Loading..
Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • ARTICLE 226 CONSTITUTION OF INDIA
  • SECTION 56 CONTRACT ACT
  • Section 56 of the Indian Contract Act.
  • provisions of the Indian Contract Act, 1872.
  • Section 56 of the Indian Contract Act, 1872
  • Section 56. 37.In Alopi Parshad & Sons Ltd.v.Union of India[Alopi Parshad & Sons Ltd.v.Union of India, (1960) 2
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • ARTICLE 226 CONSTITUTION OF INDIA
  • SECTION 56 CONTRACT ACT
  • Section 56 of the Indian Contract Act.
  • provisions of the Indian Contract Act, 1872.
  • Section 56 of the Indian Contract Act, 1872
  • Section 56. 37.In Alopi Parshad & Sons Ltd.v.Union of India[Alopi Parshad & Sons Ltd.v.Union of India, (1960) 2
Smart Summary

Factual and Procedural Background

Tamil Nadu Civil Supplies Corporation issued a tender notification dated 20.12.2021 for the supply of 4 crore Fortified RBD Palmolein oil pouches, with the tender opening on 06.01.2022. Petitioners submitted tenders and emerged as successful bidders, with their offers accepted on 13.01.2022. The contract required supply in two spells of specified quantities for each petitioner. Except for the petitioner in W.P.No.5994 of 2022 (M/s. Arunachala Impex Private Limited), the other petitioners effected supplies as per the contract.

Clause 17(d) of the tender notification reserved the respondent's right to vary the quantity ordered by 25% either way without constituting a contractual obligation for the tenderers to accept such variation. Invoking this clause, the respondent Corporation issued communications directing petitioners to supply an additional 25% quantity. Petitioners contended that market conditions had changed adversely due to unforeseen events, including the Russia-Ukraine war, increased crude oil and freight costs, and an Indonesian ban imposed on 27.04.2022, making performance impossible. They sent representations expressing inability to supply the additional quantity, which were rejected, leading to the filing of these writ petitions challenging the additional demand.

Legal Issues Presented

  1. Whether the petitioners can invoke Section 56 of the Indian Contract Act, 1872, to claim impossibility of performance and discharge from contractual obligations due to changed market conditions and unforeseen events.
  2. Whether the demand by the Tamil Nadu Civil Supplies Corporation for an additional 25% quantity supply under Clause 17(d) of the tender notification is valid and enforceable.
  3. Whether writ jurisdiction under Article 226 of the Constitution of India is maintainable despite existence of an arbitration clause in the contract.
  4. Whether an increase in price or cost of performance amounts to frustration of contract under Indian law.

Arguments of the Parties

Petitioners' Arguments

  • Section 56 of the Indian Contract Act applies as the outbreak of the Russia-Ukraine war and the Indonesian ban constitute force majeure events making performance impossible.
  • Market conditions changed drastically after contract formation, including diversion of supplies, increased crude oil prices, and freight costs, leading to impossibility of supplying additional quantity.
  • The respondent Corporation itself recognized the force majeure situation by canceling a similar tender process in March 2022.
  • The respondent Corporation contracted for the same quantity at a higher price with a third party, indicating unfair commercial conduct.
  • Being a State instrumentality, the respondent must adopt a fair approach and cannot insist on performance leading to commercial insolvency of the petitioners.

