that unconditional on-demand guarantees are to be honoured and disputes between parties do not affect bank's liability. Directly relied upon in the court's exposition that the bank guarantee in question is unconditional and the beneficiary is entitled to encash it, subject to narrow exceptions.
U.P. State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568 Cited in support of the general rule that unconditional on-demand bank guarantees must be honoured. Applied by the court as part of the settled line of cases confirming the principle of bank liability under unconditional BGs.
Reliance Salt Ltd. v. Cosmos Enterprises (2006) 13 SCC 599 Referenced as part of authorities on enforcement of bank guarantees and the limited exceptions to payment on demand. Used by the court to support the proposition that unconditional BGs are payable on demand and that exceptions are limited to egregious fraud or special equities.
Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. (1997) 6 SCC 450 Referenced as authority on bank guarantees being honoured according to their terms. Applied by the court to reinforce the principle that an unconditional BG must be honoured, subject to the narrow exceptions identified in precedent.
CCE v. Dunlop India Ltd. (1985) 1 SCC 260 Referenced by the respondent (as per the opinion); the opinion records the citation but does not describe a precise rule taken from it. Listed among the respondent's authorities; the court's analysis did not specifically rely on unique principles from this case beyond the general line of authority on BGs.
Madhya Pradesh Poorv Kshetra Vidyut Vitran Co. Ltd. v. Easun Reyrolle Ltd. (2016) 4 MP LJ 716 Local High Court (this Court) authority cited by the respondent; the opinion records reliance upon it but does not set out a specific rule from it. Referenced by the respondent in support of its position; not separately analyzed for a distinct rule in the opinion's core reasoning.
Haji Mohd. Yusuf Ansari v. Mohd. Salim (2015) 4 MP LJ 424 Cited for the proposition that scope of supervisory jurisdiction under Article 227 is limited and interference is appropriate only in cases of patent perversity or gross failure of justice. Applied by the court to conclude that Article 227 jurisdiction should not be exercised where there is no patent illegality or gross injustice; used to deny the petitioner's Article 227 challenge.
Suryadeep Garg v. Neha Garg (2016) 3 MP LJ 689 Cited by respondent in support of the limited scope of interference under Article 227 (as recorded by the opinion). Referenced in the court's consideration of the limited supervisory jurisdiction; the court relied on the limited scope principle to dismiss the petition.
Jai Singh v. Municipal Corporation of Delhi (2010) 9 SCC 385 Cited for the Supreme Court's statement that Article 227 jurisdiction cannot be used to correct all errors of judgment; it is limited to cases of grave dereliction, flagrant abuse or violation of basic principles of law or justice. Applied by the court to support the conclusion that the present petition did not disclose grounds for interference under Article 227.

Court's Reasoning and Analysis

The court proceeded in steps closely tied to the record and cited authorities:

  1. Factual posture: The court noted that the petitioner's contract had been terminated and a fresh tender issued; the challenge to the termination's legality is pending before the Arbitrator. The court identified the central issue before it as whether the respondent could lawfully encash the bank guarantees during the arbitration.
  2. Textual analysis of the bank guarantee: The court reproduced and examined clauses (2) and (3) of the bank guarantee issued by the State Bank of India. Clause (2) obligated the bank to pay the amount "without any demur, merely on a demand from the government" stating the reason for encashment; clause (3) committed the bank to pay "notwithstanding any dispute or disputes raised by the contractor(s)/supplier(s) in any suit or proceeding pending before any Court or Tribunal," describing the bank's liability as "absolute and unequivocal."
  3. Legal principle on bank guarantees: The court summarized settled law — an unconditional and irrevocable bank guarantee is an independent contract obliging the bank to honour the guarantee if it is on-demand/unconditional; disputes between the beneficiary and the contractor do not affect the bank's obligation. The court identified two narrow exceptions to the general rule (both drawn from precedent cited in the opinion): (a) clear fraud of an egregious nature of which the bank has notice, and (b) special equities such as irretrievable injury or irretrievable injustice warranting an injunction.
  4. Application to the present guarantee: After considering the relevant clauses and the settled law, the court concluded that the instrument in this case constituted an unconditional bank guarantee. Therefore, the beneficiary (respondent) had the right to encash the guarantee in accordance with its terms, subject only to the narrow exceptions above.
  5. Procedural posture and prior orders: The court observed that the Arbitrator had rejected the petitioner's Section 17 application to restrain encashment and that the Commercial Court had dismissed the appeal under Section 37(2), giving reasons. The court found no "patent illegality" in those orders.
  6. Scope of Article 227: The court reiterated that Article 227 is a limited supervisory jurisdiction to be exercised only in cases of patent perversity, gross failure of justice or flagrant breach of natural justice, citing authorities. Applying that standard, the court held that the petitioner's Article 227 challenge did not disclose any such exceptional circumstance.

