AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Acts
  • provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, PAPRA).
  • provisions of the Consumer Complaint No.761 of 2019 13 PAPRA and Rules
  • Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995,
  • SECTION 17 CONSUMER PROTECTION ACT 1986
  • sub-section (1) of section 6
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Acts
  • provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, PAPRA).
  • provisions of the Consumer Complaint No.761 of 2019 13 PAPRA and Rules
  • Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995,
  • SECTION 17 CONSUMER PROTECTION ACT 1986
  • sub-section (1) of section 6
Smart Summary

Structured Summary of the Provided Legal Opinion

Factual and Procedural Background

The order disposes three Consumer Complaints filed under Section 17 of the Consumer Protection Act, 1986, which arise from substantially similar facts and involve the same opposite parties (developers/promoters). The narrative is taken primarily from Consumer Complaint No. 761 of 2019, which concerns two brothers who applied to purchase a commercial unit (Unit No. 8, Tower-C, 8th Floor; super area 662 sq.ft.) in an under-construction complex promoted by the opposite parties (the project described as Bus Terminal-cum-Commercial Complex, Sector 57, Mohali).

Key factual points from Complaint No. 761 of 2019 (as presented in the opinion):

  • The complainants paid a total of Rs. 11,58,500 on 12.01.2012 and received a letter of allotment dated 12.01.2012 (Ex.C-6).
  • The letter of allotment fixed completion/possession within 48 months from compliance date (i.e., by 15.12.2013) subject to approvals and sanctions and force majeure (Clause 1.3.3).
  • No meaningful development was undertaken; construction was abandoned and the developers repeatedly postponed restart/completion dates by letters dated 07.05.2015 (Ex.C-7), 24.12.2015 (Ex.C-8) and offered alternatives in a letter of 21.11.2017 (Ex.C-9) including refund or interest at 8.8% for those who wished to stay invested.
  • Complainants became aware via public notices that GMADA had served notices on the opposite parties for non-completion and had initiated termination/cancellation processes.
  • The opposite parties did not appear before the Commission despite service and were proceeded against ex parte by order dated 10.12.2019.
  • Complainants filed evidence by way of an affidavit of their Special Power of Attorney (Sh. Nazir Ahmed Choudhary) and documents: brochure (Ex.C-1), identity documents (Ex.C-2 to Ex.C-4), ledger report (Ex.C-5), letter of allotment (Ex.C-6) and correspondence (Ex.C-7 to Ex.C-11).

The order also addresses two other complaints (referred to in the order as Consumer Complaint No. 766 of 2019 and Consumer Complaint No. 767 of 2019). Their factual matrices are similar: allotment letters, payments by the complainants for designated units in the same project, and non-delivery of possession within contractually stipulated periods (with specified completion deadlines and differing payment amounts). In each of these complaints the opposite parties failed to appear and were proceeded against ex parte.

Legal Issues Presented

  1. Whether the opposite parties (promoters/developers) committed deficiency in service and unfair trade practice by failing to complete the project and deliver possession within the stipulated period as per the allotment letters.
  2. Whether the opposite parties violated provisions of the Punjab Apartment and Property Regulation Act, 1995 (PAPRA) and the Rules framed thereunder (in particular Sections 3, 5 and 9 of PAPRA and Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995), and what consequences follow from such violations.
  3. What reliefs are appropriate for the complainants: specific performance by way of delivery of possession and execution of sale/conveyance deed subject to payment of balance consideration, or alternatively refund of deposited amounts with interest; and what rate of interest and quantum of compensation/ litigation expenses should be awarded.

Arguments of the Parties

Complainants' Arguments

  • The complainants booked units to earn livelihood via self-employment (Construction Consulting office; Boutique Training Centre; Immigration Consultancy Office) and deposited substantial sums as advance/part payment as per the respective allotment letters.
  • The letter(s) of allotment fixed a time for completion/possession (e.g., 48 months from compliance date for Complaint No. 761; 30 months for the other complaints), but the opposite parties failed to complete the projects and did not deliver possession within the stipulated periods.
  • The developers admitted delays and/or inability to finance construction by correspondence (letters of 07.05.2015, 24.12.2015, 21.11.2017 and 06.06.2018), and GMADA had initiated action for termination/cancellation; therefore the opposite parties committed deficiency in service and unfair trade practice.
  • The complainants sought either immediate delivery of possession (subject to payment of balance consideration) or refund of amounts deposited with interest; they also sought compensation for mental agony and litigation expenses.

