National Consumer Disputes Redressal Commission — Consumer Case No. 405 of 2017 (Order dated 22 Mar 2022)

Factual and Procedural Background

This proceeding arises from a Consumer Complaint filed under Section 21(a)(i) read with Section 12(1)(c) of the Consumer Protection Act, 1986 by multiple allottees (the Complainants) of residential units in a housing project called "The Kove" at Jaypee Green Sports City, Sector 25, Yamuna Expressway Industrial Authority Area, Dankaur, Gautam Budh Nagar, Uttar Pradesh. The Opposite Party (OP Developer) is Jai Prakash Associates Ltd. & others.

The Complainants allege deficiency in service and unfair trade practices for failure to hand over possession within the stipulated period (possession was promised within 42 months from allotment). They seek either possession with delayed compensation or refund of amounts deposited with interest and compensation. The Complaint was treated as a class-action under Section 12(1)(c) by IA No. 2155/2017 allowed on 18.09.2017.

The Complaint describes bookings made between 2010 and 2012, repeated demands and payments made to the OP Developer, non-execution of builder-buyer agreements, alleged construction stoppage with incomplete structure, requests for possession or refund, and annexed photographs of the site. A detailed list of named complainants, unit numbers, allotment dates, promised delivery dates and amounts deposited appears in the record.

The OP Developer resisted the complaint, filing IA No. 1010 (variously referenced as IA No. 1010/2020 and IA No. 1010/2022 in the record) seeking recall of the 18.09.2017 order that permitted class-action treatment. The OP contended there was no "sameness of interest" among all allottees, pointed to parallel proceedings before UP RERA, DRT-related cancellations/refunds, the existence of allottees who are companies or multiple unit-bookers, defaults by some allottees, and pleaded force majeure and limited liquidated remedies in the standard terms and conditions. The OP also adduced material regarding its financial position and prior deposits of ₹750 Crore with the Supreme Court registry in related proceedings.

Legal Issues Presented

  1. Whether the Complaint could be treated and maintained as a class-action under Section 12(1)(c) of the Consumer Protection Act given the alleged differences among allottees and parallel proceedings before other fora.
  2. Whether the named complainants qualify as "consumers" under the Act (including when a complainant booked multiple units or where a company booked a unit for investment).
  3. Whether the doctrine of election applies where some allottees have instituted proceedings before UP RERA or other fora, and if so whether that precludes the Commission's jurisdiction.
  4. Whether the standard terms and conditions of allotment (notably clauses providing liquidated rebates of Rs.5 per sq. ft. and interest obligations on delayed payments at 18% p.a., and exclusions for force majeure) are enforceable or constitute unfair one-sided clauses that preclude broader reliefs such as refund with interest.
  5. On the merits, whether specific allottees are entitled to possession or, alternatively, refund of deposited amounts with interest and compensation given the prolonged delay and apparent incompletion of the project.

Arguments of the Parties

Complainants' Arguments

  • Allottees booked units during 2010–2012 relying on OP Developer's advertisements and assurances of modern facilities and timely possession within the stipulated 42 months.
  • Builder-buyer agreements were not executed despite requests; payments were made as demanded, including late payment charges; some allottees took housing loans to make payments.
  • Construction stalled and basic structure remained incomplete; photographs attached to complaint demonstrate lack of progress; hence complainants seek possession with delayed compensation or refund with interest and compensation for mental agony and legal costs.
  • An application under Section 12(1)(c) (IA No. 2155/2017) sought class-action treatment because interests of all unit-buyers were said to be identical; that application was allowed on 18.09.2017.