Respondent's Arguments

  • The dispute is purely commercial and not suitable for writ proceedings; arbitration clause provides an adequate remedy.
  • Mere commercial difficulties or increased costs do not justify non-performance or discharge from contractual obligations.
  • The writ petitions should be dismissed as there is no legal ground to avoid the contract terms.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
U.P. Power Transmission Corporation Ltd. v. CG Power & Industrial Solutions Ltd. (2021) 6 SCC 15 Existence of arbitration clause does not bar writ jurisdiction under Article 226 for contract-related matters. Court overruled preliminary objections and entertained writ petitions despite arbitration clause, as no disputed facts existed and the respondent is a State instrumentality.
Tsakiroglou & Co., Ltd. v. Noblee Thorl GmbH (1962) AC 93 Increased costs may constitute frustration only if they are extreme ("astronomical"); mere increase in cost does not discharge contract. Court held that price escalation of 25% is insufficient to invoke frustration doctrine under Indian law.
Energy Watchdog v. CERC (2017) 14 SCC 80 Explanation of Section 56 Indian Contract Act and doctrine of frustration; performance may be impossible or impracticable if fundamental basis is upset. Court applied principles to reject frustration plea, finding contract foundation unaltered despite changed circumstances.
Satyabrata Ghose v. Mugneeram Bangur & Co., AIR 1954 SC 44 Definition and application of impossibility and frustration under Section 56; performance may be impracticable but not necessarily discharged. Referred to as foundational authority; confirmed that onerous performance does not discharge contract.
Alopi Parshad & Sons Ltd. v. Union of India AIR 1960 SC 588 Parties cannot ignore express contractual terms and claim relief on vague equity pleas; unforeseen price rises do not discharge contract. Court held that contract performance is not discharged by onerousness alone.
Naihati Jute Mills Ltd. v. Khyaliram Jagannath AIR 1968 SC 522 English law on frustration explained; contract not frustrated by change of circumstances making performance onerous. Supported rejection of frustration plea based on increased cost or changed circumstances.
Chitty on Contracts, 31st Edn. and Treitel on Frustration and Force Majeure, 3rd Edn. Authoritative commentary stating rise in cost does not constitute frustration; force majeure clauses not triggered if alternative performance exists. Supported court’s view that price increase alone does not discharge contractual obligations.

Court's Reasoning and Analysis

The Court first addressed the preliminary objection regarding the arbitration clause and held, relying on the Supreme Court's decision in U.P. Power Transmission Corporation Ltd., that the writ jurisdiction under Article 226 is maintainable in this case because there are no disputed factual questions and the respondent is a State instrumentality.

The Court observed that the demand for an additional 25% supply falls within the contractual terms under Clause 17(d), which expressly reserves the right to vary quantity by 25%. The petitioners’ claim of impossibility grounded on changed market conditions due to the Russia-Ukraine war, increased crude oil and freight prices, and an Indonesian export ban was examined. The Court noted that the contract was concluded on 13.01.2022, and the additional demand was made on 02.03.2022, while the Indonesian ban came later on 27.04.2022.

Applying Section 56 of the Indian Contract Act, the Court emphasized that impossibility under the section does not mean literal impossibility but includes impracticability that upsets the contract's foundation. However, the Court found that the fundamental basis of the contract remained intact as the commodity was still available in the market, albeit at higher prices.

The Court relied heavily on the Supreme Court's ruling in Energy Watchdog v. CERC and other precedents to conclude that a mere increase in price or onerousness of performance does not amount to frustration or discharge under Section 56. The petitioners, being experienced suppliers, were expected to foresee market fluctuations and price changes. The respondent’s insistence on performance at the contracted rate was lawful and within contractual rights.

The Court rejected the petitioners’ plea for relief under the doctrine of frustration or force majeure, holding that no event had rendered performance impossible or unlawful within the meaning of Section 56. The petitioners were not "hindered or prevented" from supplying the additional quantity, and commercial insolvency concerns do not justify non-performance.

Holding and Implications

DISMISSED

The Court dismissed all writ petitions challenging the demand for additional supply under the tender contract and upheld the validity of the respondent Corporation's communications. Consequently, all connected miscellaneous petitions were also dismissed with no order as to costs. This decision directly enforces the contractual terms between the parties and clarifies that price escalation or changed market conditions alone do not constitute frustration or impossibility under Indian contract law. No new precedent was established beyond the application of existing legal principles.

    Starshine Logistics v. Tamil Nadu Civil Supplies Corpn.

