National Consumer Disputes Redressal Commission — Order (31 Aug 2021)

Factual and Procedural Background

This batch of Consumer Complaints was filed under Section 21(a)(i) of the Consumer Protection Act, 1986 by multiple allottees (Complainants) against M/s Ireo Grace Realtech Pvt. Ltd. (the Developer) concerning flats in the project called "The Corridors" (Golf Course Extension Road, Sector-67-A, Gurgaon). The lead case is Consumer Complaint No. 2236 of 2016 (Sanjay Gopinath). Complainants allege the Developer failed to hand over possession within the stipulated period and seek refund of amounts paid, interest, and compensation.

Common factual elements (as reflected from the lead case) include: booking of flats after paying substantial sums (in the lead case, booking amount ₹14 lakh and total paid ₹1,55,17,716/-), execution of an Apartment Buyer's Agreement (dated 03.04.2014) which contains Clause 13.3 providing for offer of possession within 42 months from approval of building plans plus a 180-day grace period, and disputes over the applicable date from which the commitment period runs (building plan approval dated 23.07.2013; Fire Safety approval granted on 27.11.2014 per the Developer).

The Developer filed written statements raising preliminary objections (that some complainants were not "consumers" because of multiple bookings for profit, the existence of an arbitration clause, and that delays were due to statutory approvals). The Commission treated the matters together because the facts and legal questions were largely similar, and categorized complaints into groups by an order dated 02.04.2019 (multiple defaults with no cancellations; cancelled allotments; more than one booking by the same allottee). The present batch relates to the category of more than one booking by same allottees.

Legal Issues Presented

  1. Whether the complainants who made more than one booking (multiple allotments) qualify as "consumers" under Section 2(1)(d) of the Consumer Protection Act, 1986.
  2. Whether an arbitration clause in the Apartment Buyer's Agreement bars the Consumer Fora from entertaining consumer complaints.
  3. What is the relevant date from which the Developer's commitment period for offering possession is to be computed for the Project "The Corridors"?
  4. For different categories of allottees (those in towers where Occupation Certificate (O.C.) has been issued and possession offered vs. those without O.C.), what remedies are available — possession with delay compensation or refund with interest?
  5. Whether one-sided contractual clauses in the Apartment Buyer's Agreement are enforceable and whether they constitute unfair trade practice.

Arguments of the Parties

Complainants' Arguments

  • The Developer failed to deliver possession within the time stipulated by the Agreement; possession date computed from building plan approval (and/or related dates) had passed without delivery.
  • The Complainant is a "consumer" despite having another booking (the second booking was, they claim, for own use or for elderly family members), and the Developer has not produced documentary evidence to show the Complainant was dealing in real estate as a business to earn profit.
  • The Apartment Buyer's Agreement contains one-sided terms; the Complainant lost faith in the Developer and seeks refund of deposits with interest and compensation for harassment and litigation costs.
  • Counsel relied on prior Commission decisions (including Kavita Ahuja vs. Shipra Estates Ltd (2016) CPJ 31 and other coordinate-bench Commission orders) to support the position that the onus to show a purchaser was acting to earn profit lies on the Developer, and to support remedies sought.

Opposite Party (Developer)'s Arguments

  • The Complainant is not a "consumer" as he booked more than one apartment for commercial gain and profit.
  • The Agreement contains an arbitration clause and disputes ought to be referred to arbitration; thus the complaint is not maintainable before the Commission.
  • The relevant computation of commitment period must take into account the date on which the last pre-condition (Fire Safety Scheme Approval) was granted (27.11.2014), so the 42 months plus 6 months grace expires on 27.11.2018; accordingly the complaint filed in 2016 is premature.
  • Delay, if any, was due to obtaining statutory approvals from the State Government and there was no deficiency in service or unfair trade practice on the Developer's part; the reliefs claimed (20% interest and ₹5,00,000 compensation) are not tenable.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kavita Ahuja vs. Shipra Estates Ltd. (2016) CPJ 31 Onus shifts to the opposite party to establish that the complainant was dealing in real estate (i.e., buying and selling flats in ordinary course of business for profit) if multiple bookings exist. The Commission applied this principle to reject the Developer's contention that the Complainant was not a 'consumer' and held the Complainant is a 'consumer' under Section 2(1)(d).
M/s Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC) Arbitration clause in Agreement does not bar jurisdiction of consumer fora to entertain consumer complaints. The Commission relied on this Supreme Court principle to hold that the arbitration clause does not preclude entertaining the complaints before the Consumer Forum.
Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors. (Civil Appeal No. 5785/2019 & connected appeals) — Judgment dated 11.01.2021 (Hon'ble Supreme Court) Held that 27.11.2018 (date of Fire Safety approval + 42 months + 6 months grace) is the relevant date for offer of possession; held one-sided contractual clauses constitute unfair trade practice and cannot bind apartment buyers; set out remedies for two categories of allottees (Chart A and Chart B) including entitlement to refund and interest for Chart B allottees and obligation to take possession for Chart A with delay compensation. The Commission expressly followed and applied the Supreme Court's reasoning: 27.11.2018 as the relevant date; held one-sided clauses unenforceable; divided allottees into Chart A (OC obtained and possession offered) and Chart B (no OC) and applied corresponding remedies (possession with 9% interest for Chart A delay period, refund with 9% interest for Chart B, etc.).
Subodh Pawar v. IREO Grace (unnumbered citation in text) Recorded statement by Developer's counsel that the amount would be refunded with interest @ 10% p.a.; used as precedent of earlier orders granting refund with 10% interest (orders passed before COVID-19). The Commission noted these earlier orders but, having regard to pandemic-related market conditions, fixed interest at a different rate (9% simple interest) for refunds/delay compensation in the present context.
IREO v. Surendra Arora (unnumbered citation in text) Another earlier order recording refund with interest @ 10% p.a. prior to the pandemic. The Commission referenced this to explain existing practice in certain earlier matters but chose to fix 9% in the present circumstances due to the pandemic's effect on the construction industry.
Several coordinate-bench Commission orders (examples cited in the opinion): CC No. 3873/2017 Abhishek Khanna & Ors.; CC No. 1382/2018 Promila Kashyap; CC No. 525/2017 Ritu Hasija & Anr.; CC No. 696/2017 Amit Arora Earlier Commission decisions addressing issues arising from the same project ('The Corridor') and the Developer's contentions. The Commission observed that the Opposite Party had raised the same contentions in those matters and those contentions had been addressed in those orders; the present decision takes those earlier considerations into account and follows the Supreme Court's disposition of related appeals.