Opposite Party / Developer's Arguments

  • Challenged class-action treatment: asserted lack of "sameness of interest" among all applicants (some allottees sought different reliefs, some had cancellations/refunds ordered by bank under DRT, some had approached RERA or other forums).
  • Some complainants booked multiple units, some are companies (e.g., M/s Agarwal Agencies) or non-resident, and some defaulted on payments — these factors, OP argued, exclude them as "consumers" or otherwise affect maintainability.
  • Relied on standard terms and conditions: Clauses entitle OP to extension of time for force majeure and limit buyers' remedies to a rebate of Rs.5 per sq. ft. per month (Clause 7.1/7.2), while buyers owe 18% p.a. interest on unpaid sums (Clause 5.6).
  • Alleged reasons for delay included farmers' agitation, government policy changes, NGT restrictions on groundwater extraction and economic slowdown — i.e., events beyond developer's control.
  • OP pointed to its financial difficulties and prior deposit of ₹750 Crore with the Supreme Court registry in related proceedings, and submissions regarding ongoing adjudications (e.g., before NCLT) affecting available reliefs.
  • OP offered to refund with interest at 8% p.a., preferably within one year, and relied on certain higher-court orders (including Civil Appeal No.1779/2021 — Brigade Enterprises Ltd. v. Anil Kumar Virmani & Ors.) in support of some contentions regarding class-action recall.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31 Principle: Onus shifts to the Opposite Party to establish that the complainant was dealing in real estate as a business to earn profits (i.e., to prove complainant is not a consumer). The Commission applied this principle and held that the OP failed to discharge that onus; therefore the complainants qualify as "consumers" under Section 2(1)(d) of the Act.
M/s. Imperia Infrastructure Ltd. vs. Anil Patni & Anr., 2020 10 SCC 783 Doctrine of Election: A person who first approaches one forum (e.g., Consumer Commission, RERA or NCLT) is estopped from approaching another; doctrine applies to competing fora for relief. The Commission referred to this Supreme Court authority and held that, because the complainants approached the Commission in 2017 and RERA proceedings were initiated later in 2020, the doctrine of election did not bar the present complaint and the complaint remained maintainable before the Commission.
Pioneer Urban Land & Infrastructure Ltd. vs. Govindan Raghavan, II (2019) CPJ 34 (SC) Holds that contractual terms that are one-sided, unfair and where purchasers had no real option to negotiate are not binding and may constitute unfair trade practice. The Commission relied on this Supreme Court observation to conclude that the Standard Terms and Conditions (which imposed 18% interest on buyers but limited buyers' remedy to Rs.5 per sq. ft.) were one-sided and unfair and thus could not be enforced against complainants to deny broader reliefs.
Kolkata West International City Pvt. Ltd. vs. Devasis Rudra, II (2019) CPJ 29 (SC) Observation that it is unreasonable to require a buyer to wait indefinitely for possession; where excessive delay has occurred, refund orders may be justified. The Commission invoked this authority to support the proposition that where there has been an excessive unreasonable delay (here more than 12 years since allotment), complainants cannot be made to wait indefinitely and are entitled to refund with interest.
Chitra Sharma vs. Union of India, (2018) 18 SCC 575 Reference to treatment/direction concerning funds (as applied in context of deposit of amounts with Court registry) and subsequent direction about transfer to Adjudicating Authority. The Commission noted that the OP Developer had deposited ₹750 Crore with the Supreme Court registry in related matters and that the final Supreme Court directions transferred the amount to the Adjudicating Authority; this factual posture was taken into account in assessing the OP's financial contentions (controversy pending adjudication before NCLT).
Jaypee Kensington Boulevard Apartments Welfare Association vs. NBCC Ltd. & Ors., 2021 SCC online SC53 Reference in the record regarding the Supreme Court's judgment and subsequent proceedings relevant to funds / adjudication under insolvency laws. The Commission noted these higher-court proceedings in the factual recounting of the OP's financial position; the litigation over the ₹750 Crore continues before the Adjudicating Authority and informed the contextual background of the OP's submissions.
Brigade Enterprises Limited vs. Anil Kumar Virmani & Ors., Civil Appeal No. 1779/2021 (Order dated 17.12.2021) Order cited by the OP in support of its contention to recall the earlier class-action allowance (as relied upon by the OP). The OP relied on this Supreme Court order; the Commission considered the OP's IA (IA No. 1010) and ultimately disposed IA No. 1010/2020 in terms that the present Order would apply only to complainants who have approached the Commission in the present Complaint or got themselves impleaded.

Court's Reasoning and Analysis

The Commission heard learned counsel for the parties and examined the record. The analysis proceeded through discrete legal questions raised by the OP and the Complainants:

  1. Maintainability / Scope of IA No.1010: The Commission limited the effect of IA No.1010 (sought to recall the 18.09.2017 order) to complainants who had approached or were impleaded in the present complaint and disposed IA No.1010/2020 in those terms.
  2. Consumer status: Relying on the Commission's own precedent in Kavita Ahuja vs. Shipra Estates, the Commission held the OP bears the onus of proving that any complainant was engaged in the business of buying and selling flats to earn profits. The OP failed to discharge that onus by producing documentary evidence; therefore the complainants qualify as "consumers" under Section 2(1)(d) of the Act.
  3. Default in payments and cancellation requests: The Commission observed that if complainants defaulted in payments, the OP had contractual remedies (cancellation, charging delay interest) available under the standard terms; the OP could not use complainants' payment default as a blanket defence to deny their right to approach the Commission. Where allotments were cancelled at complainants' request, it was not clear whether refunds had been made; if refunds had not been made, that would amount to deficiency in service obliging refund with interest.
  4. Doctrine of Election: The Commission applied the principle from the Supreme Court in Imperia Infrastructure and observed that the complainants filed the Consumer Complaint in 2017 while some RERA proceedings were filed later in 2020. Therefore the doctrine of election did not preclude the Commission's jurisdiction and the Complaint was maintainable before the Commission.
  5. Force majeure and standard terms: The Commission examined Clauses 5.6 and 7.1 of the Standard Terms and Conditions. Clause 5.6 imposed an 18% p.a. interest obligation on buyers for late payments; Clause 7.1/7.2 limited the developer's liability on delay to a rebate of Rs.5 per sq. ft. per month and excluded force majeure periods from calculation. The Commission found these terms to be one-sided and unfair. It relied on the Supreme Court's authority in Pioneer Urban Land & Infrastructure to hold that such ex facie one-sided clauses cannot bind purchasers and constitute unfair trade practice.
  6. Remedy on merits — refund vs possession: The Commission noted the prolonged delay (more than 12 years since allotment in many cases) and the practical impossibility of giving possession in the near future given the state of construction. Citing Kolkata West International City Pvt. Ltd. v. Devasis Rudra, the Commission concluded that purchasers cannot be made to wait indefinitely and that refund of deposited monies with reasonable interest was justified.
  7. Interest rate and conditional directions: The OP offered refunds at 8% p.a. The Commission, however, having observed a "catena of Judgments" from the Supreme Court awarding interest at 9% p.a., rejected the OP's lower offer and directed refund with interest at 9% p.a. from the date of deposit until payment, to be made within 3 months; failing compliance, the interest rate would increase to 10% p.a. The Commission also directed that if any complainant has an outstanding housing loan, the complainant must first repay the bank/financial institution from the refund and then use any balance for personal purposes.

Holding and Implications

Holding (core ruling): The Consumer Complaint is partly allowed.

