Executive Summary — State Consumer Disputes Redressal Commission, Delhi (Presiding Member: Ms. Salma Noor) — Decision dated 21.10.2019

Factual and Procedural Background

This consolidated order disposes of 11 consumer complaints (Nos. 471/2013, 469/2013, 488/2013, 525/2013, 526/2013, 530/2013, 531/2013, 541/2013, 542/2013, 590/2013 and 674/2013) filed under Section 17 of the Consumer Protection Act, 1986 against M/s BPTP Ltd. The complainants are all allottees who booked residential flats in the project referenced as "BPTP Park Floor-II" (Sector 76, Faridabad). The factual core across the complaints is similar: flats were booked (mainly in 2008), buyers executed agreements (construction-linked plans) and paid substantial sums (in many cases about 90% of agreed cost), but physical possession was not lawfully deliverable because the opposite party (OP) did not possess an Occupation/Completion Certificate (OC). The OP issued a "Demand-cum-Offer of Possession for fit outs" dated 07.06.2013 and raised additional demands, which the complainants challenged as unlawful. Complainants sought setting aside of those demands, withdrawal/refund of interest or delayed payment charges, award of delayed penalty/compensation, refund of amounts with interest, and assistance in obtaining NOC from banks to clear charges on the flats. The Commission heard the matters together, recorded evidence, addressed preliminary objections, and ultimately issued the consolidated decision on 21.10.2019.

Legal Issues Presented

  1. Whether this Commission has territorial jurisdiction to adjudicate the complaints despite a clause in the agreement conferring jurisdiction to courts at Faridabad and the Punjab & Haryana High Court at Chandigarh (Clause 34).
  2. Whether the disputes arising out of allotment of residential flats, construction-linked agreements and delayed possession fall within the definition of "service" and are maintainable before the Consumer Commission.
  3. Whether the opposite party's issuance of a "Demand-cum-Offer of Possession for fit outs" and additional monetary demands without having an Occupation Certificate amounts to deficiency in service or an unfair trade practice.
  4. Whether a force majeure clause (Clause 9) covering delays in obtaining statutory approvals absolves the OP of liability for delay in obtaining OC when the delay is attributable to the OP's actions.
  5. Whether the Commission can grant refund of amounts paid with interest and compensation when complainants seek refund during pendency of proceedings but did not originally make a specific prayer for refund in the complaint.

Arguments of the Parties

Complainants' Arguments

  • Complainants booked flats in the project, paid substantial sums (in many cases around 90% of the agreed cost) and executed Flat Buyer's Agreements and, in some cases, Tripartite Agreements with finance companies.
  • Possession was to be delivered within 36 months from sanction of building plans (with an additional 180-day grace period), but OP failed to deliver possession by the stipulated date and still does not have an Occupation Certificate.
  • OP issued a demand-cum-offer dated 07.06.2013 for "fit outs" (not for habitation) and raised additional demands (escalation, electricity, power back-up, enhanced EDC, stamp duty/registration charges) that were unlawful or premature in the absence of OC.
  • Complainants relied on communications (e.g., alleged email of 30.06.2012) indicating OP would not levy interest until loan disbursal, and alleged that interest/charges were wrongly levied.
  • Given the OP still lacks OC and the complainants are unwilling to accept possession, they sought refund of amounts deposited with 18% interest and compensation for deficiency of service and litigation costs.

