Order
1. Leave granted. Having heard the learned counsel for all the parties, we find that the present is a case in which payment for extra work by the Uttar Pradesh Jal Nigam has not been made though such work was expressly sanctioned and done to their satisfaction. The appellant before us has had to run from pillar to post to get the money owed to them.
2. By an order dated 21-10-2013 2013 SCC OnLine All 14604, the High Court asked the appellant to make a representation and finally, in a contempt petition moved on 7-2-2014, directed 2014 SCC OnLine All 16549 Uttar Pradesh Jal Nigam to answer this representation. The representation so made was answered by Uttar Pradesh Jal Nigam as follows:
“Due to aforesaid facts and description it is clear that Rs 113.29 lakhs has to be released by Government/Mela Administration against the Budget presented by U.P. Jal Nigam, Magh Mela 2008 of 2009. There is no money available under account of Magh Mela 2008 of 2009 of U.P. Jal Nigam. And could not obtain the rest of amount from the Mela Administration/Government. Therefore, payment regarding M/s Surya Construction, 323/3, Alopibagh, Allahabad will be paid after availability of the money from the Government.”
3. It is clear, therefore, from the aforesaid order dated 22-3-2014 that there is no dispute as to the amount that has to be paid to the appellant. Despite this, when the appellant knocked at the doors of the High Court in a writ petition being Writ Civil No. 25216 of 2014, the impugned judgment dated 2-5-2014 2014 SCC OnLine All 6071 dismissed the writ petition stating that disputed questions of fact arise and that the amount due arises out of a contract. We are afraid the High Court was wholly incorrect inasmuch as there was no disputed question of fact. On the contrary, the amount payable to the appellant is wholly undisputed. Equally, it is well settled that where the State behaves arbitrarily, even in the realm of contract, the High Court could interfere under Article 226 of the Constitution of India (ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd. (2004) 3 SCC 553)
4. This being the case and the work having been completed long back in 2009, we direct Uttar Pradesh Jal Nigam to make the necessary payment within a period of four weeks from today. Given the long period of delay, interest @ 6% p.a. may also be awarded.
5. The appeal stands disposed of accordingly.