Specific directions and immediate consequences:

  • The OP Developer is directed to refund the entire deposited amount to the respective complainants along with interest at 9% per annum from the respective date(s) of deposit until the date of actual payment.
  • The refunds are to be effected within a period of 3 months from the date of the Order. If the OP fails to comply, the interest rate on refunds shall increase from 9% p.a. to 10% p.a.
  • If any complainant has taken a housing loan, the complainant shall first repay the outstanding amount to the lending bank or financial institution; any balance from the refund shall be used by the complainant for personal purposes.
  • IA No.1010/2020 (the OP's IA seeking recall/limitation of the class-action order) stands disposed of in the terms specified by the Commission (the Order will apply only to complainants who have approached the Commission in this Complaint or have been impleaded).
  • Pending applications, if any, are disposed of.

Implications beyond the parties: The Order applies the established principles from higher courts regarding (a) the onus on the developer to prove a purchaser is not a consumer, (b) the doctrine of election as between fora, and (c) the non-enforceability of manifestly one-sided standard contract terms. The Commission directed refunds with interest consistent with cited Supreme Court precedents; the Order does not indicate it is creating a novel legal precedent beyond applying those authorities to the facts before it.

Signed: R.K. Agrawal, President (Order dated 22 March 2022)

    Mamta Maurya And Others Complainant(S) v. Jai Prakash Associates Ltd. And Others Opp.Party(S).

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    CONSUMER CASE NO. 405 OF 2017

    1. MAMTA MAURYA & 21 ORS. W/o Mr. Ram Pukar Maurya R/o 39, Bari Mandi, Pariya Hapur

    UP

    2. Mr. Ram Pukar Maurya S/o Sh. R. L. Maurya R/o 39, Bari Mandi, Pariya Hapur

    U.P.

    3. Ms. Meenakshi Gupta W/o Mr. Sanjeev Gupta 142, Akash Kunj, Plot -I, Sector 9, Rohini

    Delhi 110085

    4. Mr. Sanjeev Gupta S/o Mr. Amar Nath Gupta 142, Akash Kunj, Plot -I, Sector 9, Rohini

    Delhi 110085

    5. Babbar Shakeel Through Power of Attorney Holder Md. Shahnawaz Iqbal

    S/o MD. Iqbal Nafis R/o Flat No. 03, 2nd Floor C-19/1, Hindon Vihar Sector 49 Noida

    UP 201301

    6. Seemin Parveen Through Power of Attorney Holder Md. Shahnawaz Iqbal

    S/o MD. Iqbal Nafis R/o Flat No. 03, 2nd Floor C-19/1, Hindon Vihar Sector 49 Noida

    UP 201301

    7. Dr. Anuradha Shukla W/o Dr. Dilip Shukla R/o B-272, Sarita Vihar New Delhi 110076

    8. Dr. Anuradha Madhukar W/o Mr. Anand Madhukar R/o C-601, Central Government Officers Residential Complex, Deen Dayal Upadhyay Marg, New Delhi 110002

    9. Mr. Anand Madhukar R/o C-601, Central Government Officers Residential Complex, Deen Dayal Upadhyay Marg,

    New Delhi 110002

    10. Dr. V. B. Prasad Through Power of Attorney Holder Dr. Anuradha Madhukar

    E/o Mr. Anand Madhukar A/IV/35 NML Colony, AGRICO, Jamshedpur,

    Jharkhand 831009

    11. mrs. Urmila Kumari Through Power of Attorney Holder Dr. Anuradha Madhukar

    W/o Mr. Anand Madhukar A/IV/35 NML Colony, AGRICO, ...........Complainant(s)

    1

    Jamshedpur, Jharkhand 831009

    12. Saroj Bala Mittal W/o Mr. M. L. Mittal R/o H. N. 2161, Sector 6, Karnal Haryana 132001

    13. Mr. Parag Mittal Through Power of Attorney holder Mr. M. L. Mittal

    S/o Jai Gopal Mittal R/o H. No. 2161, Sector 6, karnal Haryana 132001

    14. Mrs. Satya Jaiswal Through Power of Attorney Holder Mr. praveen Kumar Gupta,

    R/o First Floor, B4/45 Vinay Khand, Gomti Nagar, Lucknow Uttar Pradesh

    15. Mr. B. C. Jaiswal Through Power of Attorney Holder Mr. Praveen Kumar Gupta, R/o First Floor, B4/45 Vinay Khand, Gomti Nagar, Lucknow

    UP

    16. Mr. Sunil Kumar Sharma Through powr of Attorney Holder mr. Neeraj Gaur

    S/o Mr. Ramvir Sharma R/o Flat No. 134B, Ankur Apartment, GH2, Paschim Vihar, West Delhi 110063

    17. Mr. Shubham Jain S/o Mr. Akshay Kumar Jain R/o 1/5088, Gali No. 4, Balbir Nagar, Shahdara,

    Delhi 110032

    18. Ms. Dimple Gupta, W/o Mr. Shubham Jain R/o 1/5088, Gali No. 4, Balbir Nagar, Shahdara,

    Delhi 110032

    19. Mrs, Bharti Moudgill W/o Mr. Divey Mahajan R/o Flat No. 501, T-14, Lotus Boulevard, S-100 Noida

    UP

    20. Mr. Divey Mahajan R/o Flat No. 501, T-14, Lotus Boulevard, S-100 Noida

    UP

    21. Dr. Ankit Verma Flat no. C-503, Fifth Floor Chinar Apartments plot No. 3, Sector 18 Dwarka

    New Delhi 110078

    22. Ms. Snigdha Kumar W/o Dr. Ankit Verma Flat no. C-503, Fifth Floor Chinar Apartments Plot No. 3, Sector 18 Dwarka New Delhi 110078

    23. ASHISH MURGAI

    .