Court's Reasoning and Analysis

The Commission's reasoning proceeded in steps that track the arguments and precedents referred to in the opinion:

  1. Consumer status: Relying on the Commission's earlier decision in Kavita Ahuja, the Commission held that where multiple bookings exist the onus to establish that the allottee dealt in real estate for profit rests on the Developer. The Developer failed to discharge this onus; therefore the Complainant(s) qualify as "consumers" under Section 2(1)(d).
  2. Arbitration clause: Following the Supreme Court in M/s Emaar MGF Land Ltd. v. Aftab Singh (2019), the Commission held that the presence of an arbitration clause in the Apartment Buyer's Agreement does not oust the jurisdiction of consumer forums; accordingly, that objection was rejected.
  3. Reliance on Supreme Court judgment in Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors. (11.01.2021): The Commission treated the Supreme Court's determinations as binding guidance. The Supreme Court had (a) fixed 27.11.2018 as the relevant date for computation of the commitment period (Fire Safety approval being granted on 27.11.2014), (b) held that one-sided clauses are unfair and cannot bind buyers, and (c) classified allottees into two categories (Chart A: towers with Occupation Certificates and offer of possession made; Chart B: towers without O.C.).
  4. Remedies and balancing of interests: The Commission considered competing submissions about compensation/interest and market realities, including reference to earlier orders where 10% interest was directed but recognizing changed conditions due to the COVID-19 pandemic. Balancing the interests of allottees and the Developer, the Commission fixed interest at 9% simple interest per annum for refunds/delay compensation from 27.11.2018 until payment.
  5. Application to present matters: The Commission applied the Supreme Court's classification to the present batch, listing the complainants/allottees falling in Chart A (OC obtained and offer of possession made) and Chart B (no O.C.). For Chart A allottees, possession was to be accepted after payment of outstanding dues and the Developer to pay 9% simple interest on deposited amounts for the delay from 27.11.2018 until the date of offer of possession. For Chart B allottees, the Developer was directed to refund the entire amount deposited with 9% simple interest per annum within three months, failing which default interest at 12% simple interest p.a. would be payable. The Developer was directed not to deduct the 20% earnest money (or other deductions under Clause 21.3) on account of the Developer's defaults, including delay in obtaining the Fire NOC.

Holding and Implications

Core Ruling: The Commission disposed of the Consumer Complaints in accordance with the Supreme Court's judgment and the reasoning set out in the order. In summary:

  • Chart A allottees (OC obtained and possession offered): Directed to take possession after payment of outstanding dues. Developer to pay delay compensation in the form of simple interest @ 9% p.a. on amounts deposited for the delay from 27.11.2018 until the date of offer of possession.
  • Chart B allottees (no O.C. available): Developer directed to refund the entire amount deposited along with interest @ 9% simple interest per annum from 27.11.2018. Refund to be made within three months of the order; failing which default interest @ 12% simple interest p.a. will accrue until payment. Developer shall not deduct the 20% earnest money or other amounts under Clause 21.3 for defaults committed by the Developer (including delay in obtaining Fire NOC).
  • The Consumer Complaints were disposed of in the above terms, with no order as to costs.

Implications:

  • Direct effect on parties: Complainants listed in Chart A must accept possession after paying outstanding dues and will receive delay compensation at 9% p.a. for the relevant period; Complainants in Chart B are entitled to refunds with interest (9% p.a.) and penalty interest (12% p.a.) for default. The Developer is restrained from deducting earnest money or other contractual deductions specified in Clause 21.3 for these defaults.
  • Precedential impact: The Commission explicitly followed and applied the Supreme Court judgment dated 11.01.2021 in Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors. The order applies that ratio to the present batch but does not purport to set a new higher court precedent beyond applying the Supreme Court ruling. The Commission adjusted the rate of interest (9% rather than 10% or 20%) having regard to market conditions and the COVID-19 pandemic as recorded in the opinion.
  • No order as to costs was made.