    W.P.Nos.8522, 8521, 5994, 7681 and 8657 of 2022

    IN THE HIGH COURT OF JUDICATURE AT MADRAS

    ORDERS RESERVED ON : 13.05.2022

    PRONOUNCING ORDERS ON : 01.06.2022

    Coram:

    THE HONOURABLE JUSTICE MR.G.R.SWAMINATHAN

    W .P.Nos.8522, 8521, 5 994, 7681 and 8657 of 2022 and

    W.M.P.Nos. 8431, 8432, 8429, 8430, 6074, 6075, 7679, 7681, 8573 & 8574 of 2022 W.P.Nos.8522 and 8521 of 2022

    M/s.Starshine Logistics (Regd.Firm) Rep.by its Partner/Authorised Signatory Suresh Gatt Reddi, No.6C, Sixth Floor, Gaiety Palace No.1/L, Blackers Road,Chennai 600 002. ... Petitioner in W.P.No.8522/2022 Ganesan Chandran ... Petitioner in W.P.No.8521/2022 ..Vs..

    Tamil Nadu Civil Supplies Corporation

    Represented by its Managing Director

    No.12, Thambusamy Road, Kilpauk

    Chennai 600 010. ... Respondent in both W.Ps.

    P rayer in W.P.No.8522 of 2022: Writ Petition under Article 226 of the Constitution of India for the issuance of a Writ of Certiorari calling for the records relating to the email confirmation order dated 02.03.2022 bearing R.C.No.BS3/062350/2021-5 on the file of the respondent and quash the same.

    P rayer in W.P.No.8521 of 2022: Writ Petition under Article 226 of the Constitution of India for the issuance of a Writ of Certiorari calling for the records relating to the email confirmation order dated 02.03.2022 bearing R.C.No.BS3/062350/2021-5 on the file of

    1

    the respondent instructing the petitioner to supply an additional quantity of 20,00,000 numbers of RBD Palmolein in 1 litre pouches on or before 03.05.2022 and quash the same.

    In W.P.Nos.8522 & 8521 of 2022

    For Petitioner : Mr.Mani Sundar Gopal in W.P.No.8522/2022

    and for Mr.Ashok Chakravarthy in W.P.No.8521/2022

    For Respondent : Mr.R.Shunmugasundaram

    in both W.P.s Advocate General, Assisted by

    Ms.A.G.Shakeenaa, Standing Counsel

    W.P.No.5994 of 2022

    Arunachala Impex Private Limited Represented by its Managing Director No.192/237, Thambu Chetty Street Parrys, Chennai 600 001. ... Petitioner ..Vs..

    1. The Managing Director Tamil Nadu Civil Supplies Corporation No.12, Thambusamy Road, Kilpauk Chennai 600 010.

    2.Tender Sub-Committee

    Rep.by its Members

    No.12, Thambusamy Road, Kilpauk Chennai 600 010.

    3. Tamil Nadu Civil Supplies Corporation Represented by its Board of Directors No.12, Thambusamy Road, Kilpauk Chennai 600 010.

    4.State of Tamil Nadu

    Rep.by the Principal Secretary Cooperation, Food and Consumer Protection Department, St.George Fort, Chennai. ... Respondents

    2

    P rayer : Writ Petition under Article 226 of the Constitution of India for the issuance of a Writ of Certiorari to call for the records culminating in the impugned order namely email confirmation dated 02.03.2022 bearing Rc.No.BS3/062350/2021-3 sent by the 1st respondent to the petitioner directing it to supply an additional 25 percent quantity of 25,00,000 nos. of RBD Palmolein oil 1 litre pouches, and quash the same. For Petitioner : Mr.A.L.Somayaji, Senior Counsel

    for Ms.Pushpa Menon

    For Respondents 1-3 : Mr.R.Shunmugasundaram

    Advocate General, Assisted by

    Ms.A.G.Shakeenaa, Standing Counsel

    For Respondent No.4: Mr.R.Shunmugasundaram

    Advocate General, Assisted by

    Mr.D.Ravichander, Special Government Pleader

    W.P.Nos.7681 and 8651 of 2022

    M/s.Ruchi Soya Industries Limited Rep.by its Authorised Signatory R.Venkatraman, S/o C.Ramalingam 40-41, East Mada Church Road Royapuram, Chennai 600 013. ... Petitioner in W.P.No.7681 of 2022 M/s.Rasi Nutri Foods India Private Limited