    24. NEHA MURGAI

    2

    .

    25. DEEPAK RAJKUAMR

    .

    26. PRATIBHA MONGA

    .

    27. HARENDRA SINGH

    .

    28. MITHLESH

    .

    29. MAJOR VIVEK KUMAR

    .

    30. MAJOR RITU JAISWAL

    .

    31. SUNNY HARISH BHATIA

    .

    32. RAHUL PURI

    .

    33. SHISHIR NIGAM

    .

    34. BABITA SETHI

    .

    35. RAJEEV SETHI

    .

    36. NIRUPAM MADAAN

    .

    37. REENA VERMA

    .

    38. ASHWANI SAINI

    -

    39. SWEETY KAURA

    -

    40. HARISH PRASAD

    .

    41. SEEMA SATI

    .

    42. DEEPAK KHANNA

    .

    43. GURDARSHAN SINGH

    S/o. LAte Sh. Kaipal Singh, R/o. Shed No. 95, DSIDC SCHEME-1, Okhala Industrial Area, Phase-II, New Delhi - 110 020

    44. ANUJ KUMAR JAIN

    -

    45. ANJU JAIN

    -

    3

    46. M/S. AGARWAL AGENCIES (P) LTD. Through its Direcyor & Authorized Rep. Mr. Rakesh Agarwal, Office at D-16/2-3, Okhla Industrial Area, Phase-I, New Delhi - 110 020

    47. NITIN PURI

    S/o. Mr. Jagdish Puri, Through his Power of Attorney Holder Mr. Jagdish Puri, R/o. A-1-A/13-B, Janakpuri, New Delhi - 110 058

    48. SEEMRAN PURI

    W/o. Mr. Nikhil Puri, Through Her Power of Attorney Holder, Mr. Jagdish Puri, R/o. A-1-A/13-B, Janakpuri, New Delhi - 110 058

    49. PRIYA PRAKASH

    S/o. Mr. Sarvanand Upadhyay, R/o. B-231, Sector-55, Noida

    50. PRIYA PRAKASH

    S/o. Mr. Sarvanand Upadhyay, R/o. B-231, Sector-55, Noida

    51. SHALINI PURI

    .

    52. POOJA GUPTA

    .

    53. VIVEK GUPTA

    .

    54. NITIN KOHLI

    .

    55. AJAY RAJ GUPTA

    .

    56. MUDIT SETHI

    .

    57. SHEETAL GULATI

    .

    58. RAJESH KUMAR & PUSHPA KUMARI

    .

    59. SHRUTI JAIN & PANKAJ JAIN

    .

    60. VAIBHAV TRIPATHI

    .

    61. RAHUL MOHAN,

    S/O. OM PRAKASH GOEL, R/O. 3814, GALI NO. 6,

    KANHAIYA NAGAR, TRI NAGAR

    DELHI-110035

    62. .

    .

    63. MAMTA MAURYA

    .

    4

    Versus

    1. JAI PRAKASH ASSOCIATES LTD. & 3 ORS. Regd. Off. Sector 128 Noida 201304 Through its Executive Chairman and CEO

    2. Mr. Manoj Gaur Executive Chairman and CEO Jai Prakash Associates Ltd. Regd. OFf. Sector 128 Noida

    201304

    3. Jaypee Sports International Limited Regd. Off. Sector 128 Noida 201304 Through its Director

    4. Mr. Sunil Kumar Shama Director Jaypee Sports International Ltd. Regd. Off. Sector 128 Noida 201304 ...........Opp.Party(s)

    BEFORE:

    HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT

    For the Complainant : For the Complainants : Mr. Sonam Sharma, Advocate Mr. Arjun Rekhi, Advocate

    Mr. Shashwat Tripathi, Advocate

    For the Opp.Party : For the Opposite Party : Mr. Sukumar Pattjoshi, Sr. Advocate Mr. Sumeet Sharma, Advocate

    Mr. Tenzen Negi, Advocate

    Dated : 22 Mar 2022

    ORDER

    1. The present Consumer Complaint has been filed under Section 21(a)(i) read with Section 12(1)(c) of the Consumer Protection Act, 1986 (for short "the Act) by the Complainants/Allottees of the Units in the Residential Housing Project under the name and style "The Kove" located at Jay Pee green Sports City, Sector 25, Yamuna Expressway Industrial Authority Area, Dankaur, District Gautam Budh Nagar, Uttar Pradesh (hereinafter to be referred as the Project), by Opposite Party Jaiprakash Associates Ltd., (hereinafter referred to as the OP Developer), interalia, alleging deficiency in service in not handing over the possession of the Units within stipulated period and seeking either possession with delayed compensation or refund of amount deposited by them along with reasonable interest and compensation.

    2. Since the interest of the Complainants and other Unit buyers in the aforesaid Project is the same and identical reliefs have been claimed on behalf of all the Complainants, IA No. 2155 / 2017, an Application under Section 12(1)(c) of the Act has also been filed with the Complaint to treat the Complaint as a class-action Complaint. Vide Order dated 18thSeptember 2017, IA No. 2155 / 2017 was allowed and the Complaint was treated as filed under Section 12(1)(c) of the Act.