Source: Extracted and summarized exclusively from the provided NCDRC order dated 31 Aug 2021 (R.K. Agrawal, J., President; Dr. S.M. Kantikar, Member). All items in this summary reflect only the content and citations contained in that opinion.

    DINESH CHAND SHARMA v. M/S. IREO GRACE REALTECH PVT. LTD.

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    CONSUMER CASE NO. 2236 OF 2016

    1. SANJAY GOPINATH

    1/6, Lantana Street, Vatika City, Sector-49. Sohna Raod, Gurgaon, Haryana-122002 ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. 304, Kanchan House, Karampura Commercial Complex, New Delhi-1100015 ...........Opp.Party(s)

    CONSUMER CASE NO. 1692 OF 2017

    1. DINESH CHAND SHARMA

    S/O. MR. R.P. SHARMA, R/O. A-903, THE PALM SPRING

    GOLF COURSE ROAD, SECTOR 54,

    GURGAON-122002

    HARYANA ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD.

    304, KANCHAN HOUSE KARAMPURA COMMERCIAL

    COMPLEX,

    NEW DELHI-110015 ...........Opp.Party(s)

    CONSUMER CASE NO. 1813 OF 2018

    1. PUNIT JAIN ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & ANR. ...........Opp.Party(s)

    CONSUMER CASE NO. 1814 OF 2018

    1. BHARAT JAIN & ANR. ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & ANR. ...........Opp.Party(s)

    CONSUMER CASE NO. 2281 OF 2017

    1. BHUVAN MEHTA

    B-29, SHIVALIK, NEW DELHI-110017 ...........Complainant(s) Versus

    1. IREO GRACE REALTECH PRIVATE LIMITED

    REGD. OFFICE: 304, KANCHAN HOUSE, KARAMPURA

    COMMERCIAL COMPLEX,

    NEW DELHI-110015 ...........Opp.Party(s)

    CONSUMER CASE NO. 2354 OF 2018

    1

    1. SUDHIR GULATI & ANR. R/o H No-B-1/143,(B-1 Block) Janak Puri, New Delhi - 110058 ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PRIVATE LIMITED & 4

    ORS.

    R/o C-4, Malviya Nagar, (1st Floor), New Delhi - 110017

    2. M/S PRECISION REALTORS(P) LTD. R/O 305, KANCHAN HOUSE, KARAMPURA

    COMMERCIAL COMPLEX,

    NEW DELHI - 110015

    3. M/S BLUE PLANET INFRA DEVELOPERS (P) LTD. R/O 40/16, EAST PATEL NAGAR,

    NEW DELHI - 110008

    4. M/S MADEIRA CONBUILD (P) LTD. R/O 304, KANCHAN HOUSE, 3RD FLOOR, KARAMPURA

    COMMERCIAL COMPLEX,

    NEW DELHI - 110015

    5. M/S GLOBLE ESTATE R/O G-23, ASHOK VIHAR, PHASE-I NEW DELHI - 110052 ...........Opp.Party(s)

    CONSUMER CASE NO. 3195 OF 2017

    1. GIRISH WADHWA & ANR. ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & ANR.

    THROUGH ITS AUTHRISED REPRESENTATIVES, REGD.

    OFFICE AT: 304, KANCHAN HOUSE, KARAMPURA

    COMMERCIAL COMPLEX,

    NEW DELHI-15.

    2. M/S. PRECISION REALTORS PVT. LTD.

    THROUGH ITS AUTHRISED REPRESENTATIVES, REGD.

    OFFICE AT: 305,3RD FLOOR, KANCHAN HOUSE,

    KARAMPURA COMMERCIAL COMPLEX,

    NEW DELHI-15. ...........Opp.Party(s)

    CONSUMER CASE NO. 3205 OF 2017

    1. SHALABH NIGAM ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & 4 ORS.

    REGD. OFFICE AT : 304, KANCHAN HOUSE,

    KARAMPURA COMMERCIAL COMPLEX,

    NEW DELHI-110015

    2. M/S. PRECISION REALTORS (P) LTD.

    HAVING ITS REGD. OFFICE AT: 305, KANCHAN HOUSE,

    KARAMPURA COMMERCIAL COMPLEX, ...........Opp.Party(s)

    2

    NEW DELHI-110015.

    3. M/S. BLUE PLANET INFRA DEVELOPERS (P) LTD. HAVING ITS REGD. OFFICE AT : 40/16, EAST PATEL

    NAGAR,

    NEW DELHI.