Holding and Implications

Holding: The petition under Article 227 is dismissed. The court held that the bank guarantee in question is an unconditional bank guarantee and that the beneficiary has the right to encash it in accordance with its terms.

Implications:

  • Direct effect on the parties: The petitioner's Article 227 challenge fails and the orders of the Arbitrator and the Commercial Court (rejecting the Section 17 application and dismissing the Section 37(2) appeal) stand; the respondent (beneficiary) has a right to encash the bank guarantees subject to the narrow exceptions recognized in precedent.
  • Proceedings on the merits of termination: The court noted that the question of the legality, validity and correctness of the contract termination remains pending before the Arbitrator and was not finally determined in this opinion.
  • Broader precedent: The court applied settled principles regarding unconditional bank guarantees as reflected in earlier Supreme Court decisions; the opinion does not purport to create a novel legal principle beyond applying the existing line of authority. The decision confines itself to the direct dispute before the court and the limits of Article 227 supervisory jurisdiction.

Disposition: Petition dismissed.

    Cobra-cipl Jv v. Chief Project Manager .

    Prakash Shrivastava, J.:— By this miscellaneous petition under Article 227 of the Constitution, the petitioner has challenged the order dated 29.02.2020 whereby the appeal preferred by the petitioner under Section 37(2) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) has been dismissed by the Commercial Judge, Jabalpur.

    2. The case of the petitioner is that the petitioner was awarded the contract for the composite electrical work for design, supply, erection, testing and commissioning of single phase overhead equipment including THS and SPADA works in Manikpur(Excl) - Satna(Incl) and Satna to Rewa station of Jabalpur Division of West Central Railway. The total contract value was R.s. 60,42,06,825.25 and the work was to be completed within a period of 30 months from the date of issuance of Letter of Acceptance. The Letter of Acceptance was issued on 14.07.2016. The petitioner had executed as many as nine performance guarantee. According to the petitioner, the progress of the work at the site had suffered on account of the surprise check done by the CBI alongwith the Vigilance Officers of the Railway. The case of the petitioner is that the petitioner was asked by the railway to recast all foundation constructed by that time at its own cost. The time for execution of the work was extended upto 30 of September, 2016. On 17.12.2016, the petitioner had agreed to recast all the foundation which were cast prior to CBI-Railway Vigilance joint surprise check. Finally, the CBI had found that only ten out of 3553 foundation were defective but by that time petitioner had already recasted 983 foundation as on 06.06.2017. Respondent had issued the notice to make good the progress or else the action was proposed in terms of clause 62 of the Central General Conditions of Contract for termination of a contract and getting the balance work done without the petitioner's certification. Thereafter, the notice dated 27.06.2017 was given by granting further 48 hours time on the same terms and also informing that failure to do the work will result in forfeiture of the security deposit and encashment of performance guarantee. Thereafter, the respondent had issued fresh tender notice for the remaining work. On 17.7.2017 the contract of the petitioner was terminated and steps were taken for encashment of the bank guarantee. The petitioner had filed application under Section 9 of the Act of 1996 and the Commercial Court by order dated 04.07.2017 had stayed the encashment of bank guarantee. During the pendency of the application under Section 9 of the Act, the arbitration proceedings had commenced, therefore, the Commercial Court by order dated 21.8.2019 under Section 9(2) & (3) of the Act had restrained the encashment of the bank guarantee by further permitting the petitioner to file stay application under Section 17 of the Act before the Arbitral Tribunal. The interim order was made operative for a period of 45 days and the proceedings under Section 9 of the Act were terminated. The petitioner thereafter had filed an application under Section 17 of the Act before the Arbitrator with a prayer to restrain the respondent from encashing the nine bank guarantees. The learned Arbitrator after hearing both the parties by order dated 08.10.2019 had rejected the application under Section 17 of the Act. This order of the learned Arbitrator was subject matter of challenge before the Commercial Judge at the instance of the petitioner under Section 37(2) of the Act and by the impugned order dated 29.02.2020, the Commercial Court has dismissed the appeal.

