Smart Summary

Factual and Procedural Background

The grievance in this application concerns the violation of environmental norms by several private industrial respondents engaged in manufacturing formaldehyde and its various resins in the State of Haryana. These industries operated without obtaining the requisite Environmental Clearance (EC) and failed to comply with safeguards under the Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989. The applicant referenced ongoing proceedings on the same subject before this Tribunal, specifically O.A. No. 840/2019 (Ayush Garg v. Union of India) and O.A. No. 287/2020 (Dastak N.G.O. v. Synochem Organics Pvt. Ltd.). Previously, on 09.02.2021, the Tribunal directed a joint Committee of the Central Pollution Control Board (CPCB) and the State Pollution Control Board (PCB) to investigate and report, with the State PCB tasked to take remedial action under its statutory powers. The joint Committee reported on 25.08.2021 that out of 29 units, 14 established before 2006 did not require EC, while 15 units required EC but had not obtained it, resulting in closure orders by the State PCB. Some units challenged these orders before the Supreme Court. The Tribunal had earlier addressed the EC requirement in orders dated 03.06.2021 (O.A No. 287/2020) and 21.12.2021 (O.A No. 298/2020), affirming the necessity of EC for such units and directing State PCBs to disallow operation without EC.

Legal Issues Presented

  1. Whether the manufacturing units producing formaldehyde and its resins require Environmental Clearance under the applicable environmental laws and regulations.
  2. Whether the State Pollution Control Board is empowered and obligated to prevent operation of such units without requisite Environmental Clearance.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Ayush Garg v. Union of India (O.A. No. 840/2019) Environmental norms regarding manufacturing units and requirement of EC. Referenced as ongoing related proceedings on the same subject matter.
Dastak N.G.O. v. Synochem Organics Pvt. Ltd. (O.A No. 287/2020) Requirement of Environmental Clearance for manufacturing units. Earlier Tribunal order held EC necessary and directed State PCB to disallow operation without EC.
Vineet Nagar v. Central Ground Water Authority (O.A No. 298/2020) Environmental Clearance compliance and enforcement by State PCBs. Confirmed that units must obtain EC to continue operations; State PCBs to ensure compliance.

Court's Reasoning and Analysis

The Tribunal analyzed the status of the manufacturing units with respect to their establishment dates and the requirement of Environmental Clearance. It noted that units established before 2006 are exempt from EC requirements, while others must obtain EC to operate legally. The joint Committee's report substantiated non-compliance by several units, leading to closure orders by the State PCB. The Tribunal relied on its prior decisions affirming the mandatory nature of EC for such industrial activities and the statutory authority of the State PCB to enforce these requirements. Consequently, the Court emphasized that units without EC should not be allowed to operate, directing the State PCB to ensure compliance and take necessary remedial action.

Holding and Implications

The application is DISPOSED OF with the direction that the State Pollution Control Board must ensure compliance with the Environmental Clearance requirements wherever applicable. Until the grant of EC, the concerned units shall not be permitted to operate. All interlocutory applications related to this matter are also disposed of. The decision directly affects the operational status of the units in question but does not establish any new legal precedent beyond reaffirming existing environmental regulatory requirements.

To access the original judgment, please Sign In or Subscribe.

    National Integrated Forum For Artists & Activists v. Central Ground Water Authority

    1. Grievance in this application is against violation of environmental norms in running activities for manufacturing formaldehyde and its different resins (including melamine formaldehyde, urea formaldehyde and phenol formaldehyde) without requisite Environmental Clearance (EC) by private respondents-industries, namely, Synorhem Organics Pvt. Ltd., Apolite Polymers Pvt. Ltd., Jai Bharat Polymers & Chemicals, Pahwa Plastics Pvt. Ltd., Pahwa Plastics Pvt. Ltd., Goyal Overseas, Om Chem, Decent Drugs Pvt. Ltd., Banke Bihari Overseas Pvt. Ltd., G.B. Overseas Pvt. Ltd., JRS Industries, NMR Phyrochem Pvt. Ltd., Chemwood Industries, Guruji Overseas, Apcolite Polymers Pvt. Ltd., Globe Panel Industries Pvt. Ltd. in State of Haryana. Further, the said industrial activity is without requisite safeguards prescribed under the Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989. The applicant has referred to pending proceedings before this Tribunal on the same subject in O.A. No. 840/2019, Ayush Garg v. Union of India and O.A. No. 287/2020, Dastak N.G.O. v. Synochem Organics Pvt. Ltd.

    2. The matter was earlier considered on 09.02.2021. The Tribunal directed a joint Committee of the CPCB and the State PCB to look into the matter and give its joint report. The State PCB was directed to take remedial action in exercise of its statutory powers.

    3. In pursuance of above, the joint Committee has filed its report dated 25.08.2021 to the effect that out of 29 units in Haryana, 14 were established by 2006 and they do not require EC and remaining required EC. Since the said 15 units have not obtained EC, closure order has been passed by the State PCB. Some of the units have approached the Hon'ble Supreme Court.

    4. We also note that the Tribunal has dealt with the issue earlier vide order dated 03.06.2021 in O.A No. 287/2020, Dastak N.G.O. v. Synochem Organics Pvt. Ltd. and vide order dated 21.12.2021 in O.A No. 298/2020, Vineet Nagar v. Central Ground Water Authority, and held that EC is required for such units and unless EC is obtained, the State PCBs may not allow the said units to continue.

    5. In view of above, the Application is disposed of with the direction that the State PCB may ensure compliance of requirement of EC (wherever applicable) and till grant of EC, the units may not be allowed to operate.

    6. All I.As will also stand disposed of.