    Rep.by its Authorised Signatory P.Mohanraj

    Door No.2/205, 2/206, 2/207, R.Puliyampatti

    Village & Navani Village, Puduchatram Post

    Namakkal, Tamil Nadu 637 018. ... Petitioner in W.P.No.8651 of 2022 ..Vs..

    1.State of Tamil Nadu

    Rep.by the Principal Secretary

    Cooperation, Food and Consumer Protection

    Department, St.George Fort, Chennai.

    3

    2. Tamil Nadu Civil Supplies Corporation Represented by its Managing Director No.12, Thambusamy Road, Kilpauk Chennai 600 010. ... Respondents in both W.Ps.

    Prayer in W.P.No.7681/2022 : Writ Petition under Article 226 of the Constitution of India for the issuance of a Writ of Certiorari calling for the records relating to the relating to the confirmation order by the 2ndrespondent dated 02.03.2022 through email for supply of additional 25% quantity of 22,50,000 Nos. of RBD Palmolein Oil 1-litre pouches at the rate of Rs.120.25 net per pouch and quash the same.

    Prayer in W.P.No.8657/2022 : Writ Petition under Article 226 of the Constitution of India for the issuance of a Writ of Certiorari calling for the records relating to the confirmation order by the 2ndrespondent dated 02.03.2022 RC.No.062350/2021-4 through email for supply of additional 25 percent quantity of 16,25,000 Nos. of RBD Palmolein Oil 1-litre pouches at the rate of Rs.120.25 net per ouch and quash the same. For Petitioner in W.P.No.7681/2022 : Mr.AR.L.Sundaresan, Senior Counsel for Ms.A.L.Gandhimathi

    For Petitioner in W.P.No.8651/2022 : Mr.A.Saravanan

    For Respondents

    Respondents No.1 : Mr.R.Shunmugasundaram, Advocate General assisted by

    Mr.D.Ravichander, Special Govt. Pleader Respondent No.2: : Mr.R.Shunmugasundaram, Advocate General assisted by

    Ms.A.G.Shakeenaa, Standing Counsel

    4

    C O M M O N O R D E R

    Tamil Nadu Civil Supplies Corporation issued tender notification dated 20.12.2021 for the supply of 4 Crore nos. of Fortified RDB Palmolein oil pouches. The tender opening date was announced as 06.01.2022. The petitioners herein submitted their tenders in response to the said notification. They emerged as successful tenderers. The offers made by the petitioners were accepted by the respondent Corporation on 13.01.2022. As per the terms of the contract, the tenderers were to supply the following quantities in two spells.

    Petitioner in W.P.No.8522 of 202265,00,000
    Petitioner in W.P.No.8521 of 202280,00,000
    Petitioner in W.P.No.5994 of 20221,00,00,000
    Petitioner in W.P.No.7681 of 202290,00,000
    Petitioner in W.P.No.8657 of 202265,00,000

    2. Except the writ petitioner in W.P.No.5994 of 2022 (M/s.Arunachala Impex Private Limited) the other tenderers effected supplies under both spells. Clause 17(d) of the tender notification is as follows :

    "17(d) : The Tamil Nadu Civil Supplies Corporation reserves the right to vary the quantity finally ordered to be purchased to the extent of 25% either way of the requirement of RBD Palmolein Oil pouches indicated in the e-tender document. The tenderers cannot claim it as a matter of contractual obligation to vary the quantity either way."