Opposite Party's Arguments

  • Preliminary objections: the Commission lacked territorial jurisdiction because Clause 34 of the agreement confers exclusive jurisdiction on courts at Faridabad and the Punjab & Haryana High Court at Chandigarh.
  • The matters raise complex questions of fact and law and ought to be adjudicated by civil courts, not by the Consumer Commission.
  • On merits, OP admitted execution of allotment letters and agreements and that certain payments were made, but contended subsequent demands were in accordance with the agreement's terms (clauses 6, 7 and 26), including power back-up, electrification and escalation clauses.
  • OP contended that possession was subject to Clause 9 (Force Majeure) which included delay in procurement of approvals such as OC, and thus OP argued it was not liable for delay.
  • OP also claimed as a goodwill gesture it waived interest of Rs.5,71,314/- in one instance; OP argued refund is a substantive relief not specifically prayed for (and that OP was willing to give possession subject to payment of balance and compensation under clause 2(3)).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Radiant Infosystem Pvt. Ltd. & Others v. D. Adhilakshmi & Anr. (2013) CPJ 169 (NC) Restriction of jurisdiction to a particular court by agreement need not be determinative where Section 17(2) gives the Commission territorial jurisdiction. Relied upon to reject OP's objection that Clause 34 ousted this Commission's territorial jurisdiction.
Narne Construction P. Ltd. vs. Union of India and Ors. II (2012) CPJ 4 (SC) Housing/construction activities fall within the definition of "service" under Section 2(1)(o) of the Consumer Protection Act. Applied to hold the disputes are consumer disputes and thus maintainable before the Commission.
Haryana Agricultural Marketing Board vs. Bishambar Dayal Goyal & Ors. (AIR 2014 S.C. 1766) Affirmed the principle that housing/construction activities constitute "service" under the Act. Used to support the conclusion that the complaints fall within the Commission's jurisdiction as consumer disputes.
Shailender Singh & Ors. v. Parsvnath Developers (2018 CPJ 85 NC) Authority assessing the proposition that possession cannot be legally offered where the developer does not have an Occupancy Certificate. Relied upon for the proposition that as OP did not have OC, it could not legally offer possession to complainants.
Parsvnath Exotica Resident Association v. Parsvnath Developers Ltd. & Ors.; Devidayal Aluminum Industries (P) Ltd. IV (2016) CPJ 328 (NC) Even in absence of a specific prayer for refund, the Commission may grant relief which is justified by facts and circumstances. Applied to justify awarding refund/compensation though complainants had not originally made a specific prayer for refund.
Lucknow Development Authority v. M.K. Gupta, (1994) 1 SCC 243 When possession of property is not delivered within stipulated period, the delay amounts to denial of service. Relied upon to support finding of deficiency in service due to delayed possession.
Fortune Infrastructure & Anr. v. Trevor D'Lima & Ors., (2018) 5 SCC 442 Principle that an allottee cannot be made to wait indefinitely for possession and is entitled to refund of amounts paid along with compensation. Applied to support award of refund with interest and compensation to complainants deprived of possession indefinitely.
National Commission decisions: Subodh Pawar v. M/s Ireo Grace Realtech Pvt. Ltd. & Ors. (dated 24.09.2018) and Amit Arora v. M/s Ireo Grace Realtech Pvt. Ltd. (dated 27.03.2019) When possession is not delivered within specified time, allottee is entitled to refund with reasonable interest. Relied upon as consistent authority that supports awarding refund with interest in such consumer complaints.

Court's Reasoning and Analysis

The Commission conducted a consolidated hearing because the core issues across the 11 complaints were substantially the same. The Commission first addressed preliminary objections before considering merits.

  1. Jurisdiction: The Commission rejected the OP's territorial jurisdiction objection. The Agreement was executed in Delhi and the OP's registered office is in Delhi; Section 17(2) of the Consumer Protection Act confers territorial jurisdiction on this Commission. The decision relied on Radiant Infosystem to hold that contractual clauses conferring jurisdiction elsewhere do not defeat the Commission's jurisdiction in the circumstances of the case.
  2. Maintainability: The Commission held that housing/construction activity constitutes a "service" under Section 2(1)(o) of the Act (citing Narne Construction and Haryana Agricultural Marketing Board). Accordingly, the complaints are consumer disputes and are maintainable before the Commission. The OP's contention that the disputes were too complex for the Commission was rejected because the issues largely involved contractual interpretation and alleged deficiency in service, matters within the Commission's competence.
  3. Factual findings on possession and demands: The Commission found as an admitted fact that the building plans were sanctioned on 03.11.2010, possession was to be delivered within 36 months plus 180 days, and that as of the decision OP did not possess an Occupation Certificate. The OP had issued a demand-cum-offer for "fit outs" dated 07.06.2013 and raised additional monetary demands. The Commission held that where OP lacked OC, it could not legitimately raise such additional demands or lawfully offer possession for habitation. It considered the issuance of those letters and demands (in absence of OC) to be an unfair trade practice and indicative of deficiency in service.
  4. Force Majeure clause: The OP relied on Clause 9 (Force Majeure) to excuse delay due to non-procurement of statutory approvals. The Commission examined the record and concluded that the delay in obtaining OC was attributable to the OP; there was no material on record showing governmental delay. Therefore OP could not avail of Clause 9 to absolve itself of liability for the delay.
  5. Reliefs and refund without specific prayer: Complainants later stated they were not interested in taking possession in absence of OC and sought refund with interest and compensation. The Commission relied on National Commission precedent (Parsvnath Exotica) establishing that even without an explicit prayer, the Commission may grant reliefs justified by facts and circumstances. Consequently, the Commission considered refund and compensation permissible.
  6. Reliance on authority for remedy: The Commission cited Lucknow Development Authority v. M.K. Gupta and Fortune Infrastructure v. Trevor D'Lima and related National Commission decisions to support the legal proposition that indefeasible delay in delivering possession constitutes denial/deficiency in service and entitles the allottee to refund with interest and compensation.
  7. Quantification: The Commission compiled the admitted amounts paid by each complainant (set out in the order at Paragraph 30 and in accompanying tables) and concluded that complainants were entitled to refund of those amounts with interest. The Commission exercised discretion on the rate of interest to be awarded.