Opposite Parties' Arguments

The opposite parties did not appear or file written submissions. The Commission proceeded ex parte; therefore no defensive arguments by the opposite parties are recorded in the opinion.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Consumer Complaint No.343 of 2016 (Sharanjeet Kaur v. C and C Towers Ltd. & Ors.) decided on 02.06.2017 The opinion notes this earlier verdict as covering the merits of the present complaints; specific legal principle not separately identified in the text. The Commission held the present complaints in view of the decisions in this and the other listed cases; the precedent was relied upon to support disposition of the present matters.
Consumer Complaint No.314 of 2017 (Indu Laroia & Anr. v. C and C Towers Limited & Ors.) decided on 07.11.2017 Earlier Commission decision covering similar facts; specific rule/principle not detailed in the opinion. Used as part of a line of prior decisions establishing the Commission's approach to these facts; assisted the Court in disposing present complaints.
Consumer Complaint No.99 of 2018 (Dharam Pal Nanda v. C & C Towers Ltd. & Ors.) decided on 19.07.2018 Earlier Commission decision covering similar subject matter; specific principle not specified in opinion. Relied on collectively with other prior decisions to conclude that merits are covered and to dispose the present complaints accordingly.
Consumer Complaint No.825 of 2018 (Harpreet Singh v. C & C Towers Ltd. & Ors.) decided on 20.02.2019 Held that delays due to paucity of funds, absence of construction licence and initiation of cancellation by GMADA amount to deficiency in service and unfair trade practice; GMADA had indicated no licence/grant and had initiated cancellation proceedings. The Court specifically relied on the ratio and factual findings in this case (including GMADA's correspondence) to conclude similarly in the present matters that the developers had failed to complete the project and that such failure amounted to deficiency and unfair trade practice.
Consumer Complaint No.183 of 2019 (Darshan Singh v. C & C Towers Ltd. & Ors.) decided on 15.05.2019 Earlier Commission decision on related facts; principle not explicitly stated in the text. Included among prior decisions relied upon to dispose of the present complaints.
Consumer Complaint No.930 of 2018 (Ms. Kusum Sharma & Ors. v. C & C Towers Ltd. & Ors.) decided on 04.04.2019 Earlier Commission decision on similar factual/legal issues; principle not separately described in the opinion. Relied upon along with other precedents to support the disposition in the present matters.
Consumer Complaint No.752 of 2019 (Manoj Goyal & Anr. v. C. & C Towers Ltd. & Ors.) decided on 19.12.2019 Earlier Commission decision covering similar issues; specific rule/principle not delineated in the text. Considered as part of the line of precedents that render the merits of the present complaints squarely covered.

Court's Reasoning and Analysis

The Commission's reasoning proceeds in a sequence of factual findings and legal application, based on the un-rebutted pleadings and documentary evidence submitted by the complainants and the absence of any defence by the opposite parties:

  1. Proceeding ex parte: The opposite parties were served but did not appear; the Commission therefore proceeded ex parte (order dated 10.12.2019). Under the rules of pleadings, where no reply is filed the averments in the complaint are deemed admitted. The complainants' evidence therefore stands unrebutted and an adverse inference is drawn against the opposite parties.
  2. Documentary proof of delay and admissions by opposite parties: The Commission relied on correspondence produced by complainants (Ex.C-7, Ex.C-8, Ex.C-9, Ex.C-10, Ex.C-11) in which the developers admitted financial constraints, postponed restart/completion dates, offered refund or low interest for staying invested, and where GMADA correspondence indicated initiation of cancellation action. These documents demonstrate that construction was not completed within the contractually stipulated timeframe and that developers effectively admitted inability to complete timely.
  3. Compliance with PAPRA and Rules: The Commission examined the statutory obligations under the Punjab Apartment and Property Regulation Act, 1995 (PAPRA) and its Rules. It found that:
    • Section 3 (General Liabilities of Promoter): The developers failed to make full and true disclosure regarding title, encumbrances and approved plans and did not provide required inspection rights—hence non-compliance with Section 3.
    • Section 5 (Development of land into Colony): The developers failed to produce evidence of permission from competent authority for development—hence violation of Section 5.
    • Section 9 (Maintenance of separate account): No evidence was produced that a separate account was maintained for buyers' funds as required—hence contravention of Section 9.
    • Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995: The Rule prescribes that upon cancellation the promoter shall refund the amount collected along with interest at 12% per annum from date of receipt till repayment. The Court invoked this rule as the statutory rate for refund where cancellation/repayment is ordered.
  4. Benevolent object of consumer law and damages: The Commission emphasized the benevolent object of the Consumer Protection Act to shield consumers from exploitation. It held that misrepresentation and deception by the developers caused loss of opportunity, mental agony and harassment to the complainants; compensation should be just, fair and commensurate with the loss. The Court referred to a line of higher forum decisions (Supreme Court and National Commission) for the settled principle that builders are liable to compensate for failure to deliver possession.
  5. Relief tailoring: On facts, the Commission ordered that the developers are primarily liable to deliver physical possession complete in all respects with Completion/Occupation Certificate and execute the Sale/Conveyance Deed subject to payment of balance sale price (without interest/penalty). For delay after the stipulated delivery date, the Commission awarded interest at 12% per annum on the amounts deposited by the complainants from the respective stipulated completion dates until actual physical delivery. Alternatively, if delivery and conveyance cannot be effected, the developers shall refund the deposited amounts with interest at 12% per annum (as per Rule 17) and pay compensation/litigation expenses. Specific sums for litigation expenses/compensation were fixed for each complaint.

