AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Article 226 of the Constitution of India
  • Section 5, Subsection 2 of the 1983 Income Tax Act is not mentioned in this excerpt. However, 'Budget presented by U.P. Jal Nigam, Magh Mela 2008 of 2009' and 'Government/Mela Administration' are mentioned.
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Article 226 of the Constitution of India
  • Section 5, Subsection 2 of the 1983 Income Tax Act is not mentioned in this excerpt. However, 'Budget presented by U.P. Jal Nigam, Magh Mela 2008 of 2009' and 'Government/Mela Administration' are mentioned.
Smart Summary

Factual and Procedural Background

The appellant performed additional work for the Uttar Pradesh Jal Nigam (UPJN) during the Magh Mela 2008-2009 pursuant to an express sanction. Although the work was completed to UPJN’s satisfaction, the agreed payment of Rs 113.29 lakhs was never released.

On 21-10-2013, the Allahabad High Court directed the appellant to submit a representation for payment, and on 07-02-2014 (in a contempt petition) required UPJN to answer that representation. UPJN’s reply dated 22-03-2014 admitted the liability but claimed the requisite funds had not been received from the Government/Mela Administration.

Subsequently, the appellant filed Writ Civil No. 25216 of 2014 before the High Court. By judgment dated 02-05-2014, the High Court dismissed the writ on the ground that “disputed questions of fact” existed and that the claim arose out of a contract. The appellant then approached the Supreme Court by way of the present appeal.

Legal Issues Presented

  1. Whether a writ petition under Article 226 of the Constitution is maintainable to compel a State instrumentality to pay an undisputed contractual amount.
  2. Whether the High Court erred in dismissing the writ petition on the premise that disputed questions of fact existed when the liability was, in fact, admitted.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd., (2004) 3 SCC 553 The High Court’s power under Article 226 extends to contractual matters where State action is arbitrary. Relied upon to hold that UPJN’s failure to pay an admitted amount constitutes arbitrary State action that can be remedied in writ jurisdiction.

Court's Reasoning and Analysis

The Supreme Court observed that UPJN’s own communication unequivocally admitted the debt, negating the High Court’s finding of any factual dispute. Because the liability was undisputed and the delay was solely attributable to UPJN’s failure to obtain funds from the Government, the Court found the conduct arbitrary.

Invoking the principle in ABL International, the Court reaffirmed that Article 226 jurisdiction is available even in matters arising out of contract when State instrumentalities act arbitrarily. Accordingly, the High Court’s dismissal of the writ petition was declared “wholly incorrect.”

Given that the work had been completed in 2009 and payment had been withheld for several years, the Court deemed immediate relief necessary.

Holding and Implications

DISPOSED OF: Uttar Pradesh Jal Nigam is directed to pay the entire admitted amount to the appellant within four weeks along with interest at 6% per annum.

Implications: The decision underscores that State entities cannot evade payment of undisputed contractual dues by citing internal financial constraints, and that writ jurisdiction remains available to correct such arbitrary conduct. No new legal doctrine is created, but the judgment fortifies the enforceability of ABL International in analogous contractual disputes with the State.

    Surya Constructions v. State Of Uttar Pradesh And Others

    Order

    1. Leave granted. Having heard the learned counsel for all the parties, we find that the present is a case in which payment for extra work by the Uttar Pradesh Jal Nigam has not been made though such work was expressly sanctioned and done to their satisfaction. The appellant before us has had to run from pillar to post to get the money owed to them.

    2. By an order dated 21-10-2013 2013 SCC OnLine All 14604, the High Court asked the appellant to make a representation and finally, in a contempt petition moved on 7-2-2014, directed 2014 SCC OnLine All 16549 Uttar Pradesh Jal Nigam to answer this representation. The representation so made was answered by Uttar Pradesh Jal Nigam as follows:

    “Due to aforesaid facts and description it is clear that Rs 113.29 lakhs has to be released by Government/Mela Administration against the Budget presented by U.P. Jal Nigam, Magh Mela 2008 of 2009. There is no money available under account of Magh Mela 2008 of 2009 of U.P. Jal Nigam. And could not obtain the rest of amount from the Mela Administration/Government. Therefore, payment regarding M/s Surya Construction, 323/3, Alopibagh, Allahabad will be paid after availability of the money from the Government.”

    3. It is clear, therefore, from the aforesaid order dated 22-3-2014 that there is no dispute as to the amount that has to be paid to the appellant. Despite this, when the appellant knocked at the doors of the High Court in a writ petition being Writ Civil No. 25216 of 2014, the impugned judgment dated 2-5-2014 2014 SCC OnLine All 6071 dismissed the writ petition stating that disputed questions of fact arise and that the amount due arises out of a contract. We are afraid the High Court was wholly incorrect inasmuch as there was no disputed question of fact. On the contrary, the amount payable to the appellant is wholly undisputed. Equally, it is well settled that where the State behaves arbitrarily, even in the realm of contract, the High Court could interfere under Article 226 of the Constitution of India (ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd. (2004) 3 SCC 553)

    4. This being the case and the work having been completed long back in 2009, we direct Uttar Pradesh Jal Nigam to make the necessary payment within a period of four weeks from today. Given the long period of delay, interest @ 6% p.a. may also be awarded.

    5. The appeal stands disposed of accordingly.

    Use AI to get other relevant cases.

    Comments

    Surya Constructions v. State Of Uttar Pradesh And Others
    (Mar 8, 2019)