Holding and Implications

Holding (core ruling):

The Commission held that there was deficiency in service on the part of M/s BPTP Ltd. and directed the following:

  • The Opposite Party is directed to refund the amount deposited by each complainant (as listed in Paragraph 30 of the order) along with compensation in the form of interest at 12% per annum from the date of each deposit until realization.
  • The Opposite Party shall also pay a sum of Rs.50,000/- towards the cost of litigation to the complainants.

Additional directions and immediate effects:

  • If any complainant availed a loan from a bank or financial institution for payment towards the flat, that institution will have the first charge on the refund payable to the extent amounts are due to be paid by the complainant to the institution (i.e., lenders' interests are protected).
  • Certified copies of the order were to be placed on the connected complaints' files and a copy sent to parties free of cost as per statutory requirements; thereafter files were to be consigned to the record room.

Implications: The direct consequence of this decision is that M/s BPTP Ltd. must refund the admitted deposits listed in the order with interest at 12% p.a. and pay litigation costs to the complainants. The Commission resolved jurisdictional and maintainability objections in favour of the complainants and applied existing authorities to award refund and compensation. The order applies the legal principles cited from higher courts and the National Commission; the text of the opinion does not assert that a new legal precedent is being laid down beyond its application of established authorities to the facts of these consolidated complaints.

This summary is prepared exclusively from the text of the provided opinion and does not add information beyond that opinion.

    JASJOT SINGH DANG v. M/S BPTP LTD.

    IN THE STATE COMMISSION: DELHI

    (Constituted under Section 9 of the Consumer Protection Act, 1986) Date of Decision:21.10.2019

    1. Complaint Case No. 471/2013 In the matter of:

    1. Anindita Purkayastha Flat No.C-105, Vivek Vihar (AWHO) Sector -82, Noida, UP - 201304.

    2. Indranil Chatterjee, Flat No.C-105, Vivek Vihar (AWHO) Sector -82, Noida, UP - 201304. .....Complainants

    Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    2. Complaint Case No. 469/2013

    1

    In the matter of:

    Monotosh Sarkar SPS Residency, I-107, Indirapuram, Ghaziabad- 201014, Uttar Pradesh .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    3. Complaint Case No. 488/2013 In the matter of:

    Jasjot Singh Dang, S/o Sh. Ajit Singh Dang R/o House No. 513 Sector-30, Opposite Shiv Mandir, Faridabad, Haryana .....Complainant Versus

    M/s BPTP Ltd.

    2

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001 …Opposite Party

    4. Complaint Case No. 525/2013

    In the matter of:

    1. Ajay Singh Chaudhary J 80/3, 1st Floor, Pandav Nagar,

    Opposite Akashardham Metro Station, Delhi- 110092

    2. Meenu Chaudhary J 80/3, 1st Floor, Pandav Nagar, Opposite Akashardham Metro Station, Delhi- 110092 .....Complainants Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001 …Opposite Party

    3

    5. Complaint Case No. 526/2013 In the matter of:

    1. Subir Chaterjee S/o Sh. B.N. Chaterjee Flat No. 332, Pocket A, Sector-17, Dwarka, Delhi- 110075

    2. Shreya Chaterjee W/o Sh. Subir Chaterjee Flat No. 332, Pocket A, Sector-17, Dwarka, Delhi- 110075 ....Complainants Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    6. Complaint Case No. 530/2013

    4

    In the matter of:

    Surjeet Singh 5527, Shora Kothi, Pahar Ganj, Delhi. .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    7. Complaint Case No. 531/2013

    In the matter of:

    Rajeev Kumar House No. 3620, Gali Dariba Pan, Pahar Ganj, New Delhi- 110055. .....Complainant

    5

    Versus M/s BPTP Ltd. Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    8. Complaint Case No. 541/2013

    In the matter of:

    Naveen Sharma FIS Limited, I Park, 4th Floor, 402, Plot No. 15, Udyog Vihar, Phase-IV, Gurgaon. .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director