Holding and Implications

CORE HOLDING: The complaints are allowed and appropriate reliefs are granted in favour of the complainants.

Specific directions issued by the Commission (direct effects on the parties):

  • Primary relief (specific performance style): Opposite parties shall deliver actual and physical possession of the respective units complete in all respects, along with agreed facilities and amenities and with Completion/Occupation Certificate issued by the competent authority, subject to payment of the balance sale consideration by the complainants; the opposite parties shall execute the Sale/Conveyance Deed in favour of the complainants.
  • Interest for delay: Opposite parties shall pay interest at the rate of 12% per annum on the amounts deposited by the complainants from the stipulated completion/possession date(s) until actual physical delivery of possession (e.g., from 15.12.2013 in Complaint No. 761; from 15.06.2012 in the other complaints), as ordered by the Commission.
  • Alternative (if opposite parties fail to deliver possession and execute conveyance): They shall refund the entire amount deposited by the complainants along with interest at 12% per annum from the respective dates of deposit till realization, as per Rule 17 of PAPRA.
  • Compensation and litigation expenses: The Commission awarded composite compensation/litigation expenses to each complainant for mental agony and harassment as follows:
    • Consumer Complaint No. 761 of 2019: Rs. 20,000
    • Consumer Complaint No. 766 of 2019: Rs. 10,000
    • Consumer Complaint No. 767 of 2019: Rs. 15,000
  • Adjustment of remaining sale consideration: Any remaining sale consideration payable by the complainant shall be adjusted against the liability of the opposite parties to pay interest/compensation as directed by the Commission.

Broader implications: The order applies established principles (consumer protection and PAPRA compliance) to the facts and relies on a line of prior Commission decisions. The opinion does not set out a novel legal principle but applies existing statutory provisions (PAPRA Sections and Rule 17) and established remedial concepts (delivery vs. refund with statutory interest and compensation for mental agony). The decision's practical consequence is to require the developer either to complete and convey the units or to refund with statutory interest and pay modest compensation and litigation costs.

To access the original judgment, please Sign In or Subscribe.

    Mohammad Shahbaz v. C & C Towers Limited

    2) To be referred to the Reporters or not? Yes/No

    3) Whether judgment should be reported in the Digest? Yes/No Present:- For the complainants : Sh. A.K. Batra, Advocate For the opposite parties: Ex parte. JUSTICE PARAMJEET SINGH DHALIWAL, PRESIDENT This order will dispose of above mentioned three (3) Consumer Complaints filed by the complainants, under Section 17 of the Consumer Protection Act, 1986 (in short, the Act), as the facts and the questions of law involved in all the complaints are the same and all the complaints have been filed against the same opposite parties by the different complainant(s). The facts are taken from Consumer Complaint No.761 of 2019. Consumer Complaint No.761 of 2019

    2. The complainants, who are brothers, have filed this complaint, under Section 17 of the Act, against the opposite parties, seeking following directions to them:

    i) to hand over possession of the unit/commercial space immediately; Consumer Complaint No.761 of 2019 OR in the Alternative: to refund the amount of 11,58,500/-, along with interest; ii) to pay interest at the rate of 18% per annum on the deposited amount of 11,58,500/- till the actual date of handing over of possession or refund of the said amount; iii) to pay compensation of 3,50,000/-, on account of mental agony and harassment suffered by the complainants; and iv) to pay 31,000/- towards litigation expenses. Facts of the Complaint