    4. M/S. MADEIRA CONBUILD (P) LTD.

    HAVING ITS REGD. OFFICE AT : 304, KANCHAN

    HOUSEM 3RD FLOOR, KARAMPURA COMMERCIAL

    COMPLEX,

    NEW DELHI-110015

    5. M/S. MADEIRA CONBUILD (P) LTD.

    HAVING ITS REGD. OFFICE AT : 304, KANCHAN

    HOUSEM 3RD FLOOR, KARAMPURA COMMERCIAL

    COMPLEX,

    NEW DELHI-110015

    6. M/S. GLOBAL ESTATE HAVING ITS REGD. OFFICE AT: G-23, ASHOK VIHAR, PHASE-1,

    DELHI-110052

    CONSUMER CASE NO. 3401 OF 2017

    1. ANJU MUKHIJA

    W/O SH RAJEEV OBEROI HOUSE NO. 10, ASHOKA CRESCENT, DLF PHASE-I,

    GURUGAM-122002 ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & ANR.

    5TH FLOOR, ORCHID CENTER, GOLF COURSE ROAD,

    SECTOR-53,

    GURUGRAM-122002

    2. M/S PRECISION REALTORS PVT. LTD

    305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA

    COMMERCIAL COMPLEX,

    NEW DELHI-110015 ...........Opp.Party(s)

    CONSUMER CASE NO. 3402 OF 2017

    1. ANJU MUKHIJA

    W/O SH RAJEEV OBEROI HOUSE NO. 10, ASHOKA CRESCENT, DLF PHASE-I,

    GURUGAM-122002 ...........Complainant(s) Versus

    1. M/S. IREO GRACE REALTECH PVT. LTD. & ANR.

    5TH FLOOR, ORCHID CENTER, GOLF COURSE ROAD,

    SECTOR-53,

    GURUGRAM-122002

    2. M/S PRECISION REALTORS PVT. LTD 305, 3RD FLOOR, KANCHAN HOUSE, KARAMPURA ...........Opp.Party(s)

    3

    COMMERCIAL COMPLEX,

    NEW DELHI-110015

    BEFORE:

    HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT HON'BLE DR. S.M. KANTIKAR,MEMBER

    For the Complainant : For the Complainant : Ms. Rahella Khan, Advocate Ms. Vandana Sharma, Advocate

    Mr. Sonal Anand, Advocate

    Mr. Aayush Sai, Advocate

    Mr. Deepak Kr. Khushalani, Advocate

    Mr. Sushil Kaushik, Advocate

    Ms. Himanshi Singh, Advocate

    For the Opp.Party : For the Opposite Party : Mr. Sameer Chaudhary, Advocate Ms. Meher Bhatia, Advocate

    Mr. Palash Agarwal, Advocate

    Ms. Renu Gupta, Advocate

    Ms. Akshaya Ganpath, Advocate

    Dated : 31 Aug 2021

    ORDER

    R.K. AGRAWAL, J., PRESIDENT

    1. The present batch of Consumer Complaints has been filed under Section 21(a)(i) of the Consumer Protection Act, 1986 (for short "the Act") by the Complainants, against the Opposite Party, M/s. Ireo Grace Realtech Private Ltd. (hereinafter referred to as the 'Developer') for refunding of money as the Opposite Party Developer failed to hand-over the possession of the Flats booked by them in the Project launched by the Developer in the name and style of "The Corridor ", within stipulated period.

    2. Since the facts and question of law involved in these Complaints are similar except for minor variations in the dates and events and flat numbers, these Complaints are being disposed of by this common Order. However, for the sake of convenience, Consumer Complaint No. 2236 of 2016 is treated as the lead case and the facts enumerated hereinafter are taken from Consumer Complaint No. 2236 of 2016.

    3. According to the Complainant, the facts of the case are that in response to the Applications invited by the Opposite Party Developer for allotment of flats in their upcoming Project, "The Corridors" (hereinafter referred to as the 'Project') located at Golf Course Extension Road, Sector-67-A, Tehsil & District Gurgaon, Haryana, the Complainant booked a residential flat in the Project by paying a sum of ₹14 lakh

    4

    towards booking amount.The Complainant was allotted Unit No. CD-C6-09- 901 having super area of 1483.28 sq. ft. on 16.03.2013.Apartment Buyer's Agreement (hereinafter referred as the Agreement) was sent by the Opposite Party Developer for getting the signatures of the Complainant.It is the say of the Complainant that the Apartment was originally booked @ ₹8750/- per sq. ft. but in the Agreement, the rate of booking was mentioned as ₹9200/- per sq. ft.The Agreement was one-sided and upon resistance, the Complainant was threatened by the Developer that the Unit shall be cancelled and whole money paid shall also be forfeited and the Complainant was forced to sign upon the dotted lines on the Agreement.Agreement was executed between the Parties on 03.04.2014.As per Clause 13.3. of the Agreement, the possession of the Unit was to be handed over within a period of 42 months from the date of approval of the building plans.Clause

    13.3 of the Agreement reads as under:

    "Subject to Force Majeure, as defined herein and further subject to the allottee having complied with all its obligations under the terms and conditions of this Agreement and not having defaulted under any provision(s) of this Agreement including but not limited to the timely payment of all dues and charges including the total Sale Consideration, registration charges, stamp duty and other charges and also subject to the Allottee having complied with all formalities or documentation as prescribed by the Company, the Company proposes to offer the possession of the said Apartment to the Allottee within a period of 42 (Forty Two) months from the date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder ("Commitment period"). The Allottee further agrees and understands that the Company shall additionally be entitled to a period of 180 days ("Grace period"), after the expiry of the said Commitment Period to allow for unforeseen delays beyond the reasonable control of the Company."