    6

    M-11, Middle Circle, Connaught Place, New Delhi-110001 …Opposite Party

    9. Complaint Case No. 542/2013

    In the matter of:

    Anoop Maheshwari, House No. 645, Sector-9, Faridabad, Haryana .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    10. Complaint Case No. 590/2013

    In the matter of:

    7

    Subodh Kumar Philips Electronics India Limited, Philips Innovation Campus, Manyata Tech. Park,

    Nagavara, Bangalore- 560045 Through Attorney

    Mr. Pranay Kumar,

    A-62, DDA Flats,

    KatwwariaSarai,

    New Delhi- 110060 .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001 …Opposite Party

    11. Complaint Case No. 674/2013

    In the matter of:

    Krishan Lal Jaiswal S/o Sh. Shesh Mani

    8

    R/o 2438, Behind Govt. Snr. Sec. School Jawahar Colony,

    Nit Faridabad - 121005 .....Complainant Versus

    M/s BPTP Ltd.

    Through its Managing Director M-11, Middle Circle,

    Connaught Place,

    New Delhi-110001. …Opposite Party

    CORAM

    Ms. Salma Noor, Presiding Member

    1. Whether reporters of local newspaper be allowed to see the judgment?

    2. To be referred to the reporter or not?

    Ms. Salma Noor, Presiding Member

    1. By this order, I propose to dispose of aforesaid 11 consumer complaints, filed by the complainants under Section 17 of the Consumer Protection Act, 1986 (in short 'the Act'). Arguments were heard in common, in the above cases, as the issues involved therein, except minor variations, here and there, of law and facts involved in the above complaints, by and large, are the same, and therefore, all the complaints can be disposed of, by passing a consolidated order.

    2. In all the aforesaid complaints, apart from seeking compensation and to obtain NOC from banks towards clearing of charge created by OP on the complainant(s) flat, the complainant(s),inter-alia, have sought setting aside of demands raised by the OP and a direction to withdraw/refund the interest levied/charge or any delayed payment. Complainant(s) have also prayed for award of delayed penalty till the physical possession is actually delivered to them. However, it is an admitted position as on today OP is not having the Occupation Certificate and construction work of EWS Block has not been completed till date and Occupation Certificate issued on 13.12.2013 is withdrawn by DTCP. In these

    9

    circumstances, OP cannot legally offer possession to complainant(s).

    3. To dictate order, facts are being taken from consumer complaint bearing No.471 of 2013 titled as Anindita Purkayashta & Anr. Vs. M/s. BPTP Limited. It is the case of the complainant(s) that OP had launched a residential project by the name of M/s. BPTP Park Floor-II in Sector 76, Faridabad in the year 2008, which was promoted by way of various publishing materials, brochures and other publicity materials wherein salient features of the project were stated. Considering that the flat was within their budget, complainant(s) booked a residential flat measuring 1414 Sq. ft. by paying booking amount of Rs.2,50,000/-. Another sum of Rs.3,21,000/- was also paid by the complainant(s) and thereafter a flat bearing No. T2-204, Tower-T2 vide allotment letter dated 15.12.2008 was allotted to the complainant(s). A Flat Buyer's Agreement (in short, the "Agreement") was executed between the parties on 09.07.2009. It was a construction linked plan. The complainant(s) had availed home loan from LIC Housing Finance Ltd. A Tripartite Agreement was also executed on 10.02.2011. It is stated that building plans of project were approved only on 03.11.2010 as such the project was approved by LIC Housing Finance Ltd. and loan was disbursed thereafter. It is alleged that though there was a delay on the part of OP in obtaining approval of building plans, despite that OP had charged interest on complainant(s) for not paying the installments on time. It is alleged that vide e-mail dated 30.06.2012 it was informed by an employee of OP that no interest would be charged by OP on the outstanding amount till the disbursal of loan from financial institution. It is stated that OP was under an obligation to complete the construction of project and deliver the possession of the subject flat within 36 months from the date of sanction of building plans i.e. the possession was to be delivered by 03.11.2010. However, no offer of possession was made by the stipulated date. It is stated that OP had sent a letter dated 07.06.2013 titled "Demand-cum-Offer of Possession for fit outs" and not for actual habitation of complainant and his family members. It is stated that the aforesaid letter was issued in the absence of any completion/occupancy certificate from the concerned authorities in favour of OP. It is stated that even in the "Demand-cum-Offer of Possession for fit outs", illegal demands were raised by OP i.e. Rs.4,18,466.70 towards basic sale price which was to be payable at the time of physical possession. The cost of Rs.1,45,541.62 towards escalation was wrongly raised. Rs.30,000/- towards electricity connection charges and Rs. 1 lac towards power back up charges were also wrongly raised. It is alleged that Rs.2,16,342/- was demanded towards enhanced EDC charges though the same were stayed by the High Court of Punjab & Haryana in a writ petition filed by Apartment Owners Association of Greater Faridabad. A demand of Rs.1,56,700/- was also raised towards stamp duty and registration, which can only be raised when all approvals including but not limited to completion/occupancy certificate being in place.