    3. Brief facts, as set out in the complaint, are that being allured by the advertisement given by the opposite parties regarding their under construction Complex known as Bus Terminal-cum- Commercial Complex situated in Sector 57, Mohali, the complainants applied for purchasing a unit, exclusively for the purpose of creating the source of their livelihood by way of self-employment by running a Construction Consulting office. The opposite parties offered unit No.8, Tower-C, 8th Floor, having super area of 662 sq.ft. for basic sale price of 26,48,000/- at the rate of 4,000/- per sq.ft; which was earlier allotted to Sh. Avtar Singh and Sh. Harjit Singh. The complainants paid a total sum of 11,58,500/- to the opposite parties towards the price of that unit on 12.01.2012. Thereafter, letter of allotment dated 12.01.2012 itself was issued to them regarding the said unit. The opposite parties received various amounts from the complainants, ignoring the provisions of the Punjab Apartment and Property Regulation Act, 1995 (in short, PAPRA). They failed to complete the construction of the unit within 48 months from the date of compliance Consumer Complaint No.761 of 2019

    i.e. 16.12.2009, as per Clause 1.3.3 of the letter of allotment. The complainants opted for Construction Linked Plan for making payment of instalments of price of the unit. However, no development was started and the work was abandoned by them. On 07.05.2015, opposite party No.3 sent a letter to the complainants, stating that the project was likely to restart by July, 2015. Later on, opposite party No.3 sent another letter on 24.12.2015, stating that the project was likely to restart by June, 2016. Another letter dated 21.11.2017 was issued by opposite party No.3 to all the investors, stating that the Company would refund the deposited amount of investors, along with interest and that the investors, who wanted to stay with the Company, would be paid interest at the rate of 8.8% on their deposited amount. Since the construction was not started at the site, so there was no question of the complainants making payment of remaining instalments. The complainants came to know, through a public notice published in newspapers, that GMADA had served a notice upon the opposite parties for non-completion of the construction and also for cancellation of the agreement. On 06.06.2018, opposite party No.3 sent further letter, requesting for extension of time till 30.09.2018 for fulfilling the promises, as made in the allotment letter. GMADA had replied to a letter sent by C & C Mohali Junction Buyer Association, stating that GMADA had already issued termination notice on 04.04.2016, but opposite party No.1 had sought extension of time for completion of the project. The aforesaid act and conduct of the opposite parties amount to deficiency in service. Hence, the present complaint. Consumer Complaint No.761 of 2019

    4. The opposite parties did not appear before this Commission, despite their service and, as such, they were proceeded against ex parte, vide order dated 10.12.2019. Evidence of the Complainants

    5. To prove their claim, the complainants filed affidavit of their Special Power of Attorney Sh. Nazir Ahmed Choudhary, along with copies of documents i.e. brochure Ex.C-1, Aadhar Cards Ex.C-2 to Ex.C-4, Ledger Report Ex.C-5, letter of allotment Ex.C-6 and letters Ex.C-7 to Ex.C-11. Contentions of the Complainants

    6. I have heard learned counsel for the complainants and have gone through the record carefully.

    7. Learned counsel for the complainants has argued on the lines of the complaint. It has been further contended that the complainants purchased the unit, in question, for running Construction Consulting Office for earning their livelihood by way of self- employment. It was further contended that as per Clause 1.3.3 of allotment letter, the construction of the unit was to be completed within

    48 months from the compliance date i.e. 16.12.2009, after obtaining necessary approvals and sanctions. The opposite parties received a sum of 11,58,500/- from the complainants towards the price of the unit, in question, but they failed to complete the project, in question, within the said stipulated period, without disclosing any cogent reasons. No development was carried out at the site of Commercial Complex and the work was abandoned. The opposite parties kept on extending the dates for restart of the project, without explaining any Consumer Complaint No.761 of 2019 sufficient reason. The delay in completing the project and delivering possession has been duly admitted by the opposite parties in letter dated 21.11.2017, whereby they offered refund of the amount deposited by the investors and the investors, who wanted to retain the units, were to be awarded interest at the rate of 8.8% on their deposited amount. The opposite parties have neither delivered possession of the unit, in question, nor refunded the amount deposited by them. Thus, they committed deficiency in service and unfair trade practice, by not honouring their commitments, as per the allotment letter. Accordingly, it has been contended that the complaint be allowed and all the reliefs, as prayed for in the complaint, be awarded in favour of the complainants. Consideration of Contentions

