R.L. Mittal, President This is the complaint filed by Manoj Kumar (hereinafter referred to as Contd........2 : 2 : the complainant) against the Punjab Urban Planning & Development Authority (hereinafter referred to as OP).
2. Briefly stated, case of the complainant is that OP launched a scheme on 27.9.2012 in which the OP allotted freehold residential plots at PUDA Enclave, Budhlada. For this purpose, applications were demanded with 10% earnest money of the total amount. Complainant purchased the plot from Charan Singh, who had applied for a plot of 300 square yards vide application No.1300 and Rs.1,80,000/- were paid as earnest money to the OP. As per scheme, draw of plots was conducted on 15.1.2013 at Budhlada. Charan Singh was successful in the draw of residential plot and thereafter OP issued letter of intent dated 26.2.2013. Charan Singh paid next 15% of the total amount of Rs.2,70,000/- as per the terms and conditions of the scheme. Thereafter, Charan Singh transferred the plot in the name of the complainant after taking full consideration and OP accepted this and complainant became the owner of the said plot.
3. It is further mentioned that till date site was not fully developed as per the scheme, which amounts to deficiency in service and unfair trade practice on its part. Allotment letter for allotment of Plot No.1005/PF measuring 300 sq yards was issued on 19.9.2016 i.e. after 4 years. OP issued another letter dated 8.2.2018 vide which plot was changed to No.884/PF without the consent of complainant which is wrong and illegal and against the terms and conditions of the brochure and letter of intent. OP failed to complete the development work, basic amenities etc and to hand over the possession of the plot within a reasonable time, therefore, the complainant wrote a letter to the OP and requested for refund of the entire deposited amount with interest. In reply to this letter, OP sent cheque dated Contd.........3. : 3 : 21.5.2020 for refund of Rs.4,50,000/- as principal amount but no interest was given by the OP. Complainant sent an email to OP intimating that he has kept the amount under protest and demanded interest from OP as it had retained the amount for more than 7 years. Hence this complaint. Complainant has prayed for direction to the OP to pay interest on Rs.4,50,000/- @ 18% p.a., besides Rs.50,000/- as compensation and Rs.20,000/- as costs.
4. Upon notice, OP appeared through counsel and contested the complaint by filing written reply. OP raised legal objection on the ground of intricate questions, estoppel, beyond limitation, false, vexatious complaint, Arbitration Clause etc. It is further submitted that on receipt of an application from the complainant for refund after surrendering the plot, OP had sent cheque dated 21.5.2020 amounting Rs.4,50,000/- to the complainant, which has been received by the complainant without any objection/protest and got the amount of the cheque. Possession of the plot has been delivered to the complainant well in time and plot number was also allotted to the complainant in time. Complainant cannot get double benefit. The tentative price of the plot was Rs.18,90,000/-. Complainant had paid Rs.4,50,000/- which was less than even towards 25% of the price of the plot. Complainant did not deposit installment of the plot as scheduled in allotment letter. Complainant has no right to file the present complaint. Refund of Rs.4,50,000/- was made as per the terms and conditions and procedure of PUDA.
5. On merits, OP has reiterated its version as taken in the legal objections and as detailed above. It is further submitted that possession of plot has been delivered to the complainant as per letter dated 8.2.2018 Contd........4 : 4 : Allotment letter has been issued as per the terms and conditions of the scheme. There is no deficiency on the part of the OP. Denying all the other allegations of the complainant OP prayed for dismissal of the complaint.
6. Complainant has also filed rejoinder. On being called upon by this forum, to do so, learned counsel for the complainant has tendered Self Declaration of the complainant alongwith documents Ex.C-1 to C-7 and closed the evidence. On the other hand, ld. Counsel for the OP tendered into evidence self declaration of Amarinder Singh Tiwana, Estate Officer and photographs Ex.OP-1 and Ex.OP-2 and closed evidence. Written arguments submitted by the parties have also been taken on record.
7. Parties have reiterated the same things as stated in their respective pleadings. We have heard the learned counsels of the parties and gone through the oral and documentary evidence, with their kind assistance.
8. Admittedly, OP has made a refund of Rs.4,50,000/- vide cheque dated 21.5.2020, copy of which is placed on file as Ex.C-5. It is also not disputed that immediately after receipt of cheque, complainant lodged his objection regarding the receipt of only principal amount vide his request/ email dated 6.8.2020 Ex.C-6. Admittedly, OP has received the amount of Rs.4,50,000/- in the year 2012-2013 and has been enjoying and gaining profit on the hard earned money of complainant till its refund on 21.5.2020. Letter of intent is dated 26.2.2013, first allotment letter is dated 19.9.2016 and re-allotment letter is dated 8.2.2018. The question is whether the complainant can be forced to wait for indefinite period for allotment of the plot number. Principles of natural justice provide that OP should have acted in a reasonable time.