    4. It is further the case of the complainant(s) that even in the letter dated 07.06.2013, size of the unit was increased from 1414 Sq.ft. to 1483 Sq.ft. It is stated that complainant(s) have paid about 90% of the original agreed cost of the flat. Despite that possession of the flat has not been offered.

    5. By stating as above, the complaints aforesaid, were filed by the complainants, with a prayer for setting aside demands raised vide letter dated 07.06.2013 and seeking directions to OP to withdraw/refund the interest levied/charged or any delayed payment. Complainant(s) have also prayed for award of delayed penalty till the physical possession is actually delivered to him. There is also a prayer for award of compensation and to obtain NOC from banks towards clearing of charge created by OP on the complainant(s) flat.

    6. Upon notice, the opposite party filed its written statement, wherein, inter-alia, many preliminary objections were raised that this Commission has no territorial jurisdiction to deal with the matter as per clause 34 of the Agreement. It is stated that as per aforesaid clause, parties have mutually agreed to confer the jurisdiction exclusively to the Courts at Faridabad and Punjab and Haryana High Court at Chandigarh alone, in all the matters arising out of or in connection with the Agreement. The complaint(s) raises complex questions of fact and interpretation of law and disputes regarding rights and obligations of parties under various statutes, which requires elaborate evidence and such cases should be adjudicated by the Civil Courts.

    7. On merits it is stated that no cause of action has arisen in favour of complainant(s). OP has admitted letter of allotment dated 15.12.2008 issued to complainant(s) allotting the subject flat, the details of which are given above. The Agreement between the parties is also admitted. It is admitted that complainant had paid Rs.2,50,000/- towards booking amount and Rs.3,21,000/- subsequent to

    10

    booking. It is stated that subsequent demands were raised upon complainant(s) in accordance with the Agreement between the parties. It is also admitted that construction linked plan was agreed between the parties and the building plans of the aforesaid project were approved on 03.11.2010. The payments made by the complainant(s) as well as disbursement from sanctioned loan by LIC Housing Finance Ltd. are also admitted by the OP. It is alleged that no specific Agreement was executed between the parties for non-levying of interest till disbursement of loan as is alleged. However, as a gesture of goodwill, OP had agreed to waive the interest of Rs.5,71,314/- and requisite intimation in this regard was also sent to the complainant(s).

    8. It is stated that clause 2.1 of the Agreement deals with the possession. It is stated that as per aforesaid clause subject to clause 9 or any other circumstances and subject to complainant(s) having complied with terms and conditions of the Agreement and not being in default under any of the provisions of Agreement, OP had agreed to handover the possession within a period of 36 months from the date of sanction of building plans. A grace period of 180 days was also agreed after the expiry of 36 months for applying and obtaining occupation certificate. It is stated that though the Opposite Party had completed the construction of the flat even before the end of year 2012 but the possession could not be granted to the complainant(s) as the occupation certificate was pending from the concerned authority. It is stated that since the possession was subject to clause 9, which is a Force Majeure clause and one of the force majeure condition, which was accepted between the parties, was the non- procurement of any approval from any government authority, including delay in issuance of Occupation Certificate/Completion Certificate. It is alleged that in these circumstances, there is no delay on the part of Opposite Party as is alleged by the complainant(s).

    9. It is denied that arbitrary demands were raised in letter dated 07.06.2013 as is alleged. It is alleged that demands raised upon complainant(s) are legal and are in consonance with the Agreement and terms and conditions of application for allotment. It is alleged that complainant(s) were aware about the Power Back up charges, Electrification Charges, cost escalation in case of increase in prices in the raw materials or any other cost and charges. OP has relied upon clause 6, 7 and 26 of the Terms and Conditions of Allotment.

    10. It is denied that there is any deficiency in service on the part of OP. OP has alleged that relief prayed by complainant(s) cannot be granted as complainant has to comply with demands raised vide letter dated 07.06.2013 and has to make payments and interest towards delayed payments.