    8. I have given my thoughtful consideration to the contentions raised by the learned counsel for the complainants.

    9. At the outset, it is relevant to mention that the merits of the present complaints are squarely covered by the earlier verdicts given by this Commission in following cases:

    i) Consumer Complaint No.343 of 2016 (Sharanjeet Kaur v. C and C Towers Ltd. & Ors.) decided on 02.06.2017; ii) Consumer Complaint No.314 of 2017 (Indu Laroia & Anr. v. C and C Towers Limited & Ors.) decided on 07.11.2017; iii) Consumer Complaint No.99 of 2018 (Dharam Pal Nanda v. C & C Towers Ltd. & Ors.) decided on 19.07.2018; iv) Consumer Complaint No.825 of 2018 (Harpreet Singh v. C & C Towers Ltd. & Ors.) decided on 20.02.2019; Consumer Complaint No.761 of 2019

    v) Consumer Complaint No.183 of 2019 (Darshan Singh v. C & C Towers Ltd. & Ors.) decided on 15.05.2019; vi) Consumer Complaint No.930 of 2018 (Ms. Kusum Sharma & Ors. v. C & C Towers Ltd. & Ors.) decided on 04.04.2019; and vii) Consumer Complaint No.752 of 2019 (Manoj Goyal & Anr. v. C. & C Towers Ltd. & Ors.) decided on 19.12.2019. So, I proceed to dispose of the present complaints, in view of the decisions given in the above noted cases.

    10. Admittedly, the complainants were allotted unit No.8, 8th Floor, Tower-C, having super area of 662 sq.ft. in the above said project of the opposite parties, vide letter of allotment dated 12.01.2012 Ex.C-6. As per Annexure-A of letter of allotment, the total consideration of the said unit was 5,000/- per sq.ft. (33,10,000/-). The complainants deposited a total sum of 11,58,500/- with them towards the price of the unit, as per Ledger Report Ex.C-5. As per Clause 1.3.3 of the letter of allotment, Ex.C-6, the construction of the unit was likely to be completed within 48 months from the compliance date i.e. from 16.12.2009 after obtaining all the necessary approvals and sanctions, subject to force majeure circumstances. Therefore, the construction of the unit, in question, was to be completed and possession was to be delivered up to 15.12.2013. The complaint has been filed on 16.10.2019 i.e. more 6 years therefrom. However, the opposite parties failed to complete the construction of project/unit within the stipulated period, without any sufficient cause, so as to deliver possession of the unit, in question, to the complainants. The development/construction work in the project had been abandoned by Consumer Complaint No.761 of 2019 them. From letter dated 07.05.2015, Ex.C-7, issued by the opposite parties to the complainants, it is clear that the opposite parties were facing financial constraints and, as such, they informed the complainants that the construction of the project would be restarted by July, 2015. They further extended the date of restart of construction and handing over of possession till June, 2016, as per letter dated 24.12.2015 Ex.C-8. It is also relevant to mention that opposite parties wrote letter dated 21.11.2017, Ex.C-9, to the investors, offering refund of the amount deposited by the allottees. It was also mentioned therein that the investors, who wanted to stay invested with the Company, were to be paid interest at the rate of 8.8% per annum on the amount deposited by them, along with other applicable conditions. All these letters clearly prove that the opposite parties failed to complete the project within the stipulated timeframe, that is why they offered aforesaid rate of interest on the deposited amount of the investors, including complainants. Still further, letter dated 06.06.2018, Ex.C-10, issued by the opposite parties also proves that they were not having sufficient funds for raising the project and, as such, they requested for further extension of time till 30.09.2018 for repayment, as per commitment made vide letter Ex.C-9.

