HON'BLE MR. JUSTICE V.K.JAIN, PRESIDING MEMBER (ORAL)
The complainants booked a residential flat in a project namely 'Ramprastha Skyz' which the OPs were to develop in Sector-37D of Gurgaon. On allotment of a residential flat in the aforesaid project to them, they executed an Apartment Buyers Agreement with both the OPs on 13.09.2011, incorporating the respective rights and obligations of the parties in respect of the said transaction. The price of the flat was agreed at Rs.88,92,282/-. As per clause 15(a) of the Agreement, the possession was to be delivered to the complainants by 31.08.2014. The possession having not been offered to them despite they having paid Rs.80,03,055/-, the complainants are before this Commission seeking refund of the aforesaid amount with compensation etc.
2. The complaint has been resisted by the OPs on several grounds. The allotment made to the complainants, the agreement executed with them and the payment received from them have however, been admitted. In its written version, the OP No.1 has interalia stated that the delay in completion of the project has happened on account of the circumstances beyond its control and it is not only the complainants, they are also suffering on account of the delay, they having
1
invested the entire amount received from the complainants in the project. The delay is sought to be justified primarily on the following grounds:
(a) There was delay in receiving approval from different authorities.
(b) There was shortage of labour in the market due to schemes such as NREGA and
JNNURM.
(c) The OP faced acute shortage of water since the Hon'ble High Court of Punjab & Haryana, vide its order dated 16.07.2012, prohibited the use of ground water for construction purpose and directed use of only the filtered water from sewerage treatment plants.
(d) There was shortage of building material in the market on account of the order of the Hon'ble Supreme Court in Deepak Kumar Vs. State of Haryana, SLP Civil Number 19628- 29 of 2009 and connected matters.
(e) Govt. of India announced the demonetization of high denomination currency notes in November 2016.
It is also stated in the written version that in the event of delay, the allottees are entitled to compensation @ Rs.5 per sq. ft. per month in terms of Section 17(a) of the Agreement.
3. In its written version, OP No.2 has pleaded that it was only a financer of the project and that it had executed the Apartment Buyers Agreement only with a view to recover its funding in the Joint Development Agreement. It is also claimed that OP No.2 was neither the owner of the land on which the flats were to be constructed nor was it liable for constructing the said flats.
4. The learned counsel for the complainants submits that the issues involved in this complaint are squarely covered by the decision of this Commission in Consumer Complaint No.2384 of 2017 Mohit Sharma & Anr. Vs. M/s Ramprastha Promoters and Developers Pvt. Ltd. & Anr. and Connected Matters decided on 01.05.2019. A perusal of the above referred decision would show that several Consumer Complaints pertaining to residential flats allotted in this very project were allowed by this Commission by way of the above referred common decision. In Mohit Sharma (supra), the allotment was made in this very project and the Apartment Buyers Agreement were executed with these very OPs. The possession having not been offered to them, the complainants approached this Commission seeking refund of the amount which they had paid for the flats alongwith interest @ 18% per annum and compensation. The complaint was opposed by both the OPs. OP No.1 opposed the complaints primarily on the grounds on which this complaint has been contested and the grounds included non-availability of cement, non-availability of water, etc. It was also pleaded that the allottees were entitled only to mutually agreed compensation of Rs.5 per sq. ft. per month of the super area of the flats.
5. A perusal of the decision would show that OP No.2 filed an application seeking deletion of its name from the array of parties on the ground that there was no privity of contract between them and the complainants. The application was dismissed by this Commission vide its earlier order dated 18.01.2019 noticing that in its written version, OP No.2 itself had
2
pleaded the Joint Development Agreement and sharing of the revenue. Allowing the Consumer Complaint, this Commission inter-alia held as under:
22. It is the case of the Opposite Parties that Clause 15(a) is subject to Clause 31. It is specifically pleaded in the Written Version that at the time of handing over of the delivery was extended in terms of Clause 31 of the Builder Buyers Agreement. For better understanding of the case, the said Clauses are being reproduced as hereunder:-
"15. POSSESSION
(a) Time of handing over the Possession Subject to terms of this Clause and subject to the Allottee having complied with all the terms and condition of this Agreement and the Application, and not default under any of the provisions of this Agreement and compliance with all provisions, formalities, documentation etc., as prescribed by the Developers. Developers propose to hand over the possession of the Apartment by 31-Aug-2014. The Allottee agrees and understands that the Developers entitled to a grace period of hundred and twenty(120) days, for applying and obtaining the occupation certificate in respect of the Group Housing Complex.
(b) Subject to Clause 31, in the following circumstances, the date of possession shall get extended automatically:
(i) If the completion of the Complex including the Apartment is delayed by reason of non- availability of steel and/or cement or other building materials, or water supply or electric power or slow down, strike or lock-out or civil commotion or by reason of war or enemy action or terrorist action or earthquake or any act of God or due to any act, notice, order, rule or notification of the government and/or any other Public or Competent authority or due to delay in sanction of any revised building/zoning plans or for any other reasons beyond the control of Developers, the Allottee agrees that the Developers shall be entitled to the extension of time for handing over of the possession of the said Apartment/Unit.