    11. In the rejoinder filed, the complainant(s) reiterated all the averments contained in the complaint and repudiated those, contained in written version of the opposite party.

    12. The parties led evidence in support of their cases.

    13. The contesting parties, raised arguments in terms of pleadings noted in earlier part of this order, which were heard, in detail.

    14. Before making any reference to the merits of the case, I would like to decide preliminary objections raised by the opposite party wherein territorial jurisdiction of this Commission was challenged by the OP stating that this Commission has no territorial jurisdiction to deal with the present complaint as per Clause 34 of the Agreement Ex. CW-1/1 It is contended that only courts at Faridabad and Punjab and Haryana High Court at Chandigarh alone have the jurisdiction. The objection raised is baseless. The Agreement Ex. CW -1/1 between the parties was executed at Delhi. Even the registered office of OP is at Delhi. Under Section 17(2) of the Act, this Commission has territorial jurisdiction to deal with the present complaint. It has been held by National Commission in catena of judgments that restriction of jurisdiction to a particular court need not be given any importance in the facts and circumstances of the case. Reliance is placed upon Radiant Infosystem Pvt. Ltd. & Others v. D. Adhilakshmi & Anr.

    1(2013) CPJ 169 (NC).

    15. Another preliminary objection raised by the OP is that the complaint raises complex questions of fact and interpretation of law and disputes regarding rights and obligations of parties under various statutes, which requires elaborate evidence and such cases should be adjudicated by the Civil Courts. In case, I go through the pleadings as well as the evidence produced by the parties, the complainant(s) had booked one flat with opposite party and had paid the payment as demanded by opposite party and all the terms and conditions were incorporated in the agreement executed between the parties. As per the agreement the possession was to be delivered to the allottee within a period of 36 months from the date of sanction of building plans. A grace period of 180 days was also agreed after the expiry of 36

    11

    months for applying and obtaining occupation certificate. It is admitted position that though the Opposite Party had completed the construction of the flat even before the end of year 2012 but the possession could not be granted to the complainant(s) as the occupation certificate was not obtained by the OP from the concerned authority. Thus, it is only the interpretation of the terms and conditions and then to see whether there is any deficiency in service on the part of the opposite party? I do not see that any complicated questions of law and facts are involved, which cannot be adjudicated by this Commission.

    16. It may be stated here, that the complainant(s) hired the services of the opposite party, for purchasing the plot, in the manner, referred to above. According to condition No.2.1 of the Agreement, physical possession of the flat was to be delivered by the opposite party, within a period of 36 months, from the date of execution of the Agreement alongwith all basic amenities as mentioned in Article 2.1 of the Agreement, which they failed to do so and on the other hand, have raised demands, which is being challenged by way of filing this complaint, by the complainant(s). Section 2 (1) (o) of the Act, defines service as under:-

    "service" means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service"

    17. From the afore-extracted Section 2(1)(o) of the Act, it is evident that housing/construction, also comes within the definition of a service. In Narne Construction P. Ltd., etc. etc. Vs. Union Of India and Ors. Etc., II (2012) CPJ 4 (SC), it was held by the Hon'ble Apex Court that when a person applies for the allotment of a building or site or for a flat constructed by the Development Authority and enters into an agreement with the Developer, or the Contractor, the nature of transaction is covered by the expression 'service' of any description. Housing construction or building activity carried on by a private or statutory body constitutes 'service' within the ambit of Section 2(1)(o) of the Act. Similar, principle of law, was laid down, in Haryana Agricultural Marketing Board Vs. Bishambar Dayal Goyal &Ors. (AIR 2014 S.C. 1766). Under these circumstances, the complaint involves the consumer dispute, and the same is maintainable. Not only this, Section 3 of the 1986 Act provides an alternative remedy. Even if, it is assumed that the complainant(s) have a remedy to file a suit, in the Civil Court, the alternative remedy provided under Section 3 of the Act, can also be availed of by them, as they falls within the definition of consumer. In this view of the matter, the objection of the opposite party in this regard, being devoid of merit, must fail, and the same stands rejected.

    18. On merits, it is admitted that the complainant(s) had purchased a flat, in the project of the opposite party, in the manner, referred to above. Fact qua price of the plot, as mentioned in the complaint is also not disputed.