    11. In Harpreet Singhs case (supra), it was held as under: It is also relevant to mention that one another allottee sought information under RTI Act from GMADA. GMADA, vide letter dated 29.09.2016, Ex.C-7, supplied the requisite information to her, informing that no licence of construction was granted to the opposite parties, nor any agreement was entered into by the opposite parties with the Government. Still further, as per letter Consumer Complaint No.761 of 2019 dated 11.03.2016, Ex.C-9, issued by GMADA, the process for cancelling the agreement of the opposite parties had already been initiated, due to non-completion of the project within the stipulated period. It is also mentioned therein that the reason for delay in completing the project was disclosed by the opposite parties to be paucity of funds. In such circumstances, the complainant cannot be made to wait for an indefinite period of time for the completion of the project and delivery of the space/unit in question. This certainly amounts to deficiency in service and adoption of unfair trade practice on the part of the opposite parties. From perusal of observations made by this Commission in the aforesaid case also, it is clear that the opposite parties failed to complete the project within the stipulated period due to paucity of funds with them and GMADA had initiated process for cancellation of their licence. Similar is the ratio of letter dated 06.07.2018, Ex.C-11, issued by GMADA to C & C Mohali Junction Buyer Association, produced in the present case.

    12. The whole purpose of pleadings is to give fair notice to each party of what the opponents case is and to ascertain with precision the point(s) on which the parties agree and those on which they differ. The purpose is to eradicate irrelevancy. The complaint is a concise statement of facts and if no reply is filed to the complaint, the averments made therein are deemed to have been admitted. For the sake of repetition, it is relevant to mention that the opposite parties failed to appear before this Commission, despite their service and, as such, they were proceeded against ex parte. Thus, all the averments made in the complaint are deemed to have been admitted by them and Consumer Complaint No.761 of 2019 the evidence led by the complainants stands unrebutted; for which an adverse inference is to be drawn against them. Since the opposite parties are ex parte, so no evidence has come on record, whether they have obtained the requisite approvals and permissions from the competent authorities, before launching their project.

    13. Keeping in view the above circumstances, I hold that the opposite parties have failed to comply with the provisions of PAPRA. As per Section 3 (General Liabilities of Promoter) of the PAPRA, the opposite parties were required to make full and true disclosure of the nature of their title to the land, on which such project is developed or such building is constructed or is to be constructed, make full and true disclosure of all encumbrances on such land, including any right, title, interest or claim of any party in or over such land. They were also required to give inspection on seven days notice or demand of the layout of the colony and plan of development works to be executed in a project, as approved by the prescribed authority in the case of a project. However, they failed to comply with Section 3 of the PAPRA.

    14. As per Section 5 (Development of land into Colony) of PAPRA, the opposite parties were liable to obtain permission from the competent authority for developing the project, but they failed to produce on record any such valid permission. So, they also violated Section 5 of PAPRA.

    15. As per Section 9 of PAPRA, every builder is required to maintain a separate account in a scheduled Bank, for depositing the amount deposited by the buyers, who intend to purchase the plots/flats/commercial space/unit, but no evidence has been led on the Consumer Complaint No.761 of 2019 record by the opposite parties to prove that any account has been maintained by them in this respect. As such, the opposite parties also violated Section 9 of the PAPRA.

    16. As per Rule 17 of the Punjab Apartment and Property Regulation Rules, 1995, framed under Section 45 of the PAPRA, it has been provided as under:-

    17. Rate of interest on refund of advance money upon cancellation of agreement.- The promoter shall refund full amount collected from the prospective buyers under sub-section (1) of section 6 together with interest thereon at the rate of twelve per cent per annum payable from the date of receipt of amount so collected till the date of re-payment. The Act came into being in the year 1986. It is the benevolent piece of legislation to protect the consumers from exploitation. The spirit of the benevolent legislation cannot be overlooked and its object is not to be frustrated. The complainants have made payment of substantial amount to the opposite parties, with the hope to get the possession of the unit within a reasonable period. The circumstances clearly show that they made false statement of facts about the goods and services

    i.e. allotment of unit and delivery of possession in a stipulated period. The act and conduct of the opposite parties is a clear case of misrepresentation and deception, which resulted in the injury and loss of opportunity to the complainants. There is escalation in the price of construction also. The builder is under obligation to deliver the possession of the plot/unit/flat/space within a reasonable period. From the facts and evidence brought on the record of the complaint, it is clearly made out that the opposite parties i.e. builders knew from the very beginning that they had not complied with the provisions of the Consumer Complaint No.761 of 2019 PAPRA and Rules and would not be able to deliver the possession within the stipulated period, thus by misrepresentation induced the complainants to book the unit, due to which the complainants have suffered mental agony and harassment. It is the settled principle of law that compensation should be commensurate with the loss suffered and it should be just, fair and reasonable and not arbitrary. The builder is bound to compensate for the loss and injury suffered by the complainants for failure to deliver the possession, so has been held in catena of judgments by the Honble Supreme Court and the Honble National Commission. To get the relief, the complainants have to wage a long drawn and tedious legal battle. As such, the complainants were at loss of opportunities.