    3. Learned counsel appearing for the petitioner submits that the delay in execution of the contract is not attributable to the petitioner, therefore, termination of contract with a short notice of 7 days and 48 hours is arbitrary. He further submits that the bank guarantee cannot be encashed because in terms of the contract between the parties, the amount can be recovered only if the liability is determined as per the provisions. He further submits that the bank guaranttee (sic : guarantee) is conditional bank guarantee and in terms of the conditions of the guarantee, they could be encashed only after assessment of loss or damages and to the extent of amount found due thereafter. He has also submitted that the interim injunction is operating since 2017 and no prejudice has been caused to the other side, therefore, the same should be allowed to continue till the arbitration proceedings are concluded and that if the bank guarantee is encashed, the petitioner will have to amend the claim and agitate the issue in this regard which will delay the proceedings. In support of his submissions, he has placed reliance from the judgment of Supreme Court in the matter of Hindustan Construction Co. Ltd. v. State of Bihar, (1999) 8 SCC 436, Union Of India v. Raman Iron Foundry ., (1974) 2 SCC 231, KM. Kamaluddin Ansari & Co. v. Union of India, (1983) 4 SCC 417, State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, (1987) 2 SCC 160, Gangotri Enterprises Ltd. v. Union of India, (2016) 11 SCC 720 and State of Gujarat v. Amber Builders, (2020) 2 SCC 540.

    4. Learned counsel for the respondent opposing the prayer has submitted that the petitioner was required to lay the foundation for erection work and the foundation work done by the petitioner was defective, therefore, he was asked to recast the foundation and since the work was not completed within time, therefore, the contract was rescinded. He has further submitted that the bank guarantees are unconditional bank guarantees and any condition prescribed in the contract between the petitioner and the respondent have no effect on the bank guarantee which is a separate contract. In support of his submission, he has placed reliance upon the judgment of Supreme Court in the matter of BSES Ltd. v. Fenner India Ltd., (2006) 2 SCC 728, Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. ., (2007) 8 SCC 110, Vinitec Electronics Private Ltd. v. Hcl Infosystems Ltd. ., (2008) 1 SCC 544, CCE v. Dunlop India Ltd.], (1985) 1 SCC 260, Reliance Salt Lid. v. Cosmos Enterprises, (2006) 13 SCC 599, Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd., (1997) 6 SCC 450 and the judgment of this Court in the matter of Madhya Pradesh Poorv Kshetra Vidyut Vitran Co. Ltd. v. Easun Reyrolle Ltd. reported in (2016) 4 MP LJ 716. He has also submitted that the scope of interference in a miscellaneous petition filed under Article 227 of the Constitution is very limited and in this regard he has placed reliance upon the judgment of Supreme Court in the matter of Haji Mohd. Yusuf Ansari v. Mohd. Salim, (2015) 4 MP LJ 424 and Suryadeep Garg v. Neha Garg ., (2016) 3 MP LJ 689

    5. Having heard the learned counsel for the parties and perusal of the record, it is noticed that the contract which was awarded to the petitioner has already been terminated and fresh tender has been issued for the remaining work. The issue relating to the legality, validity and correctness of the termination of the contract is pending for decision before the learned Arbitrator. The main issue which is involved in the present case is in respect of the right of the respondent to get the bank guarantee encashed during the pendency of the proceedings before the Arbitrator.

    6. The bank guarantee executed by the State Bank of India contains the following clause which has been relied upon by counsel for both the parties:

    “2. We State Bank of India, Corporate Accounts Group Branch, 11th Floor, 1, Tolstoy Marg, Jawahar Vayopar Bhawan, New Delhi-110001, A Bank constituted/registered under the SBI Act, 1955 having our Corporate Center at Madame Coma Road, Nariman Point, Mumbai, India, do hereby undertake to pay the amount due and payable under this guarantee without any demur, merely on a demand from the government stating that the amount claimed is due by way of loss or damage caused to or would be caused to or suffered by the Government by reason of breach by the said contractor (s) of any of the terms or conditions contained in the said agreement or by reason of the contractor (s) failure to perform the said agreement. Any such demand made on the Bank shall be conclusive as regards the amount due and payable by the Bank under this Guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding Rs. 3,32,31,400,00 (RUPEES Three Crores Thirty Two Lakhs Thirty One Thousand Four Hundred Only).

    3. We State Bank Of India, Corporate Accounts Group Branch, 11th Floor, 1, Tolstoy Marg, Jawahar Vayopar Bhawan, New Delhi-110001, A Bank constituted/registered under the SBI Act, 1955 having our Corporate Center at Madame Cama Road, Nariman Point, Mumbai, India, undertake to pay to the Government any money so demanded notwithstanding any dispute or disputes raised by the contractor(s)/supplier(s) in any suit for proceeding pending before any Court or Tribunal relating thereto our liability under this present contract being absolute and unequivocal, the payment so made by us under this bond shall be a valid discharge of our liability for payment thereunder and the contractor(s)/supplier(s) shall have no claim against us for making such payment.”