    19. It is also not disputed that as per Agreement Ex. CW -1/1 executed between the parties, the possession was agreed to be delivered by OP within a period of 36 months from the date of sanction of building plan. The date of sanction of building plan is 03.11.2010. A grace period of 180 days was also allowed after 36 months for applying and obtaining OC. It is also admitted that no possession was offered even after lapse of 42 months from 03.11.2010 or even thereafter. It is also not disputed that vide letter dated 07.06.2013, OP had offered possession for fit outs only. It is also admitted position that 90% agreed cost has already been received by OP i.e. Rs.29,92,692.27. The remaining 10% of agreed cost was to be paid only at the time of possession. OP has also raised additional demands vide the aforesaid letter. Complainants have alleged that additional demands are not legitimate. Without going into said controversy, when OP was not having OC, in such circumstances, OP was not justified in raising further demands. The purpose of aforesaid letters was to collect more money, which is an unfair trade practice.

    12

    20. OP has alleged that possession was subject to clause 9 of Agreement which deals with Force Majeure circumstances. It is contended that delay in issuance of Occupation Certificate is one of Force Majeure conditions as such no delay can be attributed on the part of OP. The contention raised has no force. The delay is on the part of OP in obtaining Occupation Certificate. There is no governmental delay in the grant of Occupancy Certificate as such OP cannot claim benefit of clause (9) of the Agreement as is contended. As per material on record, the OP has applied for Occupation Certificate vide application dated 01.05.2012 to the Director of Town and Country Planning (DTCP). However, nothing is placed on record to show the status of the same. The net result is that flat was booked in the year 2008 and till date OP is not having Occupancy Certificate.

    21. Ld. Counsel for complainant(s) has submitted that though the prayer in the complaint is made for setting aside the demands raised by OP vide letter dated 07.06.2013 and for the grant of possession, however, keeping in mind the factual position discussed above i.e. OP is still not having the Occupation Certificate, complainant(s) are not interested in the reliefs prayed in the complaint case. It is submitted that during the pendency of complaint, complainants have awaited for sufficient time so that OP can get clear OC but till date there is no OC with OP as such complainant(s) are interested for refund of amount with 18% interest along with compensation and litigation cost. It is submitted that complainants have paid 90% of the agreed cost and despite that have been deprived of the possession of the flat due to inaction of the OP in obtaining the OC. It is submitted that OP has used the money and enjoyed the benefit arising out of huge payment made by the complainants. It is submitted inordinate delay in obtaining OC is deficiency in service on the part of OP. It is submitted that OP has failed to fulfil its contractual obligation of obtaining the OC as such complainants cannot be compelled to wait further to enable the OP to offer possession.

    22. On the other hand, Ld. Counsel for OP has argued that OP is still willing to offer the flat with delay compensation. It is stated that as per clause 2 (3) of Agreement, OP has agreed to compensate for delay in handing over the possession @ Rs.5/- per sq. ft. It is further submitted that refund of money is a substantive relief. It is submitted that the same cannot be allowed without there being specific prayer in this regard in complaint case. It is contended that subject to payment of balance amount, OP is ready to offer the possession with compensation.

    23. During arguments, ld. Counsel for OP has fairly admitted that as on today OP is not having the Occupancy Certificate. In these circumstances, OP cannot legally offer possession to complainant(s). Reliance is placed on the judgment of National Commission in Shailender Singh & Ors. v. Parsvnath Developers IV 2018 CPJ 85 NC.

    24. As noted above, complainant(s) are not interested in possession of the flat as OP is not having Occupancy Certificate. The question for consideration; is whether in these circumstances, the relief for the refund of amount with interest can be awarded in favour of complainant(s), when there is no specific prayer in this regard. The aforesaid question has been dealt by the National Commission in

    Parsvnath Exotica Resident Association Vs Parsvnath Developers Ltd. &Ors. Devidayal Aluminum Industries (P) Ltd. IV (2016) CPJ 328 (NC) wherein it is held that even in the absence of specific prayer, it is always open to grant relief which is justified and warranted in the facts and circumstances of the case. The relevant portion of the judgment is as under:

    "Though, in Consumer Complaint No.45 of 2015, the main prayer made by the complainant is to direct delivery of the possession of the flats to the allottees complete in all respects, coupled with execution of the tile deed in their favour, when this matter came up for hearing on 27.4.2016, the learned counsel for the complainant stated on instructions, that since the building plans for construction of towers No. A-D have already lapsed and the revised plans have not been sanctioned as yet, the said allottees are not interested in waiting any longer for delivery of the possession of the flats and want to take refund, along with appropriate compensation for the financial loss suffered as well as the harassment and mental agony caused to them. The learned counsel for the opposite party submitted in this regard that no prayer for refund has been made in Consumer Complaint No.45 of 2015. In our opinion, even in the absence of any specific prayer, it is always open to this Commission to grant a relief

    13

    which is justified and warranted in the facts and circumstances of the case."