9. Perusal of the file reveals that the complainant applied for Contd..........5. : 5 : refund of the amount deposited by him with the OP vide E-mail dated 6.8.2020 Ex.C-6. On receipt of this E-mail, OP made a refund of Rs.4,50,000/- through cheque dated 21.5.2020 (copy Ex.C-5). On receipt of cheque, complainant lodged his protest and requested for interest on the entire deposit. Perusal of the file further reveals that OP had failed to handover the possession of the plot within specified period and kept the money of the complainant for more than 7 years. Scheme for the draw/allottment of free hold residential plots was launched on dated 27.9.2012. The draw of plots was conducted on 15.1.2013 at Budhlada. As per the terms and conditions of the scheme, the allottment letter was to be issued to the successful applicants within one year from the date of draw. But the Allottment Letter was issued by the OP on dated 19.09.2016 i.e after a delay of three and a half years. Further, as per the terms and conditions of the scheme possession of the plots after completing all the necessary development works at the site ( i.e basic facilities such as water, electrcity, roads, swerage system, boundaries etc. which are like sine qua non for bare survival, safety and security) should have been handed over to the complainant/allottee within a maximum period of 18 months from the date of issuance of allottment letter. That means plot in a developed site should have been handed over by 19.3.2018. ( i.e 18 montsh from allotment letter). OP has claimed that the possession of the plot was given to the complainant on dated 8.2.2018 but the complainant has stated that OP till date has not provided Drinking water facility/connection at the concerned site and boundary wall of one side has not been constructed till date due to the dispute of the OP with the adjoining land owners/Farmers. Complainant has placed on record Ex. C-3 and C-4 in support of these assertions. Ex. C-3 Contd..........6. : 6 : is a letter of dated 11.4.2019 in which the Divisional Engineer of the OP is requesting the Executive Engineer, Patiala to give permission to lay the water lines at the concerned site from Biroke Branch Miner No.4. So that the facility of water might be arranged for the allottees as soon as possible. Ex. C-4 is a reply of dated 22.2.2019 an RTI application in which OP itself has admitted that boundary wall towards Budhlada was pending due to a dispute with farmers. Ex. C-3, C-4 satisfactorily show that the concerned site was not developed by the OP before the due date of delivery of permission of the plots to the allottes. If the allotment had been done within the prescribed time ( within 1 year from draw ) and possession after necessary development works had also been delivered within the agreed time limit ( i.e within 18 months from the allotment) then by 19.3.2018 the concerned plot would have become the property of the complainant but in the present case, even after 7 to 8 years the OP has not developed the site so as to give possession of a plot in a living able area. Thus there is deficiency in service on the part of the OP. It is a clear cut case of refund of amount for non-delivery of the possession of plot in reasonable time alongwith interest. In taking this view we are supported from case law PUDA v. Amrik Singh RP No.500 of 2017 decided on 28.05.2017 whereby Honble National Commission, in Para No.8 held as follows: No doubt, clause 12 of Letter of Intent do provide that the possession of the plot shall be handed over to the allottee after the completion of the development work at the site or within 18 months from the date of issue of allotment letter, whichever is earlier. It is also true that neither the development work has been completed as yet nor any allotment letter has Contd..........7. : 7 : been issued in favour of the complainant who deposited the demanded 15% of the consideration amount in furtherance of Letter of Intent. The question is does this mean that by providing the stipulation in clause 12,
21 & 22 of Letter of Intent, the opposite party can delay the delivery of possession of subject plot to the complainant for indefinite period ? ...................................
10. Honble Supreme Court has held in many cases that if there is a delay in possession, the allottee or consumer is entitled for refund with a reasonable interest. Public authorities cannot frisk with the hard- earned money of consumers. In Bangalore Development Authority v. Syndicate Bank ., II 2007 CPJ 17 (SC), Honble Supreme Court held that: when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to refund with reasonable interest from the date of payment till the date of refund.
11. Similar facts and same questions of law were dealt by the Hon'ble National Commission in RP No.2804 of 2018 in PUDA vs Darshan Kumar decided on 24.1.2020. Hence complainant is held entitled for interest on the principal amount of Rs.4,50,000/- alongwith compensation.
12. Resultantly, complaint is partly accepted with consolidated costs and compensation of Rs.3,000/-. OP is directed to pay interest on principal amount of Rs.4,50,000/- @ 9 % p.a. from the date of receipt of amounts from the complainant at different intervals, till the date of actual realization. Compliance of the order be made by OP within 45 days from the date of receipt of the copy of the order. Contd..........8. : 8 :
13. The complaint could not be decided within the statutory time period due to heavy pendency of cases.
14. Copy of the order be sent to the parties concerned free of cost and file be consigned to the record. PRONOUNCED: 19th Day of October, 2021. Su raj Goyal R.L.Mittal, Member. Pre sident. *krishan*