Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 12 of the Arbitration and Conciliation Act, 1996
  • Fourth Schedule of the Arbitration and Conciliation Act, 1996
  • Section 11 of the Arbitration and Conciliation Act, 1996
  • Section 9 of the Arbitration and Conciliation Act, 1996
  • Section 37(1) (b) of the Arbitration and Conciliation Act, 1996
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 12 of the Arbitration and Conciliation Act, 1996
  • Fourth Schedule of the Arbitration and Conciliation Act, 1996
  • Section 11 of the Arbitration and Conciliation Act, 1996
  • Section 9 of the Arbitration and Conciliation Act, 1996
  • Section 37(1) (b) of the Arbitration and Conciliation Act, 1996
Smart Summary

Factual and Procedural Background

The appellant, a business entity associated with the Woodland Group engaged in construction and infrastructure projects in the National Capital Region of Delhi, entered into a Memorandum of Understanding (MoU) on 03.03.2022 with respondent nos. 1 and 2, spouses and co-owners of a freehold property in Rajouri Garden, New Delhi. The MoU contemplated the appellant developing a project on the respondents' land at its own cost in exchange for 30% of the sale proceeds. The appellant mobilized resources and paid an advance of Rs. 1 crore to the respondents. Subsequently, disputes arose when the appellant issued a show cause notice on 27.05.2022 to the respondents to fulfill their obligations, to which the respondents responded with a notice seeking cancellation of the agreement. Invoking Clause 21 of the MoU, the appellant issued a Notice of Arbitration on 04.06.2022 and filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 on 06.06.2022. The Single Judge dismissed this petition by judgment dated 23.08.2022, leading to the present appeal filed under Section 37(1)(b) of the Arbitration and Conciliation Act, 1996.

Legal Issues Presented

The opinion addresses a procedural matter and does not frame distinct legal issues.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court noted that the disputes between the parties were arbitrable, as conceded by the respondents. Although the appellant had not filed a petition under Section 11 for the appointment of an arbitrator, both parties expressed no objection to the Court appointing an independent arbitrator. Consequently, the Court appointed Hon'ble Mr. Justice KG Balakrishnan, former Chief Justice of India, as the sole arbitrator. The Court directed that the arbitrator's fees be governed by the Fourth Schedule of the Arbitration and Conciliation Act, 1996, and that compliance with Section 12 of the Act be ensured before commencement of arbitration. The reasoning focused on facilitating the arbitration process to resolve the disputes expeditiously.

Holding and Implications

The appeal is disposed of accordingly by appointing an independent arbitrator to adjudicate the disputes.

This decision directly results in the appointment of an arbitrator to proceed with the arbitration as per the MoU and the Arbitration and Conciliation Act, 1996. No broader legal precedent or principle was established by this order.

To access the original judgment, please Sign In or Subscribe.

    ROYAL ORCHIDS  v. KULBIR SINGH KOHLI & ANR.

    1. The present appeal has been filed by the appellant under Section 37(1) (b) of the Arbitration and Conciliation Act, 1996 challenging the judgment dated 23.08.2022 passed by learned Single Judge in OMP (I) (COMM) 192/2022, vide which petition under Section 9 of the Arbitration and Conciliation Act, 1996 filed by the respondents has been dismissed.

    2. Appellant is a business entity which has common management with Aero Club, known as Woodland Group. Over the last few decades, appellant has been involved in and has successfully undertaken several construction and infrastructure development projects in and around the National Capital Region of Delhi.

    3. Respondent nos. 1 & 2 are spouses and are the co-owners of a plot of land and in possession of freehold property bearing number K-1, built on plot no. 1, in K block, situated in the area of Village Basai Darapur, Rajouri Garden, New Delhi.

    4. Learned counsel for the appellant submits that in February, 2022, appellant was approached by the respondents seeking a collaboration with the appellant to construct and develop the project on their abovementioned land. On 03.03.2022, parties entered into a Memorandum of Understanding in terms of which the project had to be developed by the appellant at its own cost in lieu of being paid 30% of the Sale proceeds. The appellant mobilised its resources in order to fulfill its obligations in a timely manner and as part of the planning process, refused other projects. An advance of Rs. 1 crore was paid to the respondents and the remaining part of the deposit was ready and available with the appellant to deposit to the respondents.

    5. Learned counsel also submits that appellant sent a show cause notice to the respondents on 27.05.2022 to fulfil their obligations under the Memorandum of Understanding. In response thereto, respondents also send a notice to the appellant seeking cancellation of the above said agreement.

    6. Learned counsel for appellant next submits that in light of disputes and differences that arose between the appellant and the respondents, the appellant petitioner vide Notice of Arbitration dated 04.06.2022 invoked arbitration in accordance with Clause 21 of the Memorandum of Understanding.

    7. Thereafter appellant filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 on 06.06.2022 and vide order dated 23.08.2022, the same was dismissed by learned Single Judge. Hence, the present appeal.

    8. Learned counsel appearing on behalf of the respondents has submitted that the claims raised in the present appeal are disputed, however, fairly conceded that the disputes inter se parties are arbitrable.

    9. Learned counsel for the appellant submits that though he has not filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996, he has no objection if this Court appoints an independent arbitrator. Learned counsel for the respondents also has no objection to the same.

    10. Accordingly, we hereby appoint Hon'ble Mr. Justice KG Balakrishnan, former Chief Justice of India (Mobile : 9717266700) the sole arbitrator to adjudicate the disputes between the parties.

    11. The fee of the learned Arbitrator shall be governed by the Fourth Schedule of the Arbitration and Conciliation Act, 1996.

    12. The learned Arbitrator shall ensure compliance of Section 12 of the Arbitration and Conciliation Act, 1996 before commencing the arbitration.

    13. With aforesaid, the present appeal is disposed of accordingly.