    3. It has been averred in the Complaint that in the year 2010, Opposite Party Developer launched a Housing Project under the name and style of "The Kove" located at Jay Pee green Sports City, Sector 25, Yamuna Expressway Industrial Authority Area, Dankaur, District Gautam Budh Nagar, Uttar Pradesh. Allured by the exaggerated advertisement and the assurances given by the authorised representatives of the OP Developer that there

    5

    would be every modern facility in the Project and the physical Possession would be handed over within stipulated period, the Complainants booked respective residential Units in the said Project in the year 2010-2012 by filing up the Application Form but copy of the Forms were supplied to some of the Complainants only. The Application Forms contained the Standard Terms and Conditions which were to be followed by both the Parties. It is further averred that certain terms and conditions mentioned in the Application Form were unfair and biased. Complainants were allotted distinct Units through Provisional Allotment letters by the OP Developer. In the Provisional Allotment letters, it was assured that the possession of the booked Units would be handed over within a period of 42 months. It was alleged that at the time of issuance of Provisional Allotment Letters, when the Complainants asked the OP Developer to execute Builder Buyer Agreement (hereinafter referred to as the Agreement), they were assured that the Agreements would be executed soon and the legal Department of the OP Developer is in the process of execution of the Agreement. During the passage of time when the Agreements were not executed, on enquiry made by the Complainants, the OP Developer kept delaying execution of Agreement on one pretext or the other. Despite several repeated requests and having received a lot of money from the Complainants, the OP Developer had not executed the Agreement with them till the date of filing of the Complaint. Relying upon the name and reputation of the OP Developer, the Complainants kept on depositing the amount as per demand made by the OP Developer against the payment receipts as well as Statement of Account issued by the OP Developer. Some of the Complainants have obtained Housing Loan from several financial institutions in order to make the timely payment to the OP Developer. It was also stated that in some cases, even the late payment charges @18% p.a. were also deposited alongwith demanded amount in case of late payment. The details of the Complainants, Unit Allotted, Amount deposited and expected date of delivery of the Units, is reproduced in the following table:-

    Date of

    Purported

    Complainant Name of the Provisional Total Amount

    Unit Allotted date of

    No. Allottee Allotment Paid

    delivery

    letter

    1.OC Mrs

    Mamta Maurya and

    LD1 -16-1103 13.09.2012 12.06.2016

    ₹41,52,322./- Mr

    2.OC Ram Pukar Maurya 3.OC Mrs Meenakshi Gupta and

    LD1-05-901 14.12.2011 13.09.2015

    ₹25,97,196/- Mr.Sanjeev Gupta

    6

    4.OC
    5.OC   6.OC Mr.BabbarShakeel and   Miss SeeminParveen LD1-02-1501 7.01.2012 26.10.2015 ₹26,10,510/-
    7.OC Dr. Anuradha Shukla LD1-01-1506 4.05.2012 13.02.2016 ₹14,36,128/-
    8.OC   9.OC Dr.Anuradha Madhukar   Mr.AnandMadhukar LD1-17-1003 8.01.2013 07.10.2016 ₹22,05,765/-

    10. Deleted      
    11 Deleted      
    12.OC   13.OC Mrs.SarojBala Mittal and Mr.Parag Mittal LD1-07-302 0.09.2011 19.06.2015 ₹27,15,805/-
    14.OC   15.OC Mrs SatyaJaiswal and   Mr.B.C.Jaiswal LD1-06-103 7.01.2012 16.10.2015 ₹25,20,326/-

    Mr. Sunil Kumar

    16.OC LD1-14-303 27.09.2012 26.06.2016

    ₹22,54,579/- Sharma

    7

    17 Deleted

    18 Deleted Mrs BhartiMoudgil

    19 OC

    and

    LD1-02-1701 30.03.2012 29.01.2016 ₹30,09,788/-

    20 OC

    Mr DiveyMahajan

    21 OC Dr.AnkitVerma and LD1-18-802 27.10.2012 26.07.2016

    ₹24,60,999/-

    22 OC Ms Snigdha Kumar

    23 OC Mr AshishMurgai And LD1-16-1204 13.09.2012 12.06.2016

    ₹21,23,808/-

    24 OC Ms NehaMurgai

    25 Mr Rajkumar And LD1-16-1102 24.12.2011 23.12.2015

    ₹38,49,390/-

    26 Ms PratibhaMonga

    27 Mr Harendra Singh And LD1-17-1602 12.03.2013 11.12.2016

    ₹20,92,963/-

    28 Mrs Mithilesh

    29 Major Vivek Kumar And LD000151101 15.06.2013 14.03.2017

    ₹42,03,783/-

    30 Major RituJaiswal

    8

    Mr Sunny Harsh

    31 LD1-12-2004 21.12.2012 20.09.2016

    ₹20,12,803/- Bhatia

    32 Mr Rahul Puri LD1-19-1502 5.02.2013 24.11.2016 ₹37,54,336/-
    33 Shishir Nigam   LD001160701 7.07.2013 26.04.2017  
    34 Deleted        
    35 Deleted      
    36 Dr NirupamMadaan   LD1-05-1101 3.02.2013 12.11.2016 ₹30,73,408/-
    37 Ms ReenaVerma   LD1-15-1502 4.01.2012 23.10.2015 ₹19,37,875/-
    38   39 Ms SweetaKaura and Ashwani Saini LD1-03-1004 3.07.2011 22.04.2015 ₹18,23,131/-
    40   41 Harish Prasad And Seema Sati LD1-02-406 5.10.2012 04.04.2016 ₹32,52,795/-

    9

    42 Deleted        
    43 Mr Gurdarshan Singh   LD1-17-1503 3.12.2012 12.11.2016 ₹21,73,282/-
    44   45   Mr Anuj Jain And Mrs Anju Jain LD1-12-303 4.12.2011 13.09.2015 ₹18,62,911/-