    A perusal of the clause (2) reveals that the bank had undertaken to pay the amount due and payable under the guarantee without any demur merely on a demand from the government stating the reason assigned for the encashment of bank guarantee. Clause (3) makes it clear that on making the demand under Clause (2), the bank had undertaken to pay the government any money so demanded notwithstanding any disputes raised by the contractor. The aforesaid clause makes it clear that the bank guarantee was unconditional bank guarantee.

    7. It is settled that bank guarantee is an independent contract between the bank and the beneficiary thereof, therefore, bank is always obliged to honour the guarantee if it is unconditional and irrevocable. The dispute between the beneficiary and the party at whose instance bank guarantee is given is of no consequence and has no effect on the right relating to the encashment of the bank guarantee. It is also settled that the bank guarantee which provides that the amount is payable by the guarantor on demand is considered to be the unconditional bank guarantee and that once the unconditional guarantee in course of commercial dealing is given, the beneficiary is entitled to realize the bank guarantee as per the terms contained therein. [See (2008) 1 SCC 544 (Vinitec Electronis Private Ltd. v. HCL Infosystems Ltd.), (1997) 1 SCC 568 (U.P State Sugar Corporation v. Sumac International Ltd. .)]. The general rule that bank guarantee must be honoured in accordance with its terms has two exceptions; firstly when there is clear fraud of egregious nature vitiating the entire transaction and the bank has notice of such a fraud and; secondly when there are special equities such as irretrievable injury or irretrievable injustice in favour of injunction. Leaving aside the above two exceptions, the beneficiary has right of encashment of unconditional bank guarantee. [See (2006) 2 SCC 728 (BSES Ltd. (Now Reliance Energy Ltd. v. Fenner India Ltd.), (2007) 8 SCC 110 (Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. .), (2006) 13 SCC 599 (Reliance Salt Ltd. v. Cosmos Enterprises) and (1997) 6 SCC 450 (Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd.)].

    8. Having regard to the aforesaid pronouncements and considering the relevant clauses of the bank guarantee, we are of the opinion that it is a case of unconditional bank guarantee and the beneficiary has aright of its encashment.

    9. Counsel for the petitioner has placed reliance upon the judgment in the case of Union of India v. Raman Iron Foundary (supra) but that is not a case of bank guarantee but it is a case of entitlement to recover the amount from the pending bills in respect of another contract and interpretation of clause 18 of that contract. He has also placed reliance upon the judgment of the Supreme Court in the case of H.M. Kamaluddin Ansari and Company (supra) but that was a case of grant of injunction against purchaser restraining it from withholding payment to the suppliers under other contracts which were not the subject matter of arbitration proceedings before the Court. It was also not a case of encashment of bank guarantee. He has also placed reliance upon the judgment in the matter of State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli (supra). In that case, the issue relating to government's right under the contract to recover damages as arrears of land revenue was involved. In the matter of Gangotri Enterprises Ltd. (supra) relied upon by counsel for the petitioner, the issue relating to encashment of bank guarantee furnished in an unrelated contract between the same parties was involved. That is not so in the present case. So far as the judgment in the case of Amber Builders (supra) is concerned, the issue involved was in respect of the jurisdiction of the statutory Tribunal to grant interim injunction. Hence, these judgments are distinguishable and the petitioner is not entitled to the benefit of these judgments.

    10. Record further reflects that the learned Arbitrator by a well-reasoned order has rejected the petitioner's application under Section 17 of the Act for grant of restrained order about the encashment of nine bank guarantees. The Commercial Court has also dismissed the statutory appeal by assigning due reason. These orders do not suffer from any patent illegality.

    11. This petition has been filed under Article 227 of the Constitution wherein the scope of interference is limited. This power can be exercised in appropriate case where there is a patent perversity in the order of the Tribunal or the Subordinate Court or where there has been a gross and manifest failure of justice or the basic principles of natural justice have been flouted. (See : (2015) 4 MP LJ 424 (Haji Mohd. Yusuf Ansari v. Mohd. Salim). The Supreme Court in the matter of Jai Singh v. Municipal Corporation of ‘Delhi’ reported in (2010) 9 SCC 385 while considering the scope of interference under Article 227 of the Constitution, has held that the jurisdiction under Article 227 cannot be exercised to correct all errors of judgment of a court, or tribunal acting within the limits of its jurisdiction. Correctional jurisdiction can be exercised in cases where orders have been passed in grave dereliction of duty or in flagrant abuse of fundamental principles of law or justice.

    12. In view of the aforesaid factual and legal position, no case for exercise of limited supervisory jurisdiction is made out. Hence, petition is dismissed.

    Petition dismissed