    5

    3. Invoking the said clause, the impugned communications were issued directing the petitioners to supply the additional 25% quantity. Contending that the market conditions had undergone adverse change, the petitioners claimed impossibility of performance. They sent representations to that effect expressing their inability to supply the additional quantity. Since the respondent Corporation was unrelenting in their stand, these writ petitions came to be filed challenging the additional demand.

    4. The learned Senior Counsel appearing for the petitioners reiterated their stand that this is a classic case in which Section 56 of the Indian Contract Act, 1872 deserves to be invoked. They pointed out that when the tenders were finalized, the parties did not envisage that war between Russia and Ukraine would break out. As a result of the outbreak of the war, Palmolein supplies got diverted to Ukraine. Since crude oil prices shot up, freight costs went up and the movement of cargo vessels also got affected severely. To add to their woes, Indonesia imposed a ban order on 27.04.2022. These factors cumulatively broke the back of the petitioners and therefore they could not supply the additional 25% quantity.

    5. The learned Senior Counsel took me through various articles and called upon this Court to take judicial notice of the prevailing situation. They pointed out that the changes in the market were perceived by the respondent Corporation themselves as a force majeure event and that is why they themselves cancelled one such tender process

    6

    in the second week of March 2022. They also pointed out that while the respondent Corporation insisted that the petitioners should supply the oil packets at the negotiated rate of Rs.120.25/-, the respondent Corporation entered into contract with one of the parties on 01.04.2022 for purchase of the very same quantity at a far higher price. The contention of the learned Senior Counsel is that the respondent Corporation being a State instrumentality must adopt a fair approach even in commercial dealings. Since the result of fulfilling the contractual obligations would lead to their commercial insolvency, the learned Senior Counsel wanted this Court to quash the impugned demand and allow these writ petitions. The learned Senior Counsel relied on a catena of decisions.

    6. The respondent Corporation had filed a detailed counter affidavit opposing the writ prayers. The learned Advocate General reiterated the stand set out therein. He pointed out that a pure commercial dispute cannot form the subject matter of writ proceedings. In any event, the contract between the parties provides for an arbitral remedy. There is absolutely no justification for bypassing such remedy. He also pointed out that mere commercial difficulties cannot enable the petitioners to seek exoneration from fulfilment of contractual obligations. He called upon this Court to dismiss the writ petitions.

    6. I carefully considered the rival contentions of both sides and went through the materials on record. Let me take up the preliminary objections first. It is true that Clause

    7

    23 of the tender notification provides for arbitral remedy. It is again true that the subject matter pertains to a commercial contract. The objections however stand overruled in view of the ratio laid down in "U.P. Power Transmission Corporation Ltd., -Vs- CG Power & Industrial Solutions Limited (2021) 6 S.C.C.15". The Hon'ble Supreme Court categorically held that the existence of an arbitration clause does not debar the court from entertaining a writ petition and that relief under Article 226 of the Constitution of India may be granted in a case arising out of a contract. Of course, the High Courts usually refrain from entertaining a writ petition which involves adjudication of disputed questions of fact which may require analysis of evidence of witnesses. But in this case, there are no disputed questions of fact. Since the respondent Corporation is a State instrumentality, and since the petitioners complain of violation of statutory procedure, I am inclined to consider the case on merits.

    7. I have already noted that the demand by the respondent Corporation for supply of additional 25% is well within the scope of the contract. The Corporation has not made any demand outside its framework. It is true that by the time the impugned demand was made, the market conditions had undergone a change and war between Russia and Ukraine had broken out on 24.02.2022. I carefully went through the contents of the affidavits filed in support of the writ petitions. Nowhere there is any averment that the subject matter of the contract is unavailable in the market. The petitioners in fact cannot be heard to argue so. When in April 2022, the Corporation issued a notification for supply

    8

    of Fortified RBD Palmolein, it did evoke response. Till the issuance of ban order by the Indonesian Government on 27.04.2022, there were bidders offering to supply the commodity in question, of course at a higher rate. The contract was concluded on 13.01.2022. The impugned communications for supply of additional quantity of 25% were issued on 02.03.2022.