    25. In view of above discussion, even in the absence of specific prayer, keeping in mind the facts and circumstances discussed above, the relief for refund with appropriate compensation can be considered in favour of complainants.

    26. As discussed above, the complainant(s) have made out a clear case of deficiency of service on the part of the OP. The complainant(s) cannot be compelled to wait for indefinite period for the possession of flat allotted to them, whenever it is offered by the OP.

    27. In Lucknow Development Authority v. M.K. Gupta, (1994) 1 SCC 243, Hon'ble Supreme Court has held that when possession of property is not delivered within the stipulated period, the delay so caused is denial of service.

    28. In Fortune Infrastructure &Anr. v. Trevor D'Lima & Ors., (2018) 5 SCC 442, it is held by Hon'ble Supreme Court that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.

    29. It has been held by the National Commission in catena of judgments that when possession of the allotted flat is not delivered within the specified time, the allottee is entitled to refund of amount paid, with reasonable interest thereon from the date of payment till the date of refund. Reliance is placed on the judgments of National Commission titled Subodh Pawar v. M/s Ireo Grace Realtech Pvt. Ltd. &

    4 Ors. dated 24.09.2018 in CC No.1998/2016 and Amit Arora v. M/s Ireo Grace Realtech Pvt. Ltd.

    dated 27.03.2019 in CC No.696/2017.

    30. As far as aforesaid connected consumer complaints are concerned it may be stated here that a Tripartite Agreement dated 07.06.2011 was entered into between the parties i.e. complainant, OP and finance company in Consumer Complaint No.469/2013. As stated above the facts averred by the complainant(s) in the main complaint and the defence raised by the OP are almost similar to each other, therefore, narration of the same is not required. Further, the objections taken by the OP in the main complaint bearing No.471/2013 have been dealt with by this Commission in the preceding paras of this order. However, for the sake of convenience, the details of the documents executed between the parties and the amount paid by the complainant(s) to the OP, which is admitted by the OP in its statement of accounts, in the aforesaid connected complaints are mentioned herein below:

    S.

    CC No. Date of Agreement Offer of

    allotment dated possession for Amount paidNo. Fit outs

    1.   471/2013 15.12.2008 09.07.2009 07.06.2013 29,92,639.27
    2.   469/2013 18.12.2008 01.05.2011 07.06.2013 26,32,494
    3.   488/2013 15.12.2008 28.08.2009 07.06.2013 28,84,982
    4.   525/2013 16.12.2008 12.08.2009 07.06.2013 23,13,403
    5.   526/2013 16.12.2008 12.08.2009 14.06.2013 26,25,622

    14

    6.   530/2013 18.12.2008 31.10.2009 14.06.2013 27,91,553.36
    7.   531/2013 18.12.2008 29.10.2009 07.06.2013 26,40,069
    8.   541/2013 17.02.2009 09.09.2009 07.06.2013 30,16,027
    9.   542/2013 17.12.2008 11.08.2009 07.06.2013 29,78,439.74
    10.   590/2013 - 14.04.2010 07.06.2013 29,28,904
    11.   674/2013 - 31.10.2009 14.06.2013 27,24,677.36

    31. Except from contending and arguing the averments and the objections made/raised in the complaint(s) and written statement, no other point was raised during the course, by any of the contesting parties in all the complaints.

    32. In view of the above discussion, present is a clear case of deficiency in service on the part of OP. Complainant(s) are legally entitled to seek refund of the money deposited by them with OP along with appropriate compensation. The complainant(s) have prayed for award of interest @ 18% p.a. However, keeping in mind the facts and circumstances of the case, I award compensation in the form of interest @ 12% p.a. from date of each deposit till realization.

    1) The Opposite Party is directed to refund the amount deposited by the complainants as mentioned in Para No.30 of the order along with compensation in the form of interest @ 12% p.a. from the date of each deposit till realization.

    2) The Opposite Party shall also pay a sum of Rs.50,000/- towards cost of litigation to complainant.

    33. However, it is made clear that, if the complainant(s) in any of the above complaints, have availed loan facility from any banking or financial institution, for making payment towards the said flat, they will have the first charge of the amount payable, to the extent, the same is due to be paid by them (complainant(s)), respectively.

    34. Certified copy of this order, be placed on connected complaints file, referred to above.

    35. A copy of this order as per statutory requirements be sent to the parties free of cost. Thereafter the file be consigned to record room.

    (Salma Noor)

    15

    Presiding Member