    17. In these circumstances, opposite parties are liable to deliver physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Completion/Occupation Certificate issued by the competent authority, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainants. For delay in delivery of possession, the opposite parties are also liable to pay compensation in the shape of interest at the rate of 12% per annum on the amount deposited by the complainants with them after the stipulated period for delivery of possession i.e. from 15.12.2013 till actual and physical delivery of possession of the unit, as discussed above. However, if the opposite parties will not be able to deliver possession of the unit, in question, and to execute the Sale/ Conveyance Deed, then in the alternative Consumer Complaint No.761 of 2019 they shall refund the entire amount deposited by the complainants, along with interest at the rate of 12% per annum from the respective dates of deposit till realization, as per Rule 17 of PAPRA. Besides this, the complainants are also entitled to suitable litigation expenses and compensation for the mental agony and harassment suffered by them.

    18. Accordingly, the complaint is allowed and following directions are issued to the opposite parties:

    i) to deliver actual and physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Completion/Occupation Certificate issued by the competent authority, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainants; ii) to pay compensation for delay in delivery of possession at the rate of 12% per annum on the amount deposited by the complainants i.e. 11,58,500/- with them from 15.12.2013 till actual and physical delivery of possession of the unit, as ordered above; and iii) to pay composite litigation expenses and compensation for the mental and physical harassment suffered by the complainants to the tune of 20,000/-. iv) The remaining sale consideration payable by the complainants shall be adjusted from the above said liability of the opposite parties at Sr. No.(ii). Consumer Complaint No.761 of 2019

    19. In case the opposite parties fail to comply the directions, as ordered above, then in the alternative, they shall:

    i) refund the entire amount deposited by the complainant i.e. 11,58,500/-, along with compensation for causing financial loss and depriving the complainants of the use of the said amount during the period it remained with the opposite parties at the rate of 12% per annum from the respective dates of deposit till realization as per Rule 17 of PAPRA; and ii) to pay composite litigation expenses and compensation for the mental and harassment suffered by the complainants to the tune of 20,000/-. Consumer Complaint No.766 of 2019

    20. Similarly, in this complaint, complainant was allotted unit bearing No.7 having super area of 826 sq.ft. Tower-C, C & C Capital 11th Floor, in the project/Complex of the opposite parties, vide allotment letter dated 19.10.2010, Ex.C-3. The Basic Sale Price of the said unit was 4,200/- sq.ft. plus additional charges, as per Annexure- A of letter of allotment. The complainant booked the said unit for earning her livelihood by way of self-employment by running a Boutique Training Centre. It is averred that the complainant paid a total sum of 19,86,800/- towards the price of the unit on different dates, as mentioned in Para No.4 & 6 of the complaint. As per Clause 1.3.5 of the allotment letter, construction of the unit was likely to be completed within 30 months from the date of start of lease period i.e. 15.12.2009. Thus, the possession was to be delivered up to 15.06.2012. However, the possession of the unit, in question, was not delivered by the opposite parties to the complainant within the stipulated period. Other averments are similar to that of Consumer Complaint No.761 of 2019. Consumer Complaint No.761 of 2019 Prayer for handing over of possession of the unit, along with interest at the rate of 15% per annum on the deposited amount, besides compensation and litigation expenses has been made.

    21. Similarly, in this case also, the opposite parties did not appear before this Commission, despite their service and, as such, they were proceeded against ex parte, vide order dated 10.12.2019.

    22. The complainant alleged in Para-4 of the complaint that she deposited a sum of 2,50,000/- with the opposite parties, vide cheque dated 15.09.2010 and another sum of 2,50,000/- vide cheque No.001151 dated 01.08.2011. To prove these facts, the complainant has produced on record copies of cheque No.345409 dated 15.09.2010 for 2,50,000/- and cheque No.001151 dated 01.08.2011 for 2,50,000/-, Ex.C-2 (colly.). However, it needs to be mentioned that on cheque dated 01.08.2011, an endorsement has been made and signed, to the effect that the said cheque was received against cheque No.345409 dated 15.09.2010 for 2,50,000/-. The complainant also alleged in Para-6 of the complaint that another sum of 14,86,800/- was also paid to the opposite parties in cash. However, no receipt or any other evidence has been led by her to prove that the said amount was paid by her in cash to the opposite parties.