    1. The Complainant made payment of ₹1,55,17,716/- (Rupees One Crore Fifty Five Lacs Seventeen Thousand Seven Hundred Sixteen only) on different dates upto the date of filing of the Complaint as per demand of the Opposite Party Developer, despite that the Opposite Party Developer could not complete the construction work at the Project within stipulated period and failed to deliver the possession of the Unit.The Complainant had lost trust in the Opposite Party Developer.Alleging deficiency in service and Unfair Trade Practice on the part of the Opposite Party Developer, the Complainant has filed the present Complaint with following prayer:-

    "A. Direct the Opposite Party to pay the Complainant a sum of ₹1,55,17,716/- (₹ One

    5

    Crore Fifty Five Lacs Seventeen Thousand Seven Hundred Sixteen only), which had been paid by the Complainant to the Opposite Party against the Unit No. CD-C-6-09-901 in Group Housing Colony Located at Golf Course Extension Road, Sector-67-A in the revenue estate of Village Dhumsapur and Maidwas, Tehsil & District Gurgaon, Haryana known by the Project Name as

    " THE CORRIDORS along-with interest @ 20% per annum compounding quarterly till realization;

    B. Award the cost and litigation expenses & Compensation for harassment & mental agony to the tune of ₹50,0000/- (₹ Five lacs only) to the Complainant ; C. Pass such other further order as this Hon'ble Commission may deem fit and proper in the interest of justice."

    2. Upon notice, the Complaint was resisted by the Opposite Party Developer by filing Written Statement.In the Written Statement the Opposite Party Developer took preliminary objection that the Complainant is not a 'Consumer' as defined under Section 2(1)(d) of the Consumer Protection Act, 1986 as the Complainant has invested in the Apartment for commercial gain and to earn profits.The Complainant, alongwith his wife, has also made another booking in a different Project, i.e., Skyon of the Opposite Party Developer.It was also stated that there is Arbitration Clause in the Agreement and, therefore, the Complaint is not maintainable before this Commission.The Complainant is bound by the terms of the Apartment Buyers' Agreement and as per Agreement, the Basic Sale Price is ₹9200/- per sq. ft. It was also stated that the 90 Meter HUDA Road is part of the Gurgaon-Manesar Master Plan 2031 and the Haryana Government Sectoral Plan dated 9.11.2012 and it would be developed by the State Government and not by the Opposite Party Developer. As per Clause 13.3 of the Agreement, the Developer was proposed to handover the possession of the Apartment within 42 months (Commitment Period) from the date of approval of building plans and / or fulfilment of the preconditions imposed thereunder within a grace period of 180 days. Building approval was granted on 23.07.2013 and the last pre- condition, i.e., Fire Safety Scheme Approval was granted only on 27.11.2014, therefore, in terms of the Clause 13.3 of the Agreement, the proposed time for handing over the possession has to be computed from 27.11.2014 and 48 months from 27.11.2014 (including the 6 months grace period), would expire only on 27.11.2018. The present Complaint is pre-mature as it has been filed in the year 2016, before committed date of possession, i.e.,

    6

    27.11.2018. It was also stated that the Complainant has sought refund of amount alongwith interest @20% p.a. as also a sum of ₹5,00,000/- towards litigation expenses and compensation which is not tenable. It was stated that delay is due to obtaining statutory approvals from the State Government and there was no deficiency in service or Unfair Trade Practice on their part. It was prayed that the Complaint be dismissed.

    3. Ms. Rahella Khan, learned Counsel for the Complainants submitted that the Opposite Party Developer cannot surpass to obtain mandatory licenses and necessary approvals from the concerned authorities before start of construction.The building plans were approved on 23.07.2013 and the Developer was required to hand over the possession of the apartments within a period of 42 months from the date of approval which expired on 22.01.2017, if the Grace Period of 6 months under Clause 13.3 was added, the Developer was required to give possession by 22.07.2017.But seeing the pace of construction at site, there was no possibility to hand over the possession of the Apartment within stipulated period.She further submitted that the Opposite Party Developer has failed to produce any cogent evidence in support of their contention that the Complainant is not a 'Consumer' as the Complainant has booked Apartment for commercial gain and to earn profits.As far as the plea regarding booking of second Apartment in the project 'Skyon' developed by Opposite Party Developer is concerned, she submitted that the Apartment in 'Skyon' had been booked by the Complainant for his own use and the present one for Complainant's old aged retired father and other family members. In support of her contention she relied upon an order passed by this Commission in Kavita Ahuja vs. Shipra Estates Ltd. I i> <i>(2016) CPJ 31. She further submitted that the Complainant has lost faith in the Opposite Party Developer and prayed that their Complaint be allowed and the Opposite Party Developer be directed to refund their deposited amount alongwith interest. In support of her case, she placed reliance on the decisions rendered by a coordinate bench of this Commission in the cases "CC No.3873 / 2017 entitled "Abhishek Khanna & Ors. Vs. Ireo Grace Realtech Pvt. Ltd." CC No.1382 / 2018 entitled "Promila Kashyap vs. Ireo Grace Realtech Pvt. Ltd.", CC No. 525 / 2017 entitled "Ritu Hasija & Anr. Vs. Ireo Grace Realtech Pvt. Ltd." and CC No.696 / 2017 entitled "Amit Arora vs. Ireo Grace Realtech Pvt. Ltd."