    8. The only reason put forth by the petitioners is that the prices have gone up by 25%. Can this be a ground to plead frustration of the contract is the moot question before me. There is some support in the views expressed by Lord Reid and Lord Horson in the House of Lords decision of Tsakiroglou & Co., Ltd. Vs. Noblee Thorl GmbH (1962) AC 93 for the proposition that increased costs might constitute a possible ground for frustration where they were so extreme as to be "astronomical". In an article appearing in (2011) 12 SALAnnRev 92 by Chow Kok Fong and Philip Chan Chen Fye, it is mentioned that, the said view finds favour in Glahe International Expo AG -Vs- ACS Computer Pte Ltd., (1999) 1 SLR(R) 945. But, we are governed by the provisions of the Indian Contract Act, 1872. We have to go only by Section 56 of the said Act which is as follows:

    " Section 56 : Agreement to do impossible act

    An agreement to do an act impossible in itself is void. Contract to do an act afterwards becoming impossible or unlawful.—A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.

    9

    Compensation for loss through non-performance of act known to be impossible or unlawful.—Where one person has promised to do something which he knew, or, with reasonable diligence, might have known, and which the promisee did not know, to be impossible or unlawful, such promisor must make compensation to such promisee for any loss which such promisee sustains through the nonperformance of the promise."

    9. Tsakiroglou & Co., and the aforesaid statutory provision were considered by the Hon'ble Supreme Court in Energy Watchdog -Vs- CERC (2017) 14 SCC 80. The principles set out therein furnish a complete answer to every contention advanced by the learned Senior Counsel appearing for the petitioners. It was held therein as follows:

    "36.The law in India has been laid down in the seminal decision of Satyabrata Ghosev.Mugneeram Bangur & Co.[Satyabrata Ghosev.Mugneeram Bangur & Co., 1954 SCR 310 : AIR 1954 SC 44] The second paragraph of Section 56 has been adverted to, and it was stated that this is exhaustive of the law as it stands in India. What was held was that the word "impossible" has not been used in the section in the sense of physical or literal impossibility. The performance of an act may not be literally impossible but it may be impracticable and useless from the point of view of the object and purpose of the parties. If an untoward event or change of circumstance totally upsets the very foundation upon which the parties entered their agreement, it can be said that the promisor finds it impossible to do the act which he had promised to do. It was further held that where the Court finds that the contract itself either impliedly or expressly contains a term,

    10

    according to which performance would stand discharged under certain circumstances, the dissolution of the contract would take place under the terms of the contract itself and such cases would be dealt with under Section 32 of the Act. If, however, frustration is to take place dehors the contract, it will be governed by Section

    56.

    37.In Alopi Parshad & Sons Ltd.v.Union of India[Alopi Parshad & Sons Ltd.v.Union of India, (1960) 2 SCR 793 : AIR

    1960 SC 588] , this Court, after setting out Section 56 of the Contract Act, held that the Act does not enable a party to a contract to ignore the express covenants thereof and to claim payment of consideration, for performance of the contract at rates different from the stipulated rates, on a vague plea of equity. Parties to an executable contract are often faced, in the course of carrying it out, with a turn of events which they did not at all anticipate, for example, a wholly abnormal rise or fall in prices which is an unexpected obstacle to execution. This does not in itself get rid of the bargain they have made. It is only when a consideration of the terms of the contract, in the light of the circumstances existing when it was made, showed that they never agreed to be bound in a fundamentally different situation which had unexpectedly emerged, that the contract ceases to bind. It was further held that the performance of a contract is never discharged merely because it may become onerous to one of the parties.