    Mr Gurdarshan

    43 Singh LD1-17-1503 03.12.2012 12.11.2016

    ₹21,73,282/-

    44

    Mr Anuj Jain And LD1-12-303 14.12.2011 13.09.2015

    ₹18,62,911/-

    45

    Mrs Anju Jain

    46   Ms Agrawal Agency (P) Ltd   LD1-15-802 7.10.2012 26.07.2016 ₹17,50,000/-
    47   48 Mr NitinPuri And Mrs SeemranPuri LD-15-1204 2.05.2012 11.02.2016 ₹38,62,898/-

    49 Mr PriyaPrakash   LD1-01-905 6.03.2012 13.08.2017 ₹16,80,262/-
    50 Ms ShaliniPuri   LD1-12-1803 0.09.2011 19.03.2015 ₹8,34,262/-
    51   Mrs Pooja Gupta And LD1-01-406 7.11.2011 16.08.2014 ₹13,88,184/-

    10

    52 Mr Vivek Gupta
    53 Mr NitinKolhi   LD1-02-204 2.01.2012 01.10.2015 ₹16,47,011/-
    54 Dr Ajay Raj Gupta   LD00141002 8.05.2013 13.03.2017 ₹22,80,086/-
    55 Mr MuditSethi   LD1-01-402 3.12.2012 02.09.2016 ₹17,82,029/-
    56 Ms SheetalGulati   LD1-02-603 0.03.2012 29.12.2015 ₹14,98,174/-
    57   58 Mr Rajesh Kumar And Mrs PushpaKumari      
    59   60 Mrs Shruti Jain And Pankaj Jain LD1-12-602 8.06.2012 27.03.2016 ₹21,18,096/-

    61  Mr ViabhavTripathi   LD1-03-1402 3.12.2012 01.07.2015 ₹25,04,822/-
    62 Mr Rahul Mohan (Orignally allotted to Mr Mohammad & LD1-02-1801 5.02.2014 riginally 3.01.2012 23.10.2015 ₹16,19,197/-

    11

    Mr Sachin vide letter

    Dated 23.01.2012) Mr.Ravinder Gupta

    63

    And Not Not

    Mrs Vinita Gupta Not provided provided Not provided 64 provided

    4. It is alleged that the Complainants followed the payment plan and made the payment to the OP Developer as per its Demand. Despite that the OP Developer had failed to deliver the possession of the Units within stipulated period, within 42 months along with 90 days (3 months) grace period, as mentioned in the Provisional Allotment Letter. The Complainants raised query for actual date of possession but the OP Developer without assigning any reason for the delay, kept postponing the delivery date of the said Units on one pretext or the other. Being aggrieved, some of the Complainants personally visited the site for inspection and they were shocked and surprised to see that despite lapse of stipulated period, even the basic structure of the said Project has not been completed and it was completed only till the roof slab of the ground floor and the construction work on the site had been completely stopped and seeing the pace of construction it could be concluded that there was no possibility of completion of the said Project in the next five years. The Photographs of the site are attached as Annexure C-9 with the Complaint.

    5. Alleging deficiency in service and Unfair Trade Practice on the part of the OP Developer, the Complainants have filed the present Consumer Complaint seeking following Reliefs:-

    a) Direct the Respondents to handover possession of the respective Units to each allottee of the said Project immediately along with delayed interest @ 18% per annum from date of respective due date of possession till date of actual possession; or

    b) Direct the Respondents to refund the entire consideration amount paid by each Allottee of the said Project to the respective Allottee, alongwith interest @ 18% per annum from the date of respective payments made by the respective Allottee till its actual realization; and

    c) Direct the Respondents to pay an amount of ₹5,00,000/- (Rupees Five Lakh Only) to each of the Allottee of the said project for mental agony, anguish and harassment suffered by the Allottees, including but not limited to the Complainants on account of the gross breaches committed by the Respondents

    12

    herein; and

    d) Award legal cost of ₹6,00,000/- (Rupees Six Lakh Only) for filing and prosecuting the present complaint;

    e) Pass any other or further order as is deemed necessary by this Hon'ble Commission, in the facts and circumstances of the present case."

    6. The Complaint was resisted by the OP Developer. It was stated that they have filed IA No. 1010 / 2022 for recalling the Order dated 18.09.2017, vide which the Complaint was allowed to be filed under Section 12(1)(c). It was stated that there is no 'sameness of interest' of all the Complainants in the present case. It was further stated that some of the Complainants have filed Complaint cases before UP RERA; the Units allotted to Complainant No. 5 & 6, Mr. Babar Shakeel and Seemin Shakil and Complainant No. 19 & 20, Mr. Bharti Moudgil and Mr. Divey Mahajan, have been cancelled by the Bank under DRT Proceedings and Bank has asked refund from the OP Developer; Complainant Nos. 8 & 9, Mr. Anand Madhukar, Mr. Anuradha Madhukar, Complainant Nos. 10 & 11, Mr. V.B. Prasad and Ms. Urmila Kumari, Complainant Nos. 38 & 39, Sweety Aura and Mr. Ashwani Saini and Complainant Nos. 57 & 58 Mr. Rajesh Kumar & Mr. Pushpa Kumari have requested to cancel the Allotment of the Unit booked by them and their Allotment of the units have been closed, which shows that they are not having same / similar cause of action, sameness of interest or common grievance against them. It was further submitted that IA No. 2155 / 2017 was allowed vide Order dated 18.09.2017 for the limited purpose of possession. There are 800 Allottees in the Project but in the Complaint there is no averment made that all the 800 allottees are seeking cancellation and refund of the subject Unit. Several Allottees have sought various reliefs before various forums, i.e, before High Court of Allahabad, UP RERA etc., which is not permitted under the Act. The initial purpose of Application 12(1)(c) was to give possession. However, keeping in view the latest developments, possession is impossible at this stage since Proceedings are pending before Allahabad High Court in Writ Petition No. 6049 / 2020. It was further submitted that there is no 'sameness of interest' or 'benefit of all', and therefore, prayed that the Order dated 18.9.2017 allowing the Complaint to be filed under Section 12(1)(c) be recalled. In support of his contentions he relied upon the Order dated 17.12.2021 passed by the Hon'ble Supreme Court in "Civil Appeal No. 1779 / 2021 of Brigade Enterprises Limited vs. Anil Kumar Virmani & Ors."