    4. Mr. Sameer Chaudhary, learned Counsel appearing on behalf of the Opposite Party Developer submitted that this Commission has dealt with the issues relating to the same Project 'The Corridor' in Orders dated 28.03.2019 and 27.03.2019 in 'CC No. 3873 / 2017, "Abhishek Khanna & Ors. Vs. Ireo Grace Realtech Pvt. Ltd." and "CC No.696 / 2017 entitled "Amit Arora vs. Ireo Grace Realtech Pvt. Ltd." respectively.They have challenged the said Orders before the Hon'ble Supreme Court by filing Civil Appeal Diary No. 23235 / 2019 and 34491 / 2019 and the Hon'ble Supreme Court has stayed the operation of the Impugned Orders passed by this Commission.

    7

    5. We have heard Ms. Rahella Khan, learned Counsel for the Complainant, Mr. Sameer Chaudhary, learned Counsel for the Opposite Party Developer and gone through the Complaint, Written Statement and material available on record.

    6. Several Consumer Complaints were filed against Opposite Party Developer, i.e., M/s. Ireo Grace Realtech Pvt. Ltd. by the Allottees of 'The Corridor' Project.Vide Order dated 02.04.2019, the Consumer Complaints were divided into three categories, one category comprising of the Complaints where there are multiple defaults but no cancellations, second category where the allotments have been cancelled and third category where there are more than one bookings by the same Allottees.For ready reference, Order dated 02.04.2019 is reproduced below:-

    "It is pointed out by the learned counsel for the parties that the issues are not identical in all these complaints since in some of them the allotments have been cancelled, in some of them the allottees have made more than one booking, in some others, there are multiple defaults in payment of installments.

    The matters are therefore divided into three categories, one category comprising of the complaints, where there are multiple defaults but no cancellations, second category where the allotments have been cancelled and third category where there are more than one bookings by the same allottee. The matters where there are multiple defaults will be taken up first, followed by the matters in which the allotments have been cancelled. The case in which there is more than one booking by the same allottee will be taken after the matters relating to the first two categories have been heard."

    7. The present batch of Consumer Complaints relates to the category where more than one bookings have been made by the same Allottees. All other issues were identical in all the aforesaid Consumer Complaints except the issue of more than one booking by the same Allottee.

    8. The contention of the Learned Counsel for the Opposite Party Developer that the Complainant is not a 'Consumer' as the Complainant has booked more than one Apartments for earning profits is completely unsustainable in the light of the judgement of this Commission in Kavita Ahuja vs. Shipra Estates I (2016) CPJ 31, in which the principle laid down is that the onus of establishing that the Complainant was dealing in real estate i.e. in the purchase and sale of plots/flats in his normal course of business to earn profits, shifts to the Opposite Party, which in the instant case they had failed to discharge by filing any documentary evidence to establish their case. Therefore we are of the considered view that the Complainant is a 'Consumer' as defined under Section 2 (1)(d) of the Act.

    8

    9. Regarding the issue of 'Arbitration Clause', the Hon'ble Supreme Court in M/S Emaar MGF Land Limited vs. Aftab Singh - I (2019) CPJ 5 (SC),has laid down the law that an Arbitration clause in the Agreement does not bar the jurisdiction of the Consumer Fora to entertain the Complaint. Hence, the objection raised by the Learned Counsel for the Opposite Party that the clause of Arbitration bars this Commission from entertaining the Complaint is unsustainable.

    10. All other contentions raised by the Opposite Party Developer in respect of the Project 'The Corridor' have been dealt with by this Commission in the cases, i.e., CC No.3873 / 2017 entitled "Abhishek Khanna & Ors. Vs. Ireo Grace Realtech Pvt. Ltd." CC No.1382 / 2018 entitled "Promila Kashyap vs. Ireo Grace Realtech Pvt. Ltd.", CC No. 525 / 2017 entitled "Ritu Hasija & Anr. Vs. Ireo Grace Realtech Pvt. Ltd." and CC No.696 / 2017 entitled "Amit Arora vs. Ireo Grace Realtech Pvt. Ltd.".The Opposite Party Developer filed Civil Appeals against these Orders before the Hon'ble Supreme Court.The Hon'ble Supreme Court dealt with all the contentions raised by the Opposite Party Developer and disposed off the Appeals vide their Judgment dated 11.01.2021 in the case "Ireo Grace Realtech Pvt. Ltd. vs. Abhishek Khanna & Ors." [Civil Appeal No. 5785 / 2019 & other connected Appeals].The Hon'ble Supreme Court had held that 27.11.2018 would be the relevant date for offer of possession by observing as under:-

    "On 27.11.2014, the Director, Haryana Fire Service granted approval to the Fire Fighting Scheme subject to the conditions mentioned therein. The computation of the period for handing over possession would be computed from this date. The Commitment Period of 42 months plus the Grace Period of 6 months from 27.11.2014, would be 27.11.2018, as being the relevant date for offer of possession."