31. FORCE MAJEURE
The Developers shall not be held responsible or liable for not performing any obligation or undertaking provided for in this Agreement if such performance prevented, delayed or hindered by act of god, fire, flood, explosion, war, riot, terrorist act, sabotage, inability to procure or general shortage of energy, labour equipment facilities, materials or supplies, failure of transportation, strikes, lack outs, action of labour unions, change in law or any other cause not within reasonable control of the Developers." (Emphasis Supplied).
23. In the instant case the material on record does not establish that the reasons given by the Opposite Parties would fall within the scope and definition of 'Force Majeure. Additionally, there is no documentary evidence to support the contention of the Opposite Parties that the reasons pleaded by them, can be construed as 'Force Majeure.'
25. From the afore-noted schedule it is crystal clear that the payments are construction- linked and, therefore, the contention of the Opposite Parties that there are still some amounts due and payable, is totally unacceptable. For the latches of the Opposite Parties, the
3
Complainant cannot be made to suffer. Learned Counsel appearing for the Opposite Parties vehemently contended that they are registered under RERA and the date for completion as per RERA is 31.03.2020 and that the refund, if any, should be allowed only after 31.03.2020. This Commission vide its order dated 15.04.2019 passed in CC/1764/2017 Ajay Nagpal Vs. Today Homes and Infrastructure Pvt. Ltd. (and in other connected matters) has laid down that RERA does not bar the jurisdiction of Consumer Fora.
26. The order of the NGT dated 18.12.2017, is subsequent to the filing of this Complaint and therefore this order cannot be construed to be a 'Force Majeure' condition for the delay between 31.08.2014 till the date of filing of the Complaint. As regarding the Bank loan details, during the course of final arguments, Learned Counsel appearing for the Complainant filed a statement of each Complainant regarding the Bank loan details and the interest rate charged which is reflected in the table in para No. 13.
28. We also find it a fit case to place reliance on the Judgement of the Hon'ble Supreme Court in Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra Civil Appeal No. 3182/2019 wherein the Hon'ble Apex Court has laid down as follows:-
"A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund."
30. The contention of the Learned Counsel for the Opposite Parties that if refund is being allowed then interest has to be awarded keeping in view the principles laid down by the Hon'ble Supreme Court in Ghaziabad Development Authority Vs. Balbir Singh (supra) is also being taken into consideration. In this case the Hon'ble Supreme Court has observed that power to and duty to award compensation does not mean that irrespective of the facts of the case compensation can be awarded in all matters at the uniform rate of 18% p.a. Though we agree with the submission of the Learned Counsel for the First Opposite Party that there can be no hard and fast rule while awarding compensation, we should also keep in view the principles of restitutio in integrum which provides that a person entitled to damages should, as nearly as possible, get that sum of money which would put him in the same position as he would have been if he had not sustained the wrong.
31. Needless to add, though the learned counsel for the first Opposite Party offered to settle the matter with refund of principal amount with 10% interest rate, Learned counsel for the Complainants, on instructions from the Complainants, who are present in person submitted that more than a year had lapsed since the offer was made by them which was not accepted by the Opposite Parties at that point of time and today the Complainants are not willing to accept the same and seek interest @ 12% p.a. as was awarded by this Commission in similar matters.
6. The learned counsel for OP No.2 submits that in view of the provisions contained in (RERA) Real Estate (Regulation and Development) Act, 2016, this Commission lacks jurisdiction to entertain the Consumer Complaint. The said issue however, is no more res integra in view of the decision of the Hon'ble Supreme Court in Civil Appeal No.3581/2020 M/s Imperial Structures Ltd. Vs. Anil Patni & Anr. dated 02.11.2020, where the Hon'ble Apex Court upheld the jurisdiction of a Consumer Forum to entertain the Consumer Complaint
4
even in respect of the projects covered under RERA.
7. The learned counsel for OP No.1 submits that the interest awarded by this Commission in Mohit Sharma (supra) is on the higher side and the Hon'ble Supreme Court, in a subsequent decision dated 07.05.2019 in Puri Constructions Vs. Harish Chawla Civil Appeal No. 4472 of 2019, has awarded interest only @ 8% per annum.
8. The learned counsel for the complainants having taken instructions from the complainants, submits that in order to avoid any further litigation in the matter, the complainants are restricting their claim to the refund of the principal amount alongwith compensation in the form of simple interest @ 8% per annum, as was awarded by the Hon'ble Supreme Court in Civil Appeal No. 4472 of 2019 Puri Constructions Vs. Harish Chawla
dated 07.05.2019.
9. For the reasons stated hereinabove, the Consumer Complaint is disposed of with the following directions:
(i) The OPs shall refund the entire principal amount of Rs.80,03,055/- to the complainants alongwith compensation in the form of simple interest @ 8% per annum from the date of each payment till the date of refund.
(ii) The OPs shall pay a sum of Rs.25,000/- as cost of litigation to the complainants.
(iii) The liability of the OPs shall be joint as well as several.
(iv) The payment in terms of this order shall be paid within three months from today.
......................J
V.K. JAIN
PRESIDING MEMBER