    7. It was also submitted that Complainant No. 7, Complainant No. 16 and Complainant No. 33 have booked more than one Unit in the Project, while some of the Complainants are residing far, like Denmark, Abu Dhabi, Jharkhand, Haryana and they have not mentioned in their Complaint that they are presently residing in rented house and have not disclosed the purpose of booking of the Unit, Complainant No. 46 is a Company M/s. Agarwal Agencies Ltd., therefore, booked the Units only for investment & financial benefit purpose, thus, they cannot be termed as Consumers under the Act; some of the Complainants have defaulted in making the payment as per payment plan opted by them as such they have breached the terms and conditions of Allotment and thus, do not have any right to file the instant Complaint and the present Complaint is liable to be dismissed on this ground alone. It was also stated that as per Standard Terms and Conditions, in

    13

    case of force majeure events, the OP Developer is entitled to extension of time without incurring any liability. However, in case of delay the Complainants are not entitled more than the liquidated damages in the form of ₹5/- per sq. ft. in terms of Clause 7.1 of the respective Standard Terms and Conditions. It was further stated that the delay has occurred in the Project due to Farmer's Agitation; Government's decision to not to handover the Noida-Greater Noida Expressway for collecting the toll, which resulted in substantial loss of revenue to OP Developer; Restriction by NGT restraining all the Builders of Noida and Greater Noida from extracting any quantity of underground water for the purpose of construction and economic slow-down.

    8. It was also submitted that the OP Developer is in financial crisis as in compliance of the Order dated 11.09.2017 passed by the Hon'ble Supreme Court to protect the interests of the Homebuyers who have purchased the Flats in the Projects of JIL, a subsidiary company of OP Developer, against whom Moratorium has been issued under Insolvency & Bankruptcy Code, deposited a sum of ₹750 Crore with the Registry of Hon'ble Supreme Court. The Hon'ble Supreme Court vide its final Judgment in 'Chitra Sharma vs. Union of India' reported in (2018) 18 SCC 575, directed that the said amount of ₹750 Crores be transferred to the Adjudicating Authority and continue to remain invested under the supervision and direction of the Adjudicating Authority. It was submitted that the controversy pertaining to the said ₹750 Crores is still pending adjudication before the NCLT, New Delhi pursuant to the Judgment dated 24.03.2021 passed by the Hon'ble Supreme Court in the case 'Jaypee Kensington Boulevard Apartments Welfare Association vs. NBCC Ltd. & Ors.' Reported in 2021 SCC online SC53.

    9. I have heard Mr. Sonam Sharma, learned Counsel for the Complainants, Mr. Sukumar Pattjoshi, learned Senior Counsel appearing on behalf of the OP Developer, perused the material available on record and have given our thoughtful consideration to the various pleas raised by the learned Counsel for the Parties.

    10. For the reasons stated in the Application IA No. 1010 / 2020, the present Order will apply only to the Complainants, who have approached this Commission by way of the present Complaint or have got themselves impleaded in the instant Consumer Complaint. IA No. 1010/2020 stands disposed off in above terms.

    11. The contention of the OP Developer that some Complainants have booked more than one Unit in the Project; while some Complainants are residing far and the Unit has also been booked by a Company M/s. Agarwal Agencies Ltd., therefore, booked the subject Units for earning profits is completely unsustainable in the light of the judgement of this Commission in Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31, in which the principle laid down is that the onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots / flats in his normal course of business to earn profits, shifts to the Opposite Party, which in the instant case they had failed to discharge by filing any documentary evidence to establish their case. Therefore we are of the considered view that the Complainants are 'Consumer' as defined under Section 2 (1)(d) of the Act.

    12. As far as the plea that some of the Complainants defaulted in making timely payment as

    14

    per payment plan chosen by them, which ceased them to file the present complaint, is concerned, the OP Builder could have exercised options available under the Standard Terms and Conditions of the Application Form either to cancel the Agreement or charge delay interest. The OP Builder cannot take shelter under the lame excuse that the Complainant defaulted in making payment which ceased them to file the present Complaint.

    13. The contention of the OP Developer that they have closed the Allotment of some of the Complainants on their request of cancellation, does not hold water because it has not been made clear whether the deposited amount by the said Complainants has been refunded or not. If the amounts deposited by the said Complainants are not refunded, it is a clear case of deficiency in service on the part of the OP Developer because after accepting the request of cancellation the OP Developer cannot sleep over the matter for a long time. It is the duty and responsibility of the OP Developer to refund the amount to the said Complainants within a reasonable time. In the instant case, when the Project has not taken off, the OP Developer is duty bound to refund the amount to the said Complainants alongwith appropriate interest.