    11. Hon'ble Supreme Court also held that the Agreement is one-sided and the Opposite Party Developer cannot compel the Apartment Buyer to be bound by the one-sided contractual terms contained in the Apartment Buyer's Agreement by observing as under :-

    "We are of the view that the incorporation of such one-sided and unreasonable clauses in the Apartment Buyer's Agreement constitutes an unfair trade practice under Section 2(1)(r) of the Consumer Protection Act. Even under the 1986 Act, the powers of the consumer fora were in no manner constrained to declare a contractual term as unfair or one-sided as an incident of the power to discontinue unfair or restrictive trade practices. An "unfair contract" has been defined under the 2019 Act, and powers have been conferred on the State Consumer Fora and the National Commission to declare contractual terms which are unfair, as null and void. This is a statutory recognition of a power which was implicit under the 1986 Act.

    9

    In view of the above, we hold that the Developer cannot compel the apartment buyers to be bound by the one-sided contractual terms contained in the Apartment Buyer's Agreement"

    12. Hon'ble Supreme Court on the issue "Whether the Apartment Buyers are entitled to terminate the Agreement, or refund of the amount deposited with Delay Compensation"

    held as under:-

    "In the present case, the allottees before this Court in the present batch of appeals, can be categorised into two categories:-

    i) Apartment Buyers whose allotments fall in Phase 1 of the project comprised in Towers A6 to A10, B1 to B4, and C3 to C7, where the Developer has been granted occupation certificate, and offer of possession has been made, are enlisted in Chart A;

    ii) Apartment Buyers whose allotments fall in Phase 2 of the project, where the allotments are in Towers A1 to A5, B5 to B8, C8 to C11, where the Occupation Certificate has not been granted so far, are set out in Chart B below. ………..

    Chart A allottees (i) We are of the view that allottees at Serial Nos. 1 and 2 in Chart A are obligated to take possession of the apartments, since the construction was completed, and possession offered on 28.06.2019, after the issuance of Occupation Certificate on 31.05.2019. The Developer is however obligated to pay Delay Compensation for the period of delay which has occurred from 27.11.2018 till the date of offer of possession was made to the allottees.

    ……..

    Chart B allottees

    (i) Insofar as the allottees in Chart B are concerned, they have paid part consideration, in most cases up to the 4th instalment till 2017, when they found that there was no

    10

    progress being made in respect of the Towers in which the apartments had been allotted to them. It is an admitted position that Occupation Certificate for Towers A1, A2, A3, B7, C9 and C11, in which the allotments have been made for this category has not been issued by the Municipal Corporation

    The apartments have not been ready for allotment even as on 30.06.2020, as per the date fixed before the RERA Authority.

    (ii) The allottees submitted that they were facing great hardship since they had obtained loans from Banks for purchasing these apartments, and were paying high rates of interest. In 2017, when they realised that there was no construction activity in progress, they were constrained to file consumer complaints before the National Commission, and then discontinued payment of further instalments.

    (iii) The Developer made an alternate offer of allotment of apartments in Phase 1 of the project. The allottees are however not bound to accept the same because of the inordinate delay in completing the construction of the Towers where units were allotted to them. The Occupation Certificate is not available even as on date, which clearly amounts to deficiency of service. The allottees cannot be made to wait indefinitely for possession of the apartments allotted to them, nor can they be bound to take the apartments in Phase 1 of the project. The allottees have submitted that they have taken loans, and are paying high rates of interest to the tune of 7.9% etc. to the Banks. Consequently, we hold that the allottees in Chart B are entitled to refund of the entire amount deposited by them.

    (iv) In so far as award of compensation by payment of Interest is concerned, clause

    13.4 of the Apartment Buyer's Agreement provides that the Developer shall be liable to pay the allottee compensation calculated @ ₹ 7.5 per sq. ft. of the Super Area for every month of delay, after the end of the Grace Period. The compensation will be payable only for a period of 12 months.

    The Apartment Buyers in their Complaint filed before the National Commission made a prayer for refund of the amount deposited alongwith Interest @ 20% p.a. compounding quarterly till its realisation. The Apartment Buyers, in their submissions have stated that they have obtained home loans on which Interest @ 7.90% p.a. is being

    11

    paid, even as on date. We have considered the rival submissions made by both the parties. The Delay Compensation specified in the Apartment Buyer's Agreement of ₹

    7.5 per sq. ft. which translates to 0.9% to 1% p.a. on the amount deposited by the Apartment Buyer cannot be accepted as being adequate compensation for the delay in the construction of the project. At the same time, we cannot accept the claim of the Apartment Buyers for payment of compound interest @ 20% p.a., which has no nexus with the commercial realities of the prevailing market.