    23. In view of the reasons and discussion held in Consumer Complaint No.761 of 2019, this complaint is allowed and following directions are issued to the opposite parties:

    i) to deliver actual and physical possession of the unit, in question, complete in all respects, along with agreed facilities and amenities with Completion/Occupation Certificate issued by the competent authority, subject to payment of balance sale Consumer Complaint No.761 of 2019 consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainant; ii) to pay compensation for delay in delivery of possession at the rate of 12% per annum on the amount deposited by the complainant with them after the stipulated period for delivery of possession i.e. 15.06.2012 till actual and physical delivery of possession of the unit, as ordered above; and iii) to pay composite litigation expenses and compensation for the mental and harassment suffered by the complainant to the tune of 10,000/-. iv) The remaining sale consideration payable by the complainant shall be adjusted from the above said liability of the opposite parties at Sr. No.(ii). Consumer Complaint No.767 of 2019

    24. Similarly, in this complaint, complainant was allotted unit bearing No.7 having super area of 729 sq.ft. Tower-C, C & C Capital 9th Floor, in the project/Complex of the opposite parties, vide allotment letter dated 15.09.2010, Ex.C-5. The Basic Sale Price of the said unit was 4,250/- sq.ft. plus additional charges, as per Annexure-A of letter of allotment. The complainant booked the said unit for earning his livelihood by way of self-employment by running an Immigration Consultancy Office. It is further alleged that the complainant paid a total sum of 11,96,750/- to the opposite parties towards the price of the unit. As per Clause 1.3.5 of the allotment letter, construction of the unit was likely to be completed within 30 months from the date of start of lease period i.e. 15.12.2009. Thus, the possession was to be delivered up to 15.06.2012. However, the possession of the unit, in question, was not delivered by the opposite parties to the complainant within the stipulated period. Other averments are similar to that of Consumer Complaint No.761 of 2019 Consumer Complaint No.761 of 2019. Prayer for handing over of possession of the unit, along with interest at the rate of 15% per annum on the deposited amount, besides compensation and litigation expenses has been made.

    25. Similarly, in this case also, the opposite parties did not appear before this Commission, despite their service and, as such, they were proceeded against ex parte, vide order dated 10.12.2019.

    26. The complainant has produced demand draft No.393634 dated 01.07.2010 for 4,50,000/- as Ex.C-2 and demand draft No.056961 dated 01.07.2010 for 1,50,000/- as Ex.C-3 (colly.). However, in the Provisional Receipt dated 07.07.2010 Ex.C-3 (colly.), the amount of aforesaid first demand draft No.393634 dated 01.07.2010 is wrongly mentioned as 5,00,000/- instead of 4,50,000/- . The amount of other demand draft No.056961 dated 01.07.2010 is correctly mentioned as 1,50,000/-. Besides this, the complainant has also produced cheque No.000423 dated 16.09.2010 for 1,29,000/- Ex.C-4. Thus, the total of aforesaid amounts comes to 7,29,000/-. The complainant alleged in Para-6 of the complaint that another sum of 5,46,750/- was also paid to the opposite parties in cash. However, no receipt or any other evidence has been led by him to prove that the said amount was paid by him in cash to the opposite parties.

    27. In view of the reasons and discussion held in Consumer Complaint No.761 of 2019, this complaint is allowed and following directions are issued to the opposite parties:

    i) to deliver actual and physical possession of the unit, in question, complete in all respects, along with agreed facilities and Consumer Complaint No.761 of 2019 amenities with Completion/Occupation Certificate issued by the competent authority, subject to payment of balance sale consideration, without any interest and penalty thereon and to execute the Sale/Conveyance Deed in favour of the complainant; ii) to pay compensation for delay in delivery of possession at the rate of 12% per annum on the amount deposited by the complainant with them after the stipulated period for delivery of possession i.e. 15.06.2012 till actual and physical delivery of possession of the unit, as ordered above; and iii) to pay composite litigation expenses and compensation for the mental and harassment suffered by the complainant to the tune of 15,000/-. iv) The remaining sale consideration payable by the complainant shall be adjusted from the above said liability of the opposite parties at Sr. No.(ii).

    Use AI to get other relevant cases.

    Comments

    Mohammad Shahbaz v. C & C Towers Limited
    (Jan 8, 2020)