    38.Similarly, in Naihati Jute Mills Ltd.v.Khyaliram Jagannath[Naihati Jute Mills Ltd.v.Khyaliram Jagannath, (1968)

    1 SCR 821 : AIR 1968 SC 522] , this Court went into the English law on frustration in some detail, and then cited the celebrated judgment of Satyabrata Ghose v.Mugneeram Bangur &

    11

    Co.[Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310 : AIR 1954 SC 44] Ultimately, this Court concluded that a contract is not frustrated merely because the circumstances in which it was made are altered. The courts have no general power to absolve a party from the performance of its part of the contract merely because its performance has become onerous on account of an unforeseen turn of events.

    39. It has also been held that applying the doctrine of frustration must always be within narrow limits. In an instructive English judgment, namely,Tsakiroglou & Co. Ltd.v.Noblee Thorl GmbH[Tsakiroglou & Co. Ltd.v.Noblee Thorl GmbH, 1962 AC 93 : (1961) 2 WLR 633 : (1961) 2 All ER 179 (HL)] , despite the closure of the Suez Canal, and despite the fact that the customary route for shipping the goods was only through the Suez Canal, it was held that the contract of sale of groundnuts in that case was not frustrated, even though it would have to be performed by an alternative mode of performance which was much more expensive, namely, that the ship would now have to go around the Cape of Good Hope, which is three times the distance from Hamburg to Port Sudan. The freight for such journey was also double. Despite this, the House of Lords held that even though the contract had become more onerous to perform, it was not fundamentally altered. Where performance is otherwise possible, it is clear that a mere rise in freight price would not allow one of the parties to say that the contract was discharged by impossibility of performance.

    40.This view of the law has been echoed inChitty on Contracts, 31st Edn. In Para 14-151 a rise in cost or expense has

    12

    been stated not to frustrate a contract. Similarly, in Treitel on Frustration and Force Majeure, 3rd Edn., the learned author has opined, at Para 12-034, that the cases provide many illustrations of the principle that a force majeure clause will not normally be construed to apply where the contract provides for an alternative mode of performance. It is clear that a more onerous method of performance by itself would not amount to a frustrating event. The same learned author also states that a mere rise in price rendering the contract more expensive to perform does not constitute frustration. (See Para 15-158.)"

    10. It is clear from the above that the doctrine of frustration cannot apply to these cases as the fundamental basis of the contract remains unaltered. The escalation of the price of the commodity in the market cannot be a ground to plead frustration. In any event, the escalation is only by 25% or more. The petitioners are seasoned suppliers. With their market experience, they obviously would have foreseen that prices may fluctuate. Price fluctuation cannot be construed as a force majeure event warranting invocation of Section 56 of the Indian Contract Act. The petitioners cannot be said to have been "hindered or prevented" from making the additional supplies. The Indonesian ban came only on 27.04.2022, whereas the impugned demand for additional supply was made on 02.03.2022. The profit calculation originally made by the petitioners might have gone for a toss. That is no reason to permit them to wriggle out of the consequences that flow logically from the contractual arrangements knowingly entered into by them.

    13

    11. I do not find any ground to interfere with the impugned communications issued by the respondent Corporation. All these writ petitions stand dismissed. No costs. Consequently connected miscellaneous petitions are also dismissed.

    01.06.2022

    Internet: Yes Index: Yes

    KST

    .

    To

    1. The Managing Director,Tamil Nadu Civil Supplies Corporation No.12, Thambusamy Road, Kilpauk,Chennai 600 010.

    2. The Managing Director Tamil Nadu Civil Supplies Corporation No.12, Thambusamy Road, Kilpauk Chennai 600 010.

    3.Tender Sub-Committee

    Rep.by its Members, No.12, Thambusamy Road, Kilpauk Chennai 600 010.

    4. The Board of Directors, Tamil Nadu Civil Supplies Corporation No.12, Thambusamy Road, Kilpauk, Chennai 600 010. 5.The Principal Secretary to Government

    Cooperation, Food and Consumer Protection

    Department, St.George Fort, Chennai.

    14

    G.R.SWAMINATHAN,J.

    KST

    Pre-Delivery Order in

    01.06.2022

    15