    We have also taken into consideration that in Subodh Pawar v. IREO Grace, this Court recorded the statement of the Counsel for the Developer that the amount would be refunded with Interest @ 10% p.a. A similar order was passed in the case of IREO v. Surendra Arora. However, the Order in these cases were passed prior to the out-break of the pandemic.

    We are cognizant of the prevailing market conditions as a result of Covid-19 Pandemic, which have greatly impacted the construction industry. In these circumstances, it is necessary to balance the competing interest of both parties. We think it would be in the interests of justice and fairplay that the amounts deposited by the Apartment Buyers is refunded with Interest @ 9% S.I. per annum from 27.11.2018 till the date of payment of the entire amount.

    The refund will be paid within a period of three months from the date of this judgment. If there is any further delay, the Developer will be liable to pay default interest @ 12% S.I. p.a. (v) The Developer shall not deduct the Earnest Money of 20% from the principal amount, or any other amount as mentioned in Clause 21.3 of the Agreement, on account of the various defaults committed by the Developer, including the delay of over 7 months in obtaining the Fire NOC."

    13. In the present Complaint Cases, Apartment Buyers whose allotments fall in Phase 1 of the Project comprised in Towers A6 to A10, B1 to B4 and C3 to C7, where the Opposite Party Developer has been granted Occupation Certificate (O.C.), and offer of possession has been made, are enlisted in following Chart A:

    Chart A

    12

    (List of Apartment where Occupation Certificate Obtained)

    Cause Title and Consumer Sl. Complaint No. Apartment No. / Amount Paid No. Tower No.

    CC No. 2236 / 2016

    Sanjay Gopinath vs. M/s. Ireo 901

    1

    Grace (P) Ltd. ₹1,55,17,716/-C-6 CC No. 3195 / 2017

    Girish Wadhwa vs. M/s. Ireo Grace 502

    2.

    (P) Ltd. ₹1,28,38,550/-C-7 CC No. 3402/2017

    Anju Mukhija vs. 401

    3.

    ₹1,93,69,003/- M/s. Ireo Grace (P) Ltd. A-7 CC No.1813 / 2018

    Punit Jain vs. 903

    4

    ₹1,69,10,889/- M/s. Ireo Grace (P) Ltd. B-2 CC No. 1814 / 2018

    Bharat Jain vs. 1204

    5.

    ₹1,71,61,773/- M/s. Ireo Grace (P) Ltd. B-3

    Apartment Buyers' whose allotments fall in Phase 2 of the Project comprised in Towers A1 to A5, B5 to B8 and C8 to C11, where the Occupation Certificate (O.C.) has not been granted so far, are enlisted in following Chart B:

    Chart B (List of Apartments where No O. C. Available Even as on Date)

    Sl. Cause Title and Consumer Apartment No. /

    Sl. No. ause Title and Consumer omplaint No. Apartment No. / Tower No. Amount Paid
    1 C No.1692/2017 inesh Chand Sharma vs. /s. Ireo Grace (P) Ltd. 701 B-8 ₹39,45,628/-
    2 C No. 2281/2017 huvan Mehta vs. /s. Ireo Grace (P) Ltd. 802 C-10 ₹49,97,155/-
    3 C No. 3205 / 2017 halabh Nigam vs. /s. Ireo Grace (P) Ltd. 603 B-5 ₹1,20,31,132/-
    4 C No. 3401/2017 nju Mukhija vs. /s. Ireo Grace (P) Ltd. 504 B-8 ₹1,87,78,367/-

    14

    CC No. 2354 / 2018

    404

    5 Sudhir Gulati & Anr. Vs.

    ₹66,13,262/- A-1

    M/s. Ireo Grace (P) Ltd.

    1. Respectfully following the ratio of the Judgment of the Hon'ble Supreme Court in the case of "IREO Grace Realtech Pvt. Ltd. (supra)", we direct the Complainants/Allottees enlisted in Chart A to take possession of the Apartments after making payment of outstanding dues, since the construction was completed and possession offered on 28.06.2019, after issuance of Occupation Certificate on 31.05.2019.The Developer shall however, pay Delay Compensation in the form of simple interest @9% p.a. on the deposited amount for the period of delay which has occurred from 27.11.2018 till the date of offer of possession was made to the Complainants/Allottees.

    2. The Opposite Party Developer is directed to refund the entire amount deposited by the Complainants/Allottees enlisted in Chart B, alongwith interest @9% S.I. p.a. within 3 months from the date of this Order failing which the Developer shall be liable for payment of default interest @12% S.I. p.a. till the payment is made.The Opposite Party Developer shall not deduct the Earnest Money of 20% from the principal amount, or any other amount as mentioned in Clause 21.3 of the Agreement, on account of the various defaults committed by the Developer, including the delay of over 7 months in obtaining the Fire NOC.

    3. The Consumer Complaints are disposed off in above terms, with no order as to Costs.

    ......................J

    R.K. AGRAWAL

    PRESIDENT

    ......................

    DR. S.M. KANTIKAR

    MEMBER

    15