    14. The next contention of the OP Developer is that the present Complaint is not maintainable as during the pendency of the Complaint some of the Complainants had filed Complaint before UPRERA. The Doctrine of Election is applicable in the present case, as has been laid down by the Hon'ble Supreme Court in "M/s. Imperia Infrastructure Ltd. vs. Anil Patni and Anr." reported in 2020 10 SCC 783, in which it has been held that it is always open to a person either to approach the fora under the Consumer Protection Act, 1986/2019 or to approach any other Authority under Real Estate Regulatory Authority Act, 2016 or NCLT under the provisions of Insolvency and Bankruptcy Code, 2016 for redressal of his grievance. The person who has approached to any of the Authorities referred to above, at the first instance, is estopped from approaching other two Authorities as Doctrine of Election applies. Admittedly, in the present case, the Complainants have filed the present Complaint before this Commission in the year 2017, whereas some of the Complainants had approached to the RERA in the year 2020. Thus, strictly speaking the Doctrine of Election has to be applied and the present Complaint is maintainable before this Commission.

    15. So far as the contention that the Project delayed due to Farmers' Agitation and the Government Policy is concerned, it is the dispute between OP Developer and Government and for that the innocent Complainants, who have deposited their hard- earned money with the OP Developer to have a dream house, cannot be made victim. I do not find any force in this contention and the same is rejected.

    16. As far as the plea of the learned Counsel for the OP Developer that the Complainants are bound by the terms of the Standard Terms and Conditions and they are liable to compensate the Complainant for delay in terms of Clause 7.2 of the Standard Terms and Conditions, we have gone through various clauses of the Standard Terms and Conditions. For example, Clause 5.6 and 7.1 of the Standard Terms and Conditions reads as under:-

    "5.6 Notwithstanding anything stated herein and without prejudice Company's right to cancel the Provisional Allottment or to refuse execution of the Indenture of Conveyance by JSIL, as provided herein, and without, in any manner condoning nay delay in payment of Consideration and other dues, the

    15

    Allottee shall be liable to make payment of interest of the rate of 18% per annum on the outstanding amounts of Consideration and other dues from the dues date(s) upto their payment or cancellation of the Provisional Allotment. The payment made by the Allottee shall first be adjusted against and/or any penalty, if any due from the Allottee to the JSIL under the terms herein and the balance available, if any, shall be appropriated against the installment(s) due from the Allottee under the Standard Terms & Conditions and the Provisional Allotment Letter.

    7.1 Nothing contained herein shall be construed to give rise to any right to a claim by way of compensation/damages/loss of profit or consequential losses against the Company/JSIL on account of delay in handing over possession for any of the aforesaid conditions beyond the control of the Company/JSIL. If however the Company/JSIL fails to deliver possession of the Said Premises within the stipulated period as mentioned herein above, and within the further grace period of 90 (Ninety) days thereafter, the Applicant shall be entitled to a discount in Consideration for delay thereafter @ Rs.5/- per sq. ft. ( Rs.54/- per sq. mtr.) per month for the Super Area of the Said Premises (''Rebate''). The time consumed by the occurrences of Force Majeure Event shall be excluded while computing the time delay for the delivery of possession of the Said Premises

    17. A bare perusal of above Clauses makes it clear that as per Clause 7.2 of the Standard Terms and Conditions, in case of delay the Opposite Party Developer is liable to pay ₹5 per sq. ft., whereas in terms of Clause 5.6 in case of late payment, the Complainants/Buyers are liable to pay interest @18% p.a. This shows that the Standard Terms and Conditions are wholly one-sided and unfair. Therefore, the Complainants cannot be made bound to the Standard Terms and Conditions, which are one-sided and unfair in the light of the recent Judgment of the Hon'ble Apex Court in Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, II (2019) CPJ 34 (SC), wherein the Apex Court has observed as follows:

    18.

    17. "6.7. A terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder.

    7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer's Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms."

    18. It is not in dispute that the Complainants had booked their respective Units with the OP

    16

    Developer between the year 2010 to 2012 and the agreed period of handing over the Possession was 42 months, i.e., between 2014 to 2016. But the Project could not take off and there is no possibility of giving possession of the Units by the OP Developer in the near future. The Hon'ble Supreme Court in 'Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra, II (2019) CPJ 29 (SC), has observed as hereunder:

    "……….It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the Opposite Party, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund.

    In the circumstances, we are of the view that the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified."

    19. In the instant case also the Complainants cannot be made to wait indefinitely for possession of the Units. As a period of more than 12 years has lapsed from the date of allotment and the Project is still incomplete, we are of the considered view that the Complainants are entitled for refund of the respective deposited amount along with reasonable interest.

    20. During the course of proceedings, learned Counsel Mr. Sukumar Pattjoshi, learned Senior Counsel appearing on behalf of the OP Developer relied upon the various Orders passed by RERA and submitted that the Project has not taken off and the OP Developer is ready to refund the amount to the Complainants alongwith interest @8% p.a. preferably within one year.

    21. Keeping in view the catena of Judgments passed by the Hon'ble Supreme Court in which the Hon'ble Apex Court has awarded interest @9% p.a. on the deposited amount, the submissions made by the learned Senior Counsel appearing on behalf of the OP Developer is not acceptable.

    22. For the reasons stated hereinabove, the OP Developer is directed to refund the entire deposited amount to the respective Complainants alongwith interest @9% p.a. from the respective date of deposit till the date of payment within a period of 3 months from today, failing which the rate of interest shall increase from 9% p.a. to 10% p.a.

    23. However, it is made clear in the event if any Complainant(s) has taken Housing Loan from the Banks / Financial Institutions then the Complainant(s) shall first repay the entire outstanding amount to the Banks/Financial Institution and after repaying the due amount, balance amount shall be used for their self purpose.

    24. The Consumer Complaint is partly allowed in above terms. The pending application, if any, also stands disposed off.

    ......................J

    R.K. AGRAWAL

    PRESIDENT